Académique Documents
Professionnel Documents
Culture Documents
2001 Page 1 of 24
6 December 2004
CONFIDENTIAL
The information contained
REVISED CT REQUIREMENTS FOR THE MiCOM in this document is not to
P540 RELAYS be communicated either
directly or indirectly to any
person not
authorized to receive it.
SUMMARY:
This report serves to verify whether P540 relay CT requirements could be reduced. It
also aims to interpolate more accurate CT requirements at indermediate levels of If
and X/R. Note that it does not relax the 3-shot requirement for operation and stability,
it merely re-interprets the existing results. The conclusion is that exact formulae to
calculate the CT requirements are applicable, and should appear in product literature
at the phase 2.1 MiCOM CA date.
It is noted that where a transformer is in-zone, it is important that the high set element
is enabled, to avoid possible slow operation for high current faults on the HV side of
the transformer.
1. INTRODUCTION...............................................................................2
2. ANALYSIS........................................................................................2
3. CONCLUSIONS...............................................................................24
ALSTOM T&D Protection & Control Ltd ALSTOM T&D Protection & Control Ltd
St Leonards Works Registered Office:-
Stafford St Leonards Works
ST17 4LX Stafford
England Registered in England No. 959256
Tel: +44 (0) 1785 223251
Fax: +44 (0) 1785 212232
150/HV0013 ENGINEERING REPORT
Page 2 of 24
6 December 2004
1. INTRODUCTION
P540 relays CT requirements as published to date are based upon extensive RTDS
simulator testing. This consists of 3 successive fault applications at the same point on
wave chosen to give the maximum dc offset in the flux. The CT requirements are
documented in Service Manual TG8613, and are of the form:
Where:
Vk = Required IEC knee point voltage
K = Dimensioning factor
In = CT nominal secondary current
Rct = CT resistance
RL = One-way lead impedance from CT to relay
The K factor increases in coarse steps, according to the primary system X/R ratio,
and the product (maximum fault current x X/R). This approach replicates the LFCB
claims.
This report serves to investigate the exact variation of the K factor required with fault
current and X/R, in order to verify whether CT requirements could be reduced. It also
aims to interpolate more accurate CT requirements at indermediate levels of If and
X/R. Note that it does not relax the 3-shot requirement for operation and stability, it
merely re-interprets the existing results.
2. ANALYSIS
Development Specification 50304.3203.202 outlines the RTDS tests performed to
ascertain the previous CT requirement claims. Results are tabulated in Excel
spreadsheet 50304.3303.202.
For the tests, a target K factor was determined, and then CT lead burden was added in
order to find out the point where through fault stability would just be guaranteed.
Provided the RL lead burden at this point was in excess of the target, the K factor was
deemed to be verified. However, each additional insertion of RL was in steps of 0.25,
so the results give a pessimistic view of product performance. Also, where RL was
found to be much in excess of that required to achieve the quoted K factor, a real
stability limit was not recorded.
ENGINEERING REPORT 150/HV0013
Page 3 of 24
6 December 2004
