ROAD & HARDSTANDING

Filling crusher run base course, 150mm thick, compacted in layers of 75mm thick
maximum [RM/M2]

Price Data (Delivered to site)

Material

Crusher run. RM65/m3 [100mm thick = 0.128m3/m2]

Vibratory road roller (hired) RM300/day

Back pusher (hired) RM200/day

Labour

General labourer RM50/day

Machine output

Levelling 75mm thick crusher run = 120m2/hr/layer

Rolling 75mm thick crusher run = 56m2/hr/layer

Labour output

Directing unloading of crusher run on site - 0.10hr/m2

Overheads 8%,

Profit 2%
Filling dense graded hot-mix carpet wearing course, 100mm thick, laid and compacted
[RM/m2]

[Quantity of wearing course for the project is assumed 3500m2]

Price Data (Delivered to site)

Material

Hot-mix asphalt RM80/tonne

[Covering capacity for 100mm thick = 3.88m2 /tonne]

[Guarantee rate of material delivery to site =20 tonnes/hr]

Plant

Vibratory road roller (hired) RM300/day

Mechanical paver (hired) RM300/day

30 tonnes Pneumatic roller (hired) RM250/day

1 tonne lorry (hired) RM100/day

[Transportation cost for each plant to and fro site is charged at RM1200/tonne of materials laid for the
project]

Labour

Foreman RM60.00/day

General labourer RM50/day

Machine output

Levelling 75mm thick wearing course = 120m2/hr/layer

Rolling 75mm thick wearing course = 56m2/hr/layer

Labour output

Directing unloading wearing course on site - 0.10hr/m2

Overheads 8%,

Profit 2%
[Take area of road 1.00m2]

A. Material

150mm thick crusher run

| 150mm | x 0.128m3 @RM65.00/m3 RM12.48


| 100mm |

B. Plant & Equipments

i. Levelling 2 layers of crusher run,


75mm thick maximum

2x| 1m2 | @RM200.00/day RM 0.42


|120m2/hr/layer|

ii. Compacting 2 layers of crusher run,


75mm thick maximum

2x| 1m2 | @RM300.00/day RM 1.34 RM1.76


| 56m2/hr/layer| RM14.24

C. Labour

Directing unloading of crusher run on site

0.10hr/m2@ RM50.00/day] RM 0.63


RM14.87

Allow for overheads 8% RM1.19

Allow for profit 2% RM0.30 RM 1.49

Rate per m2 for this item RM16.36


A. Material

i. Hot-mix asphalt 100mm thick

1 tonnes @RM80.00/tonne RM80.00

B. Plant & Equipments

1 nr mechanical paver @RM300/day RM37.50/hr

1 nr 30 tonnes pneumatic roller @RM250/day RM31.25/hr

1 nr vibratory road roller @RM300/day RM37.50/hr

1 nr 1 tonne lorry @ RM100/day RM12.50/hr


Cost for 20 tonnes: RM118.75/hr

Cost per tonne: RM118.75/hr RM5.94


20 tonnes/hr

C. Labour

1 nr foremen @RM60.00/day RM7.50/hr

6 nr general labourers @RM40.00/day RM30.00/hr

Cost for 20 tonnes: RM37.50/hr

Cost per tonne: RM37.50/hr RM 1.88


20 tonnes/hr

D. Transportation plant to & fro site

3 nr @ RM1200/nr RM3600
| 3500m2 | RM 3.99
|3.88m2/tonne | RM91.81

Cost per m2 RM91.81/tonne RM23.66


3.88m2/tonne

Allow for Overheads 8% RM 1.89


Allow for profit 2% RM 0.47 RM 2.36

Rate per m2 for this item RM26.02


One coat of approved thermoplastics reflective road paint, including clearing surface from dirt,
grease oil laitance or other foreign matters, double continuous line not exceeding 150mm wide.
[RM/M]

Price Data (Delivered to site)

Thermoplastic road painting powder RM 60/bag (weight per bag - 25kg)


(Consumption: 5kg/m2 - thickness: 1.8mm)

Glass beads RM35/bag (weight per bag - 25kg)


(Rate of application - 13.6kg/m2

Propane gas (say) RM1.00/m2

Road marking equipments incl. operator (hired) RM100/day


(Output: 0.03hr/m2)

Labour output for preparation of road surface 0.025hr/m2.


Wages - RM8.00/hr.

A. Material

Thermoplastic plastic road paint | 5kg/m2 |@65.00/bag RM13.00


| 25kg |
Glass beads |13.6kg/m2 | @RM35.00/bag RM19.04
| 25kg |

Propane gas (say) RM 1.00


RM33.04
Allow 2% wastage RM 0.66 RM33.70

D. Plant and Equipments

Hire road marking equipments (incl. operator)


0.03hr/m2 @ RM12.50/hr RM 0.38

E. Labour

2 general labours for preparation of surface:


0.025hr/m2@RM8.00/hr RM 0.40
RM34.48

Cost per m = | 0.30m2/m |@RM34.48 RM10.34


| 1m2 |

Overhead 10% RM1.03


Profit 2% RM0.21 RM1.24
RM11.58