QMIS: RFI Entry

User1 : SAMUEL | Role : Contractor QC | Change Password | Change Role | Logout

Contractor Data Entry For Project {10-01277-6892} Initiated By (SAMUEL)

Project No: 10-01277-6892 Plant ID.: SAUDI KAD JO/WBS:::

Contractor RFI Reference: W-577 Sub System ID.:

Discipline: Mechanical Eng. Index: W

SATIP Ref #: SATIP-W-012-01 Project Phase: INSTALLATION


SATIP Title: Welding of Pipelines
SAIC Ref #: SAIC-W-20
SAIC Title: Modification or Re-Work After Weld Acceptance (Use with SAIC-W-2051)

Contractor Insp. Level: H Scheduled Insp. Date: 03/16/2017

Aramco Insp. Level: H Scheduled Insp. Time: 9:00:00 AM

Equipment ID/Description.: .Modification or Re-Work After Weld Acceptance (Use with SAIC-W-2051)

Layout Drawing No.: .VARIOUS Layout Drawing Rev. No: . Purchase Order No. .

Aramco Activity No.: .3.17

Location
QW-325/159 SITE

Description:
INSPECTION FOR MODIFICATION OF WELD JOINTS FOR DWRG QW-159 CB-802146-001 SW-24,11 MODIFIED DUE FIELD
RFI Description:
REQUIREMENT AS FW-24RW1,11RW1 (SATIP-W-012-01 ; SAIC-W-2036; ACTIVITY NO:3.17) (QC-DANIEL)
Exceptions: .

RFI User Information


User ID Name User Type
HUSAYEJS Jarrah Husayen Saudi Aramco PMT Engineer
MOHAFX0L mohafx0l Saudi Aramco Inspector
SAMUEL SAMUEL Contractor QC
dossmg0c Mohammad Ghannam Dossary SAIR

Contractor Replies
Date Replied By Reply
3/16/2017 2:33:10 PM SAMUEL THIS RFI IS RE SCHEDULE FOR 18 MAR 2017.

PMT Replies
Date Replied By Reply
No Replies

QMIS RFI Data Entry_ 2695 asp W-577.htm[3/21/2017 10:56:30 AM]


QMIS: RFI Entry

SAPID Replies
Date Replied By Reply
No Replies

SAIR Replies
Date Replied By Reply
No Replies

Category Description
Accept & Close RFI Reject-Job Not Ready Reject-Standards Violation Work Not Inspected & Close RFI On Hold (Accepted But Not Closed)

Contractor Reply:

500 Characters Left

Click HereClick
For HereChecklist SAIC-W-20
For Checklist SAIC-W-20


Submit
For Further Assistance Please Call : Ijaz Ahmed - 880 1409 / Mohammad Ahmed- 880 1578
Inspection Department Quality Management Information System Website- Version 4.0. RFI Process || Surveillance Process || QMIS Manual
Designed & Developed by Inspection Department.