Vous êtes sur la page 1sur 10

ACI 309.

3R-92
.

Guide to Consolidation of
Concrete in Congested Areas (Reapproved 1997)
Reported by ACI Committee 309

Mikael P. J. Olsen, Chairman


Dan A. Bonikowsky* Steven H. G e b Sandor Popovics
Neil A. Cumming Gary R. Mass Thomas J. Reading
Timothy P. Dolen Richard E. Miller Jr. Donald L. Schlegel
Jerome H. Ford Roger A. Minnich Bradley K. Violetta
Joseph J. Fratianni H. Celik Ozyildirim

*Subcommittee chairman.
Originating committee chairman.
*Subcommittee members.
Steven A. Ragan actively contributed to the development of this document
and served as chairman of the editorial committee.

This guide is primarily directed toward architects/engineers and con- 3.4-Mix proportioning
structors. It describes various situations where design requirements 3.5-Concrete placing methods
result in highly congested forms that impede consolidation of con- 3.6-Construction considerations
crete. Techniques to overcome these difficulties are presented. The 3.7-Tunnel linings
guide also identifies for constructors various difficult placing and
consolidation conditions and proposes solutions such as special pro-
cedures and mix proportions. In addition, the guide alerts construc- Chapter 4-Consequences of congested areas in concrete
tors to review design drawings closely where congested areas are ex- construction, pg. 309.3R-4
pected to insure that appropriate allowances have been included in 4. l-Honeycombed concrete
their bids. 4.2-Reduced density
4.3-Increased cleaning costs
Keywords: admixtures; concrete construction; consolidation; embedment; 4.4--Increased formwork costs
formwork (construction); mix proportioning; parting agents: placing; pre- 4.5-Increased placing costs
placed aggregate concrete; reinforced concrete; reinforcing steel; splicing;
structural design; surface defects; tunnel linings.
Chapter 5-Recommended practices, pg. 309.3R-6
CONTENTS 5.1 -Design considerations
Chapter l-Introduction, pg. 309.3R-1 5.2-Construction considerations
5.3-Summary
Chapter 2-Criteria for designation as a congested area,
pg. 3093R-2
2.l-Reinforcing steel Chapter 6-References, pg. 309.3R-9
2.2-Embedments and boxouts 6.1 -Specified and/or recommended references
2.3-Formwork 6.2-Cited reference
2.4-Definitions
CHAPTER 1--INTRODUCTION
Chapter 3-Factors contributing to congestion problems, Many concrete structures such as those with seismic
pg. 309.3R-3 provisions, post-tensioning, and high-strength concrete
3.l-Reinforcing steel arrangement are difficult to consolidate because of congested areas
3.2-Embedded parts/boxouts within the formwork. This congestion can result in
3.3-Formwork

ACI Committee Reports, Guides, Standard Practices, and


Commentaries are intended for guidance in designing, plan-
ning, executing, or inspecting construction and in preparing
ACI 309.3R-92 became effective December 1,1992.
specifications. Reference to these documents shall not be made Copyright 0 1992, American Concrete Institute.
in the Project Documents. If items found in these documents AU rights reserved, including rights of reproduction and use in any form or by
are desired to be part of the Project Documents, they should any means, including the making of copies by any photo process, or by any elec-
be phrased in mandatory language and incorporated into the tronic or mechanical device, printed, written, or oral, or recording for sound or
Project Documents. use in any knowledge retrieval system or device, unless permission is obtained in
writing from the copyright proprietors.

309.3R-1
ACI COMMlTTEE REPORT

Fig. 1 -Dense reinforcing steel Fig. 3-Closely spaced embedments

CHAPTER 2-CRITERIA FOR DESIGNATION AS


A CONGESTED AREA
Congested areas are those in which the reinforcing
steel, embedments, boxouts, prestress ducts and an-
chorages, or configurations and form shape make con-
crete placement and consolidation difficult to achieve.
To obtain the desired placement results and degree of
consolidation, access for inspection and consolidation,
special concrete mixtures, special formwork, additional
consolidation effort, and specific placing methods are
frequently used.

