Vous êtes sur la page 1sur 5

Demolition of

post-tensioned concrete
Safe release of stored
energy requires a reverse
sequence of the original
construction procedures

ittle has been published

L about the demolition of post-


tensioned concrete but there
is enough such concrete now
in service to become a problem for
demolition contractors.
When a demolition sequence is
being planned it is important to
have a knowledge of the erection
p ro c e d u re and a set of the as-built
record drawings. This fact of life was
confirmed recently when 9 pre-
stressed beams had to be demol-
ished and extensive repairs made to
other beams within the decks of
bridges under construction for a
highway in England. Exact identifi-
cation of prestressing cables along
each beam was of great importance
in the demolition process and fun-
damental to the remedial stressing.
The bridges concerned were built
with 3-span continuous post-ten-
sioned segmental l-beams, with a
composite prestressed deck slab.
Each beam had been prestressed to The crack in this C segment extended in length and width after the
a load of about 750 tons. (1)* This ar- string course was complete. The crack follows the position of the
ticle describes how the beams were displaced upper cable duct. Bridge 35 west parapet beam.
severed and removed from the adja-
cent decks and discusses replace-
ment procedures briefly.

Construction details bankseats and piers, with two tem- foot(6) centers with a composite pre-
porary trestles supporting three seg- stressed deck slab 10 inches(7) thick.
An attractive design had been
ments in the main span. All seg- The two main cables, each con-
produced for ten 3-span overpasses.
ments were cast to suit a ve rt i c a l taining 19 high-strength strands of
With one exception, each had a cen-
curve of 7,000-foot(4) radius, but all 0.6-inch diameter(8) were winched
tral span of 121 feet(2) and end spans
straight grades and 3,000-foot(5) radii through the 4-inch-diameter(9) cor-
of 42 feet.(3) The main beams were
were accommodated by adjustment rugated ducts, which were designed
precast in five segments and erected
of the relative joint levels. to follow a continuously curved pro-
on their permanent bearings at the
A large range of deck widths was file. After connecting and sealing
* Numbers in parentheses refer to metric obtained in the various bridges by the cable ducts at the joints be-
equivalents listed with this article. using 3, 5, 6 or 8 beams at 6- to 7- tween segments, the gaps, nominal-
ly 4 inches,(10) were concreted at the
same time as the intermediate, pier
and end diaphragms.
Prestressing the cables was ac-
complished by pulling all 19 strands
simultaneously using double-end
stressing with identical prestressing
jacks of 500-ton (11) capacity. First-
stage prestressing consisted of ap-
plying a load of about 390 tons(12) to
the lower cables in each beam.
Cable extensions were checked at
each jack; for the standard length
bridge a total extension of about 14
to 15 inches(13) was recorded. The ap-
plied load caused the beams to lift
approximately 1 inch(14) at midspan
and made it possible to remove
t e m p o ra ry supports immediately.
The beams were fixed at one
bankseat and piers were hinged at
the base and pinned into the beams
so that the total elastic deformation
was allowed for at the sliding bear-
ings on the other bankseat.
Shortly after first-stage prestress-
ing, the deck slab was cast either in 3
bays or in a single operation, de-
pending on the width of the bridge.
The upper cables were subsequent-
ly stressed in a similar manner to
the lower group, but of course this
second stage of prestressing acted
upon the fully composite section.
The projecting lengths of high-
strength strands were trimmed back
close to the anchorage blocks, the
end recesses concreted and then
both cable ducts grouted with ordi-
nary portland cement, water and an
expanding agent to counteract
shrinkage.
The superstructure was complet-
ed by casting in place re i n f o rc e d
concrete string courses along the
edge of the parapet beams.

The cracking that led to


demolition
During prestressing operations
on the first three bridges completed,
a series of cracks was detected in the
central spans. Most cracks seemed
to start at the intermediate di-
aphragms and follow the line of the
cable ducts. At first these cracks
were not wide enough to warrant
much concern, but as a safety mea-
Cutting cables in the web at the north
intermediate joint of an internal beam
of Bridge 34 using a thermal lance.
South half of an A segment being lifted out by a 40-ton (36-metric-ton) crane.
One internal beam and both parapet beams were replaced in this deck, leaving
only two original beams in the final structure. Bridge 24.

