Vous êtes sur la page 1sur 6

Sag-Tension Calculation Program for Wood Pole

Overhead Lines
Catherine Baker John Baker Hassan Nouri
Power Systems and Electronic Scottish and Southern Energy Power Systems and Electronic
Research Laboratory john.baker@sse.com Research Laboratory
University of the West of University of the West of
England, Bristol England, Bristol
catherine4.baker@live.uwe.ac.uk Hassan.Nouri@uwe.ac.uk

plastic strain (metallurgical creep)) and the installation of


Abstract - This paper presents studies into a new program overhead line accessories. Refer to Appendix A.
used to calculate sag and tension of conductors on wood pole Scottish and Southern Energy Power Distribution (SSEPD)
lines considering all relevant parameters, such as conductor require a user friendly, reliable program which calculates sags
temperature, wind and ice loadings and creep. Based on this and tensions of overhead line conductors such that their
information and data provided by the user, the program also designers can ensure the sag of a conductor does not result in
provides information on clearances and structural loadings. an infringement of statutory ground clearances [8] at the
Furthermore, the paper describes expressions used to develop maximum likely operating temperature of the conductor.
the program. The requirements for minimum statutory ground clearances
The program is in a Microsoft Excel domain for ease of use by of overhead lines at voltages up to and including 33 kV are as
SSE planners for whom the program has been developed and is follows;
found to provide more information than readily available 5.8 metres over roads
programs on the market. 5.2 metres at other locations
A set of data is obtained experimentally at the Scottish and Clearances apply to all points along the span length thus
Southern Energy (SSE) overhead line training school using a 58 this must always be a consideration if additional objects, such
metre span of 50 millimetre Hazel conductor (all aluminium as walls, run below the line.
alloy conductor) strung at various tensions between two wood Additional factors which must be considered when
poles at an air temperature of 2.5 degrees Celsius. This data is calculating clearances are; The use of the land underneath the
used to validate the data from the new program. Attentive overhead line, for instance a higher clearance is required for
analysis of results shows a close correlation between the two fields in which combine harvesters are required to work,
methods. maximum sag of the conductor under maximum operating
conditions and the strategic availability of the line under
Index TermsClearance, Conductor, Overhead Line, PLS- severe weather conditions, for example heavy ice loadings.
CADD, Sag, Tension. Designers have to take into consideration tension and
vibration limits of the conductors and structural loadings of
I. INTRODUCTION
the supports. They also have to check every overhead line
Overhead electricity networks must comply with The span, which results in a large yield of spans. For these reasons
Electricity Safety, Quality and Continuity (ESQC) the program must be simple to use.
Regulations 2002 [8] to ensure the safety of the electricity The four methods for sag-tension calculation previously
system for the general public, Distribution Network employed SSEPD were; commercially available software,
Operators staff and to limit faults (and loss of supply to PLS-CADD [6], a Microsoft Excel program produced by The
customers) on the network itself. It is also important to design Energy Networks Association Technical Specification
the network such that limits for stress and vibration of line (ENATS) 43-40 [2], CONDSAG, and historical sag-tension
components are not exceeded throughout the lifetime of the charts. None of these fitted the purpose of simple design
asset (which is taken as at least 40 years). checking.
Conductors are strung with slack to allow expansion and PLS-CADD is a complete overhead line design software
contraction with changes in ambient temperature. The sag of package which calculates sags, tensions and structural
the conductor created by this slack causes the conductor loadings from a precision ground line survey. Although this
ground clearance to vary. Other factors which increase the appears ideal, in practice SSEPD design staff have found this
sag of a strung conductor are; wind and ice loadings, software overly complicated to use and time consuming for
conductor elongation (settlement and strand deformation routine jobs. PLS-CADD is more suited for larger jobs such
(geometrical creep), thermal strain, elastic tensile strain and as transmission circuits.
CONDSAG is a Microsoft Excel based program which Where;
uses a Catenary method to calculate the sag for conductors E Modulus of elasticity of the conductor (N/m2)
specified by SSEPD. Although it accurately calculates the sag A Conductor cross-sectional area (m2)
and tension based on maximum working tension or everyday Coefficient of linear expansion of the conductor (/C)
tension temperatures, its lack of user friendly inputs means it t1 Initial conductor temperature (C)
is restrictive. It has been modified over many years and t2 Final conductor temperature (C)
requires button activated macros and can only be used by the W1 Initial conductor total weight (N/m)
member of staff who originally designed it. ENATS 43-40 [2] W2 Final conductor unit effective weight (N/m)
works on the same principle and was produced specifically L Basic or equivalent span length (m)
for a line design engineer. T1 Initial conductor tension (N)
Sag-tension charts are conductor specific. The charts T2 Stringing conductor tension (N)
appear straight forward to use, however due to the scaling of The Modulus of Elasticity is a ratio of the strain placed
the graphs, accuracy is easily lost. The sag and temperature upon the conductor to the change in length of the conductor
curves only have specific values indicated so either the user when a load is applied until limit of proportionality of the
has to make estimations or they choose values based on the conductor material is reached [4, 5]. The differing materials
higher or lower temperature curve. The data from these charts of composite conductors mean an apparent modulus must be
may also be displayed in a table. used based on the combined Elasticity Modulus of the
In this paper attempts will be made to gain an different materials.
understanding of all parameters which affect the sag of a ensile tress
conductor at any point along the span length where odulus of lasti ity ( a) (3)
ensile train
infringements of regulatory clearances could be made.
ensile train (4)
II. CONDUCTOR SAG CALCULATION
or e on the ondu tor
Before the sag of a conductor can be calculated, the tension ensile tress ( a (5)
rea of the ondu tor
applied to the conductor must first be investigated.
The Coefficient of Linear Expansion, often referred to as
There are two types of preliminary tension used to
thermal elongation, is the increase in unit length of the
calculate the stringing tension of the conductor; these are
conductor per degree temperature rise [4]. An apparent
Everyday Tension (EDT) and Maximum Working Tension
Coefficient of Linear Expansion is again used for composite
(MWT).
conductors.
ENATS 43-40 [2] describes EDT as The design stress in
The initial temperature is the temperature at which EDT
an unloaded conductor at 5 C. Used in sag / tension
and MWT are calculated (5 C and -5.6 C respectively).
calculations to limit harmful conductor vibrations. EDT is
The final temperature is the Maximum Operating
calculated as 20 % of the rated tensile strength (RTS, also
Temperature (MOT) of the conductor as specified by the
called the breaking load) for aluminium based conductors and
designer (subject to the maximum allowable temperature
33 % for copper conductors. It is not desirable for EDT to be
specified by the manufacturer) in degrees Celsius (C). When
exceeded as this can result in excessive vibration with an
used in the tension equation, this will give the tension used to
increase in fatigue and consequential reduction in life of the
design the overhead line in compliance with the required
conductor and fittings.
ground clearance. This is important for greased conductors
MWT includes for wind and ice loadings on the conductor
where excessive temperature can result in melting and
at a temperature of -5.6 C [2]. This gives the maximum
migration of the grease used to coat the conductor strands.
design tension physically allowed to be applied to the
For EDT, the initial conductor total weight and final
conductor in maximum load cases. MWT is calculated by;
conductor unit effective weight are the bare weight of the
( (1) conductor as EDT is taken at 5 C where ice is not considered
o and wind speed is taken as 0 m/s.
Where the factor of safety (FoS) is normally greater than 2. For MWT, the initial conductor total weight is the bare
The FoS allows for the occasional overload due to excessive weight at -5.6 C augmented for wind and ice loadings. The
climatic events and for the natural loss of strength over the weight is calculated as follows [1];
lifetime of the conductor. nitial ondu tor ei ht
The following equation is used to calculate the tensioning (6)
value [2]. ( ondu tor i e) ind load ( m)

