Vous êtes sur la page 1sur 9

GOVERNANCE REGIMES FOR LARGE COMPLEX PROJECTS

Roger Miller; Brian Hobbs


Project Management Journal; Sep 2005; 36, 3; ABI/INFORM Global
pg. 42

GOVERNANCE REGIMES FOR LARGE


COMPLEX PROJECTS
ROGER MILLER, Jarilowsky Professor of Technological Innovation and
Competitiveness, Ecole Polytechnique, Universite de Montreal

BRIAN HOBBS, PMP, Department of Management and Technology Ecole


des sciences de la gestion, Universite du Quebec a Montreal

Introduction

T
(!BSTRACfJ his paper presents the basis of a new research initiative to develop gover
nance frameworks for megaprojects, both private and public, in a context
This paper presents a framework for where the owner does not undertake large numbers of such projects on a reg
building governance regimes for large
complex projects. The framework is ular basis. Many governments and most private firms, even in capital-intensive
based on three sources: 1) a re-examina industries, are in this position. The situation in which an organization manages a
tion of a study of 60 large capital projects stream of megaprojects over an extended period of time is unusual. When under
(Miller & Lessard, 2000), 2) the institu taking a very large project without an adequate governance regime, most organi
tional, corporate, and project gover zations are exposed to high probability of failure and the resulting significant
nance literatures and 3) interviews
centered on the revision of the British negative impacts. Megaprojects are qualitatively more complex and riskier, and
Private Finance Initiative and on the therefore require governance regimes that are different from those of more routine
development of the Norwegian project and less risky endeavors.
approval process. The literature tends to This paper starts with a re-examination of a study of 60 large projects in which
treat governance issues as being static, the authors were heavily involved. The literatures on the corporate, institutional
but project development processes and
environments are dynamic. The gover and project governance are then examined in light of the results of this study. This
nance regimes must adapt to the specific is followed by the examination of two situations in which long streams of
project and context, deal with emergent megaprojects have been managed over an extended period of time and in which
complexity, and change as the project there has been a concerted effort to learn from this experience. These are the revi
development process unfolds. Learning sion of the British Private Finance Initiative (PF!) and the development of the
to manage project governance regimes is
difficult for organizations that are not Nmwegian project approval process. Finally, the paper returns to the learning
involved in great numbers of large com dilemma most organizations face when undertaking a megaproject, and presents
plex projects. The framework based on the research program that is currently underway.
the progressive shaping of the project
through the project development life A Re-examination of the Results of the IMEC Research Program
cycle is designed to help overcome this
dilemma. From 1996 to 2000, the authors were ve1y heavily involved in a major research ini
tiative to investigate the management of large complex projects, the International
Keywords: project governance; life cycle; Research Program on the Management of Large Engineering and Construction
mega-project; complexity; organizational
learning Projects (IMEC) (Miller & Lessard, 2000; Miller & I Iobbs, 2002). The prima1y
focus of this research was the study of the long and complex "front end" of these
2005 by the Project Management Institute projects. The lessons learned from the IMEC Program constitute the starting point
Vol. 36, No. 3, 42-50, ISSN 8756-9728/03
for this paper and the research presently undertaken by the authors. The primary
lessons from the IMEC Program have been summarized under the following eight
themes:

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
1. The long, complex and critical front end. The front The development of the project during the front-end
ends of projects were very long, seven years on aver phase was shown to be a time-dependent, non-lin
age, and often very expensive (up to 33% of the total ear, and iterative process, during which the project
budget). The management of this phase was critical was formulated, tested, challenged, and reformulated
and showed significantly more impact on project through a series of episodes. Unforeseen risks and
performance than the management of the engineer issues emerge in successive episodes and must be
ing, procurement, and construction phase. managed. The process is described as that of project
2. Megaprojects are embedded in institutional frame shaping through episodes. (See Figure 1.)
works. The anchoring of projects to institutional 6. Strategic depth. The investigation of the strategies
frameworks was one of the most critical aspects of deployed in the development and delivery of these
these projects. In 63% of cases, important regulatory 60 projects revealed a vast array of strategic options.
or institutional changes were a critical part of the No consistent relationship was found between indi
project development process. Often the projects con vidual strategies and project performance. The proj
tributed to the creation or the modification of the ects and their contexts varied so greatly that no one
institutional framework into which they became strategy was appropriate to all cases. A strong correla
embedded, through a process of co-determination. tion was found, however, between the variety of
Projects embedded in strong institutional frame strategies deployed, or strategic depth, and project
works were much better able to withstand and sur performance. Making a wide array of strategies avail
vive the impacts of emergent uncertainty. able required a strong sponsor/developer, a strong
3. The construction of coalitions within networks of leading coalition or support network, and a flexible
relations. In large complex projects the governance governance structure. The need for strategic flexibili
relationship is very rarely a binary relationship ty is in-line with the episodic nature of the project
between one project sponsor and one governing development process and the uncertainty as to the
body. Project development, execution, and delivery nature of the challenges and risks in future episodes.
will most often involve a large number of stakehold The need for strategic flexibility creates a strategic
ers joined together in coalitions and alliances in the planning paradox in that being well prepared for the
role of project sponsor or in support of the project requirements of early episodes may result in inade
sponsor. This sponsor group will typically face a quate preparation for later episodes and the associat
series of governing bodies, each of which will have a ed emergent risks. Project development requires a
role to play in project approval. The sponsor group rich and varied pool of strategic resources and the
and the governing bodies will interact with other flexibility to adapt to emergent situations.
stakeholders, some of whom may be opponents of
the project or its sponsor. The interactions among the 7. Strong sponsors. The study showed that the capabil
different groups of stakeholders involved in project ities of the project sponsor/developer had an impor
development, approval, and delivery can best be rep tant impact on the way the project unfolded and
resented as a dynamic social network. ultimately on performance. Strong sponsors showed:
4. High uncertainty and high risk. The projects inves Integrative business perspective
tigated were exposed to many different types of risk, Ability to evaluate complex systems from mul-
several of which are not typically taken into account tiple perspectives
by traditional project management methods. Relational and coalition-building competencies
Governments reneging on commitments, slowly Political and negotiating skills
materializing or insufficient markets, and social and Resources necessary to support long develop
political challenges to legitimacy were among the ment processes
most important sources of risk. The level of uncer Possibility of diversifying risk through a por1-
tainty was extremely high, partly because of the large folio of projects or other activities
number of potential sources of risk, the projects' vis Will to abandon bad projects.
ibility, and their innovativeness. The length of time
required for project development and anchoring 8. Scrutiny. I ligh performing projects are subjected to
increased the projects' exposure to emergent risk. intensive scrutiny. The project sponsor plays an
Each project encountered an average of four unfore important role in ensuring that projects are scruti
seen and potentially catastrophic events during their nized. The involvement of other stakeholders with
long life cycles. Examples of such risks include diverse interests and perspectives in a governance
macro-economic events such as the Asian economic structure that encouraged scrutiny also contributed
crisis, changes in the political landscape, and the par to the development and delivery of feasible projects;
ent organization of a partner encountering financial examples include risk and financial evaluations by
difficulties and restructuring. those providing funding, and environmental and
5. Development through episodes of project shaping. social acceptabi Iity evaluations th rough diverse

3
4
1
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Committable
Package

Moves and Closure &


Commitments Final
Agreements

Confrontin Aband0n
Emerging Fears


Extedd Abandon
Negot1at1ons

Holisti
Proposal Abandon

lnitiat
Exploration Aband0n

1 4 30 90 120
COST OF SHAPING EFFORT ($ MILLION)

Figure 1: Project Shaping through Episodes (From Miller & Olleros, 2000, p. 106)

mechanisms of public consultation. Often, the own example, many transportation infrastructure projects and
ership structure created a context in which stake facility development projects are in the air for decades
holders with both the ability and the incentive to before the timing is right to move to some form of concrete
scrutinize projects had decision-making power. proposal for action.
Rigorous scrutiny provided through diverse mecha The search phase may be initiated by a perceived need
nisms contributed significantly to the development, or opportunity, or by a signal from an important player that
selection, and delivery of feasible projects. he or she is open to proposals for a particular project or type
of project. Governments create opportunities and signal
Interaction Between the Project and the Institutional their interest through policy statements and through
Framework Throughout the Life Cycle changes to the institutional framework. This phase is very
The life cycles of all projects have many things in common. entrepreneurial. Not only are the problem or opportunity
They all start with a relatively high level of uncertainly, and and the solution being sorted out, coalitions of players are
if they are not terminated prematurely, end with the delivery also taking form. The rhythm is broken and sporadic.
of an artifact, which is usually put into service. The IMEC Projects often go into limbo after periods of considerable
Program showed that the life cycles of large complex proj exploratory activity. Exploratory processes often lead to dead
ects have characteristics that distinguish these projects from ends and are abandoned, at least temporarily.
many other types of projects. As has been previously men The passage from the exploratory search process to the
tioned, the front end of this type of project is very long and next phase of "strategic structuring" is often quite fuzzy; it is
non-linear. Figure 2 presents a graphic representation of the much a question of gathering momentum. Several elements
life cycle of large complex projects and the interactions come into place. The opportunity or problem becomes
between the project, the institutional framework, and the more clearly defined and a conceptual solution takes form.
contextual environment. A project sponsor/developer often emerges with a coalition
At the outset, the level of ambiguity of large complex of potential participants. Political support, whether it be
projects tends to be extremely high. Most projects of this internal to the parent organization or external, starts to be
type go through a long "search" period during which both organized. During this phase, the level of activity increases
the problem and the solution are sorted out. During this but remains sporadic as the project goes through episodes of
period, some of the players are already known but many strategic shaping during which both the concept and the
more are yet to be identified. In a significant number of supporting coalitions <1re developed in more detail, tested
cases, this period of preliminary search lasts for decades. For for their acceptability, and redesigned (Miller & Olleros,

SEPTl:\,1Bl:R 2005 I P1toJt:cT MANA<;u,11:Nr JouRNAL

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Ol
C
"
= ro
a,
u U)
C
Supporting <x: C
0 Ol
Political Coalition .2
C
c:
Ol E ::::,
C
Potential ;;., 2
..0
..0
C Strategic System t,
Participants 0
....J
a,
cc

Commissioning
and Ramp-Up
Project
Opportunity = Robustness and Resilience
u
a,
U)
C (/)
0 .:x:
(/)

-
E C
a,
.2 Ol
E a.i
Sponsor's Strategic Shaping E

Search Strategic Structuring Design and Execution Commissioning and Ramp-Up

PROJECT ENVIRONMENT

Figure 2: The life cycle of large complex projects (Adapted from Miller & Hobbs, 2002, p. 209)

2000). The process of shaping and reshaping the project con with benefits management, large complex projects often face
cept is cyclical. Major setbacks are not uncommon because particular issues related to both market and social-political
this protracted process is vulnerable to significant and unfore reactions to their delive1y. Large infrastructure and capacity
seen changes in the project environment. Timing is key. development projects take a long time to implement. The
During this phase, considerable effort is put into nego market conditions and the market's immediate response are
tiating institutional arrangements that will anchor the proj often very difficult to predict. If the initial market reaction is
ect, giving it legitimacy and protection from challenges in unfavorable or slow in materializing, the financial impact
the future. A retrospective analysis of this phase will often can be catastrophic. When this happens, the sponsoring
identify a project champion, a person, or organization that coalition and/or the institutional actors often step up to play
has played the role of sponsor and developer of the project. a vital role in restructuring the project to prevent its immi
This role is central to the efforts to shape and reshape the nent demise. As this scenario is not uncommon, a gover
project and to the timing of successive periods of more nance regime for large complex projects should include the
intense activity. possibility that such actions will be necessary.
In most major projects, a time can be identified when The IMEC Program showed that project performance is
most of, if not all, the pieces come into place, and when sig heavily determined by the activities of the very long front
nificant and irreversible commitments are made. This is typ end phases. This research also showed that once a deal has
ically the time when major contracts are signed and been made, financing has been obtained and contracts
financing is secured. This point marks the end of the strate signed, the engineering and construction phases tend to be
gic structuring phase and the beginning of the design and comparatively short, typically three years. Because this type
execution phase. From this point, the management of the of project is often vulnerable Lo both market and/or social
project is more in line with conventional project manage political reactions upon delivery, the commissioning and/or
ment the01y and practice, which does not mean that it is ramp-up phases are also critical to its success, and must be
issue-free, but that the issues and their management are more included within the scope of project governance.
in line with well established project management practice. This is, of course, a schematic representation of the evo
The final phase of large complex projects is the delive1y lution of large complex projects. It highlights the four phas
and commissioning of an artifact and its being put into serv es that have been described, each with its particular dynamic
ice. This phase is receiving more attention in the project properties. A governance framework for such projects must
management literature and is often treated as part of bene account for this variability and non-linearity. The driving
fits management (OGC, 2003). In addition to the issues force is the interplay between the sponsor's efforts in strate
related to realizing business benefits typically associated gic shaping, the actions and reactions of the institutional

