CANADIAN ELECTRICAL ASSOCIATION
Hydraulic Power Section
March, 1990
Montreal, Quebec
HEADGATE REHABILITATION
KW. Faisst
Ontario Hydro
SUMMARY
This paper identifies several options for restoring the closing and sealing
capabilities of headgates in older hydraulic plants. The study applies to
vertical-lift, fixed-wheel, downstream-seal-type gates, which no longer close
under their own weight due to deteriorated rolling and sliding surfaces.
Site-specific solutions are presented, which were developed on the basis of
drop test results, gate and gain Inspections, friction force calculations and
hydraulic model studies.“ The solutions’ include: wheel and bearing
replacements, seal modifications, roller path repairs and modifications to the
gate bottom. .
Key Words: Headgates, Vertical Lift Gates, Hydraulic Gates, Emergency
Closure, Water Intakes
0293H1.0
2.0
21
INTRODUCTION
Headgates in hydraulic plants are usually situated at penstock or
scroll case inlets (Figure 1), where they serve two distinct
functions. First and foremost, the gates are intended as safety
devices to shut off the water supply to the turbine in case of an
emergency, ¢.g., station fire, unit runaway, penstock rupture.
Secondly, the gates are used as convenient isolation barriers to enable
inspections and repairs of the penstock or the turbine during a unit
shutdown.
As safety devices, the gates must be self-closing under their own
weight and at full unit flow. As Isolation barriers for a dewatered
unit, the gates are expected to retain the forebay water with minimum
seal leakage (preferably without cindering).
Emergency closures of headgates to stop hydraulic generating units are
infrequent. However, when such emergencies do occur, reliable gate
operation is essential, since headgate closure constitutes the last
resort to protect the plant from flooding or other destruction.
At Ontario Hydro, annual drop tests are now conducted to demonstrate
that the headgates close under full unit flow. These tests have shown
that the self-closing capability at a number of older plants no longer
exists. Subsequent inspections revealed deterioration in the gate's
rolling and sliding elements, which would result in excessive friction
forces, thus preventing gate closure.
To restore reliable headgate operation at these plants, several
rehabilitation concepts and improvements were developed. These
concepts and ideas could also be of use to other utilities facing
similar headgate problems at their hydro-electric plants.
BACKGROUND
Headgate Type and Sizes
The headgates identified as having closing problems are fixed wheel,
vertical lift gates with downstream seals and sloped gate bottoms as
shown in Figure 2. They are installed in generating units of 20 to
60 MW capacity, with up to three headgates per unit. Size ranges and
operating parameters for the identified problem headgates are shown in
Table 1.
These gates were all supplied and installed between 1930 and 1955 and
have the following design features:
~ Gates completely submerged.
~ Riveted gate construction featuring double end girders with the
wheels between them.
0293H2.2
2.3
~ Side seals and top seals consisting of formed brass strips, bent over
32 mm diameter rubber hoses and attached to the downstream side of
the skin plate (Figures 3 and 4).
~ Bottom seal by metal to metal contact between the gate lip and the
sil] beam.
~ Gate wheels made of cast tron with chill-hardened rims, slightly
crowned.
~ Hheel bearings consisting of self-lubricating bushings rotating on
concentric axles (Figure 3),
~ Gates equipped with one pair of side guide rollers at the bottom and
four back guide shoes.
~ Roller paths made of hot rolled plain carbon steel, aligned to a
tolerance of *0.8 mm over 3 m.
~ Motor shaft of gate hoist (cable drum type) equipped with a
solenoid-operated brake for holding, and a fan brake for lowering.
Headgate Operation
Headgates are used either fully open or fully closed. During normal
plant operation, the gates are suspended in a poised position above the
Penstock inlets by the hoist cable which is wound around the cable
drum. The solenoid-operated holding brake prevents the drum from
rotating. If the solenoid becomes de-energized (e.g., by an overspeed
Signal), it releases the holding brake and the gate begins to descend.
In the downward mode, the cable drum is driven by the weight of the
gate only, which unwinds the hoist cable until the gate arrives at the
bottom. “The fan brake keeps the lowering speed within safe limits.
Lifting the gate is accomplished by an electric motor via speed
reduction gears driving the cable drum.
In an emergency shut-off, the wicket gate position switch in the unit
brake circuit is bypassed and all headgates at a given unit are dropped
simultaneously.
