Activities Summary

-----End of February

ELECTRICAL WORKS:- (as on 28.02.2017)


Building Building Building
S. No Activity Description
No.1 No.2 No.3
1 Slab Conduiting %20 %20 %20
2 Marking on Blockwall 10% 10% %10
3 Cutting & Chasing works 5% 5% 5%
4 Conduit piping 5% 5% 5%
5 Distribution Board & back boxes (I.G) Fixing 0% 0% 0%

MARCH (1st Week)


Activities Planned for the Week (01.03.17 to 08.03.17)

Building Building Building


S. No Activity Description
No.1 No.2 No.3
1 Slab Conduiting %50 %50 %50
2 Marking on Blockwall 30% 30% 30%
3 Cutting & Chasing works 10% 10% 10%
4 Conduit piping 20% 20% 20%
5 Distribution Board & back boxes (I.G) Fixing 10% 10% %10

MARCH (1st Week)


Activities Completed for the Week (01.03.17 to 08.03.17)

Building Building Building


S. No Activity Description
No.1 No.2 No.3
1 Slab Conduiting %40 %40 %40
2 Marking on Blockwall %40 %40 %40
3 Cutting & Chasing works 20% 20% 20%
4 Conduit piping 18% 18% 18%
5 Distribution Board & back boxes (I.G) Fixing 15% 15% %15
MARCH (2ND Week)

Activities Planned for the Week (09.03.17 to 16.03.17)


Building Building Building
S. No Activity Description
No.1 No.2 No.3
1 Slab Conduiting %60 %60 %60
2 Marking on Blockwall %50 %50 %50
3 Cutting & Chasing works 30% 30% 30%
4 Conduit piping 30% 30% 30%
5 Distribution Board & back boxes (I.G) Fixing 30% 30% 30%

MARCH (2ND Week)

Activities Completed for the Week (09.03.17 to 16.03.17)


Building Building Building
S. No Activity Description
No.1 No.2 No.3
1 Slab Conduiting
2 Marking on Blockwall
3 Cutting & Chasing works
4 Conduit piping
5 Distribution Board & back boxes (I.G) Fixing