Vous êtes sur la page 1sur 3

BY WILLIAM C.

PANARESE
SENIOR CONCRETE TECHNOLOGIST
PORTLAND CEMENT ASSOCIATION
Lightweight concrete
for pumping
T he use of pumps for transport-
ing and handling stru c t u ra l
lightweight aggregate concrete is
High water absorption and different grading
requirements of lightweight aggregates influence
increasing. Lightweight aggregates
are inherently porous, due to their aggregate preparation and mix proportioning
method of manufacture, and will
absorb greater amounts of water lightweight aggregates. The aggre- but the actual time should be based
than conventional concrete aggre- gates are sprinkled at the producers on tests or experience with a partic-
gates. At atmospheric pressure this stockpiles during loading for ship- ular aggregate. Before use in a
absorption may vary from five to 25 ment and again after unloading at pump mix the aggregate should
percent by weight for different the concrete batch plant. From two equal or exceed the 24-hour absorp-
lightweight aggregates; under the to three days of repeated sprinklings tion as measured by Method of Test
pressure exerted by pumping it can may be required to adequately pre- for Specific Gravity and Absorption
be considerably more. If the ab- soak coarse lightweight aggregates of Coarse Aggregate (ASTM C 127).
sorption is significantly increased
during pumping, water loss from
the mortar can impair the pumpa- Aggregate shown
bility of the concrete. Therefore, to greatly enlarged.
pump lightweight concrete suc-
cessfully it is usually necessary to
presoak absorptive aggregates or
otherwise offset the loss of mix wa-
ter. Such processing is not neces-
sarily required for handling light-
weight concrete by methods other
than pumping.

Presoaking
lightweight aggregates
By using a series of sprinklings
some producers have been able to
satisfy absorption requirements of