X/R (If x X/R) Fault Target A-N Table Calculated K Vkp Rct Actual K
Current factor needed
(A)
5 200 40 0.69 1 7.1.4.3 85 160 0.5 64
10 100 10 0.98 1.5 7.1.4.1 65 160 0.5 46
10 200 20 0.69 1.25 7.1.4.1 85 160 0.5 53
10 200 20 0.53 1.25 7.1.4.2 103 160 0.5 53
10 400 40 0.53 0.75 7.1.4.1 103 160 0.5 80
10 400 40 0.53 0.75 7.1.4.3 103 160 0.5 80
10 500 50 0.53 1 7.1.4.1 103 160 0.5 64
20 40 2 0.98 1 7.1.4.3 65 160 0.5 64
20 800 40 ? 1.25 7.1.4.3 160 0.5 53
30 60 2 0.98 1 7.1.4.3 65 160 0.5 64
30 120 4 0.98 1.25 7.1.4.3 65 160 0.5 53
30 1200 40 ? 1 7.1.4.3 160 0.5 64
40 60 1.5 0.98 1.25 7.1.4.1 65 160 0.5 53
40 60 1.5 0.98 1.25 7.1.4.3 65 160 0.5 53
40 160 4 0.69 1 7.1.4.1 85 160 0.5 64
40 160 4 0.69 1 7.1.4.2 85 160 0.5 64
40 160 4 0.69 1 7.1.4.3 85 160 0.5 64
40 160 4 0.69 1 7.1.4.7 85 160 0.5 64
40 160 4 1.63 2.5 7.1.4.7 85 320 0.5 58
40 240 6 0.69 1.25 7.1.4.1 85 160 0.5 53
40 320 8 0.69 1.25 7.1.4.1 85 160 0.5 53
40 400 10 0.53 1.25 7.1.4.1 103 160 0.5 53
40 400 10 0.53 1.25 7.1.4.2 103 160 0.5 53
40 400 10 0.53 1.25 7.1.4.7 103 160 0.5 53
40 400 10 1.3 2.5 7.1.4.7 103 320 0.5 58
40 800 20 ? 1.25 7.1.4.1 160 0.5 53
40 800 20 0.53 1.25 7.1.4.2 103 160 0.5 53
150/HV0013 ENGINEERING REPORT
Page 4 of 24
6 December 2004
In column 10 of the table, the actual K factor really needed at the tested value of If
and X/R is shown. This is calculated from:
K > Vk / (Rct + 2 RL) For 1A relays.
As noted before, the coarse steps in lead resistance could be leading to an over-
pessimistic K.
For most instantaneous protection, CT knee point formulae increase according to the
factor If x X/R, or If x (1 + X/R). This given, the extremities up to which a particular
value of K applies can be analysed with reference to columns 1, 2, 3 and 10 above.
10 46 53 80
20
30
40 64 91
60 91
90
120 107 107 107
For interest, these K factors are also tabulated against (If x X/R) below:
If x X/R K
100 46
200 53
400 64
500 80
800 91
1200 107
2400 107
4800 107
In order to try to establish a trend in the K factor, three graphs can be plotted:
150/HV0013 ENGINEERING REPORT
Page 6 of 24
6 December 2004
110
100
90
80 If = 10 In
K factor
If = 20 In
If = 40 In
70 Linear (If = 10 In)
60
50
40
0 20 40 60 80 100 120
X/R Ratio
110
100
90
80
X/R Ratio = 10
K factor
X/R Ratio = 40
X/R Ratio = 120
70 Linear (X/R Ratio = 10)
60
50
40
0 5 10 15 20 25 30 35 40 45 50
Fault Current
ENGINEERING REPORT 150/HV0013
Page 7 of 24
6 December 2004
Graph 1:
At If = 10 . In: K = 40 + 0.6 X/R
= 40 + (0.06 x (If x X/R))
Graph 2:
At X/R = 10: K = 37 + 0.86 X/R
= 37 + (0.086 x (If x X/R))
110
100
90
80
K factor
70
60
50
40
0 500 1000 1500 2000 2500 3000 3500 4000 4500 5000
(If x X/R)
Graph 3:
150/HV0013 ENGINEERING REPORT
Page 8 of 24
6 December 2004
Thus, it is seen that there is noticeable correlation between the results at a K factor
equation of:
A preliminary check reveals that this equation holds true, except for some faults where
If is close to 2.In. Here, imposing a minimum value of K = 65 ensures stability.
The 3 constraints for the K factor can be tested against all the RTDS results. This is
shown in the table below. The approach used is to compare the actual K value
required for stability with the formula. As the actual K value could be pessimistic
due to the 0.25 step in lead burdens on testing, the final column will indicate OK if
the formula yielded results within the effective error percentage spread due to the
0.25 steps.