The demolition method adopted Demolition of parapet beam


sure the next two bridges were pre- was to reverse the construction se- The first beam to be demolished
stressed in 50-percent and 25-per- quence by isolating the affected was the west parapet beam of
cent increments of final load to even beam and cutting it into the origi- Bridge Number 35. Grouting opera-
out any local effects. Initially there nal simply supported segments. tions had proved rather trouble-
was little cracking on these two These segments were split further some on this beam, so it was feared
bridges but as time passed cracks into half-lengths to ensure complete that there might be a number of
began to appear and grow in length. loss of prestress in the cables and to voids in the mid-span region which
The significance of these cracks provide convenient 15-ton(18) por- could lead to a violent release of the
was reassessed when a particularly tions for removal by crane. energy stored in the cables.
bad one on a parapet opened to 18 From the first three bridges, each The various positions at which
inch(15) in width shortly after the of which had been fully stressed and the deck slab, beams and main ca-
parapet was cast. X-ray radiographs grouted, five parapet beams and bles were cut and the typical man-
taken through the 10-inch-thick (16) three internal beams had to be de- ner of removal of a parapet beam
web revealed the upper cable duct molished. One parapet beam was are shown in the figure.
had floated some 18 inches(17) up- removed from the fourth bridge, but First the cast-in-place reinforced
ward from its design position. This it had only been constructed to the concrete string course was removed
discovery led to a systematic check point where the deck slab had been by breaking out a longitudinal slot
of all beam segments. cast after first-stage prestress. in the deck with heavy pneumatic
Te m p o ra ry supports were erect- hammers and burning through the
Demolition of fully ed under the condemned beams t ra n s verse reinforcement with
grouted beams and positioned at each end of the acetylene torches. Pieces of string
A major concern was to remove 10 half-segments. The intermediate course about 10 feet(19) long were
the condemned beams without sig- piers and areas below were protect- gently removed by holding them
nificantly damaging or alteri n g ed from falling pieces of concrete by with a crane while the last few trans-
s t ress conditions in adjacent means of scaffolding and timber verse bars were cut.
beams. When main cables were be- decking just below beam soffit level. The next step was to cut slots in
ing cut the sizes and lengths of all As a safety precaution, the immedi- the deck slab about 6 feet long(20) by
existing cracks on the remainder of ate bridge area was fenced off at 12 to 18 inches(21) wide over the posi-
the bridge were noted before, dur- ground level to channel the traffic tion of the intermediate di-
ing and after the demolition proce- below the bridge at well-defined a p h ra g m s. The slots were situated
dures. positions. close to the edge of the upper flange
so that the transverse deck steel the beam webs cracked heavily on the fully grouted beams. Even
could be cut with the maximum lap along the line of each duct but again though the lower cable was un-
length available for connecting into there was no instance of any beam grouted and the cable ends had not
the replacement beam. By bending concrete bursting away. been cropped off close to the end
this deck steel up into a vertical po- At midspan of C segment. Little blocks, destressing was not com-
sition access was given to the inter- energy remained in the cables after pletely straightforward.
mediate diaphragms from above. the first four major cuts so no obvi- The multistrand system could not
The diaphragms were then broken ous change occurred in the existing be detensioned with the 500-ton(11)
out with pneumatic hammers, leav- cracks in this segment. jack used for tensioning, so individ-
ing the bottom diaphragm steel to At midspan of B segments. Cut- ual strands were destressed by a
act as a flexible tie into the remain- ting the tendons at these positions small jack that could release the
ing deck and be reused with the re- caused some local increase in crack- wedges and allow their withdrawal.
placement beam. ing; the segments were cracked The additional friction between
The longitudinal slot in the deck along their entire length. strands required that forces up to 93
was extended adjacent to the beam At midspan of A segments. The percent of the ultimate strength of a
for its full length except for bridging end anchorages had re m a i n e d strand had to be applied before
pieces 30 inches(22) wide. These untouched so some energy still some wedges could be released.