If the gates are used for unit isolation (dewatering), they are lowered
in still water, t.e., wicket gates closed and penstock full. Priming a
dewatered penstock 18 accomplished by lifting one headgate by about
10 cm off the sill and allowing the penstock to fill. This initial
lifting exerts maximum loading on the hoist mechanism, because the gate
in this condition is subjected to maximum hydrostatic pressure.
Maintenance History
Typically the subject headgates were removed from the gate slots every
15 to 20 years for sandblasting and recoating. At the same time, the
gates were also inspected for structural integrity and repaired as
required. Repairs included: rivet head welds, freeing seized wheel
bearings, straightening deformed seals and replacing deteriorated
rubber hoses under the seals.
0293H2.4
3.0
3.1
3.2
Performance History
There 1s no documented commissioning record showing that the headgates
closed under flow when they were new, although headgate closing
Problems have been documented as far back’ as the 1930's. The standard
approach tn dealing with the problem was to add weight to the gates,
2-9. concrete or pig iron. The additional ballast seemed to help in
the short term, but a few years later the problem situation reoccurred
and became progressively worse. Sometimes, even more weight was added;
however, the lifting capacity of the gate hoist clearly was the
limiting factor of this practice.
Instrumented drop tests were carried out in 1956 at the Chenaux
Generating Station. Subsequent analysis of the obtained force
measurements showed that the net vertical force available to complete
Closure was unduly small. The maximum measured hoist load during
priming was 280 per cent of the gate submerged weight. Adding more
ballast to the gates was clearly not an option in this case, because
the hoist rating was already exceeded by 35%. No inspections were
Performed at the time to check the condition of the rolling and sliding
components.
PROBLEM ASSESSMENT
Methodology
In an attempt to obtain a more accurate and complete picture of the
gate closing problem at the identified plants, and to establish some
order of priority for future rehabilitation work, it was decided to
take the following steps:
Perform drop tests to find out how far the gates go down.
Carry out inspections to assess deteriorations and deficiencies.
= Compute and analyze forces acting on the problem gates.
~ Conduct a hydraulic model study to visualize gate movement under flow
and to investigate hydraulic downpull.
Drop Tests
Headgate drop tests were carried out at full unit flow, {.e., with the
wicket gates blocked at 100%. All headgates of a given unit were
released simultaneously by push button control from the hoist house.
The following parameters were recorded:
~- Head pond level
~ Hoist load
= Gate position
0293H3.3
3.3.1
3.3.2
~ Scroll case pressure
- Unit output with headgates in final position. (If the water flow
became too small to maintain an electric output, the generator
circuit breaker was opened.)
The hoist load was measured with a strain gauge balance and was plotted
on a strip chart, together with gate position as a function of time.
The headgates typically came to a stop at some distance above the sill,
with enough water flowing under the hung-up gates to keep the unit on
line. The only way to drop the gates all the way down to the sill from
this position was to refill the penstock by closing the wicket gates.
Inspections
Inspection Techniques
Inspections were generally performed only on one headgate of a given
unit, usually on the gate which stayed open the most in the drop test.
Sectional service gates were installed upstream of this gate to enable
dewatering of the penstock, with the neighbouring headgates in the down
position. This always provided an opportunity to observe gate leakage
(from the downstream side) of the closed gates.
The first part in the inspection procedure was to verify free movement
of the gate in the gate slot. For this purpose, the gate was raised
and lowered while checking side and back clearances and observing gate
travel. The wheels usually did not rotate in this operating mode,
because they were not pressed against the roller path.
The gate was then removed from the gate slot and laid down flat (skin
plate up) on the headworks deck. This enabled a detailed inspection of
Seals, wheels, wheel alignment, side rollers, back guides and gate
bottom lip. Wheel alignment was checked with a tight wire along the
wheel trains. Seal protrusion relative to the wheel crowns was checked
with a tight wire across wheel pairs. Wheel rim pitting was recorded
on a mold.
With the gate removed from the gate slot, the gains could readily be
inspected from top to bottom using a suspended, motorized inspection
platform. Wear patterns, material loss and surface deterioration on
the embedded rolling and sealing surfaces were recorded on plastic
molds. Photographs 1 to 4 show some typical headgate inspection scenes
Inspection Results
Specific inspection results varied from site to site; however, a number
Of findings were common to all of the inspected installations. They
are as follows:
0293HGate Seals
The side seals always showed excessive wear especially in the bottom
half of the gate. The brass seal profile was usually flattened and had
a shiny wear surface (up to 20 mm wide). Seal profile changes are
compared in Figure 5. Seal protrusions relative to the wheel crowns
varied within *4 mm. Local indentations of up to 6 mm were observed
in the side seals and the top seal. Corner joints between side seals
and top seal were generally deformed and misaligned, and this situation
would always result in gate leakage. Rubber hoses under the side seals
were often found to be plugged with debris (cinder) and deteriorated.