2.1-Reinforcing steel
Congestion causes problems when the clear spacing
between reinforcing bars or between a bar and the form
is less than 1 l1/3 times the maximum size of coarse ag-
gregate used in the concrete mixture. This condition is
more likely to occur at splices and bends in reinforce-
ment and at beam-column connections. Sometimes,
congestion is caused by multiple layers of reinforce-
ment in which the bars in the lower layers are not di-
rectly below those in the upper layers, as shown in Fig.
1 and 2. See A CI 117 for tolerances for concrete con-
struction and materials.
Fig. 2-Dense reinforcing steel
2.2-Embedments and boxouts
structural inadequacy and time-consuming and expen- Embedments consist of items such as plumbing,
sive remedial work. prestress hardware, ducts, connection inserts, and an-
Various techniques have been employed to alleviate chorages for handling devices that are cast into the
this type of problem. This document presents an over- concrete (see Fig. 3). Boxouts are used to form open-
view of the factors contributing to the problem, the ings, keyways, or pockets in the concrete. When these
consequences of inappropriate concrete procedures in items restrict the placement and consolidation of the
these areas, and recommended practices to minimize concrete, they cause congestion. The spacing between
the problem. embedments, boxouts, and the form must be at least
As a prerequisite to successful concreting in con- 1% times the nominal maximum size of the coarse ag-
gested areas or difficult placing conditions, it is impor- gregate to avoid this problem. Frequently, these items
tant that architects/engineers become more aware of cause congestion because the concrete cannot be placed
how their designs will be constructed, and that con- and consolidated easily underneath them (see Fig. 4).
structors become more aware of special procedures and The architect/engineer must be alert to such condi-
necessary precautions. Most importantly, communica- tions, and construction procedures must provide for
tion between the architect/engineer and constructor is proper placement and consolidation of concrete on the
essential to insure that the design details, construction undersides of these embedments.
materials, and procedures are compatible. 2.2.1 Embedments may be anchors, weld plates, me-
GUIDE TO CONSOLIDATION OF CONCRETE

chanical and electrical boxes, threaded inserts, or other


devices used to attach or incorporate items after form-
work is removed.
2.2.2 Sleeves are openings that generally go all the
way through a wall or slab to allow piping or other
penetrations to pass. Formwork for these openings is
often completely removed prior to piping placement.
2.2.3 Boxouts are either removable or stay-in-place.
Removable boxouts are similar to sleeves but generally
are much larger, as in door and window boxouts or
hatch boxouts in slabs. Most removable boxout forms
can be adapted readily for placement and vibration
tubes, as described in Section 5.1.2. If these removable
forms are not provided, the constructor must move the
concrete horizontally under the formed boxout, which
usually results in segregation of the concrete, adds ad-
ditional stress to the boxout form, allows the buildup
of frictional resistance along the formwork, and slows
down the entire placement. Without placement and vi-
bration tubes, the degree of consolidation is generally
reduced under a boxout. Boxouts often are designed
with open bottoms.
Stay-in-place boxout forms, such as hollow metal
door and window frames, often require bracing and do
not allow placement and vibration tubes to be cut
through them. This increases the chances of voids or Fig.4--Stacked boxouts
incomplete consolidation.
2.2.4 Formwork accessories, architectural items such purchased in 4- or 5-m. (100- or 125-mm) diameter by
as cast-in numbers and letters, form liners, rustication, 300-ft (92-m) long rolls.
chamfers, and keyways can cause simple to complex 2.4.3 Side ports-Side ports are temporary openings
consolidation problems in one manner or another. This in the form on one side of narrow walls. The purpose
is especially true of horizontal rustication or keyways in of the side ports is to allow insertion and extraction of
a wall. vibrators and to observe consolidation of the concrete.
2.4.4 Slide valve-A slide valve is a short piece of
steel pipe with a slide plate mounted in it. The pipe is
the same diameter as the concrete discharge hose and
2.3- Formwork the other end is bolted to the form. The purpose is to
The surface texture, shape, type, and orientation of allow pumping of concrete through the open slide valve
the formwork may restrict concrete placement. Consid- to completely fill a form to the underside of a horizon-
eration needs to be given to form release agents that are tal structural steel beam. When the form is full, the
compatible with form texture, particularly if intricate slide plate is closed, preventing the concrete from seep-
shapes are to be cast into the concrete at the formed ing back through the valve.
surface. These release agents may also serve to some- 2.4.5 Steel reinforced hose-Steel reinforced hose is
what reduce the frictional resistance between the plastic a rubber concrete-discharge hose reinforced with
concrete and the form, thereby improving the ease of strands of steel wire between the tube and outer cover.
removing entrapped air. The forms must also be de-
signed for easy removal. CHAPTER 3-FACTORS CONTRIBUTING TO
Used or poorly oiled wood forms are more likely to CONGESTION PROBLEMS
hinder consolidation than steel or plastic-lined forms. 3.1 -Reinforcing steel arrangement
The frictional resistance of a wood form impedes the The reinforcing steel arrangement must take into ac-
flow of concrete and can create difficulty when used i n count the factors that contribute to congestion. Seismic
conjunction with congested embedments. and strength design requirements often result in a rein-
forcing steel layout that inhibits access for preplace-
2.4-Definitions ment cleanup and concrete placement and consolida-
2.4.1 External form tie rods-External form tie rods tion. Recommended practices are described in Chapter
are installed on the outside of narrow wall forms in the 5.
longitudinal direction. The tie rods are attached to the 3.1.1 Splices-The density of reinforcing steel result-
bulkhead walers at the ends of the wall. ing from current design procedures often makes it dif-
2.4.2 Lie-flat hose-Lie-flat hose is a very pliable ficult to provide continuity of reinforcing bars by the
polyvinyl chloride reinforced discharge hose, typically traditional method of lap splices. The various methods
309.3R-4 ACI COMMITTEE REPORT

