Académique Documents
Professionnel Documents
Culture Documents
Sean Elliffe
Reveal USA
1
What Well Cover
2
Manufacturing Flow
This means you can use the following SAP Planning Tools in
each of the above manufacturing flows:
SCM-APO Demand Planning and Supply Network Planning
Execution
Industry
Type
2
Repetitive
Production
(PP)
Discrete
Process 3
(PP-Pi) Planned Orders
Production Orders Not converted to Production
1 Orders
Process Orders
Cost
Order Based Collector
Type of
Period Based
Costing
4
Repetitive Manufacturing
Repetitive Manufacturing no Production Orders
Simple routings one operation / Generally easiest flow for Cost collector is an open order
one work center producing in SAP for a specific combination of FG
Simple BOM one or two levels Plnd orders not converted to or product version which collects
Semi-finished products processed Production orders all costs and revenues for a long
immediately not put into an period of time (even indefinitely)
No reservations for raw material
interim storage Shop Floor must know what to put Each time we produce the FG or
No confirmations, or if needed, on the line product version , revenues and
they are less detailed, and the costs (via backflush and
Components consumed
recording of actual data is very confirmation) are posted on this
anonymously during backflush
simplified CO-objects. Cost follow up is
Traceability reporting possible simple usually too simple for
Usually, there is no Quality Control only through the batch number of
in SAP in a REM process complex production.
the FG
REM can be used for make-to- No finite scheduling of the orders
stock or make-to-order albeit that
we usually see it in a MTS
Costing is done on cost collector.
business. 5
Repetitive Manufacturing: Process Flow
Processing the Master Plan:
Planned orders created in the MRP run for a material in a
planning table.
Here, you no longer refer to planned orders but to run
schedule quantities.
You can then change these run schedule quantities in
the planning table taking the capacity situation into
account, if necessary.
Production is now controlled on the basis of these run
schedule quantities.
System generates purchase requisitions for externally
Production Execution and procured material components or services.
Backflushing:
Product is usually manufactured in a constant flow Material Staging
over the production line. Interactive pull list is to inform you of
You record actual data (backflush) at regular components whose stock levels have to be
intervals for production quantities manufactured. replenished at the production storage
The system posts the component consumption location.
and production activities with the goods receipt of From the missing quantities screen, you can
the finished product. directly trigger a stock transfer from the
If you work with longer lead times, you can also central warehouse to the production storage
backflush at reporting points on production line. location.
This means you can post component consumption
closer to the actual time that the components were
consumed.
6
Discrete Manufacturing
Discrete Manufacturing based on Production Orders
Grouping requirements into lots Produce products with reference Form of MTO where Assembly
during requirements planning to a particular sales order order is created with the SO
Planning with existing basic data Quantities managed, in terms of Components for the product have
stock for individual sales order already been produced and now
Independent of a particular sales
order. Assemblies and components can only need to be assembled
also be procured for the sales Availability check is carried out for
order that generates the the components when SO created
requirements, and managed in increases reliability with which
stock for this sales order dates can be confirmed
A sales order BOM can then be Changes to the sales order are
generated for sales order BOM automatically made in the
is used to produce the product production order and vice-versa
Planning with existing basic data Planning with existing basic data
independent of a sales order. independent of a sales order.
7
Discrete Manufacturing: Process Flow
Creation / processing of production order:
Manually or by converting a planned order that was
created in production planning and procurement
planning
Reservations are automatically generated for the
necessary material components
System generates purchase requisitions for externally
procured material components or services.
Production:
Components to produce the product are Capacity Management:
withdrawn from stock for the production Capacity requirements are generated in the work
order and the goods issue is posted centers that are to process the production order
Required product is produced according to Evaluation of capacity and if necessary levelling
the production order capacities at any stage in production order
Quantities produced and the times needed processing before production starts
to do so are confirmed for the production Preliminary costing carried out to determine the
order planned costs
Products are placed into stock and the Relevant materials and capacities are available to
goods receipt is posted release the production order and print the
Quality Inspection aligned to production relevant shop floor papers.
process 8
Process Manufacturing
Process Manufacturing Process Orders similar to Production
Orders
10
What Well Cover
11
Detailed Comparison
Order-Based Production (Discrete) Repetitive Manufacturing (REM)
1. PLANNING
1. Capacity Planning is done at the work center level 1. MPS creates planned orders
2. Planned orders are transformed by Planning into 2. Capacity planning is done against production Lines
Production Orders (Planning Table)
3. Reservations are created for the components 3. Thus, there is no release of production orders, nor
4. Finished products are typically manufactured in reservation for raw material
individual lots, and the sequence on the work centers 4. The same product is produced on a certain production
can vary between different finished products line over a longer period of time
2. MASTER DATA
1. Bills of material and routings are more complex 1. Routings tend to be very simple
2. Production versions optional 2. Usually simple bills-of-material (one or two levels
maximum)
3. Production versions required
12
Order-Based Detailed Comparison
Planned Order
13
Production Orders: Processes
14
Structure: Master Data
Finance
Cost
Materials Work Center Activity Type
Center
Activity rates at this level
Production Routing
Version
Read PP Copied into Operation
Data Operation
Planned Operation
Order Operation
Operation
Production
Order
15
Detailed Comparison
Order-Based Production (Discrete) Repetitive Manufacturing (REM)
3. SHOP FLOOR CONTROL
1. Discrete manufacturing is characterized by 1. Products are not manufactured in individual lots (lot is
requirements that occur on an irregular basis and a typically one shift)
workshop-oriented process 2. The semi-finished products are processed
2. Semi-finished products are usually put into an interim immediately, without being put into an interim storage
storage location prior to further processing location
3. Confirmations are usually based on actual quantities 3. There is no confirmation, or if needed, they are less
(labor, machine, energy, etc.) detailed, and the recording of actual data is very
4. Confirmations are done at Production Order Operation simplified
level or at Order level 4. Traceability reporting is possible, but only through the
5. Better shop floor visibility batch number of the finished product
6. Production lines are thus replenished via the 5. Confirmation will be without ref to planned orders
production orders
7. Back flush is possible, but often, the actual quantities
of components are issued by production order
16
Shop Floor Control
MRP Related
Update of
Expected Yield
Confirmation
Reduction of
Quantity Automatic GR
Capacity on Activity Used
Processed in
to Carry out
for FG
Resources Operation (
scrap and Yield) Operation
Actual Start
and Finish
Date
Who carried
Update of Resource
out the Backflushing
cost information
Operation
Update of the
Order Data
17
Comparison: Shop Floor Control
Discrete STD SAP Reports
Repetitive STD SAP Reports
18
Detailed Comparison
19
Detailed Comparison (cont.)
20
Detailed Comparison (cont.)
Order-Based Production (Discrete) Repetitive Manufacturing (REM)
6. CONTROLLING
1. Order-based 1. Period-based
2. Detailed controlling for each order by comparing plan 2. Costing is done on cost collector level
and actual figures 3. Settlement is at Material level
3. Settlement is done at the Production Order level 4. Cost follow up is really simple in REM; usually too
4. Actual production costs at Order level simple for complex production
Routings are valuated with activity prices at standard Similar functionalities as production orders, except:
Primary costs on cost center divided by planned activities Only visible at product level
from Long-Term Planning as an example Settlement happens at month-end
Bill of Material
Consumption of raw material, packaging at moving average
price
Consumption of semi-finished or finished goods at standard
Month-end
Revaluate the activities at actual price
WIP calculation based on Production Order Status
Calculated Variances are charged to P&L
Settlement of Variances at month-end or at close status
Costing runs for standard cost can be done on a monthly basis
Can break down costs by component, i.e., packaging, steel,
molding (up to 46)
Can use additives for various costs, such as forwarding
freight between plants
Overhead cost as a % or quantity of a component
Costing templates for complex calculation
21
Comparison Summary
Order-Based Production (Discrete) Repetitive Manufacturing (Period/Rate-Based)
1. There is frequent switching from one product to another 1. The same product is produced on a certain production
2. Each product is manufactured in individually defined line over a longer period of time
lots 2. In production, a total quantity is produced according to
3. Costs are calculated per order a certain production rate over a certain period of time