(t t ) ( ) ( ) (2) This is a resultant force as the weight of the loaded


conductor is taken as being 90 to the wind loading and
where the wind loading acts transverse to the conductor.
The final conductor unit effective weight for MWT is the
same as that for EDT as it is in still air, ice free conditions.
The basic or equivalent span length is defined as [3] The
basic (or normal) span is the most economic span for which
the line is designed over level ground. It will be determined
by the allowable sag for the particular conductor as shown
on the final sag and tension chart, taking account also of
basic clearances and height and strength of supports.
The initial conductor tension depends on the ruling case of
the lesser of either EDT or MWT. This ruling tension will Fig. 1. Conductor Sag at any point along Span Length
ensure that the conductor is not subject to dangerous vibration
which could weaken and ultimately damage conductors and V. SAG AT MAXIMUM OPERATING TEMPERATURE
fittings.
The stringing tension is calculated at the erection (ambient) Utilising the formula for a basic parabola, X represents the
temperature of the conductor. It is used when installing a new distance from the mid-point to the user defined position, Y
line or verifying the height of an existing line. represents the distance between a horizontal line drawn below
the conductor to the conductor itself and k is a constant.
Manipulation of and substitution into this parabolic
III. CONDUCTOR SAG AT THE MID-POINT OF THE SPAN
expression creates an equation for the sag of a conductor
There are two methods for calculating the sag of a anywhere along the span length;
conductor;
mot
Catenary Method gives an exact value of sag, and can udp mot ( )( udp) (9)
be used for level and non-level spans.
Parabolic Method gives an approximate value of sag Where Sudp and Smot are the sag at a user defined position
for level spans only (although the basic formulae can be (udp) and sag at maximum operating temperature
modified to allow for changes in level). respectively.
This paper explores the use of the Parabolic Method. This
decision was made based on the difference in accuracy VI. SAG AT USER DEFINED TEMPERATURE
between the two methods being minimal for wood pole
Utilising (9), the only difference for a user defined
overhead lines.
temperature is that the maximum operating temperature (mot)
The sag of a conductor is calculated using the following
is no longer used and must be replaced by Sudt (Sag at user
equation [7];
defined temperature).
(m (7) udt (10)
udp udt ( )( udp)
Where W2 is the final conductor unit effective weight, L is
the actual span length and T2 is the tension at the maximum
VII. CLEARANCES
likely operating temperature of the conductor.
The actual span length is the distance between the two The clearance of the conductor can be calculated for new
supports of the conductor. The actual span length is not line design and for existing lines.
normally greater than 10 % of the recommended basic span as For new line design, the clearance is calculated to give the
denoted by individual distribution network operators. erection height at the fixing points of the conductor. This is
known through knowledge of the sag of the conductor at
IV. CONDUCTOR SAG AT ANY POINT ALONG THE SPAN maximum operating temperature at any point along the span
length and statutory clearances. Simply adding these two
In some cases, the maximum sag of the conductor may not heights together gives the minimum erection height.
be located at the mid-point of the span. For instance, there For existing lines, site measurements of the smallest
may be a wall located a quarter of the way along the span at clearance and the air temperature allow for the clearance of
which a clearance check is still required. Due to the sag of a the conductor at its maximum operating temperature to be
conductor being non-linear (the closer to the pole the sag is calculated, and hence a statement as to whether statutory
measured, the steeper the slope), it can be determined using clearances are infringed and if so how much by for
the parabolic equation; rectification purposes.
(8)
VIII. FIELD TEST The error does not occur from the use of the integer
Although the basic program (basic sag-tension calculation) temperature value of 3 C. The innovative program has been
had been tested and compared with another calculation run looking at the calculations at 2 C and 3 C and there is a
program to prove its theoretical validity, practical testing to difference of less than 0.01 m in the resulting sag, which is
include for temperature and sag at any point along the line negligible for on-site measurements.
was a further requirement to provide evidence that the The reason for the vast difference in the fifth test is due to
program was functioning in the expected manor. the tensioning equipment. At low tensions, the tensioning