X/R (If x X/R) Fault Current Table Actual K K from Allowable Within
(A) needed Formula Error (%) error
tolerance
5 200 40 7.1.4.3 64 65 20 YES
10 100 10 7.1.4.1 46 65 14 YES
10 200 20 7.1.4.1 53 65 17 YES
10 200 20 7.1.4.2 53 65 17 YES
10 400 40 7.1.4.1 80 68 25 YES
10 400 40 7.1.4.3 80 68 25 YES
10 500 50 7.1.4.1 64 75 20 YES
20 40 2 7.1.4.3 64 65 20 YES
20 800 40 7.1.4.3 53 96 17 YES
30 60 2 7.1.4.3 64 65 20 YES
30 120 4 7.1.4.3 53 65 17 YES
30 1200 40 7.1.4.3 64 107 20 YES
40 60 1.5 7.1.4.1 53 65 17 YES
40 60 1.5 7.1.4.3 53 65 17 YES
ENGINEERING REPORT 150/HV0013
Page 9 of 24
6 December 2004
As can be seen, the formula only fails for fault currents = 2 x In, ie. positioned at the
knee of the dual slope bias characteristic. It can be seen that in reality, a CT would
never be sized based on a through fault current of 2 x In, even for a transformer
150/HV0013 ENGINEERING REPORT
Page 10 of 24
6 December 2004
feeder, a minimum of 10 In would be assumed. At the X/R ratios where the equation
failed, substituting 10 In, as per a real system condition would yield a K factor more
than sufficient for stability.
Thus, use of the formula is justified, allowing example K factors as below to be used:
Fault
Current
X/R If 10 20 30 40
5 65 65 65 65
10 65 65 65 68
20 65 68 82 96
30 65 82 103 107
40 68 96 107
60 82 107
90 103
(Figures in black show the imposition of the minimum K factor of 65, blue figures use
the formula, and red for (If x X/R) > 1000
10
20
30
40
50
60 50
70
70 90
80
90
100
110
120
130
5 10 15 20 25 30
Fault Current (x In)
Having proven that the new formula ensures stability for through faults, it is also
important to check that reliable operation for internal faults can also be guaranteed.
The trips times must not be extended. Reviewing the existing RTDS results it is seen
that the lead burden step increments are too large, and dont cover the required range
to adequately check performance. Thus, repeat tests were performed, at the values of
If and X/R from the table on page 3 where CT saturation was observed to be most
likely (ie. right on the boundary of the new formula).
The tests performed for the P542 relay, with default settings applied and K2 slope set
to 150% were chosen as:
Table Vkp X/R Fault (If x X/R) K from new RL limit from
Current (A) Formula new formula
As per the original tests, three shots at the worst-case point on wave were performed,
to achieve the worst-case distortion due to saturation. The results for the maximum
and minimum trip time of the relay at either line end, on a per shot basis are tabulated
below (in ms).
Test 1:
If = 10 Shot1 Shot1 Shot2 Shot2 Shot3 Shot3
(min) (max) (min) (max) (min) (max)
X/R = 10
Burden
0 28.4 31.5 24.1 27.9 28.4 28.8
0.5 27.1 30.1 27.4 30.4 26.9 27.2
0.75 30.4 30.9 22.6 25.8 25.6 27.2
1 26.8 30.5 27.9 29.2 25.8 29.4
(Maximum burden according to the formula is 0.98)
Conclusion: No trend increase in operating time with lead burden, hence formula is
acceptable at this value of If and X/R.
Test 2:
If = 20 Shot1 Shot1 Shot2 Shot2 Shot3 Shot3
(min) (max) (min) (max) (min) (max)
X/R = 10
Burden
0 25.4 29.2 24.6 25.9 24.9 26.4
0.5 28.1 28.8 23.3 24.6 28.6 29.1
0.75 28.4 29.4 23.2 26.2 26.4 28.2
1 23.2 27.8 28.2 28.4 27.5 28.2
(Maximum burden according to the formula is 0.98)
Conclusion: No trend increase in operating time with lead burden, hence formula is
acceptable at this value of If and X/R.
ENGINEERING REPORT 150/HV0013
Page 13 of 24
6 December 2004
Test 3:
If = 10 Shot1 Shot1 Shot2 Shot2 Shot3 Shot3
(min) (max) (min) (max) (min) (max)
X/R = 40
Burden
0 27.8 27.8 27.6 28.5 26.1 27.2
0.5 26.5 30.7 25.6 26.5 25.6 35.1
0.75 26.2 29.2 26.1 30.5 26.4 30.8
1 26.2 28.4 27.9 28.5 24.1 28.6
1.25 26.8 27.9 27.1 28.8 24.5 26.9
1.5 25.2 25.5 24.9 30.1 30.8 31.8
1.75 24.2 27.2 28.8 29.6 24.5 29.6
2 28.6 31.1 23.5 28.4 28.4 28.6
2.25 27.1 28.1 27.2 28.2 25.1 27.4
(Maximum burden according to the formula is 2.10)
Conclusion: No trend increase in operating time with lead burden, hence formula is
acceptable at this value of If and X/R.