5
4
1
Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
pl ayers, and the evolving project environment. Through this Governments as project participants. Governments
i n teraction, the concept and the sponsoring coalition take participate i n large infrastructure proj ects, even in "pri
form, and the project is anchored i n to the i nstitutional vate" projects. They play diverse roles, i ncluding pro
framework. m o ter, provider of funds and other resources,
facilitator, and protector. I l owever, m any govern ment
Reconciling Uncertainty and Responsibility offi cials refuse to accept this reality i n defense of their
The primary focus of the analysis of the GO proj ects i n the role as independent guardian of the publ ic good. This
I MEC Program was on the reconcil i ation of u ncertainty and l eads to contradictio ns, del ays, and m isunderstandi ng.
feasibil ity, but what about responsibil ity? The questi ons of Complex network of actors and i n terests. Issues of
social responsibil ity and the pub l i c good are complex. I t is social responsibi l i ty and the pub l i c good are not sort
n ot feasible to address them i n any depth in the context of ed out in the context of a b i nary rel ationship, but
a summary re-exam i nation of the case studies. H owever, this rather in the context of a complex n etwork of actors
re-exa m i nation did produce some i nteresting observations, and i nterests.
both of exa mples of "responsible" and "i rresponsible" I ndeterminacy. Not al I issues, i n terests, and actors are
behavior and i l lustrations o f the complexity of these issues known at the outset. The project con cept and the con
in the particu lar context of l arge infrastructure projects. text will evolve over t i me through successive episodes.
Naively, one m ight picture the issue of social responsi
bil ity in a framework where a govern i ng body, be it a corpo
rate governance structu re or a pub l i c i nstitutional IDEALIZED GOVERNANCE REALITY
framework, has established a process for approving projects
that are proposed by i ndependent parties, both pub l ic and Bi nary relation Network relations
p rivate. The govern i ng body has the role of i nsuring that Established process Evolution & indeterminacy
responsible choices are m ade and that the project promoter Set by governing body Co-evolution
behaves responsibly. The fo l lowi ng observations from the
Assures responsible choice Not necessarily
examination of large i n frastructure projects contrast s harply
with this na ive straw man model of project governance. Assures promoter is Not necessarily
responsible
These are summarized in Figure 3 .
The assumption o f the moral high ground. Assuming
that one pa11y will necessaril y occupy the moral high ROLE OF THE STATE
ground has been shown empirically to be inappropriate.
Th e "worst exa mples of i rresponsi ble behavior" I ndependent body Participant
observed during the IMEC Program were governments Moral high ground Not necessarily
reneging on their commitments. Furthermore, Fl yvberg,
Bruzelius, and Rothengatter (2003 ) have shown that in Figure 3: Contrasts between an idealized vision of mega project
this type of project, the governing bodies do not always governance and em pirical observations
make responsible choices.
Large i nfrastructure projects are visible and con Because of the h igh l evel of uncertai n ty, the reso lution
testable. They are never truly private endeavors. of issues of social responsib i l i ty cannot be thought of i n
Because of their visib i l ity and their environmental, terms of a predeterm i ned process for resolving known
social and economic i m pacts, these types of projects are issues. It must be thought of as a flexible process for making
always subjected to considerable public scrutiny and certai n that issues are identified and resolved, knowing that
are frequently contested ve1y actively by groups with new issues will em erge as the proj ect unfolds. Because of the
widely varyi ng i nterests and perspectives. Public scruti visibility and contestabi l i ty of l arge infrastructure proj ects,
ny and contestab ility are central to the promotion of the issues of proj ect feasib i l i ty and soci al responsibility are
the publ ic good. H owever, these can lead to perverse tightly intertwined. The mechanisms for resolving both are
effects such as constituents pressuring politici ans to strongly conditioned by the uncertain and emergent nature
renege on their co mmitments and projects being cap of the project development process.
tured by interest groups and being held for ransom.
I n stitution a l frameworks are often co-determi n ed. Paradoxes in the "Ideal" Role of the State
The lega l and regu latory fram eworks i nto which proj Major i n frastructure proj ects are very u n l i kely to be under
ects are anchored are subj ect to change. The changes taken and realized un less the state is actively i nvolved i n
can be t h e resu l t of l obbying and n egotiation . both the promotion a n d t h e structuri ng of such projects.
Governments also in troduce changes to sti mulate Likewise, the introduction of new proj ect development and
i nterest in and to promote certain types of projects. delivery strategies is i mpossible un less the state is actively
The more strntegica l ly i m portant and innovative the i nvolved in the strategies' promotion and i mplementation.
project, the more l i kely i ts development w i l l require On the other hand, the state has a role as protector of the
changes to the i nstitutional framework. pub l i c good, a rol e that is m ore easily fi l l ed from the posi-

S E l' T E \ 1 1\EH 2 0 0 5 I P R O J E t."f M ,\ N /\( : E \


. i E N T J 1 > t : R J\: A I .