The practical tests were undertaken at the electricity equipment causes the conductor to act less like a Catenary
ompanys Overhead ine rainin hool. Appendix B curve due to its effective weight on the line (higher weight
illustrates the set up of the site for test purposes. per metre than the conductor and being at the point of load
A 58 metre section of 50 mm2 Hazel AAAC (All rather than a linear load).
Aluminium Alloy Conductor) was strung between two wood For future tests, a larger span length and different sizes of
poles at a height such that measurements could be made conductor would be beneficial to allow for a greater range of
easily at ground level. The conductor was fitted with a dead- tests to be carried out and to reduce errors. Time would also
end at one end and attached through a dynamometer and need to be allowed to cater for a range of temperatures to test
tensioning equipment at the other such that the tension of the for its effects on the conductor.
conductor could be altered during the test process.
A rangefinder was used to find the mid-point of the span, X. CONCLUSION
the point where the distance to both poles was equal. At this
An innovative Sag-Tension Calculation Program has been
location an indicator was fixed in position.
successfully developed. Practical testing ensured the program
The rangefinder was then used give an imaginary
met the requirements of the electricity company of which it
horizontal line along the span. At the indicator, tape was
has done entirely.
used to mark the point at which the indicator crossed the
The following conclusions can be drawn;
imaginary horizontal line. The sag of the conductor could
Due to short span lengths on wood pole lines the
then be measured using a tape measure between the tape
Parabolic method of calculating sag can be used in
marker and the centre of the conductor.
preference to the Catenary method without loss of
A Linesmens thermometer was be used to measure the air
accuracy. This is for easier manipulation by the end user
temperature, which stayed at a steady 2.5 C for the entirety
rather than for the ease of the innovative program
of the test.
designer.
The above procedure was then be repeated for different
It is possible to calculate the sag of a conductor at any
points along the line and at differing tension values.
point along the span length. This is important if the
Once the tests were complete the innovative program was
smallest clearance does not occur at the mid-point of the
used to check the field test results corresponded with the
span.
theoretical results, however an ambient temperature of 3 C
The program has been designed in an efficient manner
had to be used as the program does not allow for decimal
such that anyone other than the designer can manipulate
temperature values.
it as required ith help from the asso iated users
manual.
IX. ANALYSIS OF RESULTS The innovative program has compared successfully to
Table I in Apendix C lists the results with the final column the already existing software design packages.
illustrating the difference between the two tests. It is possible to practically test such a program to ensure
From the results it can be seen that the maximum variance the real life aspects of the requirements are met.
between theory and practice, excluding test 5, is 0.025 The innovative program will successfully replace old
metres. This is deemed an acceptable error. The differences in software packages and any historical sag-tension charts for
measurement could be due to a number of causes. wood pole lines with no additional cost to the electricity
To find the horizontal line between the conductor fittings, company in a way which is user friendly for the designers.
the rangefinder had to be held level looking from one pole to
the other. A second person then had to find the point on this ACKNOWLEDGEMENTS
horizontal line where the indicator was positioned through the
I would like to express gratitude to the staff at SSE who
use of hand signals. Tape was then marked on the indicator
have collaborated with me over the past six months to ensure
where this point was believed to be and the measurement of
the program was developed to a high standard, with particular
the sag was taken. This gave way for human error. There was
thanks given to John Baker, Overhead Line Policy Engineer
also some inaccuracy when reading from the analogue
and Engineering Policy Manager, for the time and effort he
dynamometer. The procedure could have been improved by
has put in with regards to gathering data sheets and technical
using a visible laser level and digital dynamometer.
documentation which would have otherwise been unavailable
to me. I would also like to recognise the help provided to me
by David Judd, Overhead Line Trainer, who facilitated the
practical testing.
I would like to recognise the support and advice given by
my supervisor, Dr Hassan Nouri, whose help with the study
has enabled it to be completed to the best of its ability.