Test 4:
If = 20 Shot1 Shot1 Shot2 Shot2 Shot3 Shot3
(min) (max) (min) (max) (min) (max)
X/R = 40
Burden
0 24.9 28.1 24.8 25.1 24.2 29.4
0.5 28.8 29.2 23.3 24.1 23.5 29.2
0.75 27.8 27.9 23.5 27.6 23.5 27.6
1 24.5 27.5 24.9 26.8 26.8 27.5
1.25 24.8 27.4 26.2 29.4 22.5 27.4
1.5 26.5 29.2 26.5 31.4 26.2 26.8
(Maximum burden according to the formula is 1.42)
Conclusion: Only a marginal trend increase in operating time with lead burden, hence
formula is acceptable at this value of If and X/R.
Overall, the use of the formula has been proven to be justified, both on the grounds of
through fault stability, and satisfactory internal operating times.
150/HV0013 ENGINEERING REPORT
Page 14 of 24
6 December 2004
X/R (If x X/R) Fault Target A-N Table Calculated Vkp Rct Actual K
Current (A) K factor needed
5 200 40 0.19 0.25 7.4.4.3 180 160 0.5 160
10 80 8 0.59 1 7.4.4.1 95 160 0.5 64
10 100 10 0.59 1 7.4.4.1 95 160 0.5 64
10 200 20 0.19 0.5 7.4.4.1 180 160 0.5 107
10 400 40 ? 0.2 7.4.4.1 160 0.5 178
10 400 40 0.19 0.2 7.4.4.3 180 160 0.5 178
20 40 2 0.59 1 7.4.4.3 95 160 0.5 64
20 80 4 0.59 1 7.4.4.3 95 160 0.5 64
20 800 40 0.19 0.25 7.4.4.3 180 160 0.5 160
30 60 2 0.59 0.75 7.4.4.3 95 160 0.5 80
30 120 4 0.59 0.75 7.4.4.3 95 160 0.5 80
30 1200 40 ? 0.15 7.4.4.3 160 0.5 200
40 60 1.5 0.59 1.25 7.4.4.1 95 160 0.5 53
40 60 1.5 0.59 1.25 7.4.4.3 95 160 0.5 53
40 80 2 0.59 0.75 7.4.4.1 95 160 0.5 80
40 80 2 0.59 0.75 7.4.4.3 95 160 0.5 80
40 80 2 1.43 1.5 7.4.4.5 95 320 0.5 91
40 80 2 3.12 3.5 7.4.4.5 95 640 0.5 85
40 160 4 0.19 0.75 7.4.4.1 180 160 0.5 80
40 160 4 0.19 0.75 7.4.4.3 180 160 0.5 80
40 160 4 0.64 1.5 7.4.4.5 180 320 0.5 91
40 160 4 1.53 3.5 7.4.4.5 180 640 0.5 85
40 240 6 0.19 0.5 7.4.4.1 180 160 0.5 107
40 320 8 0.19 0.5 7.4.4.1 180 160 0.5 107
40 400 10 ? 0.25 7.4.4.1 160 0.5 160
40 400 10 ? 1 7.4.4.5 160 0.5 64
40 400 10 ? 1 7.4.4.5 320 0.5 128
ENGINEERING REPORT 150/HV0013
Page 15 of 24
6 December 2004
In column 10 of the table, the actual K factor really needed at the tested value of If
and X/R is shown. This is calculated from:
As noted before, the coarse steps in lead resistance could be leading to an over-
pessimistic K.
For most instantaneous protection, CT knee point formulae increase according to the
factor If x X/R, or If x (1 + X/R). This given, the extremities up to which a particular
value of K applies can be analysed with reference to columns 1, 2, 3 and 10 above.
