1.0 TITLE
Method statement for construction of Pump House.
2.0 PURPOSE:
To understand the total project activities and preparation of an execution plan/scheme. To guide
further planning of manpower, major equipment, specialized agencies and identification of critical activities,
requirements of method statement, Quality plan for effective project execution.
3.0 SCOPE:
This procedure covers the sequence of method shall be followed for construction of Pump house
as per project specification.
5.0 RESPONSIBILITY:
Responsibility shall be lies with Section in-Charge, Site Engineer & Supervisor. However ultimate
responsibility will be with Project Manager.
The following equipments shall be used in order to execute the work. Ensure that available at site
prior to start the work as per the actual requirement.
Excavator
New Generation Hydra Crane with hook latch.
Mixer Machine
Vibrator (Diesel / electric)
Dewatering Pump
Diesel Generator
Bar Cutting Machine
Total station, Auto Level
Measuring steel tape
Sprit Level and Tri square
Water Level
Plum bob
7.0 SAFETY
EHS Safe work method shall be strictly followed while execution of work. Necessary safety pep talk
shall be conducted prior to start of activity in order to create awareness to the workmen.
To protect persons from injury and to avoid damage to property, adequate barricades, construction
signs, and guards, as required, shall be placed and maintained during the progress of the
construction work.
5 PROCEDURES:
5.1 MATERIALS:
Concrete: The M15 (Nominal Mix), M20 & M25 (Nominal mix / Design mix) grade of
Concrete conforming to the Specification /Drawing. The concrete shall have a slump
of 70 to 120 mm for manual concrete.
Reinforcement: General reinforcement steel shall be Deformed High Yield Steel Bars
conforming to IS: 1786:2008 with characteristics yield strength of 415 N/mm2.
Formwork System: The components, assembly, and execution shall be as per the
site requirement.
Cement: OPC 43Grade Cement of approved make to be used for civil works shall
confirm to all relevant IS code 8112:2013 as mentioned in the reference and as
specified in the contract. The cement shall be stored above ground in a suitable
weather tight go-down and in such a manner to permit easy access for proper
inspection and also to prevent deformation due to moisture.
Water: Water used in construction for all civil works shall be clean and free from
injurious amount of oil, acids, alkalis, organic matters or other harmful substances
which may be decorous to concrete and it shall meet all the requirements of IS: 456. If
required the water shall be got tested from an approved laboratory before starting of
construction work.
Ensure that sufficient quantity of materials required is available for the days pour.
Ensure that all the P&M required for concreting are in working condition.
Ensure that man power required are in sufficient quantity for the days pour
Ensure that embedment like insert plates, bolts etc.
Concrete of required grade and workability shall be poured within 1 hour since mixing
Concrete shall not segregate while conveying and placing and the concrete shall be
mixed as near as possible to its final location. Concrete shall not be moved over long
distance using vibrator.
Always Vertical drop chute shall be used at the end of sloping chutes to avoid
segregation.
Vibrator shall be applied systematically to cover all the areas immediately after placing
concrete.
The vibrator needle 40MM to 60MM shall penetrate the layer of concrete vertically and
into the underlying layer previously placed and vibrated if possible.
Stop the vibrating when the concrete flattens and takes up glistering appearance, the
rise of entrapped air ceases, the coarse aggregate blends into the surface but does
not completely disappear in the vibrator after an initial slowdown when inserted
resumes its speed.
Withdraw the vibrator slowly to ensure closing of the void resulting from insertion.
Always follow correct placing and techniques.
Ensure that the top layer of concrete is as required and finished suitably.
Ensure the curing for specified duration.
For large, unformed area structures like slabs, mass foundation curing shall be started
as soon as concrete has set and for formed surfaces curing shall start as soon as
formwork is removed.
SURVEY
Survey shall be conducted by the surveyor as per the co-ordinates shown in the
drawing with reference to the GPS identified by the Engineer / Client.
Levels shall be transferred from the identified benchmarks, which shall be established
near the site in an undisturbed structure. This will be used in future activities &
periodically these survey points shall be checked to find the accuracy.
Before starting the activities for any building the closed transverse shall be completed.
The survey team shall do the marking for the column and other structures, which will
be checked by the site engineer.
EXCAVATION
Once the survey work is completed, the centerline shall be marked on the Portion to
be excavated.
The excavation may be done mechanically or manually according to the site and soil
condition to the required dimension and to the required depth as per the drawing with
due consideration for the workable space. Excavate as per the excavation scheme.
Avoid over excavation.
If the excavation is deeper adopt shoring if required.
Keep excavation pits free from water .use dewatering pumps if required.
Completed excavation, trim to required level, check level and dimensions. Approve for
PCC.
If the excavated soil is found sandy the same shall be used for backfilling otherwise
any other approved earth shall be used for backfilling.
Spread earth in layering of 300 mm. Sprinkle water for optimum moisture content
compact using rollers or earth rammers.
The compaction shall be checked with sand replacement and Core cutter method.
REINFORCEMENT
Approved Brands of steel shall be used for reinforcement.
Prepare the BBS based on the reinforcement drawings.
Ensure that reinforcement rod of required size is only put in use. The reinforcement
rods shall be cut and bend as per the BBS prepared. Gas cutting is not permitted for
cutting and bending the rods.
Place the rods as per the drawing, Take care that the lapping is always staggered &
no adjacent bars have laps at same location or in the zone of 1.1 times lap length in
either direction & the lapping length shall be as per the drawing.