of splicing reinforcing bars, as discussed in Section ered in selecting the best method for getting the con-
5.1.1.1, need to be considered by the architect/engi- crete to its final consolidated state (see ACI 304R).
neer .
3.6-Construction considerations
3.2-Embedded parts/boxouts
Design considerations should include construction
There is increasing use of embedments and boxouts
to incorporate piping and electrical and mechanical methods and should not be solely limited to the re-
systems into placements. The use of embedments and quirements in the design code and specifications. The
design of heavily congested areas can have serious im-
boxouts, in conjunction with dense reinforcement, of-
ten results in congestion that inhibits acceptable plac- pact on quality, construction costs, and constructabil-
ity.
ing and consolidation practices.
3.2.1 Tolerances for placement of concrete around Best results are achieved when the architect/engineer
embedments and boxouts should be considered at the works closely with the constructor to insure that the in-
tent of the design can be met under field conditions.
design stage. Frequently, mechanical and electrical em-
bedments are located adjacent to doors and windows.
These areas usually require additional reinforcing due 3.7-Tunnel linings
to stress concentrations around the boxout. The core The concrete lining of tunnels is a difficult operation
area in buildings is another example where additional due to the logistics of concrete transportation and lim-
reinforcement, embedments, and boxouts cause con- ited access for concrete placement and consolidation.
gestion. Congestion can be caused by temporary support mem-
bers, reinforcing steel requirements, and grouting pipes.
3.3- Formwork Heavily reinforced concrete tunnel linings have become
The design of formwork can contribute significantly more common in the 1980s.
to congestion in placements if the design does not take Best results are obtained with a plastic concrete mix-
into account other factors, e.g., location of embed- ture that has been proportioned to flow readily along
ments and boxouts, reinforcing steel arrangements, form sidewalls, yet remain cohesive. Ample openings of
placing equipment, and form-tie spacing. sufficient size must be provided in the formwork for
The design should consider the number, location, access by workers to consolidate concrete with immer-
and size of form-tie rods; location of embedments and sion-type vibrators and for inspection as the work pro-
blockouts; location of trunks or concrete hose; height gresses. Larger reinforcing bars at increased spacing is
of forms; and possible use of side ports. In narrow, preferred to smaller, more closely spaced bars to pro-
congested walls, external form-tie rods should be con- vide maximum access. Where heavily reinforced sec-
sidered. Reduced spacing of wales leads to an increased tions are essential, the concrete lining thickness should
number of form ties, resulting in added congestion. In- be increased to allow room behind the form for work-
creased spacing of load-bearing members with higher ers. The cost of the additional concrete volume due to
capacity ties and form sheathing can ease congestion. increased thickness often can be offset by a higher
3.3.1 More concentrated vibration may be needed in quality lining. In general, 14 to 16 in. (356 to 406 mm)
congested areas. Since this may result in increased hy- clear distance is required between the reinforcement
drostatic head during placement, this should be taken and ground excavation lines.
into account in the formwork design. Allowance must be made for temporary steel sup-
ports that may interfere with access. The placement of
3.4-Mix proportioning concrete in heavily reinforced sections can also be im-
The advantages of a large maximum size aggregate proved by bundling reinforcing bars into groups of two
concrete can quickly be lost if the mix proportioning or three bars to increase spacing. When encasing per-
does not take into account the congestion existing in the manent steel plate liners in underground work, it is es-
proposed placement. sential to provide adequate concrete thickness for ac-
The use of modified mix proportions with smaller cess by workers during concreting.
maximum size aggregate is becoming a necessary tool to
achieve proper consolidation in certain congested areas
of a placement. The modified mixture may also include CHAPTER 4-CONSEQUENCES OF
admixtures, increased cement content, and fly ash. CONGESTED AREAS IN CONCRETE
The modified mixture need only replace the original CONSTRUCTION
mix proportions in the zones of extreme congestion, 4.1 -Honeycombed concrete
e.g., around multiple embedments, boxouts, or dense Honeycombed concrete can occur in congested areas
reinforcement configurations. due to the inability of vibrators to consolidate the con-
crete around and through the congestion and out to the
3.5-Concrete placing methods form face. There are several primary reasons for hon-
The constructor must assess whether traditional con- eycombed concrete.
crete placing methods will be adequate in congested ar- l The nominal maximum size aggregate may be too