For interest, these K factors are also tabulated against (If x X/R) below:
If x X/R K
100 64
200 107
400 160
800 256
1600 256
ENGINEERING REPORT 150/HV0013
Page 17 of 24
6 December 2004
In order to try to establish a trend in the K factor, three graphs were plotted, as
follows:
240
200
160
K factor
X/R = 10
X/R = 40
Linear (X/R = 10)
120
80
40
0 5 10 15 20 25 30 35 40 45 50
Fault Current If
150/HV0013 ENGINEERING REPORT
Page 18 of 24
6 December 2004
240
Graph
240 1:
At If160
= 10 . In: K = 34 + 3.16 X/R If = 10 In
K factor
If = 20 In
If = 40 In
= 34 + (0.316 x (If x X/R)) Linear (If = 10 In)
200 Poly. (If = 40 In)
120
160
= 34 + (0.376 x (If x X/R))
80
K factor
(Insufficient
40 points for X/R = 40 line).
0 200 400 600 800 1000 1200 1400 1600
(If x X/R)
Graph 3:
K = 38 + (0.32 x (If x X/R))
Thus, it is seen that there is noticeable correlation between the results at a K factor
equation of:
A preliminary check reveals that this equation holds true, except for some faults where
If is close to 2.In. Here, imposing a minimum value of K = 65 ensures stability.
ENGINEERING REPORT 150/HV0013
Page 19 of 24
6 December 2004
The 3 constraints for the K factor can be tested against all the real results. This is
shown in the table below. The approach used is to compare the actual K value
required for stability with the formula. As the actual K value could be pessimistic
due to the 0.25 step in lead burdens on testing, the final column will indicate OK if
the formula yielded results within the effective error percentage spread due to the
0.25 steps.
X/R (If x X/R) Fault Table Calculated Actual K K from Allowable Within error
Current (A) K factor needed Formula Error (%) tolerance
5 200 40 7.4.4.3 180 160 110 50 YES
10 80 8 7.4.4.1 95 64 68 20 YES
10 100 10 7.4.4.1 95 64 75 20 YES
10 200 20 7.4.4.1 180 107 110 33 YES
10 400 40 7.4.4.1 178 180 56 YES
10 400 40 7.4.4.3 180 178 180 56 YES
20 40 2 7.4.4.3 95 64 65 20 YES
20 80 4 7.4.4.3 95 64 68 20 YES
20 800 40 7.4.4.3 180 160 256 50 YES
30 60 2 7.4.4.3 95 80 65 25 YES
30 120 4 7.4.4.3 95 80 82 25 YES
30 1200 40 7.4.4.3 200 256 63 YES
40 60 1.5 7.4.4.1 95 53 65 17 YES
40 60 1.5 7.4.4.3 95 53 65 17 YES
40 80 2 7.4.4.1 95 80 68 25 YES
40 80 2 7.4.4.3 95 80 68 25 YES
40 80 2 7.4.4.5 95 91 68 14 NO
40 80 2 7.4.4.5 95 85 68 7 NO
40 160 4 7.4.4.1 180 80 96 25 YES
40 160 4 7.4.4.3 180 80 96 25 YES
40 160 4 7.4.4.5 180 91 96 14 YES
40 160 4 7.4.4.5 180 85 96 7 YES
40 240 6 7.4.4.1 180 107 124 33 YES
40 320 8 7.4.4.1 180 107 152 33 YES
40 400 10 7.4.4.1 160 180 50 YES
40 400 10 7.4.4.5 64 180 20 YES
40 400 10 7.4.4.5 128 180 20 YES
40 400 10 7.4.4.5 116 180 9 YES
150/HV0013 ENGINEERING REPORT
Page 20 of 24
6 December 2004
As can be seen, the formula only fails for fault currents = 2 x In, ie. positioned at the
knee of the dual slope bias characteristic. It can be seen that in reality, a CT would
never be sized based on a through fault current of 2 x In, even for a transformer
feeder, a minimum of 10 In would be assumed. At the X/R ratios where the equation
failed, substituting 10 In, as per a real system condition would yield a K factor more
than sufficient for stability.
