Vous êtes sur la page 1sur 4

Development of Innovative Water Treatment and

Cooling Technologies for Power Plant


Water Consumption Reduction
June 2012 EPRI Request for Information

be found here. The mission of this program is to identify and fund


Updates early stage water conserving technologies with a high potential to
1. Due to IT issues, we may not have received all submitted be widely implemented within 20 years. Information about the
proposals. If your submission does not appear on this list, projects selected from the first solicitation in 2011 can be
please contact us immediately. found here. In early 2013, a joint EPRI Request for Information
(RFI) with National Science Foundation on water conserving
2. The deadline to submit proposals has been extended to August cooling technologies will be released.
14th, 2012
Background
3. The contract terms have been updated. Please refer to page 4.
U.S. steam-electric plants account for approximately 40% of the
Objective nations total freshwater withdrawals anddue primarily to evapo-
EPRI is seeking innovative and energy efficient water treatment rative and drift losses from cooling systems with wet cooling tow-
ideas and technologies which will enable thermoelectric power ersapproximately 3% of overall consumption. Water use rates at
plants to reduce their freshwater consumption needs (Figure 1) plants with these closed-cycle wet cooling systems may not be sus-
through the reuse of major water streams internal to the power tainable in some locations, while thermal discharges from once-
plants and the reclamation of degraded and non-traditional water through cooling face increasing regulatory scrutiny. Already, some
streams external to the plants. EPRI is also seeking out of the plants operate under water use restrictions or are being required to
box and breakthrough cooling and waste heat utilization ideas install water-conserving technologies. Furthermore, the siting of
and technologies with high potential to dramatically reduce water new capacity is challenged by water supply constraints. As a result,
consumption and withdrawal. Selected responses may be funded breakthrough cooling and water treatment technology develop-
or cofunded by EPRI and its collaboration sponsors. ment to enable both the reclamation of non-traditional water
sources and the reuse of major internal water and wastewater
Program Overview streams are emerging as top priorities for various types of power
This is a 2nd round of solicitation released by EPRIs plants.
Technology Innovation Water Conservation Program which can

Figure 1. Illustration of a 500 MW Power Plant Steam and Cooling Water Flow System and Innovation Opportunities.
Currently used air cooled steam condensers oo Post treatment of blowdown water from evaporative
(Figure 2)the most water-efficient optionhave up to 10% cooling tower operations to enable reuse on site,
power production penalties on hot days, and up to five times preferably for cooling system make-up water.
oo Pre-treatment and side stream treatment in order to
higher capital costs compared to current cooling tower and water-
increase the cycles of concentration in the cooling
cooled surface condenser systems. Game changing energy efficient
system.
technologies for reclamation of non-traditional water sources and oo Technologies which leverage existing processes and
the reuse of major internal water streams, as well as cooling infrastructure such as waste heat.
technologies for reducing the cooling water requirements General plant water and wastewater systems (Note: The
represent a critical industry need. Key Measures of Merit are not all applicable to ideas in
this category as they may be funded at different funding
Eligibility levels by other EPRI programs.):
Ideas are being solicited from academia, manufacturers, startups, oo Including regenerative waste, plant process streams and
national laboratories, consultants, independent inventors, and low volume wastewater and plant sumps and collection
systems.
others. Responses from the international community and those
oo Cost effective tritium separation technologies for light
outside and unfamiliar with the power industry are also water reactor nuclear power plants;
encouraged. oo Treatment of flue gas desulfurization (FGD) wastewater
For those unfamiliar with the power industry, EPRI has assembled for removal of contaminants of concern for onsite reuse
and/or compliance with environmental discharge limits;
water chemistry considerations which can be found here. Typical
oo Zero liquids discharge (ZLD) processes, including more
operating conditions of cooling systems and other relevant infor- cost effective: concentrate management (concentrating,
mation can be found here. sorting, disposal), re-use of RO reject and/or water from
demineralization processes.
Innovative Technologies of Interest (but not oo Please note that power plant water quality requirements
limited to) (e.g. cooling tower chemistry criteria) defy a generic
prescription; there exists wide variability among
We seek innovative technologies to treat major streams of water for
plants and among water streams within each plant.
water resource expansion and to significantly reduce cooling water However, the common goal to manage water resources
consumption and/or withdrawal at electric power generating stations. effectively is shared among all power providers. The
Examples of areas of primary interest include, but are not limited to, chief objectives of developing above water treatment
the following: technologies are to achieve significant reductions in
Water Treatment Technologies cost, energy usage, and/or operating issues such as
Degraded and nontraditional water sources: scaling, corrosion and fouling.
oo Technologies which enable cost effective utilization of Advanced cooling technologies
municipal wastewater effluent and brackish water. More efficient and compact dry cooling solutions:
Process cooling applications: oo Reduced steam condensation temperature from 30C to
oo Moisture recovery from cooling tower (more than 20%) 10C above the ambient temperature.
or boiler flue gas oo Improved air side heat transfer coefficient by three times
from 50 W/m2/K to 150 W/m2/K without significant
increase of ACC size and fan power consumption
oo Alternative dry cooling solutions to further reduce
steam condensation temperature
Less water consumption from wet cooling systems:
oo Less evaporative loss in cooling towers (> 20%)
oo More efficient and compact liquid cooled heat
exchangers or condensers
oo More efficient once-through cooling designs (meeting
EPA Clean Water Act Section 316 requirements)
More efficient hybrid dry and wet cooling systems
Heat driven chillers (COP > 1.2) to reduce steam
condensation temperature in hot days resulting in improved
power production
(New cooling concepts taking advantage of waste heat utilization, and the
adoption of advanced cooling systems used in other industries are also of
primary interest.)