Verify the spacing & number of shear rings before tying the rods. The rods shall be
tied with binding wire and all ends of wire shall be kept within the cage & no wire ends
should protrude in the cover zone.
Ensure sufficient numbers of cover blocks for (Raft 60mm, 50mm, 40mm for Plinth
beam & Columns, 25mm for slab) at approximately 1 m distance is fixed.
If any insert plates are to fixed for beams, the same shall be cut to the required
dimension
Weld the required no of lugs in the plate. Ensure proper arresting of the plates while
welding the plate with the lugs so that the face is not distorted.
Tie / Weld the lugs of the insert plate along with the main and shear rods. Check the
face of the insert plates after tying / welding the lugs, any rectification shall be done by
adjusting the lugs in the required locations.
If the concreting is a continuation of the existing structure, ensure that the structure is
chipped before placing the reinforcement & also the reinforcement of the existing
structure shall be over lapped and tied properly with the Reinforcement for which
concrete is to be done.
As per the requirement of the structure, select the shuttering sheets/ plates.
The shuttering shall be placed as per the requirement of the building / structure.
The shutters shall be properly cleaned and oiled before put in use; this shall enable us
to get a good finish of the concrete. If the shuttering sheets are found to be having any
minor damages, rectify the same before they are placed.
Ensure that the shuttering plates are properly supported, to avoid bulging while
concreting.
Check for the verticality and rectify the same by adjusting the supports provided.
The shuttering shall be leak proof, if any gap is found the same may be filled with
Cement mortar below the formwork. For vertical faces sponge sheet or putty shall be
used.
CONCRETE
Ensure that enough bulk materials such as cement, aggregates & Admixture are
available for the concreting work.
Before starting the concreting work check whether the materials were brought from
approved source or not. Also you can check the calibration of respective equipments
to be used for the concreting mixing work
Prior to start of placement of concrete, the entire area, which has been approved for
pouring of concrete.
If the old concrete surface has remained exposed for more than two weeks, it shall be
prepared by chipping to a depth of two centimetres and the surface coated or covered
with a layer of cement mortar (1:2) for a depth of 5 to 8 cm.
The concreting shall be started from one end of the segment. The concreting shall
progress towards other end of the sector. The slump of each pour of concrete shall be
checked at site.
Concrete shall not be dropped from excessive heights and free fall shall be kept to a
maximum of 1.5m.
All the concrete shall be placed directly in its final position within 30 minutes of mixing.
The concrete shall be compacted with high frequency immersion vibrators. The size of
vibrator needle shall generally be 40 or 60mm. Dia. Adequate no. Of vibrators needles
shall be provided for compaction of concrete.
The leveling of concrete shall generally be done with manual screed. It shall be done
two times, first, just after placing concrete and II nd, after two hours of concrete
placing. This finished level of concrete shall be checked regularly during concreting.
The required number of cubes shall be taken and tested for strength for 7 & 28 days.
The acceptance shall be based on the cube results.
The curing shall be done, with wet Hessian cloth and later by flooding with water.
Curing shall be done as per technical specification. Concrete casting date to be
painted on column to ensure curing period and curing register shall be maintained
The required grade of concrete as per approved drawings/Technical Specification shall
be taken from the alternatively from the mixer machine placed near the concreting
area.
Opening space to be provide at plot form slab for cable tray
Required to provide 150x300x8mm thick MS insert plates at every 2.0m Horizontal
distance at Roof beam 1 to provide 200 ISMB
Fan hooks to be providing at roof slab.
COLUMN CONSTRUCTION
Prepare the column joint by properly chipping & removing all loose material.
Prepare Column / starter construction Joint. Minimum size of the starter shall be 150
mm.
Install prefabricated column cage in place, position cage with Starter Bars of footing,
Place cover blocks.
Alternately - place two sides of readymade column shutter, mark casting level by
nailing 40 x 20mm Timber on shutter place reinf cage. Align (use foam strips at
Construction Joint)
Close Shutter, Provide top of conc. Level required, by nailing 40 x 20 mm Timber.
Align Column Shutter using push pull props. Check alignment with Theodolite for both
directions.
Hang Plumb 300mm away from Column face. Check plumb top and bottom both
directions.
Concrete Column after Checks and record in format.
De shutter after 12 hrs. Check product, Plumb etc., Record in format and start curing.
Concrete casting date to be painted on column to ensure curing period and curing
register shall be maintained
Provide shear key at the top of concrete for next lift.
PLASTERING
Confirm Plaster type / coat as per drawing and specification.
Select sand as per requirements.
Ensure required quantity of cement, measuring box, Thickness gauges, Wooden float
straight edge kept at location.
Dampen the surface which is to receive plastering
Provide adequate scaffold for safety in advance.
Mix of sand (1:4 & 1:6 as per Approved Drg, cement & sand by volume), Cement to
specified proportions as per drawing, on a mixing platform.
For base coat after finishing true and even, roughen the surface with wooden float to
provide bond for finish coat.
Damp cure base coat for at least 2 days and allow it to dry before starting finish coat.
Dampen the basecoat / masonry surface before applying finish coat.
Mix sand, cement as per specified proportions. (Use mortar within 1 hr. of mixing).
Apply and finish true to plane and to the required surface finish Check at every stage
and record checks.
FLOOR WORK:
ACCCEPTANCE CRITERIA: