1. Client PETROPERU
2. Vendor /Sub-vendor John Zink Hamworthy
Jiangsu process Metal equipment CO.,LTD.
3. Inspector Name Shao Chunwei
4. PO number 020700114
5. Project Name P02070, Modernizacion de la Refineria de Talara
(TRM)
6. Inspection Location Dongping Town,Lishui District,
Nanjing,Jiangsu,P.R.China
7. Date of Inspection Fab. 17, 2016
8. Next Inspection date Tomorrow
9. Type of Inspection Visual inspection
10. Material Inspected N/A
11.Details and Results of Inspection:
11.1 Witness welding and verification welding consumable and parameter
TR inspector andom checking the welding parameter and consumble according to the
WPS, confirm that use the correct consumble and the welding parameter within the
requirement rang. Also verified that the welding profile and size conform to the drawing and
welding procedure specification.
Photos:
Ask manufacturer to repair the scratched
FB2-L-002 (15JZ-37-1) of piping
area
The pad plates hole diemnsion smaller The pad plates hole diemnsion smaller
than lifting lugs hole dimension than lifting lugs hole dimension
Ask manufacturer to repair Ask manufacturer to repair
Found air hole on the welding seam Found spatters on the welding seam
Ask manufacturer to repair Ask manufacturer to cleaning
12.NCR Raised : Yes No
If Yes, please attach the NCR copy.