Figure 2. Illustration of a Typical Air Cooled Condenser for Power Plants

Development
of Innovative Water Treatment and Cooling 2 June 2012
Technologies for Power Plant Water Consumption Reduction
EPRI is interested in all types of generation including fossil, nuclear, Technology basic operating principles with diagrams
solar, biomass, geothermal, and various combined cycles. Responses describing unique and innovative facts
may address technologies that are applicable to a group of generation Target level of performance with technical data or other
types or specific to one. For instance, specific water treatment tech- support to show how the proposed target could be met
nologies may be more or less applicable to cooling systems of a specific Current technology readiness level (TRL) and the
metallurgy. Responses should clearly articulate and quantify the anticipated TRL at project completion
Current state-of-the-art and competing technologies in the
benefit(s) from deployment of the technology or concept at power
relevant field and application, including key shortcomings,
plant(s). limitations, and challenges
How the proposed technology will overcome the
Key Measures of Technical Merit shortcomings, limitations, and challenges in the relevant
Innovation (out of the box or cutting edge) field and application
Impact on reduction of fresh water withdrawal and/or Potential impact on the relevant field and application
consumption, and energy use Anticipated number of years required for commercialization
Economic potential in terms of cost and space in 10 to 20 Anticipated cost of the commercialized technology or
years project economics
Respondents capabilities and related experience Efficiency
Realism of the proposed plan and cost estimates Specifications (for example, flow rate, capacity, pressure,
and temperature)
Flow diagram with flow rate, temperature, and energy
Budget balance data at both component level and system level for
EPRI is currently planning to make this research area one of the integrated approach A system level diagram with above
main foci of its research in coming years. For this RFI, please sub- required data is required if waste heat is needed.
mit a budget for each project not to exceed $500K over a maxi- Preliminary assessment plots, data, and calculations
mum of a three year period. The key technical risks/issues associated with the proposed
technology development plan
Timetable Scope of work
Project tasks
RFI posting: June 12, 2012 Modeling and simulation experiences and plans
RFI Informational Webcast (Slides, Recording) Testing experiences and plans
Schedule (project length not to exceed three years)
RFI response due: 5pm PDT: August 14, 2012 Funding expectation (not to exceed $500K per project)
Deliverables
Tentative Award/Rejection Notice: November, 2012
Additional Information
This is the second round of solicitation of concepts. Responses received
after the deadline will be considered for future rounds of funding. Responses should not exceed 10 pages, including drawings, tables,
pictures, and references (excluding cover page, bios and resumes).
Minimum 12-point font, single spacing, and standard margins
Response Guidelines should be used.

Requested Information (if relevant to response) More than one response is allowed per respondent.
Respondents are requested to provide the following information The following guidance describes legal considerations regarding
in their response: how EPRI intends to manage the information received in response
Company/institutional name to this RFI, and EPRIs general stance on intellectual property
Company/institutional technical and business contacts considerations relevant to funded proposals. Please note that EPRI
Company/institutional background and experience may be willing to negotiate contract terms on an individual basis
Brief description of the operations and mission of business or for top proposals. For example, EPRI may have greater flexibility
institution (several sentences will suffice) on terms of intellectual property ownership and license rights to
Addresses, phone numbers, and e-mail addresses of principal domestic universities, government labs, and other federal, state, or
investigator(s)
municipal government agencies. For specific information regard-
Bios or resumes of principal investigator(s)
Web links ing our university agreements, please click here.
Explicit project title, such as Solar/Waste Heat Driven Dry Our external reviewers are asked to sign confidentiality and con-
Cooling System flict of interest agreements before reviewing any submission mate-
Abstract (no more than 500 words with technology innovation
rial. In any public releases, EPRI may acknowledge contributions
description and impact data)
Objective from developers and collaborators.
Technology description
Please describe the following succinctly:


