02/12/2015
Tailings planning with
Muck3D
Carlo Cooper
MineBridge Software Inc.
Remembering why we plan
+ We plan so we achieve our goals and objectives
+ Safety to humans
* Safety to the environment
+ We plan so we do not fail.
+ We plan so we can minimise costs without compromising integrity.
* We plan so we are not surprised.02/12/2015
How do we plan effectively?
* By repeatedly asking the question “What if my assumption is wrong”
* By being critical of design assumptions.
* By recognising that things change and adapting to it.
* By understanding that planning is an ongoing process.
* By adapting an observational approach.
What are the main outputs?
* An understanding of the state of a structure at the end of its life/post-
closure.
* Aset of steps that show how a facility is developed.
* Critical points in a facility life (e.g. transition between facilities, rate of
rise approaching limits, etc.)
* Consideration of mitigation strategies for potential issues before they
eventuate.
+ Input into Operation & Maintenance docs, looking for signs of
impending issues.
* Visualisations of scenarios.02/12/2015
Tailings staging/planning
* Modelling from a volumetric viewpoint.
+ Understanding requirements to store target volumes.
* Understanding construction effort.
* Understand pond behaviour.
* Understand rate of rise of pond, tailings, dams.
+ Identify failure modes.
+ Understand what’s needed for tailings transportation & pumping.
Key concepts
* Solids are generally easy to store. Water is the problem.
* Beach steeper than terrain -> need elevation to pour from.
« Terrain steeper than beach -> need containment.
+ More water -> more effort for dam (design wise,
elevation/construction effort).
* For thin lift deposition, required area = f (inflow rate + drying time)02/12/2015
Planning in 3D
* We do this by building 3D models of the TSF and other waste
structures over time.
* These are simplified models of complex behaviour, but we capture
the key behaviours and model them.
* Level of detail & effort we go into depends on planning timeframe.
* The outputs are only as good as their inputs.
Which brings us to Muck3D...
* Muck3D is a 3D design tool, designed to support the development of
3D tailings volume models.
* Provides a range of tools to enable rapid prototyping of design
concepts for tailings, general mine waste, & dams.
* Tailings deposition models are tightly coupled to the pond
management strategy.
* Given the level of uncertainty in input parameters, and the likely
operational deviation from any prescribed plan, we deal with
uncertainty by evaluating many different scenarios, rapidly.02/12/2015
Using 3D models effectively
* To make this a practical exercise, we need to dumb down complex
processes.
+ Keep the level of detail to a minimum.
* Operations are simplified.
+ Beaches are reduced to linear or compound linear slopes.
* Consolidation behaviour simplified.
* Ahigh level of analytical accuracy (e.g. consolidation) is generally not
warranted or practical since plans are rarely the way things pan out.
Ways we can use 3D models
Capacity calculations:
* Determination of the total capacity of a facility.
+ Remaining space for current containment elevation.
Scheduling:
« Identifying state of a facility at a point in time.
* Determines effort required over a time period to build/operate.02/12/2015
Key inputs
* Good topographic & bathymetric survey data.
* Assumptions for tailings dry density, beach slopes.
* Tailings production data.
* Water management data.
* Dam designs.
* Understanding of what site Ops will actually do.
Topo & bathymetric data
* Lidar is great.
* Bathymetric data should be collected at the same time to create a
nice surface that ties in properly.
* Satellite photogrammetric data is an option where Lidar data isn’t
available.
* SRTM data is old, 90m grid, only available between 6ON and 60S but
better than nothing, especially for conceptual design.
+ Bathymetric data should be thoughtfully collected, focusing on areas
that give us useful information.02/12/2015
Collecting bathymetric data
* Section lines that green give us
good information about BBW
slopes.
* Orange ones less so — we want
to be perpendicular to the
tailings contours.
* Red doesn’t tell us a lot — at this
stage of the life there are little to
no tailings out here.
Estimating slopes
* For a single stream can vary around the perimeter and can vary over
time.
+ Where there are multiple streams entering a TSF, the areas of
interaction between then can make it hard to assess true beach
slopes.
* Operational decisions can impact variability in slopes in different
parts of a TSF.02/12/2015
®,
Slope varies with time
rom eum)
Ms
lopes from the same tailings line02/12/2015
Slopes from the same tailings line
Section 1: 4.03 - 4.27% Section 2: 3.31 - 4.02%
Slopes from the same tailings line
Section 3: 3.0- 3.26% Section 4; 3.98-4.16%02/12/2015
‘Beach slopes from a CTD deposit
Working with slope prediction models
* Predict beach slopes/profiles based slurry density, flow rates, and
rheological parameters.
* Fitton (2014) shows different slope prediction models and how they
compare to measured tailings slopes.
* He concluded that none of these models perfectly predict beach
slopes.
