Académique Documents
Professionnel Documents
Culture Documents
1. Related Policy
2. Purpose
3. Scope
Although with Berma Procesys Corporation, some projects may be similar, each
project is actually unique as differences may occur e.g. in the deliverables
provided by the project, the stakeholders influencing the project, the resources
used, the way processes are adapted to create the deliverables, etc..
4. Project Phases
The Initial Phase begins the process of determining how the project will be
executed. Using the content in the Business Case as its foundation, the Initial
Phase has two outcomes:
The major activity in the Initiate Phase is the preparation of the Project Initiation
Document. The Project Manager, in consultation with key stakeholders, outlines
1
ISO 21500 Definition
the intended approach to project governance, executing work, and managing
resources and risk.
The Planning Phase of the project management process determines how the the
project will be executed. Using the Project Charter as its foundation, the planning
phase has two objectives:
It is sufficient to update
the budget information
provided in the Project
Initiation Document to
reflect any changes to
project budget.
4. Submit the Project Project Manager Scheduled and budget
Charter Document for information must be
approval of the additional approved by the Project
schedule and budget Sponsor
information
5. Develop a Risk Project Manager For small projects, the
Management Plan (for Business Case completed
medium and large in the Initiation Phase
projects) includes considerations of
project risks that have
been identified and the
risks of not doing the
project.
6. Prepare a Communication Project Manager
Plan (for medium and
large projects)
7. Develop a Quality Quality Assurance/Control
Management Plan Manager
8. Develop Procurement Procurement/Supply
Management Plan Chain Head-Manager
9. Prepare a Risk Register Project Manager The Risk Register should
(for large projects) be updated as required
through to the Close
Phase of the project.
1 Prepare an End of Phase Project Manager End of Phase Reports are
0. Report (for medium and used to provide an
large projects) update to the appropriate
governing body as
outlined in the Project
Initiation Document.
Once project approval is granted, there are two aspects to executing the project.
The first is the work done to create and deliver the project outputs, the second is
the work done to manage creation and delivery of the project outputs. Both are
essential to successful project execution. During execution, the project manager
will manage risks and issues; adhere to budget and notify any budget overruns to
the delegate; communicate regularly with stakeholders; manage and support the
team; report to governing bodies; review and rework the project management
plan; process change requests, and track and assess the project finances.
The Closure Phase is the formal closure of the delivery component of the project.
It has two main outcomes: