Académique Documents
Professionnel Documents
Culture Documents
and boiler control .The total set up cost of the plant is 1200
crores and the capacity of the plant is 2 *210 =420 MW. The
Space requirements.
Nature of land.
3
Availability of labour.
Transport facilities.
Board
Thermal Plant
Km, Milestone on
Bathinda-Barnala Road
4
EVOLVED BHEL
CONSTRUCTION IN 1992
STARTED
OF 1ST UNIT
OF 2ND UNIT
THE PLANT
TOTAL UNITS IN 2
THE PLANT
5
OF THE PLANT
Sirhind Canal
POWER DISTRIBUTION
cubic meters.
ENTROPY DIAGRAM
temperature is achieved.
Addition)
Addition)
EXPLANATION
into pulverizing mills; which grind the coal into powder. The
air in the air heater driven by primary air fan (PA) to boiler
the road for safe. The fuel gas passes by an induced draft
the turbine rotor rotates, other rotor rotates with it. The
power lines into grid system. Mean while, the steam that is
Plant overview
COAL PLANT
Conveyer belt
BOILER BUNKERS
14
PULVERISING MILLS
BOILER BURNER
FD Fan
COMBUSION
Dust
Ash
COAL BURN
Heat released
BOILS WATER WHICH GIVES STEAM
STEAM IS SUPERHEATED
WATER IS PUMPED
15
Steam
TURBINE BLADES
DEAERATED IN
STEAM IS RETURNED TO
DEAERATOR
BOILER FOR REHEATING
PRESSURE INCREASES
TIRBINE SHAFT IS COMPLED BY BOILER FEED PUMPS
TO ROTOR OF GENERATOR
POWER IS STEPED UP
BY TRANSFORMER STEAM IS HEATED
Power Lines IN SUPERHEATER
GRID SYSTEMS
HP TURBINE
PLANT OVERVIEW
BLOCKS DISCRIPTION
16
SUPERHEATER (SH)
supports.
17
DEAERATOR (DEA)
drum pressure.
MILLS
this coal is fed into the mill through Raw Coal Feeder.
18
CONDENSER (COND)
stages.
and leaving from the other end. Air steam mixture passes
tube system.
enters first in this H.P heater and after getting heated goes
the tubes from coldest zone to the hot most zones before it
leaves the heater. The steam flows from hot most zones to
(RAH) is the same as the liung storm type except that the
assembly.
the furnace and throw them into the stack. Handles fly ash
POWER GENERATION
23
furnace.
header called the PA fan duct of the air is made and two
outgoing flue gases, heats the air, now called the hot
primary air. This hot primary air is now divide into six parts
&< 10C.
feed from other mills also enters the furnace at corners but
at different elevations.
consider only one corner of the furnace. The feed from mill
The forced draft fans are used to generate the secondary air,
fans (A&B) and this passed through the two air pre-heaters,
which heat the air using the heat from the flue gases, so
that the cold air doesnt bring down the temperature of the
of service.
26
FD SCAPH RAH
Air I/l FAN A&B A&B
A&B
27
AIR CYCLE
RAH ID FAN
FURNACE ESP A, B, C
A&B
CHIMNEY
OR
FLUE GAS CYCLE STACK
29
WATER CYCLE: -
deaerating header.
30
REG STN).
FM DM
M/U
LP
HTRS
FW HP BFP DEA
REG STN HTRS 5,6 A, B, C
FURNACE
STEAM CYCLE
furnace.
absorbed by the water walls and gets heated up. This gives
HPT
FURNACE
HP BP
ECON SH
RH IPT
33
LPT
COND LP BP
GENER
ATOR
steam and the dry steam is sent to the T.G.set, and the
of hot water is put into the hot wall. From where it is again
furnace charge are flue gases and ash. About 20%of the ash
And this dry ash is dumped in the ash disposal area. The
purposes.
37
SYSTEM DESCRIPTION
38
D.M. Plant.
produced.
through Chimney.
When the coal is burnt in the boiler nearly 35% of the ash
ash and gases are coupled out by the reduce draft fan from
Ionic &dissolved
Gaseous
CONTROL&INSTRUMENTATION
42
suppliers.
up, shut down, normal run sudden load throw off positions.
TDC-3000
following objects.
POWER PLANT
BOILER TURBUNE
FU FG CA
FU
AA
TIC FIC
100 100
46
Alarm and messages will only reported for the points, which
area.
WHAT IS TDC3000: -
48
control logic.
functional processors.
51
Process N/w
Supervisory N/w
emerging as a DCS.
AROUND A DCS?
their use:
53
MADE AVAILABLE?
54
(HG).
controllers
displays.
Manipulating parameters.
UNIVERSAL STATION
Station.
security.
60
Operators keyboard.
Printer (optional).
screen.
2.OPERATING KEYBOARD: -
62
alarm systems.
2
nd
one is plugged into appropriate model of US.
capacity of 1.2-MB.
20/40/150 MB.
A record of alarms.
recorder paper.
8.VIDEO COPIER: -
9.TRACK BALL: -
from US.
message.
histories.
reports.
diagnostics.