1002/12/2015
Accuracy of slope
predictions
+ Almost never rac the slopes perfect
+ Somatime the dference been
predited vs atl con be enormous
+ Consequence ofthis stat the
‘operations ean not
+ Thisplotis eeated fom several : y
comparisons presented byFiton (2014). i va
Types of facilities modelled in 3D
* Paste
+ Filtered/dumped
* Cross valley/down valley
+ Co-disposal
+ Inpit disposal
* Integrated tailings + waste rockFacility examples
Down-valley thickened tailings
Ring dyke, conventional
ABE
qi Facility examples
Trucked, filtered tailings Central discharge
02/12/2015
1202/12/2015
Planning horizons
* Short range (< 1 year)
* Mid range/business planning (< 5 years)
* Long range ( thm2 of
catchment are02/12/2015
Storage criteria
‘Total storage volume (solids) 35Mm3-
Operating pond volume. 2Mm3-
— asi
Downstream slope avast
‘Crest width 20m
earn Lm eb eal
Pee,
Sites to evaluate
4 ses have been chosen to evaluate ina
high evel
For exch option, we wil See what Rakes to
store target volumes.
24Site 1
70m igh dom
Toe of dam in aval mteialin the vale
“os of dam n stream with <12 km?
catchment feeding
Site 2
Catchment area around 4. km
‘Dyke max height: 52m
02/12/2015
2502/12/2015
Site 3
‘catehment area: “5. kn?
Case study: Minera Centinela02/12/2015
About the project
* Northern Chile (approx. 155 km
NE of Antofagasta)
+ 2000 m above sea level
+ 95,000 tons per day
* Copper tailings
* High-density Thickened Tailings
(3 x 60m diameter)
+ Operating since Q4 2010
Basic assumptions (Luppnow et al, 2008)
* Design tailings slope: 4%
+ Target storage volume: 480 Mm3
+ Max deposition elevation: 2268 masl
+ Main containment dam ultimate elevation: 2217 masl
a02/12/2015
a
The terrain
Base grade of TSF Base topography/section location
2802/12/2015
How it should have developed
First 1 Mm3 of tailings Deposition extents
Proposed mitigation methods (Luppnow et
al, 2008)
* Design consultant identified the possibility of low density tailings &
flat beach slopes.
* Options for mitigation were emergency storage areas and multiple
deposition points, respectively.
+ The emergency storage area was the starter dam at the north end of
the TSF.
* Assumed volume was 10 x 4 hr events in the first year of operations
(approximately 0.1 Mm3)
2902/12/2015
Performance
* Actual thickener performance:
62% underflow
* Achieved beach slopes: 0.5 —
1.2%
* Off-spec tailings storage at
starter dam filled rapidly.
3002/12/2015
Thickness of deposited tailings
0.7 Mm3 (approx. 10 days) 4.7 Mm3 (approx. 74 days)
3102/12/2015
Communication
Communication needs to be clear
+ Once we've developed plans, we need to communicate what we've
found.
* Consumers of this can include:
+ Technical reviewers
+ Site personnel
+ Non-technical management
+ Regulatory agencies
* The public
3202/12/2015
Different stakeholders want to see different things
Tools for communication
* 3D images from design tools.
* High quality ray traced images
* Simple animations
* Flyover
* Time-based
* ‘Professional’ 3D animations
* Virtual reality
+ Photo-spheres
3302/12/2015
3D printed models
* Different 3D printing materials allow for demonstration of different
features
+ Plaster printers allow for full colour air photos/thematic overlays to
be included to highlight different features.
* Transparent plastic materials can represent water bodies.
* Different options can be shown on a single topographic surface.
One last thing...
Always remember Why we plan and make sure you use it as an
opportunity to make the safest, most efficient designs.
3402/12/2015
Ask us questions anytime
Carlo Cooper, MineBridge Software Inc.
carlo@minebridgesoftware.com
http://www.minebridgesoftware.com
References
+ Fitton, 6, (2014) The accuracy of talings beach slope predictions, In Proceedings of 17%
International Seminar on Paste and Thickened Talings (Paste 2014) RJ Jewel, AB. Fourie, 5.P.
Wells (eds), 8-12 June 2014, Vancouver, Canada, Australian Center for Geomechanics, pp 47-58.
+ Luppnow,D., Moreno, J. and Berna, L. (2008) Esperanza Project - Drivers for Using Thickened
Tallings Disposal, in Proceedings of 12° international Seminar on Paste and Thickened Tallngs,
{Paste 2008) A.B. Fourie, Ri. Jewel, P Slatter, and A. Paterson (eds), 5-9" May 2008, Kasane,
Botswana, Australian Center for Geomechanics, pp 189-198.
+ USGS (2004), Shuttle Radar Topography Mission, 3 Arc Second scene SRTM_u03_s022w069,
Unfilled Unfinished 2.0, Global Land Cover Facility, University of Maryland, College Park,
Maryland, February 2000
35