Brass seal strips were always free of marine growth.
Gate Bottom Lip
The bottom lip surface of most gates was found to be uneven and rough
with local material loss of up to 6mm. This would result in bottom
leakage.
Wheels
Gate wheels with lubrication lines always rotated freely. This was not
consistently the case for wheels without them. The wheel rims had lost
their crown and the tread surface was generally rough, with local
surface depressions of up to 4 mn.
Wheel alignment as measured by a tight wire over the wheel trains was
off by as much as 4 mm on the largest gates. The smaller gates had
better wheel alignments (1.5 mm).
Wheel diameters on some gates varied from nominal wheel size to 6 mm
undersize.
Side Rollers
Generally, one side roller was free to rotate while the other was
seized on its axle. The free roller was typically worn and under size:
whereas, the seized roller showed no wear or material loss.
Gains
The embedded steel surfaces were generally covered with crusts of
marine growth (barnacles), sometimes up to 20 mm thick. Inspections
performed after a full flow drop test clearly showed the tracks left by
the gate wheels, the seals and the side rollers. The roller path
usually showed significant material loss. At one installation,
material loss was up to 8 mm. Material loss on the seal path was less
Pronounced, only up to 2 mm. A typical condition of deterioration is
depicted in Figure Sb. At several installations, the grooves produced
by the side rollers were up to 2 mm deep
0293H3.4
3.4.1
3.4.2
At Abitibi Canyon GS a sample of the roller path was cut out and
analyzed by Ontario Hydro's Research Division. They found that the
steel used for the roller path fabrication was grade UNS G10150 hot
rolled plain carbon steel meeting the requirements of ASTM
specification A830. This material has only modest strength and wear
resistance (tested yield strength only 27% of wheel contact stress).
It is also highly susceptible to under-deposit pitting corrosion in
neutral or mildly alkaline natural waters.
Si11_and Lintel
The condition of both the sill and the lintel varied greatly from site
to site ranging from even and smooth to grooved and rough.
Gain Bottom Corners
At two sites, excessive accumulation of debris was observed on the sill
in the gain corners. This would prevent complete gate closure, since
the gate end girders would sit on this build up.
Problem Analysis
Seal Friction
The inspections have conclusively shown that the gates are riding too
hard on the side seals due to material loss on the wheel treads and the
roller paths (Figure 5b). This reduces the benefit of the wheels. In
essence, the gates perform more like "sliders" and, hence, experience
additional sliding friction. The brass seal has such a stiff profile
that it is quite capable of carrying a major portion of the hydrostatic
load. Furthermore, sliding friction along the two sides is likely
uneven. This would tilt the gate into an off-plumb position on its
downward travel, since the top of the gate can move freely to either
side (no side rollers at the top). With the wheel tracks aligned
off-plumb, the gate would immediately steer to one side, and would
experience excessive lateral friction on the side rollers and the wheel
hubs.
Mechanism of Roller Path Deterioration
Roller path deterioration as shown in Figure 5b is likely caused by
excessive wheel contact stresses and bio-fouling. Calculations show
that the Hertz contact stresses between wheel rim and roller path
exceed the yield strength of the roller path steel plate by at least
250%. In practice, this would produce plastic deformation of the
roller path during initial use, resulting in a wheel groove of the same
shape as the wheel crown
0293H3.5
4.0
4
Bio-fouling is caused by barnacles (marine growth) which attach
themselves to the steel surfaces and grow protective crusts around
themselves. The steel surface under the barnacle crusts are reduced to
iron oxide in this process. When a headgate 1s dropped under flow,
barnacles and the layer of iron oxide below the barnacles are crushed
by the wheels. This exposes bare metal and attracts new barnacle
growth, hence, the destructive cycle is repeated. The seal paths
deteriorate In a similar way since the leading edges of the brass seals
act as scrapers on the seai paths. Scraping also exposes bare metal
which then attracts new growth. Repetition of this process over many
years can lead to significant material loss as depicted in Figure 5b
Force Analysis
All forces acting on a headgate are a function of gate position with
the exception of gate weight. The “almost closed" position is the one
of most interest since friction forces are maximum and hydraulic
downpull can be considered negligible.
