Vous êtes sur la page 1sur 2

On January 2, 1995, Architect Ernesto Bognalbal (E.B.

Bognalbal Construction) was hired by


petitioner, Victoria Ong, for the construction of her boutique on a contract price of P200,000 but
subject to change in respect to economic factors and change of order. The agreement was to
complete the work within 45 days and payment shall be made every two weeks based on the
accomplishment of work value. The project started on Jan. 19, 1995.

The contract between petitioner and respondent provides:

4.01 Progress Billing will commence 15 days after the Contractor receive[s] the notice to
proceed from the Owner.

4.02 Balance will be collected every 2-weeks, based on the accomplishment of work
value submitted by the contractor to the Owner and to be certified for payment by the
architect assigned on site.

4.03 Final and full payment of the consideration herein above-mentioned shall be made
by the owner to the contractor upon fulfilling the condition set forth and approved by the
architect assigned on site.9

Work Accomplished Billing


Jan 19-28, 1995 17.975% petitioner paid P 35,950
Jan 19 to Feb 15, 1995 34.65% petitioner paid P 69,300
Feb 16 to March 3, 1995 20.63% petitioner paid P 41,500
March 4-18 Work 15.47% No payment P 30,950
Total 88.85% P 181,700

Petitioner wanted a change of order within 3 days from vinyl tiles to kenzo flooring on April 22,
1995. Kenzo flooring took time to construct because of the curing process and additional costs
shall be incurred. The rushed work of kenzo flooring was not acceptable to petitioner Victoria
Ong. She refused to pay the 4th billing. Demand of respondent Bognalbal for petitioner Ong
to pay for the kenzo flooring was made on or before April 24, 1995. Petitioner Victoria Ong
didnt pay, respondent Bognalbal abandoned the kenzo flooring job on April 25, 1995.

(Petitioner Ong hired another contractor, she incurred P 78,000 and additional damages, and the
completion of the kenzo flooring was delayed for 82 days.)
Petitioner Ong claims, as a defense against payment of the fourth progress billing, that "the only
reason why the fourth billing was not paid was because [respondent Bogalbal] himself agreed
and committed to collect the fourth progress billing after he completed the Kenzo
flooring."24 Petitioner Ong claims that, because of this promise, her obligation to pay respondent
Bogalbal has not yet become due and demandable.

Issue: Is Bognalbal liable to pay?

Ruling:
SC (Petition for Certiorari is dismissed) ruled in favor of respondent Bognalbal. MeTCs
decision was affirmed. (Respondent Victoria Ong is liable pay.)
Novation is never presumed. Unless it is clearly shown either by express agreement of the
parties or by acts of equivalent import, defense will never be allowed.
assuming that there was indeed a novation of the obligation of Petitioner Ong to pay the
fourth billing so as to include as additional condition the completion of the Kenzo flooring, such
new condition would, nevertheless, be deemed fulfilled. This is pursuant to Article 1186 of the
Civil Code which provides:

Article 1186. The condition shall be deemed fulfilled when the obligor voluntarily prevents
its fulfillment.

(This could mean that the prevention of petitioner Ong of the fulfillment of the vinyl tiles,
made the condition of the contract fulfilled, without due course to any of her change order.)
(petitioner) Ong has not sufficiently proven the alleged contract novation

Breach of contract was her [petitioner Ong] failure to pay what she was legally bound to pay
under her contract with respondent Bognalbal. Payment, being the very consideration of the
contract, is certainly not a mere casual or slight breach but a very substantial and fundamental
breach as to defeat the object of the parties making the agreement, due to which rescission of the
contract may be had (Ang vs. CA, 170 SCRA 286, 296).

Vous aimerez peut-être aussi