eas. The conditions of the placement must be consid- large to pass through the clearances provided, result-
GUIDE TO CONSOLIDATION OF CONCRETE 309.3%5

Fig. 5-Side ports in wall form Fig. 6-Lie-flat hose viewed through side port

ing in bridging of aggregate particles and blockage of 4.4-Increased formwork costs


flow. A harsh mix may also cause bridging and thus Congested placements can lead to additional form-
block flow. work costs when form design changes are required to
The densely placed reinforcing steel or embedded minimize consolidation problems.
parts may prevent access for the vibrator to complete It may be necessary to increase the form-tie spacing
consolidation in these congested areas. to reduce the number of form ties passing through a
Extension of vertical reinforcement above the form- form. Stronger form faces, walers, and strongbacks are
work in heavily congested forms can restrict the required to accomplish this.
lateral movement of workers. This restriction of In short narrow walls, bulkhead ties may need to be
movement can lead to operator fatigue and result in placed outside the form to prevent the longitudinal
incomplete consolidation of the concrete. form ties from interfering with concrete consolidation.
It also may be necessary to install side ports, as
shown in Fig. 5, for observation and consolidation
purposes. If lie-flat hose is used for placement, it can
4.2-Reduced density be conveniently cut off and removed through the side
Proper density of in-place concrete is dependent ports (see Fig.6). As the concrete reaches the level of
upon adequate consolidation. Incomplete consolida- the side ports, the ports are closed and secured by bolt-
tion will lead to excessive amounts of entrapped air. ing or nailing them to the main form walers. Congested
This entrapped air causes reduced strength and in- areas within forms may require that embedded parts be
creased permeability and can also decrease bond of supported from a framework spanning the top of the
concrete to the reinforcement. formwork. This reduces the need to install stiffeners
Large or numerous embedded parts can result in un- and positioning supports in an already congested form.
der-consolidation on the undersides of these parts, cre-
ating air pockets. Unless corrective action is taken, ad- 4.5-Increased placing costs
equate consolidation may not be achieved. Congested regions of reinforcing steel, primarily due
to increased seismic requirements, have resulted in
steadily increasing concrete placing costs.
4.3-Increased cleaning costs Placing methods are being modified due to increased
Congestion within forms can lead to significant ad- form congestion and the reduction of clearances avail-
ditional costs for clearing the formed space of debris. able to get concrete to its final location.
Construction materials left behind during form build- The use of cranes and buckets in conjunction with
ing; reinforcing steel installation; and setting of em- hoppers and trunks is often not possible due to the
bedded parts, boxouts, cableways, and pipes create se- space restrictions in forms. Placing methods for con-
rious cleaning problems. crete are now frequently planned as independent oper-
Debris in the bottom of the placement area cannot be ations to avoid using crane time for such activities as
blown across from one end to the other due to block- placement of forms, reinforcement, and embedded
age by the reinforcement; therefore, cleaning costs are parts.
increased due to the need to clear the form in several Concrete pumps are available with boom lengths ex-
isolated cells. The time required for hand removal of ceeding 200 ft (60 m). Concrete also can be pumped
debris is substantially increased because workers must through stationary pipelines hundreds of feet long and
continuously climb in and out to cover the total area of then placed with a placing boom at the end of the line.
the placement. The constructor can attach steel reinforced rubber
309.3R-6 ACI COMMITTEE REPORT

cient room is provided for placement.