With the existing situation, it fs not possible to separate the
Friction force components (seal, bearing, rolling, side roller) in an
accurate manner, because of unknown wheei/seal load-sharing and unknown
side loads. However, for a typical rehabilitated headgate and roller
path arrangement which is properly guided, these forces can be broken
down and expressed as a percentage of submerged gate weight as follows:
Submerged Gate Weight 100% (down)
Bearing friction including side loads 70% Cup)
Seal friction 5% (up)
Rolling friction 5% Cup)
Downpul1 approx 0
Net Closing Force 20% (down)
In the above analysis, bearing friction is based on self-lubricating
bushings with a friction coefficient of 0.12. Seal friction is based
on PTFE - coated rubber "J" - seals with a friction coefficient of 0.10.
REHABILITATION CONCEPTS
Implementation Plan
The overall objective of the planned rehabilitation projects is to
restore the self-closing and sealing capabilities of the headgates,
without energy production losses. Headgate rehabilitation work will,
therefore, be synchronized with unit overhauls.
0293H4.2
4.3
44
Rehabilitation solutions will depend on the nature and the extent of
deterioration, and may involve any or all of the following activities:
- Refurbishing of roller path and seal face
~ Replacement of seals
- Replacement of wheels and bearings
- Addition of one pair of side rollers
- Addition of deflector vanes
~ Modification of gate bottom to alter hydraulic downpull
Roller Path and Seal Faces
The principal roller path material requirements are: strength,
corrosion resistance and straightness. The choice of material for
roller path refurbishment will, therefore, be a high strength,
Corrosion and wear resistant stainless steel, such as type 630, ordered
to ASTM specification A693 and heat-treated to the H1150 condition.
The seal face requires only moderate wear resistance, but must be
non-bio-fouling and corrosion resistant, to provide a clean contact
Surface with the J-type replacement ‘seal. Figure 6 shows three
rehabilitation options, including a weld repair option (possibly using
robotic welding and grinding). The concept of Figure 6b would require
in-situ machining to prepare an accurate surface for stainless steel
plates. In the option shown in Figure 6c, the material loss on the old
roller path is filled back with: grouting prior to mounting a single new
plate on top. .
~ Seal Replacements
Replacing the existing brass seals with PTFE-coated J-type seals would
appear to be the most obvious requirement in the rehabilitation work.
This type of seal would substantially reduce seal friction. Also, it
has molded corner pieces, thereby, eliminating corner leakage.
However, the J-seals work only on smooth, corrosion-resistant surfaces
which must remain free of barnacles. Therefore, the seal faces on the
gains and the lintel will have to be refurbished too. J-seals on clean
Seal surfaces will also eliminate the requirement for cindering.
Wheel Replacements
The Inspection showed that wheel deficiencies essentially pertain to
the rim portion of the wheel, e.g., loss of material, rough tread
Surface, and out of round. The rest’ of the wheel appeared to be in
good shape and reusable. The intent, therefore, is to provide only one
unit of a plant with new wheels. This will free one set of old wheels
for machine shop work in preparation for the next unit. Material
choices for replacement wheels are:
0293H4.5
4.6
47
- Chilled cast iron as per original specification.
~ Stainless steel type 630, precipitation hardened to condition #1150.
Options for reusing the existing wheels include shrinking or casting
new stainless steel rims to the old wheels.
Bearings
The selection of bearings will be site specific and will depend on the
weight of the gate in water and the wheel load. Self-lubricating
bushings (properly protected and greased) would be the preferred choice
because of their simplicity and reliability. In order to reduce
friction between wheel hubs and gate end girders due to lateral loads,
self-lubricating side washers are proposed.
In cases where the net closing force ts smaller than 20% of the
submerged gate weight, it is intended to use roller bearings in a few
wheel pairs of a given gate. This provision is expected to be most
effective in increasing the net closing force, since friction developed
in a roller bearing is about 8 to 10 times smaller than in a journal
bearing. Roller bearings will also help to reduce the hoist load when
cracking a gate open for priming. The proposed roller bearing
arrangement 15 shown in Figure 7.
The wheels will be equipped with eccentric axles to enable accurate
wheel alignment. This will ensure that the gate load due to the
hydrostatic force 1s evenly spread over all wheels. The axle material
will be high strength stainless steel, type 416 MX.
