CUADERNO DE OBRA

Fecha:05/11/2016
Obra : "Mejoramiento Del Asfaltado De Calles De La Localidad De Omate -Ge.
Proyecto : Neral Snchez Cerro -Moquegua
Programa : 270 Das Del Calendario
Entidad Ejecutora : Municipalidad Distrital De Omate

Informe Mensual De Octubre


Informe Tcnico

1. Documentos Administrativos
1.1. Resolucin De Aprobacin De Expediente Tcnico
1.2. Designacin : (Residente De Obra E Inspector De Obra)
1.3. Acta De Entrega De Terreno
1.4. Acta De Inicio De Obra
2. Parte Tcnica
2.1. Ficha Tcnica
2.2 Datos Generales
2.3. Panilla De Metrados
2.4. Valorizacin Mensual De Obra Resumen Total
2.4.1. Valorizacin Mensual De Obra Resumen Total
2.5 Descripcin De Partidos Ejecutados
3. Parte Financiera
3.1. Resumen Financiero
3.1.1. Recursos Utilizados (Costo Directo Y Costo Indirecto)
3.1.2 Recursos Humanos
3.1.3. Recursos Utilizados - Servicios
3.2. Movimiento De Almacn
3.2.1 Recursos Utilizados - Materiales
3.2.2. Recursos Utilizados - Implementos De Seguridad
3.2.3 Recursos Utilizados - Combustibles Y Lubricantes
4. Observaciones ,Conclusiones, Y Recomendaciones
4.1. Observaciones ,Conclusiones, Y Recomendaciones
5. Cuaderno De Obra Y Panel Fotogrfico
5.1. Copia De Cuaderno De Obra
5.2. Panel Fotogrfico
6. Anexos
6.1. Copia De Plantillas Del Mes
6.2. rdenes De Compra
6.3. rdenes De Servicio
6.4. Vales De Combustible
6.5. Partes Diarios De Maquinarias
CONFORME (Archivar) ----------------------------
Ingrid Cabreras F.
OBSERVADO (Devolucion al Residente)
Ing. Civil
fecha: 05/11/2016 CIP N 128666
O DE OBRA

Modalidad Administracin Directa


De La Localidad De Omate -Ge.

sual De Octubre
e Tcnico

ecomendaciones

ico
----------------- ----------------------------
Cabreras F. Vicente Durand V
g. Civil Ing. Civil
N 128666 CIP N 288931
2.1.- RESUMEN DE AVANCE DE OBRA D

"MEJORAMIENTO DEL SERVICIO DE INFRAESTRUCTURA


PROYECTO
- MARISCAL NIETO - MOQUEGUA"
E.EJECUTORA MUNICIPALIDAD DISTRITAL DE SAN CRISTOBAL CALACO
MODALIDAD ADMINISTRACION DIRECTA
MONTO DE LA OBRA S/. 2'097,932.40
FECHA DE INICIO DE LA OBRA 06 DE OCTUBRE DEL 2015
PLAZO DE EJECUCION 180 DIAS DE CALENDARIO

MODALIDAD DE EJECUCION:
ADMINISTRACION DIRECTA
EXPEDIENTE TCNICO REFORMULADO PARA CULMINAR OBRA:
S/. 890,301.66 Nuevos soles

VALOR
PROGRAMADO
N de Quin. Del Monto % Ejecucin %
informe informe S/. Programada Acumulado
Inicio 0.00%
1.0 OCTUBRE 108567.31 6.66% 6.66%
2.0 NOVIEMBRE 512504.93 31.46% 38.12%
3.0 DICIEMBRE 250816.44 15.39% 53.51%
4.0 ENERO 397071.50 24.37% 77.88%
5.0 FEBRERO 178482.43 10.95% 88.84%
6.0 MARZO 170158.93 10.44% 99.28%
7.0 ABRIL 11684.12 0.72% 100.00%

Total a la Fecha S/. 1,629,285.66 100.00%


AVANCE DE OBRA DE OBRA "CURVA S"

DE INFRAESTRUCTURA DE CALLES DE LA LOCALIDAD DE CALACOA, DISTRITO DE SAN CRISTOBAL, CALACOA


"
AN CRISTOBAL CALACOA
DEPARTAMENTO :MOQUEGUA
PROVINCIA :MARISCAL NIETO
DISTRITO :SAN CRISTOBAL - CALACOA
LUGAR :CALACOA
ING. RESIDENTE :ING. ROBERTO NINCA GARCIA
ING.INSPECTOR :ING. ROMULO JULIO CHOQUE ARMUTO

PLAZO DE EJECUCIN:
: 180 DIAS CALENDARIOS
ASIGNACIN PRESUPUESTAL:
S/. 1'000,000.000 Nuevos soles ao15

VALORIZACION DE OBRA
FISICO EJECUTADO FINANCIERO EJECUTADO
Monto Porcentaje % Porcentaje %
MontoS/.
S/. de ejecucin Acumulado de ejecucin Acumulado
0.00% 0.00%
67117.37 4.12% 4.12% 185331.63 8.83% 8.83%

S/. 67,117.37 4.12% S/. 185,331.63 8.83%


2.2.- DATOS GENERALES

Codigo SNIP 2284246 Fecha de viabilidad


Sector: GOBIERNOS LOCALES
Pliego: MUNICIPALIDAD DISTRITAL DE SAN CRISTOBAL - CALACOA
Obra: "MEJORAMIENTO DELSERV1C DE INFRAESTRUCTURA DECALIS DE LA LOCALIDAD DE
CALACOA, DISTRITO SAN CRISTOBAL CALACOA - MARISCAL NIETO -MOQUEGUA"
Meta: 65
Modalidad de Ejecucin: ADMINISTRACION DIRECTA
Ejecutor: MUNICIPALIDAD DISTRITAL DE SAN CRISTOBAL - CALACOA

2.- UBICACIN.

Regin: MOQUEGUA
Distrito: SAN CRISTOBAL - CALACOA

3.- PLAZOS.
Plazo de ejecucin de Obra (programada) 180 DIAS CALENDARIOS
Fecha de inicio de Obra. 06 DE OCTUBRE DEL 2015
Fecha de termino (programado). 02 DE ABRIL DEL 2015

4.- PRESUPUESTO.
Presupuesto del expediente Tcnico (inicial)
Resolucin de Aprobacin N: S.R.A.N" 241- 2015-MDSC/C
Total presupuesto Aprobado: 2*097,932.40

5.- PESONAL TECNICO - ADMINISTRATIVO D EL A O B RA

Jefe de Supervisin: CIP N 76121


Sub Gerente de Inversiones D.U.I CIP N 107902
Inspector de Obra: CIP N 64539
Residente de Obra: CIP N 139696
Proyectista: CIP N
Asistente Tcnico: DNI N
Asistente Administrativo: DNI N 0
Maestro de Obra: DNI N 0

6.- ANTECEDENTES DEL PROYECTO.