In extreme cases, it may be necessary for the ar-
rangement to include accessways through the reinforc-
ing steel.
5.1.1.1 Reinforcement splicing methods-Until the
late 197Os, most reinforcing steel arrangements pro-
vided for lapping reinforcing steel bars without causing
undue congestion problems. More stringent seismic re-
quirements have resulted in a dramatic increase in the
amount of reinforcing steel per unit area, especially at
beam and column connections.
Lapping the bars would cause such severe congestion
that space between bars would almost disappear, re-
quiring a change to splicing.
Sometimes this congestion problem associated with
splicing can be solved by mechanically connecting the
Fig. 7-Lie-flat hose coupled to concrete line reinforcing bars, as described by ACI 439.3R. In spe-
cial cases, the reinforcing bars may be spliced by
welded connections, provided that proper welding pro-
cedures are used considering the metallurgy of the re-
inforcing steels being joined. However, with either a
mechanical or welded connection, there will be some
localized increase in the reinforcement diameter, which
should be considered in detailing clearances and bar
spacing.
5.1.2 Embedded parts/boxouts-Embedment, sleeve,
and boxout configuration should consider reinforcing
details, concrete mix proportions, and especially the
nominal maximum size of aggregate. If possible, em-
bedments should be spread out.
Void forms should be used to eliminate form pene-
trations, but if they are large [more than 2 ft (0.6 m) in
either direction], a placement and vibration tube (see
Fig. 8) should be provided.
Boxouts that remain in place should have tolerances
to allow them to be shifted and placement and vibra-
tion tubes should be provided. Boxouts that are to be
Fig. 8-Placement and vibration tubes: Large blockout
within a wall with pipes through the formed blockout removed and exceed 2 ft (0.6 m) in either direction also
to permit access for concrete placement and vibration should provide placement and vibration tubes.
In situations where the boxout spans from one form
face to the other, access should be provided through the
hose up to 5 in. (125 mm) in diameter and 30 ft (9 m) bottom of the boxout. As the concrete reaches the bot-
long to the end of the pump boom to get concrete to tom of the boxout, the access can be closed off with a
the point of deposition. Fragile lie-flat hose is often re- preformed insert, which is then bolted to the boxout
quired at the end of the rubber hose to get past extreme form.
congestion (see Fig. 7). 5.1.3 Placing-The constructor must assess whether
Where it is not possible for the vibrator operator to his traditional placing methods will be adequate for the
insert the vibrator all the way to the bottom of wall job. Bidding merely on the total volume, average
forms, the constructor should install side ports in the placement size, and known project access conditions
form to allow lowering the vibrators through these can result in reduced profit margins. The constructor
ports. must review reinforcing steel, embedment, and form-
work drawings to tailor the placing methods to suit the
conditions. The constructor may need to request
CHAPTER 5-RECOMMENDED PRACTICES changes in the design of the placement or formwork to
5.1 -Design considerations obtain a quality product at a reasonable cost.
5.1.1 Reinforcing steel arrangement-Arrangement Increased cooperation between the architect/engi-
of reinforcing steel should provide enough space to al- neer and constructor prior to beginning work will facil-
low concrete placement into the form. The architect/ itate quality construction. Prebid and preconcreting
engineer may have to increase the member size over meetings to discuss all phases of the concrete work are
that required. by the design calculations so that suffi- encouraged.
5.2-Construction considerations mum size aggregate of 3/4 in. (20 mm) for extremely
5.2.1 Use of admixtures-Proper placement of con- congested areas, the architect/engineer may allow sub-
crete in congested areas usually requires the concrete to stitution of a portion of the placement with nominal
have flowing characteristics. Flowing concrete is gen- maximum sized aggregate of 1/2 in. (13 mm). When the
erally considered to have a slump of 7% in. (190 mm) maximum aggregate size of a specified mix is reduced,
or more, while remaining cohesive without excessive the mix has to be modified by adjusting the water and
bleeding or segregation (ACI 309R). The use of such cement content to maintain the water-cement ratio and
material permits placement and consolidation in areas design strength. Some specifications also allow the ad-
where less workable concrete mixtures cannot be prop- dition of fly ash to enhance workability. Typically, an
erly placed and consolidated due to lack of mobility addition of fly ash equal to 5 percent of the cement
and vibrator access. weight will provide excellent lubrication. At times, up