Side Rollers
All headgates require a second pair of side rollers at the gate top to
Prevent tilting to one side. It would appear that headgates rarely
move down in a straight line, even if seal and wheel friction is equal
on both sides, because of Flow-induced bias to one side.
Deflector Vanes
Gain corners on the sill tend to accumulate debris (stones, bolts,
rivets, silt) because of local flow eddies set up by the gain
geometry. Provision 1s required to flush the area clean, otherwise,
the gate will rest on this debris and will fail to seal. This could be
accomplished by flow diversion vanes attached to the gate bottom.
Model tests would be required to verify the concept.
0293H4.8
5.0
Gate Bottom Changes
A headgate model study is currently being conducted at Ontario Hydro's
Flow Systems Laboratory. The purpose of this study is to determine if
the hydrodynamic characteristics can be modified so that hydraulic
downpull becomes a significant force for gate closure. The intent is
not necessarily to change the magnitude of the downpull (limited
because of hoist capacity), but to alter the location where the maximum
downpull occurs in relation to gate opening. Since the problem
headgates get hung-up in the 5 to 10% opening range, it would be
desirable to maximize hydraulic downpull in this region.
CONCLUDING REMARKS
Headgate rehabilitation requires a firm commitment to safety and plant
reliability. The extent of rehabilitation work should be assessed on a
site specific basis, depending on the nature and degree of
deteriorations, as well as the life expectancy of a given plant.
Technical and financial evaluations will be required to compare
short-term with long-term solutions.
-10-
0293HACKNOWLEDGEMENT
The author wishes to thank Mr. K. Reid for his assistance in completing this
Paper. Also, acknowledgement is given to all the associated departments
within Ontario Hydro who were involved in performing headgate drop tests,
inspections and data analysis.
0293HTABLE |
Size and Operating Range of Headgates with Closing Problems
Unit Generating Capacity 20 to 60 MW
Gate Size (Area) 15 to 62 m*
Head on Sill 10 to 28 m
Nass of Gate 10 to 80 Mg
Max. Hydrostatic Force 1 to 13 MN
Number of Wheels per Gate 8 to 18
Maximum Wheel Load 125 to 722 KN
Wheel Diameter 400 to 840 mm
Gate Lifting Speed 1.2 to 1.5 m/min
Gate Lowering Speed 1.7 to 4 m/min
0293HaSLYA
VL
ages
ASNOHYAAOd
INA yIV —-
luvadvai ~
SAOMTY3H
8
5
8
“
8
g
8
2
z
é
2
2
8
5
8
2
°
g
z
&
5
2
3
3
é
4
y
gfz
2
BIEHOISTING macHNERY, worst House:
ELEVATION
be af
4 gE
}
'
row §
: Le eace or
5 8 eecce® parm
|
z i Sk
lololeloioje ee
VIEW OF GATE LOOKING DOWNSTREAM
TYPICAL HEAD GATE DESIGNSEALING FACE AND FACE OF ROLLER PATH
Bann BRASS OVER
S2nm @ RUBGER HOSE
Sae-/040,
SKIN PLATE:
33mm iw PLACE
SELF-LUBRICATING BRONZE.
Rass wasnen
Sae-s100
KEEPER PLATE-
CAST MOM WHEEL WITH:
cnneeo ano chowneo
roeam.
END GIRDERS.
SIE ROLLER.
baen Gui0E-
row
FigURE-3
SECTIONAL PLAN OF WHEEL ASSEMBLY ANO GATE GUIDESseme race ano tact of —
eee
2.4mm BRASS SEAL OVER
32mm # RUBBER HOSE
| -———_ MEADGATE SKIN PLATE
Figure - 4
SECTION OF LINTEL SEAL£
puare
sein PLarE-
wees oumere noses ZSSS x -
wneee | i i | N ae
(b)
FiguRe-§
PLAN VIEW SECTION OF ROLLER PATH AND SIDE SEAL
(o) New
(b) AFTER 85 YEARS OF SERVICEEXISTING PLATE
fo) $$ wevoine
Ano GRINoING
(6) 8 PLATES Bowe Ano
BOLTED To EXISTING PLATE
AFTER MACHINING
fe) 55 PLATE once ano
BOLTED To EXISTING PLATE ii om
AFTER GRoUTING < KK Foe
SA <<
FIGURE ~6
ROLLER PATH REHABILITATION CONCEPTS.x GUSTS paaeeeh pare *
Na
SS)
EiguRe~7
ROLLER BEARING WHEEL ASSEMBLY