Piling Handbook, 9th edition (2016)
11.1. Introduction
This chapter provides an introduction to the modern methods of installing sheet
piles, taking into account the equipment available for safe working practice with
due consideration of site environmental requirements
Knowledge of the characteristics of the steel and the section are not enough to
guararitee good results prior to installation and this chapter briefly describes the
practical information to be considered to ensure proper product installation. It also
indicates how pile drivability can be predicted following a thorough evaluation of
the ground conditions.
This chapter also contains information on pile driving equipment which is current
at the time of writing and includes impact hammers, vibratory pile drivers,
hydraulic press-in piling and special systems. Descriptions of driving methods,
ancillary equipment and guideline procedures to assist in the adoption of good
practice when installing sheet piles are also included,
Finally some guidance is given on optimization of driving techniques to minimise
noise and vibration during installation and extraction.
Note: the terms “pre-augering” and “augering” used in this chapter refer to a
procedure consisting in loosening the soil with an auger without remnoving the
soil fron the hole (as fat 2s practically possible). [Lis sumelitnes alsv called “pre
driling’ or “driling’.
11.2. Driving methods
11.2.1. General
Whilst it is recognised that, in common with most civil engineering projects, a
measure of flexibility is desirable to meet site conditions, every precaution must
be taken to maintain the necessary standards of safety whilst giving the required
alignment and verticality of the installed piles.
Therefore principal consideration must be given to access of plant and labour as
well as working positions for handling the piles and threading the sheets together.
The length of the piles and height, from which they can be pitched and driven
safely and accurately, is also important.
Whenever possible, sheet piles should be driven in pairs. The first sheet ples in a
wall must be installed with great care and attention to ensure verticality in both
planes of the wall. Control of the sheet pile installation must be maintained during
both, the pitching and driving phases of the installation process. Twisting of sheet
piles at the interlocks should be minimized and prevented to be less than
5 degrees rotation.
The principal pile driving methods available to installers are pitch and drive and
panel driving, or a method which entails a combination of both by final driving the
individual piles in panel form. The features, advantages and disadvantages of each
method are described in this chapter.
‘Cope -ntotaon |3Piling Handbook, 9th edition (2016)
1.2.2. Pitch and drive method
This method requires equipment to control the verticality of the pile during
installation so that piles can be pitched and driven one by one. The pitching
‘operation can be carried out close to ground level, meaning that operatives are
potentially at less risk. Downtime in windy conditions can be reduced. Piles can be
installed ta final level by this method For example, it is necessary when using the
Japanese press-in piling machines, or left at a higher level before final driving using
panel driving techniques, as a second stage operation. Usually a different hammer
is then to be used. This is called back-driving and is carried out in a particular
sequence. Generally heavier more powerful hammers are required in a second
stage driving operation for driving into more difficult strata, The piles should
always be paired up if possible for the second stage back-driving,
The pitch and drive method for completing pile driving is the simplest way of
driving piles but is only really suited to loose soils and short piles, For dense sands
and stiff cohesive soils or in the case of possible obstructions, pitch and drive is
not recommended. However, in suitable conditions, productivity is maximised.
Driving direction
_—_
fig. 11.1. Ptchand ive stration
It is more difficult to control forward lean using the pitch and drive method
because the leading lock has less resistance than the trailing or connected lock as
a result of soil and interlock friction. Although the piling may commence from a
true vertical position, the top of the piles will have a natural tendency to lean in
the direction of driving. Very careful site supervision will be needed, otherwise this
situation will get progressively worse if not countered. When anticipating driving
long straight sections of wall with a planned pitch & drive method, it may be
advisable for Engineers to incorporate design features giving changes of direction
to the pile line at approximately 50 m intervals. This is important to consider when
using some silent press-in pling machines, for example in basement projects. It is
to be noted, that it may not be possible to revert back to a panel driving system to
(Chupter 1 -nsutaton | 4Piling Handbook, 9th edition (2016)
avoid or correct the forward lean problem without the use of specially fabricated
tapered piles.
With pitch and drive, the free leading interlock is constantly in danger of rotation
in plan which increases, the deeper the free end penetrates the ground, as itis
unsupported during the driving operation. When a pile rotates during installation,
friction develops in the connected locks, making driving progressively more
difficult
When using leader rigs, a ground guide waling is recommended to prevent the
piles being excessively rotated at the interlock.