Flowing concrete is commonly used in congested ar- to 30 percent is allowed.
eas where the member itself is unusual in shape or size 5.2.3 Formwork-Formwork design should be based
or a large amount of reinforcement is present. on full hydrostatic head conditions wherever practical.
Since producing flowing concrete only by adding ex- Form-tie locations need to be considered when choos-
tra water results in lower quality concrete, such con- ing a form system and are often fixed in liquid head
crete should be obtained through the use of chemical forms. Full hydrostatic head forms often have large ties
admixtures. Admixtures used to achieve flowing con- [l-in. (25-mm) diameter or greater] and require place-
crete should meet the requirements of ASTM C 494 and ment, pockets and cleanouts. Bulkhead design should
ASTM C 1017. Commonly used materials for produc- also consider full hydrostatic head. If longitudinal ties
ing flowing concrete include: or special corner ties are required, external ties should
1. High-range water-reducing admixtures (superplas- be considered. Formwork accessories such as rustica-
ticizers), ASTM C 494, Types F or G. tion, chamfers, and keyways should be considered in
2. A combination of high-range water-reducing ad- reinforcement details, mix proportions, and placement,
mixtures plus a water-reducing and retarding admix- as well as consolidation.
ture, ASTM C 494, Type D, or water-reducing and ac- In general, formwork design should follow the prac-
celerating admixture, ASTM C 494, Type E. tices and guidelines presented in ACI 303R and ACI
3. High dosages of a water-reducing normal-setting 347R. Careful consideration should be given to areas of
admixture, ASTM C 494, Type A, plus a water-reduc- congested reinforcement or other embedments. In ar-
ing and accelerating admixture, ASTM C 494, Type E. eas of heavy congestion, concentrated vibration is likely
Where flowing concrete is required, trial mixtures to occur that can increase the hydrostatic pressure on
should be tested with materials representative of those the forms. When needed, the spacing of load-bearing
to be used in the project and under the environmental members should be increased and combined with higher
conditions expected on the project. Trial mixtures capacity ties and sheathing. The use of external tie rods
should be made using the initial slump resulting from in narrow congested walls also can help reduce the con-
the maximum allowable specified water-cement ratio. gestion. When vertical access to the forms from the top
Chemical admixture dosages can be varied to achieve is limited and internal chutes cannot be used, side ports
the desired slump range. If necessary, the initial slumps should be incorporated to allow for the placement of
can be reduced by lowering the water-cement ratio and the concrete and consolidation by internal vibration.
thus improving the hardened properties of the con- Battered form faces or counterforts generally result
crete. Excessive retardation and loss of air content in areas of poor consolidation due to the problems of
should be avoided. placement, vibrator access, and restricted air migration
5.2.2 Use of modified mixtures (ACI 211.1 and during vibration. The additional concrete required for
211.2)-Normally, architects/engineers will specify the a vertical rather than sloped face may be highly cost-
largest nominal maximum size aggregate mixtures that effective if required repair of the formed surface is sig-
are readily available and can be consolidated by con- nificantly reduced.
ventional placing methods. However, the need to meet Corbels and haunches generally are areas of conges-
stringent seismic requirements has led architects/engi- tion. Similarity of shape and position can reduce form-
neers to make provisions in the specifications to use work costs.
smaller maximum size aggregate for some placements 5.2.4 Consolidation methods--Congestion is forcing
or portions of placements. The architect/engineer architects/engineers to take into consideration the con-
should consider this substitution based on the degree of struction aspects of placing and consolidating quality
congestion of reinforcing steel or embedded parts. concrete. Some reinforcing steel arrangements are in-
As an example, when the concrete is specified with a corporating openings to provide access for cleaning,
nominal maximum size aggregate of 1 l/2 in. (40 mm), placing, and consolidation. Fig. 5 shows designed-in
the architect/engineer may allow for substitution of a accesses in a heavily reinforced wall section.
portion of the concrete (in practice about 20 to 30 per- All aspects of the consolidation operation in con-
cent) with %-in. (20-mm) nominal maximum size ag- gested forms should be well planned prior to start of
gregate (Bonikowsky). the concrete placement. Smaller size vibrators may be
Where the design mixture specifies nominal maxi- used in the lower areas within the forms when a high-
309.3R-8 ACI COMMITTEE REPORT