Development of Innovative Water Treatment and Cooling 3 June 2012
Technologies for Power Plant Water Consumption Reduction
All submittals will be considered non-confidential and non-pro- Due to funding EPRI provides, as well as its tax-exempt status,
prietary. Any information obtained as a result of this RFI is EPRI will generally take ownership of all intellectual property
intended to be used by EPRI on a nonattribution basis for rights that arise in connection with the work performed under the
program planning and possible future funding. EPRI plans to contract. The contractor is not granted any license rights to this
distribute the submittals to potential funding organizations and intellectual property in the contract. However, EPRI is very inter-
its review committee for consideration. EPRI may also provide ested in commercializing the results of its research and welcomes
summaries of some proposals in an EPRI report. inquiries on the licensing of the technology. If there are back-
ground intellectual property rights necessary to practice the fore-
EPRI has no obligation to respondents, and will not be required ground technology being developed under the EPRI contract, the
to provide feedback on any decision, but may contact selected contractor must agree to grant EPRI, on a royalty-free or reason-
respondents for questions. EPRI will not pay for information pro- able royalty basis, a non-exclusive, worldwide license to practice
vided under this Request for Information (RFI) and there is no the background technology, including the right to sublicense.
guarantee that any submittal will be supported as a result of this
RFI. This RFI is not accepting applications for financial assistance More detail may be found under About EPRI/Contractor
or financial incentives. This RFI does not limit EPRI from provid- Resources on www.epri.com.
ing to third parties products or services (including research ser-
vices) which may be competitive with the products or services of No resubmission of any previous RFI response without updating
the respondent or providing products or services to third parties is necessary. All unrejected responses from the first round of RFI
who may compete with the respondent. Accordingly, nothing in will be compared with new proposals.
this Agreement shall be construed as a representation or inference Submission and Deadline
that EPRI will not independently develop products or services for
itself or for third parties, that compete with the products or ser- All responses to this RFI must be delivered electronically in Micro-
vices of respondents. soft Word (.doc) or PDF format as an attachment to an e-mail
sent to waterrfi@epri.com.
A response to this RFI will not be viewed as a binding commit-
ment to develop or pursue the project or ideas proposed. All proj- E-mails should have the subject line: RFI-Organization Name-
ects will depend upon adequate funding and successful negotia- Project Title of the Response. Responses to this RFI must be sub-
tion and execution of a written contract. The contract provides a mitted by 5 p.m. PDT on August 14, 2012.
framework for the research effort by stating the rights and obliga- Responses received after the deadline will be considered for the
tions of the parties. The contract consists of the EPRI general future rounds of funding.
terms and conditions, applicable to all work to be performed by
the respondent as contractor, and the project agreements specifi-
cally tailored to each research effort. Each project agreement Frequently Asked Questions
includes scope of work, period of performance, funding, and General questions regarding this RFI should be emailed to Water-
deliverables. EPRI generally awards cost reimbursement contracts. RFI@epri.com. Questions collected by Wed. may be answered
Fixed-price contracts are awarded only in certain circumstances. here by the following Tuesday.
EPRI thanks you for your consideration and response in address-
ing this very important societal issue.

General Contact
Technical Contact
WaterRFI@epri.com or Vivian Li, BSc, Technical Assistant
Water treatment: Sarah Inwood, MS, Project Engineer/Scientist;
vli@epri.com or at 650.855.2309
sinwood@epri.com or at 650.855.2320
Please notify Vivian if you would like to be on EPRIs e-mail
Cooling: Jessica Shi, PhD, Sr. Project Manager; jshi@epri.com or
distribution list for future related notifications.
at 650.855.8516

1025767 June 2012

Electric Power Research Institute


3420 Hillview Avenue, Palo Alto, California 94304PO Box 10412, Palo Alto, California 94303 USA
800.313.3774 650.855.2121askepri@epri.comwww.epri.com

2012 Electric Power Research Institute (EPRI), Inc. All rights reserved. Electric Power Research Institute, EPRI, and TOGETHERSHAPING THE FUTURE OF ELECTRICTY are registered
service marks of the Electric Power Research Institute, Inc.

Vous aimerez peut-être aussi