Académique Documents
Professionnel Documents
Culture Documents
Uses Specification
For pumped or free flow grouting, it can be used in a wide Performance specification
range of applications:
All grouting, where shown on the drawing, must be carried
! Post tensioned bridge deck ducts out with a specialised grout admixture which is iron-free
and chloride-free. It shall be mixed with clean water and
! Prestressed structural element cables ducts
cement to the required consistency. The plastic grout must
! Slip form silo tendon ducts not bleed or segregate.
To enable the grouting operation to be carried out continuously, 2) The Cebex Cable Grout shall be mixed in the laboratory
it is essential that sufficient mixing capacity and labour are following the instructions listed on the product data sheet.
available. The use of a grout holding tank with provision to
3) All sampling shall be conducted using 50 mm cube
gently agitate the grout may be required.
moulds, any other size is not permissible.
32 to 42 litres of clean water (depending on nature of cement)
4) When mixed, the Cebex Cable Grout shall be poured into
and 100 kg of cement are required to be added per 6 kg bag to
50 mm cube moulds, treated with release agent, in two
achieve the correct consistency.
lifts of 25 mm each with a 60 second interval between
The water should be accurately measured into the mixer. The pours. The Cebex Cable Grout shall not be tamped, but
total contents of the Cebex Cable Grout bag should be slowly gentle tapping of the cube mould is permitted to promote
added with the cement and continuous mixing should take the release of air.
place for 5 minutes. This will ensure that the grout has a
5) Fill three 50 mm cube moulds with the Cebex Cable Grout
smooth even consistency.
for each curing time interval specified. Mould filling should
Placing be completed within 15 minutes of the end of the mixing
cycle. The filled moulds should be stacked three high on
Place the grout within 20 minutes of mixing.
top of each other to provide conditions of restraint. The top
Cebex Cable Grout can be placed in annular gaps of up to mould should be restrained either with a weighted metal
60mm in thickness. plate or an empty cube mould.
Pumping should be from a single point to eliminate any air or 6) The cubes should be stored at a 20C+ 2C temperature
entrapment of water used for presoaking. for 24 hours in the laboratory. After 24 hours the cubes are
to be demoulded and placed in a water curing tank
A heavy duty diaphragm pump is recommended for pumping.
maintained at a 20C+ 2C temperature. The cubes are
Screw feed and piston pumps may also be suitable.
then to be cured in accordance with BS1881.
Limitations Estimating
When the air or contact surface temperatures are 5C or below Cebex Cable Grout : approx. 68 litres when mixed
on a falling thermometer, warm water (30-40C) is with 100 kg cement and 34
recommended to accelerate strength development. litres of water
Normal precautions for winter working with cementitious Note: Allowance should be made for wastage when
materials should then be adopted. estimating quantities required.
(ii) Keep equipment cool, arranging shade protection if Health and safety
necessary. It is especially important to keep cool those Cebex Cable Grout is alkaline and should not come into contact
surfaces of the equipment which will come into direct with skin and eyes. Avoid inhalation of dust during mixing.
contact with the material itself. Gloves, goggles and dust mask should be worn. If contact
(iii) Try to eliminate application during the hottest times of the with skin occurs, wash with water. Splashes to eyes should
day. be washed immediately with plenty of clean water and medical
advice sought.
(iv) Make sufficient material, plant and labour available to
ensure that application is a continuous process. Fire
(v) Water (below 20C) should be used for mixing the grout Cebex Cable Grout is non-flammable.
prior to placement.
Technical support
Additional Information
! fluid micro-concretes
Important note
Fosroc products are guaranteed against defective materials and manufacture and are sold subject to its standard
Conditions for the Supply of Goods and Service
Head Office
Al Gurg Fosroc telephone: (+9714) 2858606 fax: (+9714) 2859649 email: agf@fosroc.com
LLC Regional offices
Dubai, Al Gurg Fosroc telephone: 285 8787 fax: 285 2023 email: dubai@fosroc.com
Post Box 657, Dubai Abu Dhabi, Al Gurg Fosroc telephone: 673 1779 fax: 673 1449 email: abudhabi@fosroc.com
United Arab Emirates Bahrain, YBA Kanoo telephone: 17735454 fax: 17732828 email: bahrain@fosroc.com
Kuwait, Boodai telephone: 4817618 fax: 4832124 email: kuwait@fosroc.com
www.fosroc.com
Oman, Al Amana telephone: 771 5080 fax: 771 7554 email: oman@fosroc.com
Qatar, Tadmur telephone: 413628 fax: 440812 email: qatar@fosroc.com
UAE/0357/03/E