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
tion of an independent governing body that sets up regula the one best structure, the design of such regimes can be
tory regimes prior to project proposal and that makes deci thought of as a flexible strategic process that will draw on a
sions to authorize projects proposed by others. In their variety of governance mechanisms to deal with different
important study of public infrastructure mega projects, issues in different phases of the project life cycle. Some of
Flybjerg et al. (2003, p. 109) state that "Governments should these issues are predictable, while others will be emergent.
not act as project promoter, but should, instead, enforce the This opportunity is unique to large complex projects.
arm's-length principle" and that regulatory regimes "should
be specified up front as far as possible. " (p. 1 1 8) The argu A Re-examination of the Literature on Governance
ment behind these is the need for the state to maintain its When designing or analyzing a project governance structure,
independence as protector of the public good, a role that the one turns naturally to three streams of literature: on corpo
state must fill. H owever, examination of public infrastruc rate governance, on institutional governance, and on project
ture projects reveals that without the state's active involve governance. The corporate governance literature addresses
ment, megaprojects are not possible. Furthermore, the the issue of what structures should be set up to govern an
examination of such projects has revealed that the regulato- organization, and is most often presented as a hierarchical
1y regimes that govern such projects often require modifica binary relationship between a principal and an agent
tion as the project concept and the regulatory regimes (Williamson, 1 996). Those writing on corporate governance
co-evolve over a period of several years until a feasible solu make an assumption that the governance structure will
tion is developed. remain in place for some time. There is a sharp contrast
The state is, thus, in a paradoxical situation in which it between the bina1y, hierarchical, and static nature of corpo
is difficult to reconcile its roles as promoter, active partici rate principal-agent governance relations, and the time
pant, regulator, and ultimate approval authority. The diffi dependent co-determination found in the network relations
cult co-existence of these roles manifested itself in the form typical of the governance of megaprojects.
of hesitations and contradictions in several of the projects The institutional governance literature provides rich
studied during the IMEC research program. It may be descriptions of several regimes, including markets, contracts,
impossible to resolve this paradox completely. I lowever, hierarchies, regulatory, and associations ( Hollingsworth,
mechanisms must be found to develop and implement proj Rogers, & Boyer, 1997; North, 1 990). Rather than asking
ects that reconcile stakeholder interests and public policy. which of these is the most appropriate for a given project or
The IMEC Program showed that effective scrutinizing of context, these governance regimes can be seen as design ele
projects contributed to their performance and to the resolu ments in the context of large complex projects. A particular
tion of this paradox. There are many mechanisms that can project or institutional framework could draw on several of
support the scrutinizing of projects, but these must be these governance regimes and vary their usage to manage
adapted to the specific project and its context. The design of different issues at different phases of the project life cycle.
the governance regime should allocate risks, responsibilities, The IMEC Program showed that the best project strategies
and decision-making power in such as way that those with combined a large number of individual strategies, a reality
the expertise to scrutinize projects have both the opportuni captured by the concept of strategic depth and flexibility.
ty and the incentive to do so. For issues related to the pub Analogously, project governance regimes could be analyzed
lic good, the transparency and access to information are not with the goal of identifying the single best structure to
essential components of the process (Flybjerg et al., 2003, put in place, but for the rich mix of governance regimes to
pp. 111- 11 5). be put in place to manage different issues and different
stages of the life cycle and the variation in their usage as the
Rethinking the Design of Governance Regimes project and its context evolve.
The length of the life cycle in general and the front end in Project governance has only recently become an issue of
particular is a challenge and an opportunity for the design importance in the project management community and lit
of project governance structures. Its very length is a chal erature. The Association for Project Management (APM)
lenge because the governance structure must adapt to con Governance Specific Interest Croup (S I C) has published a
ditions that will undoubtedly change and to many standard on project governance titled "Directing Change: A
unforeseen events that will emerge over this time period. For Guide to Gove rnance of Project Management " (APM
example, most such projects will need to survive at least one Governance S IC, 2004). This standard specifically addresses
election in democratic countries. In addition, the nature of the bridge between corporate governance and corporate
the issues that need to be addressed will also change as the strategy on the one hand, and project management on the
project unfolds in successive episodes of project shaping, other. The standard does not specify the specific structures
and as conditions evolve. The protracted nature of the proj and processes that should be put in place. It provides guide
ect life cycle also provides an opportunity for adaptation. lines largely in the form of key questions to be addressed.
Because the process is spread out over a long period of time, Many of these can be seen as criteria for the design of proj
there is an opportunity to transform the governance struc ect governance regimes, or as issues that must be resolved.
ture as the project unfolds. Rather than thinking of the The standard is set in the context of the management of the
design of megaproject governance structures as a search for projects of a particular organization, public or private.