4. Usually has a changing sequence of work centers 3. Costs are collected periodically at a product cost
where the products are processed collector
5. The order of work centers is determined in routings, 4. Usually involves a relatively constant flow through
which can often be very complex production lines
6. Semi-finished products are frequently placed in interim 5. The routings of the individual products are very similar
storage prior to further processing 6. Semi-finished products often directly processed
7. Component materials are staged with specific reference without interim storage
to the individual production orders 7. Components are often staged at the production lines
8. Confirmations for the various steps and orders without reference to a particular order
document the work progress and can be used for fine 8. The confirmations (back flushes) are usually executed
control periodically with no reference to an order (for example,
9. Order-based cost controlling all the quantities produced in one shift)
9. Period-based cost controlling
22
What Well Cover
23
Connect to the Strategic Business Focus
Typical Business Cycle
Typical Areas of
Optimization
Production and Capacity Planning
process often relies on
information outside of SAP
Data Integrity
1 Challenge Business Rules
2
Housekeeping SAP Integration
24
Information Maturity Drives Value
25
Integrating the Supply Chain
Managing Capacity Constraints Is Critical
Sales Forecast
Rough
Strategic
1 Cut Check Sales & Ops Planning
SO
ATP
Demand Management Tactical
Capacity
2 Evaluation Master Prod Sched
Actual
Orders
consume
forecast
Sequencing,
3 Capacity
Leveling,
Create Sales
Forecast
Scheduling based on
Quantities and
Historic
Dates
Demand
External Mat Req. Planning Prod
Procurement
ATP
Requisitions Planned Orders
Raw Finished
Materials
Production/Process Goods
Supplier Customer
Inventory Order Execution Inventory
Sales Orders
Purchase Orders
Supply Chain Exception Monitoring for
End-to-End Visibility essential 26
Integrating the Supply Chain
Managing Capacity Constraints Is Critical (cont.) Align S&OP in SAP Sales Forecast,
Rough Cut Resource CO-PA, RCCP, Business Plans, and
Sales Forecast simplify process, e.g., Planning Books
Planning
Rough
Strategic
1 Cut Check Sales & Ops Planning
Capacity Evaluation functionality SO
available and not used effectively in ATP
SAP, resulting in move to introduce
Demand Management Tactical
external systems to compensate
Sales Order ATP set up to
Capacity align to business
Actual needs
2 Evaluation Master Prod Sched Orders
consume
Poor Data Integrity/Housekeeping
forecast
negatively impact S/D planning
Sequencing, Planning strategies/business
Sequencing, capacity rules aligned/adjusted
3 Capacity
Leveling, levelling, and scheduling
Create Sales
Forecast
Scheduling functionality to be used Quantities and Component availability
based on
Historic
Dates for production orders Demand
Conversion of Production
Orders at opening period
External Mat Req. Planning Prod
Procurement
ATP
Requisitions Planned Orders
Raw Finished
Materials
Production/Process Goods
Supplier Customer
Inventory Order Execution Inventory
Sales Orders
Purchase Orders
Supply Chain Exception Monitoring for Fair Share allocations
End-to-End Visibility essential 27
Customer demand driven in product hierarchies from
Bringing It All Together S&OP through demand management supported by
product allocation and available-to-promise
New
Strategic Supply Make Distribution
Products
Areas of Strategic
Focus Pull
Demand
Master with
Data S&OP
Reduce
Safety Cycle Time
Stock
Scheduli-
Waste
ng in SAP
Inventory
28
What Well Cover
29
Correct Planning Strategies
Key to Driving Your Advantage
We need the planning strategy for a product to create the
demand program. Planning strategies:
Represent the methods of production for planning and
manufacturing or procuring a product
Provide the business procedures for planning
production quantities and dates MTS/MTO/FTO
By using these correctly, we can:
Use sales orders and/or sales forecast values to
create the demand program
Move the stocking level down to the assembly level,
so that final assembly is triggered by the incoming
sales order
Carry out Demand Management specifically for the
assembly
We can combine planning strategies at, say, the finished
good level (40) and still apply a different strategy for an
assembly (70) in the Bill of Materials (BOM)
30
Planning Strategies and Available to Promise (ATP)
Will sales orders that exceed the Demand plan add to the
plan or be ignored?
Will Replenishment lead time be taken into account in the
ATP check if Stock and Production/Process orders do not
exist?
Will ATP be performed based on Scope of Check or simply
against the Plan (Planned Independent Requirements)
31
Making the Decision MTS vs. MTO vs. FTO
Does Procurement/Production Take Place Before/After Sales
Order?