A dry, highly absorptive aggregate absorbs


much of the surrounding mix water during
pumping and makes the concrete difficult to
pump. If the dame aggregate has been
hydrothermally or vacuum saturated it does
not absorb the mix water and the concrete
remains satisfactory for pumping.
To permit more uniform slump con- TABLE I Volume of normal weight coarse aggregate
trol, free water should be allowed to per cubic yard of concrete*
drain from aggregates for seve ra l
hours before they are used in con- Maximum Fineness modulus of fine aggregate
crete. size of
2.40 2.60 2.80 3.00
Lightweight fine aggregates,* if aggregate,
used, should be presoaked but pre- inches Coarse aggregate, cubic feet per cubic yard**
soaking of lightweight fines in stock-
3/8 13.5 13.0 12.4 11.9
piles or bunkers is difficult because 1/2 15.9 15.4 14.8 14.3
water will not penetrate the fine ma- 3/4 17.8 17.3 16.7 16.2
terial easily. Howe ve r, fine particles 1 19.2 18.6 18.1 17.6
absorb water faster than coarse par- 1 1/2 20.2 19.7 19.2 18.6
ticles. Accordingly, presoaking is oc- 2 21.1 20.5 20.0 19.4
3 22.1 21.6 21.1 20.5
casionally done right in the mixer by
adding two-thirds of the mixing wa- * Adapted from Recommended Practice for Selecting Proportions for Normal Weight
ter before adding other ingredients. Concrete, ACI 211.1-70.
With this method presoaking light- ** Volumes are based on aggregates in dry-rodded condition as described in Method of
Test for Unit Weight of Aggregate (ASTM C 29). These volumes are selected from empirical
weight fines takes only about five relationships to produce concrete with a degree of workability suitable for usual reinforced
minutes. construction. For more workable concrete, such as may sometimes be required for pump-
A patented process for presoaking ing, they may be reduced up to 10 percent.
lightweight aggregates has been de-
veloped wherein the aggregates are
placed in a tank and saturated un-
der a vacuum. The moisture absorp-
TABLE II Volume of coarse lightweight coarse aggregate
tion with the vacuum process may
per cubic yard of concrete*
be two to three times the 24-hour
absorption at atmospheric pressure. Maximum Fineness modulus of fine aggregate
size of
Another presoaking process
Lightweight 2.20 2.40 2.60 2.80
known as hydrothermal saturation aggregate,
consists of immersing heated light- inches Coarse aggregate, cubic feet per cubic yard**
weight aggregate in water. To obtain
maximum absorption and to avoid 3/8 9.7 9.3 8.9 8.5
1/2 11.5 11.1 10.7 10.3
thermal shock and possible damage
3/4 13.6 13.2 12.8 12.4
to the aggregate, the optimum tem-
perature for each specific aggregate *Adapted from Placing Concrete by Pumping Methods, by ACI Committee 304.
and the quenching time period **Volumes are based on atmospherically soaked lightweight aggregates in loose condition
as described in Method of Test for Unit Weight of Aggregate (ASTM C 29). Values are based
should be determined in advance by upon an unpublished survey of average practices by U. S. lightweight aggregate producers.
a laboratory test program. Hy- Pumpability of lightweight concrete tends to vary with the aggregate source and some aggre-
drothermal saturation is particular- gates require saturation beyond that possible at atmospheric pressures and/or other mix ad-
justments in order to achieve a pumpable concrete. For recommendations consult the aggre-
ly adaptable to lightweight aggre- gate producer.
gate plants that employ mechanical
cooling equipment. Moisture ab-
sorbed by the aggregate in the hy- as concrete made with normal to dry loose volume, increase dry
drothermal saturation process may weight aggregates. Because of their rodded volume by about 10 per-
be as much as that absorbed in the high degree of saturation, the aggre- cent.) A limited number of tests of
vacuum process. gate particles resist further absorp- concrete made with these specially
Concrete made with hyd ro t h e r- tion under the pressure of pumping. processed lightweight aggregates
mally or vacuum-saturated light- Therefore, the same proportioning indicates that this type of concrete
weight aggregates responds to procedures recommended for nor- has a low resistance to freezing and
pumping in much the same manner mal weight concrete pump mixes thawing. Howe ve r, after moist cur-
should be used. (Volume of coarse ing, if this type concrete is allowed
aggregate per cubic yard of concrete to air dry for an extended period
shown in Table 1 may be used for (two weeks to six months) its resis-
* Very little all-lightweight aggregate lightweight aggregate if an appro- tance is greatly improved.
concrete is produced Most of it is priate allowance is made for the dif-
sanded lightweight aggregate in ference between dry loose volume Lightweight aggregate grading
which the lightweight fines have and dry rodded volume. To convert The grading of coarse lightweight
been replaced with natural sand.
aggregates should fall within the hanced by the addition of material When designing lightweight con-
limits stated in Specification for passing the Number 50 and 100 crete mixes, the total/ water require-
Lightweight Aggregates for Structur- sieves it should also be remembered ment is different from that used for
al Concrete (ASTM C 330). The max- that an excess of these very fine normal weight mixes. This is due to
imum size of aggregate will be gov- sizes will require more mixing water, differences in the absorptive prop-
erned primarily by the sizes which reduces strength and increas- erties of lightweight and normal
available from the aggregate pro- es drying shrinkage. weight aggregates. For simplicity,
ducer. Most producers have one- the total water in a lightweight mix
half- or three quarter-inch aggre- Proportioning lightweight con- may be considered divided into two
gate or both and either size is cretes segments: active water and ab-
suitable for any pipeline three or When proportioning stru c t u ra l sorbed water. It is the active water
more inches in diameter. Some- lightweight aggregates to produce a that establishes the slump and wa-
times coarse lightweight aggregates pumpable concrete, the aggregate ter-cement ratio. The absorbed wa-
larger than the Number 4 sieve are producer should be consulted for ter is contained within the light-
produced in two separate fractions. his suggestions and recommenda- weight particles and, as such, does
These two sizes should be com- tions. In some areas only a limited not directly affect the quality of the
bined (preferably at the concrete selection of materials may be avail- paste. The requirements for active
batch plant) to meet ASTM C 330 able and it may be necessary to im- water in lightweight mixes are about
grading requirements. Care should port supplemental materials to the same as for similar mixes of nor-
be taken to maintain uniformity of achieve the best results. For exam- mal weight concrete. The absorbed
grading from one batch to the next ple, a pozzolan might be successful- water will vary and, to minimize
since fluctuations can affect the de- ly used as a fine aggregate supple- these variations, presoaking is rec-
gree of pumpability. ment. Pozzolanic materials in the ommended as discussed previous-
Structural lightweight aggregates amounts generally used to improve ly. If additional absorption occurs
may be rounded, cubical or angular grading have no significant effect on during transport in truck mixers
in shape and their exterior surface the unit weight of concrete. In most with resulting slump loss, the mix
may be coated or uncoated, de- cases structural lightweight mixes should be brought to the re q u i re d
pending on the production method. are designed with 100 percent re- design slump by the addition of ex-
Proper allowances for shape and placement of lightweight fines by tra water. This practice will not up-
texture are possible by making slight natural sand. set the water-cement ratio if the
changes in the ratio of mortar to Table 2 is suggested as a guide for original mix proportions were based
coarse aggregate. Hence any type of selecting the volume of coarse light on sufficient active water to pro-
lightweight aggregate can be han- weight aggregate for trial mixes duce the desired strength at the de-
dled in a pump mix. when using aggregates presoaked at sign slump. A slump loss that takes
If fine lightweight aggregates are atmospheric pressure. (Use Table 1 place in a lightweight mix between
used their grading also should fall for hydrothermally or vacuum-satu- the pump hopper and the discharge
within the limits stated in ASTM C rated lightweight aggregates.) The end of the line is usually caused by
330. In addition, it is important that values in Table 2 (in contrast to further aggregate absorption under
from 20 to 35 percent of the light- Table 1 ) are for aggregates in a loose pumping pressure. This may be due
weight fines should pass the Num- condition (rather than rodded) to to insufficient presoaking of the ag-
ber 50 sieve and 10 to 20 percent conform with ASTM C 330. The val- g re g a t e s, an amount of coarse ag-
should pass the Number 100 sieve. If ues for fineness modulus shown in gregate that is excessive for a
a lightweight fine aggregate is defi- Table 2 are intended to re p re s e n t pumpable mix, abnormally high
cient in these sizes. addition of a the FM of the composite fine aggre- pump pressures, or other less obvi-
finely divided mineral admixture gate to be used including any nat- ous causes. It is satisfactory for con-
such as pozzolan or rock dust will ural sand or mineral supplement crete to enter the pump at higher
improve pumpability. Also, it is pos- that may have been added. Differ- than design slump if the concrete
sible to blend lightweight fine aggre- ences in particle shape, grading, discharged at the end of the pipeline
gate with natural sand to improve surface chara c t e ri s t i c s, void con- is within design slump limitations
the overall grading. Howe ve r, this tents and degree of presoaking may and if the slump loss is due simply
may increase the final weight of the each have an influence on the opti- to aggregate absorption.
c o n c re t e. Adverse weight effects mum volume of coarse aggregates
may be minimized by the use of a for a particular mix. It should be
relatively small amount of very fine noted that these values are only a
natural sand if this combination re- guide based upon broad experience PUBLICATION #C730155
sults in improved grading. Although and might vary by plus or minus ten Copyright 1973, The Aberdeen Group
the pumpability of a mix may be en- percent. All rights reserved

Vous aimerez peut-être aussi