7
-..:. 1 1' 1 1 \ 1 h l IZ 2 0 0 1 I P R o J H ' T \L,:"-l ..\ < , E 1 1 :...; r ] o t R :,... , 1
4
1

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
Megaprojects can rarely be treated within the context of a Norwegian Ministry of Finance put in place a quality control
single organization. The standard is, therefore, not directly process by which the cost of major projects was validated by
applicable to megaprojects. I lowever, both the general independent consultants. The conclusion after five years is
approach of specifying design criteria and issues that must that independent scrutiny may make project budgets more
be resolved and some of the specific key questions can be reliable, but that more fundamental scrutiny of project con
drawn upon in the design or analysis of governance regimes cepts is needed earlier in the life cycle if very significant
for megaprojects. improvements in performance are to be forthcoming. In
In both the corporate and project governance litera 2005, a new quality control process was put in place that
tures, governance is conceptualized as an oversight function. requires scrutiny of the project concept earlier in the front
The structures that exercise the oversight function are stable, end. The aim is to validate the choice of concept before the
while the activities and the context are seen as dynamic and pre-planning phase. This process will include the require
changing. The structures are designed to manage the dynam ment to present alternatives and to validate the needs analy
ic nature of the activities and the context without changing sis. It will also require the examination of uncertainties,
themselves. The governance of large complex projects anticipated socio-economic benefits, relevance, efficiency,
requires governance regimes that are themselves dynamic and sustainability. This is referred to as the "quality-at-entry
that can change themselves to adapt to the emerging con regime.
text. If corporate and project governance can be seen as The experiment with this regime is interesting for sever
typically addressing first-order control, then governance of al reasons. It is an experiment in institutional learning in
large complex project can be seen as requiring second-order which the NLIST is playing a significant role. The modifica
control or self-organizing properties. tions that are being put in place after the initial five-year
experiment are consistent with the obse1vations made here
Institutional Learning on the value of scrutiny early in the project front end. The
The creation and management of project governance struc fact that all large government projects must go through a
tures and institutional frameworks is critical to the success central clearinghouse is likely to support both more rigor
ful development and delivery of megaprojects. Their ous scrutiny and allow for further institutional learning.
development and operation is extremely complex. H ow do The second example is the revision of the Private
organizations learn to manage such complexity? The period Finance Initiative (Pf!) in Great Britain. In 2004, a series of
of the IMEC Program was one of much innovation and inte1views were conducted with key actors in this program
experimentation with alternative strategies for project devel from both the government and private sector. Within the
opment and delivery. Much was undoubtedly being learned. Pf!, the British Government has undertaken over 450 proj
The results of the IMEC Program showed that some spon ects for a total value in excess of 35 billion pounds over a
sors and developers had acquired skill in this area through 1 2-year period. There has, therefore, been considerable
considerable effort and through involvement in a stream of opportunity for learning. In 1 997, Sir Malcolm Bates
large projects over time. reviewed the program and recommended several significant
Over the last 10 years, there has been more interest in changes to its management. (Bates, 1997) This review and
the governance of projects in general and the governance of the subsequent changes are presented here as an example of
large complex public projects in particular. Enough experi institutional learning.
ence has also been acquired to allow significant learning on In the first wave of PF! in Great Britain between 1 992
the governance of this type of project. Where a stream of and 1997, the management of projects was fragmented
projects had been managed over a period of time, there is an among many different government agencies. This resulted
opportunity for significant learning. A systematic approach not only in significant redundancy in effort and often-unsat
would be to examine the results of the past stream of proj isfactory project performance, but also a fragmented, expen
ects, identify appropriate changes, implement them, and sive, and incomplete learning process. During the first wave
measure their impact. Despite the opportunities for learn of Pr!, the cost of external consultants represented 12% of
ing, few systematic efforts have been found. Two examples total project costs, as inexperienced organizations searched
have been identified and are described briefly. These are the for advice on how to set up private-public partnerships.
development of the Norwegian megaproject approval following the Bates Review, a task force was set up in
process and the revision of the British Private Finance HM Treasury to centralize and channel learning. This task
Initiative (PF!). force influenced future PFI projects by producing policies,
The Norwegian partners in the IMEC Program from the tools, processes, guidelines, standard contracts, and docu
Norwegian University of Science and Technology (N LIST) mentation for use in the many different agencies undertak
have been pursuing the development of a framework for ing PF! projects. Through the Bates Review and later
scrutinizing large public projects in cooperation with their publications, the program has been restructured (Bates,
ministry of finance (Magnussen & Samset, 2005; N LIST, 1 997). Results reported by H M Treasury show that National
2005). From 1995 to 2000, the N UST with several partners, Audit Office assessments have documented significant
ran a major initiative on project management, of which par improvement in project performance following these
ticipation in the IMEC Program was part. In 2000, the changes. "Over 7 5 % of PFI projects were delivered on time