11.2.3. Panel driving
Piles may be threaded together above the ground in a support frame to form a
panel prior to driving. In this situation, both interlocks are engaged before any
driving takes place. This balancing of the friction forces ensures maximum control
and accuracy. The piles are then driven in stages and in sequence into the ground.
Sequential driving enables verticality to be maintained.
Sheet piles should be installed or back driven using the panel-driving technique to
ensure that good verticality and alignment is achieved and to minimise the risk of
driving difficulties or declutching problems.
This technique is important for maintaining accuracy when driving long piles or
driving into difficult ground.
(oper -ntotaton |5Piling Handbook, 9th edition (2016)
When a whole panel of piles has been pitched, there, is no need to drive all piles,
completely to maintain progress of the piling operations. During driving, the toe
of alternate pairs of piles can be kept clase to the same level. This is ensuring that
the maximum stiffness of the piles is maintained and allows for the pile toe to be
driven through soil of greater resistance without undue deviation.
The interlocks of adjacent piles are effectively guiding the pile being driven
through more difficult ground. The lead on the driven pile should be kept to a
minimum (refer to Table 11.10.). If obstructions are encountered, individual
piles can be left high without fear of disruption to the overall efficiency of the
installation process. Engineering decisions can then be taken to attempt to remove
the obstruction or drive piles carefully at either side of the obstruction before
trying once more to drive or punch through it if further penetration is necessary.
Panel driving is the best method for driving sheet piles in difficult ground or for
penetrating rack - which is unlikely to be possible with the pitch and drive method,
except press-in piling equipment with a crus auger attachment. Piles are usually
paired up or neighbouring sheets are leveled up at the head before commencing
the hard driving operation with a heavier hammer. Care should be taken when
piles are firstly pitched and installed in singles and driven in the first stage with
a vibro-hammer. It is easier to execute two stage driving in pairs if the piles are
pre-ordered and installed in crimped pairs. Difficulty of pairing up in the panel is,
avoided in this way, piles are straighter in plan, and safer more efficient operation
of impact hammers can he ensured
(Chapter -nsutaion | 6Piling Handbook, 9th edition (2016)
1. iteh, align and plumb 1 pair
2. Drive 1 pir carefully & accurately pitch rest of panel
3. Ensue last pair are accurately positioned & plumbed,
drive last pai.
4. Drive reminder of panel - working back towards 1st pal.
“panel... 2" panel panel
5. 1 panel part driven.
6. 2nd panel pitched, ast pair of 1* panel Become
‘pair ot 2° panel, Wales supported by through
bolting to last driven pair
7.1% panel driven t final oven stages.
Last pair of 2” panel plumbed & driven accurately
‘The lower frame is usually let in position after removal of
the upper frame until diving is sufficiently progressed fort
toberemoved.
Fig 11.3, Panel ving,
8.1 panel completed. 2 panel part driven. 2 pancl pitched
Last pair of 2" panel becomes 1 pair of 3" panel
(hupier 1 tsa] 7Piling Handbook, 9th edition (2016)
1.2.4. Staggered driving
Itis essential that the heads of adjacent piles or pairs are kept close together to
maximise the pile performance when driving in hard conditions. This means that
the installer should keep moving the hammer from one pile pair to another in
sequence to advance the toe of the piling with less risk of damage or refusal. This,
technique is known as staggered driving, It is nat recommended that piles are
advanced more than 2 metres beyond neighbouring piles unless driving conditions
are relatively easy for the pile section and equipment used (refer to Table 11.10.)
ing dracon ring oston (1. 9,6) ring deton (42)
a — =“
‘Only the reinforcing elements 1, 3,5 are pre-pressed; the ther 2,4, follow.
Fig 114, Staggered diving.
(Chupter 1 -nsataton | 8Piling Handbook, 9th edition (2016)
1.2.5. Cofferdam and closure installation techniques
Fig. 11.5, Greular offerdam and closure.
When installing cofferdains or combined walls, accuracy is essential - particularly
where it is necessary to pitch a pile of significant length into both adjacent pile
interlocks to close a gap. If the gap tapers, it will be very difficult to interlock
and drive the closure pile successfully. Therefore the panel driving method is the
favoured method for installing structures of this type. It is recommended to pitch
all the piles in a cofferdam structure and close all the free interlocks fully before
driving. In general Z-piles are to be preterred over U-piles in this case, because ot
higher flexibility due to the existing middle interlock. U-piles have the interlock in
the well axis, Uus having less rotation capacity. The sheet piles need to be fully
supported by temporary framing, Stability needs to be assured by using temporary
piles if necessary. With any sheet pile project, the risk of declutching should
be minimised especially when it is required to work in dewatered cofferdams
When joining walls or closing to fixed positions, panel installation methods are
obligatory to maintain accuracy. It is necessary to avoid the risks and potential
disaster caused by declutched or damaged piles when planning, designing and
executing the works. The panel driving technique is also best for the control of wall
length and creep by using appropriate guide walings to facilitate setting out and
adjustments. This may be important when dimensions are critical. Curved walls can
also be set out using this method with curved walings to suit.