water-reducing admixture with extended slump reten-


tion. Great care must be taken by the operator not to
lodge or snag the vibrator within the placement be-
cause it can become virtually impossible to extract.
The constructor and inspector must be aware that it
is a far lesser evil to overvibrate than to undervibrate
due to the risk of honeycombed concrete, air pockets,
and lack of density in congested areas.
5.2.5 Placing methods-Congested forms and diffi-
cult placing conditions have resulted in drastic changes
in placing methods. Concrete pumping or conveyors are
used more frequently than crane and bucket under such
conditions. The prime means of insuring good consoli-
dation continues to be the ability to place concrete as
close to its final position as possible.
The majority of concrete placed in congested forms
is placed by pump booms or placing booms using 4- or
5-in. (100- or 125-mm) diameter steel reinforced hose.
Fig. 9-Slide valves for pressure pumping of narrow
congested walls to the underside of horizontal struc- To insure good pumpability, the architect/engineer is
tural steel beams usually restricted to a maximum of l 1/2-in. (40-mm)
nominal maximum size aggregate.
The majority of concrete in congested forms can be
range water-reducing admixture is used with a modi- placed by lowering the concrete hose through the rein-
fied concrete mixture as described in Section 5.2.2. forcement to within 6 ft (1.8 m) of the surface, dis-
When it is reasonable to return to the normal concrete charging the lift thickness, then raising and reinserting
mixture using larger maximum size aggregate, bigger the hose at typically 10-ft (3-m) centers.
and more effective vibrators [typically up to 3 in. (75 In narrow wall forms where it is not possible to lower
mm) in diameter] should be used. the concrete hose through the reinforcement, lie-flat
When access into the form by the placing crew is hose coupled to the steel reinforced hose has been used
limited due to reinforcing steel, additional vibrators successfully. The lie-flat hose is very pliable and can
should be lowered down through the upper reinforcing transfer concrete vertically through very narrow spaces.
mat from the top of the placement. This practice will The hose is relatively inexpensive, making it economi-
reduce the tendency of operators to try to throw the vi- cal to cut off for removal from the placement if it be-
brators horizontally past interferences and will encour- comes caught on reinforcement or embedments (see
age them to operate vibrators in a nearly vertical posi- Fig. 7).
tion. Where wall placements extend up to the underside of
If the constructor is using pneumatic vibrators, he structural steel members or concrete beams, concrete
should insure a good supply of compressed air with should be placed under pressure through slide valves, as
headers located near the form. Oilers should be depicted in Fig. 9. When the form is full, the slide valve
mounted on each line coming off the air header. He is closed and the line disconnected. After the concrete
should also provide sufficient spare vibrators in the has set, the slide valve and supporting form are re-
event of a vibrator breakdown. Adequate power should moved. The remaining concrete stub is removed by
also be provided for electric vibrators. chipping and the wall is ground smooth.
In congested narrow wall forms, it may be necessary Pumping concrete from the bottom of the form can
to place side ports in one of the wall forms. The side offer a solution to congestion in some instances. Flow-
ports are typically 2 ft (0.6 m) square with a spacing of ing concrete is recommended for use with this method.
6 ft (1.8 m). The side ports are used to lower the vibra- The shape of the element has a great deal to do with
tors into the form and to observe the concrete placing whether or not the technique is viable. Rectangles,
within the form. This is necessary to insure that bridg- squares, and other polygons require special design of
ing of the concrete during placement has not occurred. formwork because pressure concentrates at the corners
It may also be possible to lower small-diameter vibra- of angles or point loading is developed. Circular unres-
tors between the outer layer of reinforcement and the tricted structures lend themselves best to pumping from
form face, except in the case of architectural faces, the bottom. Unrestricted means that the concrete must
where external form vibrators should be used. External be unimpeded all the way around the inside of the col-
form vibrators are discussed in ACI 309R, Chapter 5, umn and there are no baffles that restrict upward
and formwork considerations are discussed in SP-4, movement.
Chapter 5. If there is a vertical steel H section within the col-
Due to the increased time required for congested umn, the concrete will not pump if the concrete enters
placements, it may be necessary to use high-range wa- at a point perpendicular to one of the flanges of the
ter-reducing and retarding admixtures or a high-range H. If concrete is discharged directly into the web of
GUIDE TO CONSOLIDATION OF CONCRETE 309.3R-9