Ll ' T L \ \ H L I{ 2 0 0 ) I P R O I F C I 0- I .A, t\ A. ( , l '.\l l-. I .l ( ) \ " R '.\/ . \ L

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
or early, and in no case did the pub I ic sector bear the cost of recent years, the firm had made large capital investments
construction overruns, a significant improvement on previ to increased capacity in two different areas of activity. I n
ous non-PFI experience" ( 1 IM Treasury, 2003 , p. 4 ). They o n e o f the areas, project performance has been very good,
also report projects meeting public sector managers' initial but it has been questionable in the other. llpon further
expectations in 75% of cases. This rather spectarnlar investigation, it was discovered that projects in the high
improvement in project performance is cited here in support performing sector were being seriously scrutinized by the
of the argument that organizations can learn how to struc board following the established process, while in the other
ture project governance regimes and that this learning can sector of activity, senior executives acting as project cham
have a significant impact on project results. pions had short-circuited the process and not subjected the
In order for such learning to take place, the organiza projects to the same intense scrutiny. Subjecting one's own
tion must do a large number of projects, and there must be projects to serious scrutiny requires considerable courage.
the political will to scrutinize both projects and the institu In both the private and public sectors, the presence of
tional framework through which they are managed. The strong political will for critical examination and process
presence of a stream of projects seems a necessary, but not a improvement is as exceptional as it is necessary.
sufficient, condition for institutional learning and improve
ment in project performance. In the Norwegian and British The Learning Dilemma
examples, both the examination and redesign of the frame The British PF!, with its volume of large complex projects,
work and the scrutinizing of projects have been centralized, is a rather extreme example of an opportunity to learn
with the ministry of finance having an important role. from experience in managing such projects. Many organi
zations are in a situation where they will not have a suffi
Necessary Political Will cient stream of projects to support learning, either because
Organization al barriers to scrutiny and learning have been large complex projects are exceptional in their context, or
observed in both the British and Norwegian examples, because they are experimen ting with what is, to them, a
and elsewhere. The political will to establish better newer type of project. The government of the territory in
processes-to scrutinize and to be scrutinized-is often which the authors reside has issued a policy statement sup
lacking both at higher levels and in local agencies of gov porting the use of public-private partnership projects for
ernments and divisions of corporations. It is unusual for the supply of public infrastructure projects of many types.
a powerful politician or corporate executive to invite The local government has little or no experience in the
scrutiny of either his or her pet projects, or of the process matter and is forecasting that this type of project will be
es that are in place for the development, selection , and used only exceptionally. The possibilities for acquiring
govern ance of major projects. Likewise, lower-level organ extensive knowledge on the governance of this type of
izations often attempt to avoid scrutiny. There is a will to project are, therefore, very limited. This same learning
control the decision-making processes that govern strate dilemma is also present in the private sector, as very few
gic investments. This will to maintain influence and free firms undertake very large, risky projects on a regular basis.
dom to act motivates attempts to avoid scrutiny. Even in capital-intensive and resource-based industries,
Political will has driven both the British and such projects are less than common . Both the desire to
Norwegian examples cited above. The 1997 review of the maintain control of the decision-making process, and the
Fl'! program was undertaken by the newly elected Labor lack of experience and know-how, foster a situation in
government to examine the program set up by the previ which improvisation is common.
ous Conservative government. The revised program has
since become a major policy instrument of the Labor gov Conclusion: The Research Agenda
ernment. In Norway, the initiative to critically review and This paper and the material and ideas behind it are the
improve the governance process for large projects has basis of a new research agenda, the objective of which is
been driven by the prime minister's office. Both of these to contribute to the building of a governance framework
initiatives are exceptional and required strong political upon which decision-makers could draw. A specific gover
will at ve1y high levels. However, it is unlikely that a gov nance regime must adapt to the particular project and its
ern ment would make such a critical examination of pro context. The approach taken is, therefore, not the design
grams it has initiated itself. Likewise, one might question of a governance regime but rather the identification of
whether the prime minister's office will subject its own design criteria that should be brought to bear when devel
high-priority "political" projects to the same scrutiny as oping a governance regime for a megaproject. Several of
other projects. the criteria contrast with the traditional conception of
Strong political will and courage are as important in governance as a static, bin ary, hierarchical process.
the private sector. In a recent investigation of large invest Governance regimes for megaprojects are time-dependent
ment projects in a company from a capital-intensive and self- organizing. They involve a network of actors in a
industty, one of the authors discovered that a thorough process through which the project concept, the sponsor
process was in place to scrutinize large capital invest ing coalition, and the institutional framework co-evolve.
ments, a process involving the board of directors. I n

