Académique Documents
Professionnel Documents
Culture Documents
1
Contract & Tender
2
Basic Construction contract, contract
document:-
Offer
Acceptance
Consideration
3
At this time, Client will approach respective experts
to ready with:-
Architect Architecture drawings
C&S Consultant C&S drawings
M&E Consultant M&E drawings
QS Bill of Quantities
4
All buildings must COMPLY to Laws of Malaysia:-
Uniform Building By-Laws 1984
Part I - Preliminary
Part II - Submission of plans for approval
Part III - Space, Light and Ventilation
Part IV - Temporary Works in connection with
building operations
Part V - Structural Requirements
5
All buildings must COMPLY to Laws of Malaysia:-
Uniform Building By-Laws 1984
Part VI - Constructional requirements
Part VII - Fire requirements
Part VIII - Fire alarms, fire detection, fire
extinguishment and fire fighting process
Part IX - Miscellaneous
6
At the same time, Client office will start preparing:-
7
The elements of contract comprises of:-
Definition
It defines the main duty for:-
Architect
Consultants (C&S, M&E, QS)
Contractor
Domestic Sub-Con (DSC), Nominated Sub-Con
(NSC)
8
The elements of contract comprises of:-
It consists of:-
Form of tender
Article of Agreement
LA (Letter of Award)
Appendix to the Conditions
Bill of Quantities
Specifications
Drawings
Schedule of Rates
9
Form of tender
10
Article of Agreement
11
ITEM DESCRIPTION UNIT QTY. RATE AMOUNT
(RM) (RM)
B Pit for pad footing not exceeding 1.50m deep m3 273 10.00 2,730.00
C Pit for stump footing (S1) not exceeding 1.50m deep m3 8 10.00 80.00
D Pit for lift pit not exceeding 1.50m deep m3 27 10.00 270.00
E Ditto exceeding 1.50m and not exceeding 3.00m deep m3 15 12.00 180.00
12
Quanti Amount
Item Description Unit Rate (RM)
ty (RM)
D ELECTRICAL INSTALLATION
13
15.0 LIST OF MATERIAL/CATELOGUE SUBMISSION
Brand/Su
plier
Brand/Supplier
ITE Material Brand/Supplier as stated in the as stated
(Contractor
M Description BQ (APPROVED BY SJMC) in the
Proposed)
Specifica
tion
ELECTRICAL
1
SERVICES
a H. T. Switchgear ABB, MG, GE, SIEMEN or Eq.
TESAR, TRIHAL, SIEMENS,
b Transformer
SUNTEN or Eq.
c Generator Set CATERPILLAR or Eq.
d Bus Duct BICC, SQUARE D or Eq
LV MSB/Bub SMB, SRS POWER,
e
Switchboards COPPERTECH or Eq
f Distribution Boards HAGER, SMB, SRS, or Eq.
14
Specifications
Criteria of Compliance
Sampling
Method of testing
Tolerance
15
Specifications
It consists of:-
a. Architectural Specification.
Eg. Detail of work done, sampling and method of testing
etc.
b. C&S Specification
Eg. Concrete cover, overlapping steel, link type & size etc.
c. M&E Specification
Eg. Type of cable, Brand of DB and genset, Testing &
commissioning etc.
16
Drawings
17
18
19
20
21
Other Tender Drawings
Earthwork drawing
Piling drawing
Drainage drawing
22
Other Drawings
Authority drawing
(Syabas, Hydrant,
TNB) etc
Fire Protection
System drawing
Plumbing Services
23
And,
Schedule of Rates
Rate to provide for future references for
addition or omission work
24
In the Condition of Contract, It also includes :-
Performance guarantees
Bank Guarantee To ensure the Company is clean and
financially capable to carry out the work
25
Commencement, completion and defect liability
Clearly indicate the duration for the overall project
and defect liability period
26
Insurances & public safety
Refer to project, team, individual
that involve in the particular
project
Dispute & resolution In such a case when the activity carry out
not comply to the requirements as in contract document
27
Last but not least, It also includes :-
Form of tender
Important document to show the interest of tenderer
with the companys authorized signature.
28
Preliminaries and General Condition
It describes the information relating to the Works
as whole.
Contractors general cost, provision sums and
work by others
Law requirement
Submission requirement
Explanation of condition of contract
A general summary
General site summary
Insurance and bond requirement
Maintenance requirement
29
Preliminaries and General Condition (Continued)
Pre-construction information
Progress claim method
Progress report
Site waste management
Work scheduling
Utility application & installation
Safety & Health Management
Quality Management
and so on
30
Form of Contract
PAM 2006
IEM Form of Contract
P.W.D Form of Contract
CIDB Form of Contract
31
Certification
CPC - Certificate of Practical Completion
Issued by the architect (Superintendent Officer (SO) to the
main contractor
Architect satisfies with all the physical works being
completed in the building.
CPC might includes getting all the supporting documents
from all relevant authority for the application of CF (Certificate
of Fitness) such as bomba, tnb, syabas, TM, local council
(forgotten how many departments in total), JPS (road and
drainage), IWK (sewerage) and a few more.
Main contractor able to claim for the release of 1st 2.5% of
the 5% retention sum
32
Certification
33
You are now ready to compile
tender document
34
In general, the contract planning, scheduling & Implementation
process as follow:-
Planning & Scheduling HR & Material planning
stage Financial planning
Appointment of Subcon
& suppliers
35
After compiling, you can now call for
tendering
36
The main purpose of tendering to:-
Risk management
37
Invitation for tender
Not consider as an offer
Tender submission is an offer
Client has no obligation to accept any tender
Invited tender
38
The selection may based on:
Financial qualified
Company size
Bank guarantee
Companys assets
Technically qualified
Expertise in the team
Qualification
Year of experience
39
The selection may based on:
Mandatory requirement
CIDB, ISO, OSHAS, CONQUAS
Project in hand
40
Other considerations:
Reputation of the company
Office & Site support
Performance
Word of mouth
41
Others require information in tender document:-
Period of tender
Cost of tender
42
Shortlisted:-
Tender interview after 1st round of shortlisting
43
Letter of Award (LA)
44
Bear in mind, all the discussion MUST:-
Documented in the letter and forming part of
the award
If involves new conditions, must clearly
stated in the letter of Award
All new scopes of work must be clearly spelt
out
45
However, the offer could become invalid if:-
Exceed the period of offer
Rejected by tenderer
46
However, the Contract is deemed to be Voidable
Contract if:-
Misrepresentation
Fraud
Illegal
Duress or coercion
47
Kick of meeting work starts
Congrats
on your new Project
48
CONCLUSION FOR CONTRACT & TENDER
Topic discussed:
Communication and tender as invitation to treat
Tender process and tender document
Preliminary & General condition
Specification
Bill of quantity
Implementation of contract and project monitoring
Claim & certification, and standard method of
measurement
Variation order, completion, dispute resolution
49