REFERENCES
[1] Bayliss, C and Hardy, B (2012) Transmission and Distribution
Electrical Engineering. 4th ed. Oxford: Newnes.
[2] Energy Networks Association (2004) Specification for Single Circuit
Overhead Lines on Wood Poles for use at High Voltage up to and
including 33kV. Technical Specification 43-40. 2nd ed. London:
Energy Networks Association.
[3] Gracey, G (1963). Overhead Electric Power Lines (First Edition).
London: Ernest Benn Limited.
[4] McCombe, J and Haigh, F (1966) Overhead Line Practice. 3rd ed.
London: Macdonald & Co. (Publishers) Ltd.
[5] Nelkon, M and Parker, P (1970) Advanced Level Physics. 3rd ed.
London: Heinemann Educational Books Ltd.
[6] Power Systems Inc (2012) PLS-CADDTM (Power Line Systems
Computer Aided Design and Drafting). Available from:
http://www.powerlinesystems.com/products/pls_cadd.html [Accessed
19 October 2012].
[7] Task Force B2.12.3 (2007) Sag-Tension Calculation Methods for
Overhead Lines [online]. Report Number: 324. Paris: Cigr. Available
from: http://www.e-cigre.org/Order/select.asp?ID=13561 [Accessed
09 October 2012].
[8] The Electricity Safety, Quality and Continuity Regulations 2002 Order
2002 (SI 2002/2665).

Appendicies

Appendix A

Fig. 2. Demonstration of Overhead Line Measurement Locations


Appendix B

Fig. 3. Practical Testing Setup

Fig. 4. Test Site

Appendix C
Table I
Practical Test Results

Vous aimerez peut-être aussi