9
l l ' 1 1 \ J I ; \ IZ 2 0 0 ", I P R ( ) l f: C I l .\ :-4 A < , r l l N r ./ u t R /\ A J
4
1

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.
References project management research (pp. 201 -21 0 ) . Newtown Square,
APM Governance S I G . ( 2004 ) . Directing change: A guide PA: Project Management Institute.
to governance of project management. APM. Miller, R., & Lessard, D . R. ( 2000). The strategic manage
www. myl ara.com/gopm/ default.asp ment of lmge engineering projects: Shaping i nstitutions, risils and
Bates, S i r Malco l m . ( 1 9 9 7 ) . Bates Pl'/ Re11iew. Londo n : governance. Cambridge, MA: MIT Press.
H M Treasu1y. Mil ler, R., & O l leros, X. (2000 ) . l,roject shaping as a
Flyvberg, B., B ruzelius, N ., & Rothengatter, W. (2 003 ) , competitive advantage. I n M i l ler, R., & Lessard, D . R. ( Eds. ) ,
Megaprojects and rish: An anatomy of ambition. Cambridge, The s trategic mm111gement of large engineering projects: Shaping
l l K: Cambridge U niversi ty Press. institutions, ris!?s and go11ern11nce ( pp . 93 - 1 1 2 ) . Cambridge,
H M Treasu ry, (200 3 ) . PFI : Meeting t.h e investment chal MA: M IT Press.
lenge. Lon don. North, D. ( 1 9 90). Institutions, institutional change and eco
I l o l l i ngsworth, J . R., Rogers, J., & Boyer, R. ( I 9 9 7 ) . nomic pe1jimnance. Cambridge, l lK: Cambridge University Press.
Contemporary cap i tal ism: The embeddedness o f institu N l l ST. ( 2 005 ) . The Concept Research Program Website.
tions. Cambridge, U K: Cambri dge U n iversity Press. Retri eved June 26, 2005, from www.concept. n t n u . no/
Magnussen, 0. M., & Samsel, K. ( 2005 ) . Successful i ndex_engelsk.htm.
megaprojects: Ensuring quality a t entry Munich: Proceedi ngs Office of C overnment Co m m erce ( O G C ) . ( 2 003 ) .
of EL I RAM 2005 . Managing successful programs. No1wich, l l K : The Stationa1y
M i l l er, R., & I l obbs, B. ( 2002 ) . A framework for analyz Office.
ing the development and del ive1y of large cap ital projects. I n Will iamson, 0. E. ( 1 9 9 6 ) . The mechanisms of governance.
D . Slevin, D . Cleland, & J . Pi nto ( Eds. ), The Jiontiers of Oxford, l l K : Oxford U n iversity Press.

ROGER MILLER is Jarislowsky Professor of Innovation and Project Management at Ecole Polytechnique in Montreal, and a founding partner
of SECOR, a strategy consulting firm with offices in Montreal, Toronto, and Paris. His work has focused on strategy and industry dynamics,
public policies i n science and tech nology, and project management. H e was the director of the IMEC (I nternational program in the
Management of Engineering and Construction), sponsored by 10 large international project developers. IMEC results were published by
MIT Press as The Strategic Management of Large Engineering Projects: Shaping Risks, I n stitutions and Governance.

Roger is presently the di rector of MINE Programme, a program aiming to understand the management of in novation in the context of the
new economy. The data for this research consists of 240 case studies and a worldwide survey of 1 500 Chief Technology Officers. The
research is conducted by a core team located in Ecole Polytech nique, with partners at University of Sussex, Torino, MIT, Stanford
and Toronto.

BRIAN HOBBS, PHD, PMP holds a degree in ind ustrial engineering, an MBA, and a PhD in management. He has been a professor in the
master's program in project management at the University of Quebec at Montreal for over 20 years. This program, of which he is a past
d i rector, is accredited by PMl's G lobal Accreditation Center. Dr. Hobbs is very active internationally in both the project management
professional and research com munities. He filled a three-year term on PMl's Standards Members Advisory Group (MAG) ending in 2002.
He is a reviewer for both the Project Management Journal and the International Journal ofProject Management. He has presented several
papers at both research and professional conferences organized by PMI and other project management organizations worldwide. In recent
years, he has been the member of two teams of researchers that have been awarded com petitively bid research grants by PMI.

S U' T L \ 1 1>E]\ 2 0 0 ) I P R l > _I E l " T 0- I A N :\ t l E \I E :'J T .l ( ) l : fU\ A !

Reproduced with permission of the copyright owner. Further reproduction prohibited without permission.

Vous aimerez peut-être aussi