the H, the concrete will pump. This effect is dimin-


ished when at least 12 in. (300 mm) of concrete cover
over the H is present. Successful pumping has been
achieved with less than 4-in. (lOO-mm) cover if pumped
into the web.
When pumping from the bottom, there should be re-
strictions on the number and size of embedments or
boxouts and their position in the form. Also, if there
are large numbers of dowels, the flow of concrete may
be restricted, causing pump and/or form failures. At
least a 4-in. (lOO-mm) clearance should be provided be-
tween the embedment and the reinforcement or 4 in.
(100 mm) free at the top of the placement below the
structural steel or turned out reinforcement.
Preplaced aggregate (PA) is another placing method
that has been used effectively in congested areas. To
produce concrete by the PA method, coarse aggregate
is first placed in the prepared form. Then the voids in Fig. 10-Preplaced aggregate method: Close-up of
the preplaced aggregate are filled with a fluid grout congested reinforcement in blockout in side of a con-
tainment structure. Grout inserts [l-in. (25mm) diam-
consisting of cement, sand, water, and sometimes an eter pipes] are shown in right center (one uncapped)
admixture, which is pumped into the forms from the and near bottom (two, temporarily capped). Top of
bottom through form inserts or pipes. Materials re- first lift of coarse aggregate [approximately 7 ft (2.1 m)
quirements, procedures, and properties are described in deep] is visible at bottom of photo. Grout will be
ACI 304.1R. pumped to a few inches below surface of the coarse ag-
The PA method has been used to advantage for gregate to provide a keyed joint with the succeeding lift
placing concrete around congested reinforcement.
Where the reinforcing steel and forms are already in
place, grout pipes are inserted from the top or sides to Disadvantages of the PA method include the diffi-
the bottom of the space to be filled. Coarse aggregate culty of isolating congested sections to be placed mon-
is then dropped into place or shoved in from the sides, olithically from less heavily reinforced concrete. PA
and assisted by rodding and/or blowing with the help concrete may be somewhat time-consuming and labor-
of air lances. intensive.
After the form has been completely filled with aggre-
gate, the grout is pumped into the forms. Alterna-
tively, the coarse aggregate may be placed in lifts as the 5.3-Summary
reinforcement and forms are erected. Fig. 10 shows a Successful concreting under difficult conditions or in
portion of a boxout left in the side of a nuclear con- highly congested sections requires an effective combi-
tainment structure 50 ft long by 35 ft wide by 6 ft thick nation of design, placement, and consolidation tech-
(15.2 x 10.6 x 1.8 m). The reinforcement placed during niques. While this document has presented a number of
initial construction was too congested to permit the use options that can be considered by architects/engineers
of vibrators, especially because the rear wall was a steel and constructors, it must be recognized that each situ-
membrane that could not be cut to receive ports. The ation may be unique. The architect/engineer and con-
boxout was filled with PA concrete in 7-ft (2.1-m) lifts. structor, in consultation with each other, must assess
The preplaced aggregate method provides three plac- each situation and agree on the most appropriate ap-
ing advantages: proach for the situation in question. However, it is of
1. There is no time limit on placing the coarse aggre- utmost importance that situations requiring special at-
gate. tention be identified with sufficient lead time to allow
2. Areas that do not contain aggregates due to bridg- proper planning.
ing are not critical because all spaces are filled with
grout having approximately the same strength as the
surrounding concrete. The PA method can signifi-
CHAPTER 6-REFERENCES
cantly reduce the chances of honeycomb.
6.1 -Specified and/or recommended references
3. Continuous pumping of the grout eliminates cold
joints. However, if pumping is interrupted for any rea- The documents of the various standards-producing
son, the effect of the cold joint that forms is negligible organizations referred to in this document are listed
with their serial designations.
because coarse aggregate particles extending through
the grout surface provide structural continuity across
the interface between the two grout placements with a
high probability that the negative effects of the cold These publications may be obtained from the follow-
joint can be minimized or eliminated. ing organizations:
309.3R-10 ACI COMMITTEE REPORT

American Concrete Institute 304R Guide for Measuring, Mixing, Transporting


P.O. Box 19150 and Placing Concrete
Detroit, MI 48219 304.1R Guide for the Use of Preplaced Aggregate
Concrete for Structural and Mass Concrete
Applications
ASTM 309R Guide for Consolidation of Concrete
1916 Race Street 347R Guide to Formwork for Concrete
Philadelphia, PA 19103 R Mechanical Connections of Reinforcing Bars
439.3R
SP-4 Formwork for Concrete
ASTM
American Concrete Institute c 494 Standard Specification for Chemical Admix-
117 Standard Specifications for Tolerances for tures for Concrete
Concrete Construction and Materials c 1017 Chemical Admixtures for Use in Producing
211.1 Standard Practice for Selecting Proportions for Flowing Concrete
Normal, Heavyweight and Mass Concrete
211.2 Standard Practice for Selecting Proportions for
Structural Lightweight Concrete 6.2-Cited reference
212.3R Chemical Admixtures for Concrete Bonikowsky, Dan, Consolidation of Concrete in Congested Ar-
303R Guide to Cast-in-Place Architectural Concrete eas at Darlington NGS," Consolidation of Concrete, SP-96, Ameri-
Practice can Concrete Institute, Detroit, 1987, pp. 10-18.

ACI 309.3R-92 was submitted to letter ballot of the committee and processed
in accordance with ACI standardization procedures.

Vous aimerez peut-être aussi