Network configuration.
Designing reports.
troubleshooting.
69
functions.
steps:
Prompt on US.
Screen.
programs.
SECURITY: -
Following operational security is implemented in universal
station: -
72
programs.
Operator level
73
Supervisor level
Engineer level
operating level.
Supervisors key
74
Engineers key
SUPERVISORS KEY
ENGINEERS KEY
the key switch only by bringing the key switch position back
VIEW ONLY
screen for viewing, but does not permit any data entry.
75
console.
console.
76
same place.
below:
77
FUNCTION KEYS.
not removed.
FAST: Fast update key causes the update rate for process
related display information to increase to 2-second interval
condition.
82
UNIT TREND: unit trend key calls the unit trend display.
A unit ID is required to be entered after pressing this key.
84
station.
alarms.
summary display.
station display.
92
operation.
SP: set point key used to initiate set point value changes of
a point. A value is required to be entered either by numeric
system configuration.
the PLCG.
OVERVIEW
97
SYSTEM ARE: -
98
3000.
control schemes.
applications.
FUNCTIONAL DESDCRIPTION: -
The universal control network provide a power
LCN DESCRIPTION
kernel.
TOKEN PASSING
103
order.
LCN OVERVIEW
104
a serial interface.
107
ADVANCED FEATURES: -
plus:
String variables.
Time variable.
108
FUNCTIONAL DESCRIPTION: -
NIM. The NIM broadcast LCN time over the UCN. The APM
devices.
Processor Rack
I/O Rack
racks and the UCN. It converts the PLC data into UCN
620-35 PLC.
inserted.
REDUNDANCY SYSTEM
processor.
BACKUP processor.
processor.
processors.
REDUNDANT SIOM
is in:
halted.
117
SYSTEM
instead of processor A.
control of serial and parallel I/O racks and turns off the
redundancy is as follows:
and wait till the lead status indicator becomes on. Now
121
steps 2 to 6.
or RUN/ROG mode.
122
INDUSTRIAL TRAINING
REPORT
Doing at
GURU HARGOBIND THERMAL PLANT
LEHRA MOHABATT
DISTT. BATHINDA
In
The Partial Fulfillment For The Requirement Of
Award of DEGREE
In
Electronics&communication
SUBMITTED TO:
H.O.D.
ELECTRONICS&COMMUNICATION
S.U.S.C.E.T.TANGORI
MOHALI
SUBMITTED BY:
INDER VERSHA
E.C.E-FINAL YEAR
ROLL NO. 9901744
123
ACKNOWLEDGEMENT
Industrial training is the effort to provide linkage between the student and Industry in order to develop the
awareness of industrial approach for saving the problem based on broad understanding of tools, modes of
operation of Industrial Organization.
With the deep sense of gratitude, I express my sincere thanks to PSEB,
Patiala, who permitted me to take up training at the Organization. I wish to extend my thanks to Er.
M.S.Thind (S.E./C&I), Er.A.K.Chugh (Add. S.E.), Er.K.K.Jain (Add.S.E)&Er. Chhabra (Add.S.E) for
their considerable help to join the training in different sections of C&I department. I humbly express my
cordial thanks to Mr. Parveen Jain (A.E), Mr.AjitPal Singh (A.E), Mr. Dhiraj Bansal (A.E) and Mr.
S.k.Sharma (A.E) for their extra pain to see me through my problems. They have been always a source of
encouragement and inspiration for me. Under their efficient guidance, I had no problem in acquiring and
getting various jobs done. I am always thankful to staff of industry for their kind cooperation and help,
which made me training a success.
I feel that information gathered by me during this training will surely help me
a lot in coming future.
ABSTRACT
INDERVE
RSHA
I
125
CONTENTS
126
1. INTRODUCTION
2. WORKING OF THERMAL PLANT
3. SYSTEM DESCRIPTION
4. TDC 3000
5. UNIVERSAL STATION
6. TOTAL PLANT SOLUTION
7. REDUNDANCY SYSTEM
INTRODUCTION
POWER DISTRIBUTION
127
DIAGRAM
PLANT OVERVIEW
BLOCKS DISCRIPTION
GENERATION
128
129
SYSTEM DISCRIPTION
COAL HANDLINGSYSTEM
FUEL OIL SYSTEM
ASH HANDLING SYSTEM
D.M.PLANT
EMERGENCY POWER SUPPLY SYSTEM
CONTROL&INSTRUMENTATION SYSTEM
DATA ACQUISATION SYSTEM
POWER SUPPLY DISTRIBUTION SYSTEM
BENEFITS OF DCS
TDC ARCHITECTURE
UNIVERSAL STATION
LOADING OF U.S
OPERATORS KEYBOARD
FUNTION KEYS
132
1. OVERVIEW OF TPS
DESCRIPTION
TOKEN PASSING
OVERVIEW OF LCN
CAPABILITIES OF APM
ADVANCE FEATURES
FUNCTIONAL DESCRIPTION
OVERVIEW OF LM
133
REDUNDANCY SYSTEM
REDUNDANT SIOM
SYSTEM