(Cope -ntotaon |Piling Handbook, 9th edition (2016)
11.3. Driving systems
The choice of a suitable driving system is of fundamental importance to ensure
successful pile installation with due regard to the safety of operatives and
environmental disturbance.
The basic driving methods are:
Impact driving
This is the best method for driving piles into difficult ground or final driving of
piles to level in panel form. With a correctly selected and sized hammer it is in
most conditions the most effective way of completing deep penetration into
hard soils. The downside is that it can be quite noisy and not suitable for sensitive
or restricted sites as well as driving time is usually longer than with the use of a
vibratory hammer.
Vibro-driving
This is usually the fastest and most economical method of pile installation but
usually needs loose or cohesionless soil conditions for best results. Vibration and
noise occurs, but this can be kept to a minimum provided the right equipment is
used and when conditions are suitable as well as the site does nat expressly require
a vibrationless method of installation.
Press-in piling
Otherwise known as silent vibrationless hydraulic jacking. Machines of various
types are now widely used, This method is very effective in fine cohesive soils,
but less so in dense coarse soils unless pre-drilling or jetting techniques are used.
This is the most effective method to use when installing sheet piles in sensitive
locations where piling would have not been considered in the past. Length
limitations are given by soil conditions.
114. Types of hammers
1141. Impact hammers
‘There are several types of impact hammers available to suit the particular
requirements of the job site. Most impact hammers will involve a piston or ram
and an anvil block with a driving cap which spreads the blow to the pile head,
The machines are usually supported by a heavy frame or chassis and normally
need leg guides set up to fit snugly to the pile section being driven to maintain a
vertical position during operation. Alternatively, the hammers can be set up to be
supported and aligned by a leader rig, Itis very important that, because of the
height and slenderness of these types of hammer, the hammer is prevented from
rocking or swaying when delivering powerful blows to the piles.
The main differences between hammers are size and mechanism for delivering
the blow from the ram. Some hammers deliver the blow freely under gravity;
others are able to accelerate the fall of the ram and are described as double acting.
Inall cases the effectiveness of driving will depend on the power and efficiency
(Chupter 1 -nsutaon [10Piling Handbook, 9th edition (2016)
g
N
z
£ soo
£ sn
8
§ 1000
é
s00 =
ese
0
a
Pile weight (tonnes)
Pg. 11.72, Guidance for size of vorotory Rarer (ated by Centrifugal Tore) in ters OF ple weght and arving
conditions
The necessary centrifugal force can be calculated with the following empiric
formula (see EAU 2012, chapter 8.1.23.4.) [v}
Fa15x (0+ 2) xe
100
With centrifugal force [kN];
drivingdepth {mi};
me pile weight (kal
E adaption factor for driving conditions (value 1.0 ~ 1.2).
The amplitude is also an important factor when sizing vibro-drivers
2000 x eccentric moment (kgm)
dynamic weight (kg)
where the dynamic weight includes the clamp and sheet pile
amplitude ~
Easy driving Normal driving Hard driving
Typical amplitude <4mm 6mm 8mm
Table 17.1, Minimum typico working amplitude requirement fr vio-consider HYS
crush piler
son Very dificut Suitable Very difficult
Pre-auger essential requires =>crush plier required
HYS: High Yield Strength Steel
Table 17.2. Driving in coarse sais or predominantly cohesioness ground.
Driving method
C.value Vibro drive Impact drive Press-in
Runaway problem
0-15 Easy = use vibro method Possble stabity problem
tocrip pile
16-25 Suitable Easy Easy
Becoming less effective
26-50 Raion Normal Normal
51-75 Very difficult Normal Normal
76-100 Not recommended pultable Difficult
= drive in pairs
Suitable Difficult
100+ Not recommended =pessentialto drive => consider ground
in pairs pretreatment or jetting
Table 11.3, Driving n cohesive strata
Chupter 1 -tsaaon| 31