Académique Documents
Professionnel Documents
Culture Documents
146
Table 1: Risk factors for project failure
Risk factor for project failure Significance in large Significance in small EMR
rjcs(to+)*
projects (0 to I I poet(to+)**
project (0 to I I+)~
Related to organization
1. Lack of commitment from upper management +++ 0
2. No clear statement of system objectives +++ 0
3. Lack of "project champion" ++ +++
4. Inability to gain end-user conmitment ++ ++
5. Inadequate technology infrastructure ++ ++
6. Difficulty working with "parent organization" 0 +++
Related to system developer or vendor
7. Inadequate technical skills of developer +
8. Failure of system developers to understand +++ +++
project requirements or scope
9. Turnover of developer project team members + +++
Related to communication
10. Unrealistic end-user expectations ++ ++
IL Ineffective communication among project +++ +
team and organization members
12. Insufficient user involvement in project design +++ +
and planning
*Based on number of citations from seven studies2'5'8"2-5 (0: noitations; +: <3 citations; ++: 3-4 citations;
+++: 5-7 citations)
Based on analysis of small departmental EMR system in this paper (0: no effect on project delay; +: minimal
contribution to delay; ++: moderate contribution to delay; +++: significant contribution to delay)
Documents were reviewed regarding the patient enterprise-wide medical information system,
volume and demographics of the group practice, the maintained by the Department of Medical
annual expenses and revenues of the group practice, Informatics, which integrates a clinical data
and the expenses associated with the EMR project. repository with administrative systems, research
databases, and billing systems'6. Several members of
Results: Analysis of the EMR Project the Department of Medical Informatics were included
on the project team for implementing this vendor
Factors contributing to the delayed implementation of EMR system. This was primarily to ensure that
this EMR system will be assessed and discussed appropriate interfaces could be developed by the
within the conceptual framework for risk factors of vendor to share patient financial and demographic
project failure, as shown in Table 1. data with the Columbia enterprise-wide databases.
No immediate plans were made to integrate clinical
Factors related to the organization data from the vendor EMR system with the Columbia
enterprise-wide repository.
Within this small specialty group, high-level
commitment to the EMR project (Factor 1 in Table) Although the vendor worked closely with both the
was very strong. The organization's requirements practice group and its parent organization, a delay
were specialized and well-defined, and the desired resulted from difficulty with installation of
objectives of this system were clearly expressed networking infrastructure into the office building
during the contract negotiation process (Factor 2). (Factor 5). An additional significant delay was
caused by the inability to develop an interface for
Several difficulties occurred during the process of transferring financial and demographic data between
integrating this EMR system into the larger the vendor system and the Columbia enterprise-wide
computing infrastructure of the group's "parent system. This was in large part because of failure to
organization," Columbia-Presbyterian Medical reach a consensus on the standards for data transfer
Center. This parent organization has an extensive (Factor 6).
147
organizational leaders are often separated from
Support among physicians within the group practice project managers by several intermediate layers of
was initially high. However, during the two-year management, and therefore may be less directly
implementation process, increasing resistance toward involved with the project management process5''3.
the EMR system began to develop. Several In contrast, project team leaders in small groups
physicians felt satisfied with the existing paper-based typically work much more closely with upper
record system and became skeptical about the EMR management, as was the case in this project.
(Factors 4 and 10). There was no end-user "project Therefore, it is not surprising that the risk factors
champion" to support the new system within this involving organizational commitment and objectives
small group (Factor 3). were much less important in this small EMR project
than is typically seen in larger projects.
Factors related to the system developer
Furthermore, the classic large-project risk factors of
The vendor was a small organization whose "ineffective communication" and "insufficient end-
prototype product was based on a system that had user involvement in project planning" were not
been voted "best EMR" at a major national important in causing delay of this small EMR project
conference. The vendor project team possessed (Factors 11 and 12). Traditional software
excellent technical capability and knowledge (Factor engineering methodology has emphasized these
7). However, they had never implemented an EMR issues by focusing on management, reporting,
system for this specialty domain. They therefore communication, and the separation of roles.
pursued a difficult, iterative process of soliciting However, the limited size of small organizations and
knowledge and suggestions from group physicians to projects inherently facilitates communication among
better understand project requirements (Factor 8). team members, often without these formalized
This process was further delayed by turnover of techniques. An implication for developers of small
several project team members (Factor 9). medical information systems is that the traditional,
communication-intensive software engineering
Factors related to communication approach may require more administrative overhead
than can be sustained by small organizations".
Communication between the vendor and group
practice was facilitated by the relatively small size of It is also important to note that the vendor in this
both groups (Factors 11 and 12). Most project team project encountered significant problems while
members worked closely together. However, the working with the "parent organization" of the group
requirements of this particular project demanded that practice, Columbia-Presbyterian Medical Center
a large amount of domain knowledge be transferred (Factor 6). Delays were caused by difficulties with
from the group to the vendor. installing appropriate network infrastructure, as well
as difficulties with reaching agreement about
Discussion standards for data transfer between the vendor EMR
system and the Columbia enterprise-wide clinical
While factors contributing to project failure in large information system. Similar problems have not been
and small organizations share some attributes, there frequently reported in the literature for large-scale
are important differences. Risk factors that have projects, most likely because these large projects
been shown to be important in large-scale projects usually do not fall under the control of a larger parent
such as lack of a project champion (Factor 3), organization. In contrast, small medical groups
inability to gain end-user commitment (Factor 4), and usually do not have their own information technology
failure of system developers to understand project groups, and often must be supported by a hospital-
requirements (Factor 8) did contribute significantly to wide IT department that will not necessarily have the
the difficulties with this small-scale EMR project. same underlying goals and commitment to the
project. Smaller medical groups will benefit from
One significant difference is that lack of commitment securing this commitment and technical support from
from upper management is typically cited as the most their parent organizations before undertaking
significant risk factor for failure of large projects8 information system project implementation.