Conforme a la ley Orgnica de Municipalidades N 23853 y Constitucin Poltica del Per, la Municipalidad tiene por objeto brindar atencin de lo
servicios de la localidad y el desarrollo cultural entre otros, as como la Construccin, Conservacin, Mantenimiento y Mejoramiento de las vas de
jurisdiccin.
Para la elaboracin del presente Expediente Tcnico se ha tomado en cuenta la alternativa 1 del perfil del Proyecto, el cual tiene asignado Cdigo
N 322481.
La presente obra se ejecutara con la finalidad de ampliar el rea de pavimentacin, atender las necesidades de la poblacin y mejorar el ornato d
localidad; considerando que las calles Lima, Calacoa, Ancahs y Arequipa I son vas perimetrales a la plaza principal y que las calles Jos Carlos
Mariategui, Moquegua , lea y Arequipa II son vas secundarias; las mencionadas arterias son de transito liviano de mediana intensidad que permit
descongestionamiento vial de ese sector de la localidad.
OBJETIVOS
-Mejorar las condiciones de vida de los pobladores de la localidad de Calacoa
7.- DESCRIPCION DEL PROYECTO.
La localidad de Calacoa es la capital del distrito de San Cristbal, tiene una poblacin de 1077 habitantes , y de acuerdo a las evaluaciones realiz
campo se ha encontrado que dicha Infraestructura Urbana, actualmente se encuentra en mal estado (tierra natural) en las principales calles con g
desniveles, sin pavimento ni veredas, por lo que todos los vecinos de la zona estn expuestos a diversos inconvenientes, as como dificultades en
acceso a sus viviendas, sobre todo en pocas de lluvia, por falta de pavimento sobre las vias y veredas.
Cabe indicar que la "Infraestructura de las calles consideradas en el proyecto", no han tenido intervencin ni atencin alguna desde su creacin c
Comunidad de Calacoa, por parte de instituciones ya sean pblicas o privadas, lo cual ha sido una limitacin imperante en el desarrollo de las act
socioculturales, de mantenerse as sin ninguna intervencin, pues simplemente se estar contribuyendo al retraso y subdesarrollo de la poblacin
Calacoa.
Esta situacin negativa refleja una circunstancia de ndole permanente, debido a que se trata no solo de una infraestructura urbana y/o espacios p
sino de la adecuada y suficiente prestacin de servicios de transitablidad vehicular y peatonal que hasta la actualidad no existe dicha infraestruct
Las calles Jos Carlos Maritegui, Moquegua, lea y Arequipa tramo II se encuentran sin tratamiento con material natural y perfil desnivelado.
Las calles Lima, Calacoa, Ancash y Arequipa se encuentran con material base que presentan deterioro por el paso de los vehculos e inundacin
las precipitaciones pluviales, quedando desnivelado la subrasante.
La subrasante que se presenta no se proyecta la evacuacin de las aguas pluviales que se acumulan sobre la superficie de las calles Lima y Areq
por lo que requieren un replanteo topogrfico y or lo tanto el replanteo del nivel de los buzones.
Tanto las reas verdes y el equipamiento del ornato se encuentra noperativo por falta de elementos de funcionamiento en el sistema de riego de
reas verdes, sistema de iluminacin y el sistema de bombeo para los puntos de agua. Tambin a fuente de la pileta.
La red de desage en la calle Moquegua no tiene conexin a red principal para su evacuacin, proyectndose empalmar a la red que viene del ce
poblado de Bellavista.
ATOS GENERALES

9/1/2015

RECTA
TRITAL DE SAN CRISTOBAL - CALACOA

Provincia: MARISCAL NIETO


Sector: CALACOA

180 DIAS CALENDARIOS


06 DE OCTUBRE DEL 2015
02 DE ABRIL DEL 2015

2'09'7,932.40
Fecha: 01 DE SETIEMBRE DEL 2015
2*097,932.40

ING. WALTER MAXIMO CONDORI LLANOS


ING. ALIPIO DURAN ESTUCO
ING. ROMULO JULIO CHOQUE ARMUTO
ING. ROBERTO E. NINA GARCIA

TEC. OSCAR ARIZACA TINTA YA


TEC. ROSA ALARCON VALDEZ
SR:-

Municipalidad tiene por objeto brindar atencin de los


vacin, Mantenimiento y Mejoramiento de las vas de su

del perfil del Proyecto, el cual tiene asignado Cdigo SNIP

as necesidades de la poblacin y mejorar el ornato de la


ales a la plaza principal y que las calles Jos Carlos
de transito liviano de mediana intensidad que permitir el
7 habitantes , y de acuerdo a las evaluaciones realizadas en
estado (tierra natural) en las principales calles con grandes
s a diversos inconvenientes, as como dificultades en el

intervencin ni atencin alguna desde su creacin como


o una limitacin imperante en el desarrollo de las actividades
ntribuyendo al retraso y subdesarrollo de la poblacin de

no solo de una infraestructura urbana y/o espacios pblicos,


al que hasta la actualidad no existe dicha infraestructura.
miento con material natural y perfil desnivelado.
n deterioro por el paso de los vehculos e inundacin por