pieces were left at about 8-foot(23) remained in these segments. This level of overstress is well above
and 12-foot(24) centers alternately, so Cracks developed throughout the the allowable limit of 77 percent of
that there were two restraining deck A segments along the line of the the ultimate tensile strength applied
slab ties to each half segment. cable ducts. during stressing operations. Conse-
Pier and end diaphragms were Once cable cutting was complet- quently the cable was no longer safe
broken out at virtually the same ed, each beam segment was divided for use and could not be incorporat-
time, with an effort again being at the cut position and lifting gear ed into the new beam.
made to leave the main diaphragm was attached to the half segments.
steel for reuse with the new beam. The remaining bridging pieces of Construction of
Then came the critical operation deck were then broken out so that replacement beams
of cutting the main cables; an acety- the segment could be lifted clear of The deck slab adjacent to the de-
lene torch was used on the first the supports. molished beams was trimmed back
beam. The cables were carefully ex- Although the effect of cutting the to provide a suitable 2-foot 6-inch
posed with small pneumatic ham- cables was undoubtedly transmit- (25)
minimum lap for the main trans-
mers, the intention being to cut out ted through the adjacent deck in the verse deck steel.
only a minimum amount of con- form of an impact force, no obvious Since pier positions were now
crete to gain access. signs of damage or worsening of fixed by the existing deck, new slid-
Prestressing cables were seve re d cracks were detected in other ing bearings were necessary at the
in a strict sequence as detailed on beams. The above procedure was piers to accommodate the relative
Section AA, which shows a half- t h e re f o re repeated for subsequent movements of the new beams dur-
length of a typical 3-span beam. parapet and internal beams, except ing stressing but no change in the
At pier diaphragms. As each cable that cable and concrete cutting was bearing type was required at the
was being burned the last few much improved with the use of a bankseats.
strands snapped with a sudden re- thermal lance. This eliminated te- The general reconstruction pro-
lease of energy and the cable ends dious exposure of the cables with cedure followed a pattern similar to
moved apart as the bond with the pneumatic hammers, speeded the that used for the original beams ex-
grout failed. The joints between A cutting sequence and allowed the cept for the following modifications.
and B segments opened out at the operator to stand well clear. Cables Joints between the beam segments
top as expected and the segments became hot only around the cutting were cast without completing the
rotated downward as continuity was position since it did not take long to diaphragm connections with the
lost over each pier. Longitudinal cut a cable. adjacent deck; the new deck slab
cracking appeared along the junc- Thus the cable tension did not was cast leaving a 6-inch (26) gap be-
tion of the web and upper flanges appear to relax significantly due to tween the old and new slabs, so that
on both sides of each pier but no expansion and a similar mode of vertical and horizontal movements
spalling of the concrete occurred. cracking was observed after each could freely occur in the new beam
At intermediate diaphragms. It sudden release of energy. during second-stage stressing; after
was obvious at these points that a waiting for a minimum period of 7
great deal of energy remained in the Demolition of ungrouted beam days to permit some further creep
cables, since substantial shocks The ungrouted parapet beam was and shrinkage movements to occur,
were heard and felt throughout the isolated from the adjacent deck in a the gaps in the deck and transverse
remaining deck. Simultaneously, manner similar to the method used diaphragms were finally concreted.
The results of tests performed af- 6. 1.8- to 2.1-metre 20. 1.8 metres
ter reconstruction had been com- 7. 250 millimetres 21. 300 to 450 millimetres
pleted indicate that both the demo- 8. 15.2 millimetres 22. 760 millimetres
lition and remedial stressing 9. 100-millimetre-diameter 23. 2.4-metre
p ro c e d u res used on these bridges 10. 100 millimetres 24. 3.6-metre
had been successful. 11. 455-metric-ton 25. 0.76-metre
12. 350 metric tons 26. 150-millimetre
13. 355 to 380 millimetres
Metric equivalents 14. 25 millimetres
1. 680 metric tons 15. 3-millimetre
2. 36.9 metres 16. 250-millimetre-thick
3. 12.9 metres 17. 460 millimetres PUBLICATION #C760256
4. 2100-metre 18. 13.6-metric-ton Copyright 1976, The Aberdeen Group
5. 910-metre 19. 3 metres All rights reserved

Vous aimerez peut-être aussi