(Factor 1). This problem did not at all contribute to
delays in this case study of a small project. Likewise, Finally, the risk factor of "turnover of developer
the "lack of clear statement of system objectives" project team members" is only rarely cited in the
was not factor in this EMR project (Factor 2). A literature on large-scale project failures (Factor 9).
possible explanation for these differences is that large Yet it was among the most significant causes of the
groups are sufficiently complex that upper-level delays in this small-scale EMR implementation. It is
148
reasonable to hypothesize that stability of the project 5. Ewusi-Mensah K. Critical issues in abandoned
team may be most significant for small-scale information systems development projects. Comm
projects, since individual team members will have ACM 1997; 40: 74-80.
bigger roles in these smaller projects.
6. Brooks, FP. The mythical man-month: Essays on
It is critically important for medical information software engineering. Anniversary edition. Boston:
system developers to identify projects whose Addison-Wesley; 1995.
characteristics place them at high risk for failure. In 7. Abe J, Sakamura K, Aiso H. An analysis of
this paper, we have presented a framework for software project failure. In: Proceedings of the 4th
understanding the risk factors in small-scale medical International Conference on Software Engineering;
informatics projects, and have contrasted them with 1979 Sep 17-19; Munich, Germany. Washington,
those seen in larger-scale projects. The problems DC: IEEE Computer Society; 1979. p. 378-385.
with the small EMR system described in this paper
are currently being addressed, for example by 8. Keil M, Cule PE, Lyytinen K, Schmidt RC. A
designating a "project champion" with affiliation to framework for identifying software project risks.
the medical organization as well as the Columbia Comm ACM 1998; 41: 76-83.
information technology department. It is too early to 9. Glass RL. Short-term and long-term remedies for
determine the outcome of this scenario. runaway projects. Comm ACM 1998; 41: 13-15.
Of course, it is not sufficient to recognize troubled 10. Oz E. The Confirm failure and its lessons.
projects. The reality is that these often become Comm A CM 1994; 37: 29-36.
"runaway projects" because they continue to be
supported by an escalating commitment of personnel, 11. Laitinen M, Fayad ME, Ward RP. The problem
money, and other resources'7. Explanations for this with scalability. Comm A CM 2000; 43: 105-107.
phenomenon are related to financial factors such as 12. Sumner M. Critical success factors in enterprise
sunk costs and low salvage value of incomplete wide information management systems projects. In:
projects, social factors such as the association of Prasad J. Proceedings of the 1999 ACM SIGCPR
persistence with strong project leadership, and Conference; 1999 Apr 8-10; New Orleans, Louisiana,
organizational factors such as the difficulty of USA. New York: ACM Press; 1999. p. 297-303.
overcoming administrative inertia to disrupt existing
project plans'8. By understanding the risk factors 13. Sumner M. Risk factors in enterprise wide
associated with project failure, the role of scalability, information management systems projects. In: Nance
and the most appropriate response to difficulties that W. Proceedings of the 2000 ACM SIGCPR
arise, the developers of small medical information Conference; 2000 Apr 6-8; Evanston, Illinois, USA.
systems will maximize the likelihood of successful New York: ACM Press; 2000. p. 180-187.
project implementation. 14. Boehm BW. Software risk management:
Principles and practices. IEEE Software 1991; 3:
32-41.
References 15. Lucas HC. Information technology and the
1. Wiederhold G, Shortliffe EH. System design and productivity paradox. Assessing the value of
engineering. In: Shortliffe EH, Perreault LE, editors. investing in IT. New York: Oxford University Press;
Medical informatics: Computer applications in 1999.
health care and biomedicine. Second edition. New 16. Hripcsak G, Cimino JJ, Sengupta S. WebCIS:
York: Springer-Verlag; 2001. p. 180-21 1. large scale deployment of a Web-based clinical
2. Mahaney RC, Lederer AL. Runaway information information system. Proc AMIA Symp 1999;; 804-
systems projects and escalating commitment. In: 808.
Prasad J. Proceedings of the 1999 ACM SIGCPR 17. Brockner J. The escalation of commitment to a
Conference; 1999 Apr 8-10; New Orleans, Louisiana, failing course of action: Toward theoretical progress.
USA. New York: ACM Press; 1999. p. 291-296. AMR 1992; 17: 39-61.
3. Pinto JK, Slevin DP. Project success: 18. Staw BM, Ross J. Knowing when to pull the
Definitions and measurement techniques. Project plug. Harvard Business Review 1987; 65: 68-74.
Management Journal 1988; 19: 67-72.
4. Keil M, Robey D. Blowing the whistle on troubled
software projects. Comm ACM 2001; 44: 87-93.
149