FG Forecast Driver
Make to stock means you make and
procure in anticipation of actual orders
10
This supply plan is generated by MRP based on
11 forecasted demand
40
Stock purchased or manufactured is placed in
free available stock and issued to actual
52 63
Generic Stock demand as required
FTO Planning Material
FG Forecast Driver excl 20
Make to Order means your procurement plan is
generated based upon the entry of actual orders
only
20 You can be MTO for a finished product, but still
be MTS for the sub-assemblies and/or raw
SO-Specific Stock 50 60 materials
FTO Planning Material
33
Balancing Supply and Demand Across the Supply
Chain
8 Demand Production Schedule
Forecast (S&OP)
Over/Under Sales 1
Cant plan Integration
Production
6 7 Maintenance
ATP Rules MRP
MRP
Proposal Planned Order
Inventory 4 Purchase Requisition
Actual
Plan
Supply
Expedite
5 BOM
3
Finish Schedule Start
Process/Production Order
Purchase Order 2
Exception Monitoring (EM) Wheel Schedule Firming 34
Exception Messages Measure Process Efficiency
35
EM Aligns Supply Chain: Plan Schedule Actual
Finished Semi-Finished RAW
Plan Finished Product Product
Product Material
Planned Dep Req Purchase
Ind Req
Order Requisition
X X X
Supplier
Forecast
X X X
Sales Production Purchase
Schedule Order Order
Reservation
Order
Actual Vendor
X X X
Customer Del GR GI GR
Sales FG Inventory
Order
36
What Well Cover
37
Capacity Planning Links with Business Goals
and S&OP
38
Capacity Planning Is 3
Relevant in the long-
1 term and the short-
Process to determine term, although there Link back
how much and when are different issues to S&OP
2 capacity is needed to at stake for each
Factors affecting produce new or more
capacity include: product
Number of workers
and ability of Issues facing Capacity Planning over a Time Horizon
workers
Number of
machines
Waste, scrap,
defects, errors
Productivity
Suppliers
Government
regulations
Preventive
maintenance
39
Capacity Planning and Bottleneck Management
Evaluation
Capacity Available capacity & capacity
Evaluation requirements are determined &
compared with each other in lists or graphics
CRP functionality Planner manually makes changes to the demand
broken into two main
constituent parts and/or supply and rechecks the evaluation (an iterative
process)
Capacity Leveling
Leveling Optimal capacity commitment is made automatically to
all capacities (e.g., labor and machine)
Optional: sequence like orders together to spend less
time setting up and more time producing
41
Capacity Information
Capacity requirement
Represents the capacity load and is calculated using formulas from the work center,
Generating dates, and quantities from planned and production orders
capacity Load distribution
requirements
(load) Determines how a capacity requirement for a given capacity type, which spans multiple
days, is distributed across each day in the time interval
Capacity requirement reduction
Progress-based reduction of planned capacity load
Capacity evaluation
Evaluating
Provides an overview of the capacity load and available capacity
available
capacity Hierarchy/accumulation
Available capacity, load, and evaluation for a group of work centers
43
Multiple Capacities at One Work Center
Person
45
Capacity Planning During Sales & Operations
Planning
Dispatch the operations from the lower pool to the upper work
center, taking into consideration the capacity and working times 49
Capacity Adjustment Decisions
Defining
available
capacity
Generating
Evaluating
capacity
available
requirements
capacity
(load)
51
Analysis Helps Drive Us to Predictability
53
Grouping the Data: Swim Lanes
Critical
A, B, C
54
Data Hierarchy and Ownership
55
Integrated Supply to Demand
Gate Control
MRP
Master Data
Routings
Crowd Control Work Centers
MRP
BOMs
Master Data
Logistics
56
Integrated Supply to Demand (cont.)
Produce Later than Planned
Gate Control
MRP
Master Data Schedule In
Impacting Customer Orders
Crowd Control
MRP
Master Data
Schedule Out
Inflating Inventory
58
5 Competitive Priorities That Add Value to Decisions
Increase Upper-Quartile Performance
1. Cost standardized products enabling economies of scale
2. Quality conform to requirements or fitness for use
3. Delivery speed and reliability
4. Flexibility product range, volume capability, introduce new
5. Innovation focus on target market segments with tailored mix
Maha Muzumdar and John Fontanella, The Secrets to S&OP Success (Supply
Chain Management Review, Aberdeen Group, April 2006).
62
What Well Cover
63
Where to Find More Information
SAP and other SAP products and services mentioned herein as well as their respective logos are trademarks or registered trademarks of SAP SE (or
an SAP affiliate company) in Germany and other countries. All other product and service names mentioned are the trademarks of their respective
companies. Wellesley Information Services is neither owned nor controlled by SAP SE.
68
Wellesley Information Services, 20 Carematrix Drive, Dedham, MA 02026
Copyright 2015 Wellesley Information Services. All rights reserved.