Thus, use of the formula is justified, allowing example K factors as below to be used:
Fault
Current
X/R If 10 20 30 40
5 65 75 93 110
10 75 110 145 180
20 110 180 250 256
ENGINEERING REPORT 150/HV0013
Page 21 of 24
6 December 2004
(Figures in black show the imposition of the minimum K factor of 65, blue figures use
the formula, and red for (If x X/R) > 600
A graphical illustration for selected K factors is plotted below:
10
20
30
100
140
180
40
50
60
70
5 10 15 20 25 30
Fault Current (x In)
Having proven that the new formula ensures stability for through faults, it is also
important to check that reliable operation for internal faults can also be guaranteed.
The trips times must not be extended. Reviewing the existing RTDS results it is seen
that the lead burden step increments are too large, and dont cover the required range
to adequately check performance. Thus, repeat tests were performed, at the values of
If and X/R from the table on page 13 where CT saturation was observed to be most
likely (ie. right on the boundary of the new formula).
150/HV0013 ENGINEERING REPORT
Page 22 of 24
6 December 2004
The tests performed for the P543 relay, with default settings applied and K2 slope set
to 100% were chosen as overleaf:
ENGINEERING REPORT 150/HV0013
Page 23 of 24
6 December 2004
Table Vkp X/R Fault (If x X/R) K from new RL limit from
Current (A) Formula new formula
Test 1:
If = 10 Shot1 Shot1 Shot2 Shot2 Shot3 Shot3
(min) (max) (min) (max) (min) (max)
X/R = 10
Burden
0 28.2 30.7 28.1 30.7 28.9 31.1
0.5 27.6 30.2 27.4 29.9 26.8 29.5
0.75 28.2 30.8 28.4 30.1 29.4 30.1
1 27.6 33.2 27.5 32.5 27.4 32.4
(Maximum burden according to the formula is 0.82)
Conclusion: No trend increase in operating time with lead burden, hence formula is
acceptable at this value of If and X/R.
Test 2:
If = 20 Shot1 Shot1 Shot2 Shot2 Shot3 Shot3
(min) (max) (min) (max) (min) (max)
X/R = 10
Burden
0 28.4 28.5 28.4 28.4 27.8 28.8
0.5 26.2 28.6 26.2 28.6 25.8 28.6
(Maximum burden according to the formula is 0.48)
Conclusion: No trend increase in operating time with lead burden, hence formula is
acceptable at this value of If and X/R.
150/HV0013 ENGINEERING REPORT
Page 24 of 24
6 December 2004
Test 3:
If = 10 Shot1 Shot1 Shot2 Shot2 Shot3 Shot3
(min) (max) (min) (max) (min) (max)
X/R = 40
Burden
0 29.6 31.2 29.5 30.8 28.8 30.5
0.1 28.1 28.9 27.6 28.6 26.9 28.6
0.2 29.9 32.7 29.8 32.5 29.4 32.1
(Maximum burden according to the formula is 0.19)
Conclusion: Only a slight possible trend increase in operating time with lead burden,
hence formula is acceptable at this value of If and X/R.
Test 4:
If = 20 Shot1 Shot1 Shot2 Shot2 Shot3 Shot3
(min) (max) (min) (max) (min) (max)
X/R = 40
Burden
0 24.1 26.5 23.5 27.5 24.3 27.4
0.2 26.2 27.2 24.8 26.9 25.6 27.4
0.4 28.4 28.8 28.1 28.6 28.2 28.8
0.6 26.5 27.2 26.6 27.2 26.2 27.2
0.8 25.6 28.4 25.2 27.9 25.6 27.9
1 28.8 31.2 28.2 30.7 28.5 30.8
(Maximum burden according to the formula is 1.00)
Conclusion: A slight trend increase in operating time with lead burden, hence formula
is acceptable at this value of If and X/R.
Overall, the use of the formula has been proven to be justified, both on the grounds of
through fault stability, and satisfactory internal operating times.
ENGINEERING REPORT 150/HV0013
Page 25 of 24
6 December 2004
3. CONCLUSIONS
In-depth analysis of the P540 CT requirement test results has allowed CT oversizing
K factors to be determined which allow more economical CTs to be used typically
20% lower than previously. Finding a formula which can be applied also allows
interpolation of the K factor at intermediate values of If and X/R.
Where:
Vk = Required IEC knee point voltage
K = Dimensioning factor
In = CT nominal secondary current
Rct = CT resistance
RL = One-way lead impedance from CT to relay