Académique Documents
Professionnel Documents
Culture Documents
Abbreviations
You'll start to see many different abbreviations in the next few sections - I've listed them out here
to help as you continue reading.
EV = Earned Value
PV = Planned Value
AC = Actual Cost
Formulas
The following formulas will be used for the following examples.
CPI = EV/AC
SPI = EV/PV
Now, lets see how healthy the project is by computing the CPI and SPI.
BAC = $900,000
AC = $100,000
The Planned Value (PV) and Earned Value (EV) can then be computed as follows:
Step 1: Calculate the Planned Value (PV) and Earned Value (EV)
slide 1 of 3
Earned Value is a part of the Project Cost Management knowledge area. This is the last in the series
of articles on Earned Value computations. The other articles in this series are:
slide 2 of 3
Example 1
Suppose you have a budgeted cost of a project at $900,000. The project is to be completed in 9
months. After a month, you have completed 10 percent of the project at a total expense of
$100,000. The planned completion should have been 15 percent. Now, lets see the project
performance.
From the scenario, you can extract the following project performance parameters:
BAC = $900,000
AC = $100,000
The project performance in terms of Planned Value and Earned Value can then be computed as
follows:
Note: Read the Protect Your Project Against Cost Overruns article to understand how to use
buffers.
slide 3 of 3
Example 2
Suppose you are managing a software development project. The project is expected to be
completed in 8 months at a cost of $10,000 per month. After 2 months, you realize that the project
is 30 percent completed at a cost of $40,000. You need to determine whether the project is on-time
and on-budget after 2 months. Let's see the project performance.
Step 1: Calculate the Planned Value (PV) and Earned Value (EV)
slide 1 of 3
Earned Value is a part of the Project Cost Management knowledge area. This is the last in the series
of articles on Earned Value computations. The other articles in this series are:
To gauge project performance by using Earned Value Analysis formulae, use the following:
slide 2 of 3
Example 1
Suppose you have a budgeted cost of a project at $900,000. The project is to be completed in 9
months. After a month, you have completed 10 percent of the project at a total expense of
$100,000. The planned completion should have been 15 percent. Now, lets see the project
performance.
From the scenario, you can extract the following project performance parameters:
BAC = $900,000
AC = $100,000
The project performance in terms of Planned Value and Earned Value can then be computed as
follows:
Note: Read the Protect Your Project Against Cost Overruns article to understand how to use
buffers.
slide 3 of 3
Example 2
Suppose you are managing a software development project. The project is expected to be
completed in 8 months at a cost of $10,000 per month. After 2 months, you realize that the project
is 30 percent completed at a cost of $40,000. You need to determine whether the project is on-time
and on-budget after 2 months. Let's see the project performance.
Step 1: Calculate the Planned Value (PV) and Earned Value (EV)
From the scenario, you can extract the following project performance parameters:
Budget at Completion (BAC) = $10,000 * 8 = $80,000
Actual Cost (AC) = $40,000
Planned Completion = 2/8 = 25%
Actual Completion = 30%
Therefore, the project performance in terms of Planned Value, Earned Value, and Cost Performance
Index is:
Following the golden rules for managing risk and scope creep will get the project back on-track.