cumulan sobre la superficie de las calles Lima y Arequipa

mentos de funcionamiento en el sistema de riego de las

n, proyectndose empalmar a la red que viene del centro


2.3.- PLANILLA DE ME

ITEM DESCRIPCION

01 PAVIMENTACIN OE PISTAS Y VEREDAS


01.01 OBRAS PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE OBRAS DE 3.6X2.4D M
01.01.02 CASETA ADICIONAL P/GUARDIANIA 1/O DEPOSITO
CASETA ADICIONAL DEPOSITO ALMACEFS-DE OBRA
CASETA ADICIONAL DE GUARDIANIA
CASETA ADICIONAL DEPOSIIO OE HERRAMIENTAS
01.01.03 CERCO DE PROTPITLON DE MALLA ARPILLERA
PROTECCION CON MALLA ARPILLERA
01.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS
01.01.05 TRANSPORTE DE CEMENTO
01.01.06 TRANSPORTE 0 MATERIALES MOQUEGUA-CALACOA
01.01.07 TRANSPORTE DE AGREGADOS MOQUEGUA. OBRA
01.01.08 TRANSPORTELE PIEDRA ALTO TRANSITO AREQUIPA CALACOA J375 KM _
01.01.09 APERTURA DE VIAS DE ACCESO PROVICIONAL
01.02 TRABAJOS PRELIMINARES
01.02.01 TRAZO Y REPLANTEO
01.02.02 TRAZO V REPLANTEO DURANTE LA EJECUCION DE OBRA
01.03 MOVIMIENTO DE TIERRAS
01.03.01 DEMOLICION DE OBRAS DE CONCRETO
01.03.01.01 DEMOLICION DE VEREDAS DE CONCRETO
01.03.01.02 DEMOLICION ESTRUCTURAS DE CONCRETO
01.03.02 ELIMINACION DE MATERIAL EXEOENTE
01.03.02.01 CARGUIO DE MATERIAL EXCEDENTE DE DEMOLICIONES
01.03.02.02 CORTE SUPERFICIAL DE SUBRASANTE HASTA 0.20M
01.03.02.03 PERFILADO Y COMPACTADO DE SUBRASANTE
01.03.02.04 AFIRMADO DE 1" PARA VEREDAS COMPACTADO
01.03.02.05 CARGUIO DE MATERIAL EXCEDENTE DE CORTE
01.03.02.06 TRANSPORTE DE MATERIAL EXECEDENTE DE CORTE
01.03.02.07 NIVELACION Y COMPACTADO DE MAT. BASE PREVIO AL PAVIMENTO H=0.20 CM
01.03.03 EXTRACCION PREPARACION DE MATERIAL BASE
01.03.03.01 EXTRACCION DE CANTERA MATERIAL BASE
01.03.03.02 ZARANDEADO DE MATERIAL DE PRESTAMO
01.03.03.03 CARGUIO DE MATERIALDE PRESTAMO (BASEI
01.03.03.04 TRANSPORTE A LA OBRA MATERIAL BASE
01.03.04 EXTRACCION PREPARACION TIERRA DE CHACRA
01.03.04.01 EXTRACCION DE CANTERA TIERRA OE CHACRA
01.03.04.02 ZARANDEO DE MATERIAL TIERRA DE CHACRA
01.03.04.03 CARGUIO DE TIERRA OE CHACRA
01.03.04.04 TRANSPORTE A LA OBRA I1ERRA DT CHACRA
01.04 OBRAS DE CONCRETO SIMPLE
01.04.01 FALSO PISO DE 4" DE CONCRETO 1:10
01.05 PISOS, PAVIMENTOS V VEREDAS
01.05.01 PISO DE PIEDRA LAJA O=5.0CM
01.05.02 VEREDA ASENT. PIEDRA SELECCIONADA Y HABILITADA FC=175 KG/CM2 T70%PM T=0.20M
01.05.03 VEREDA ENCOFRADO Y DESENCOFRADO
01.05.04 VEREDA RIGIDA DE CONCRETO DE 4"
01.05.05 VEREDA DE PIEDRA LAJA E- 5CTN
01.05.06 PISO DE APAREJO AMERICANO DE PIEDRA LAJA GRANITO
01.05.07 LOSA OE CONCRETO F'C"210 KG/CM2 E =0.T0M
01.05.08 COLOCACION DE ADOQUINES DE PIEDRA PARA TRANSITO ALTO
01.05.09 CONCRETO FC=210 KG/CM2 + 60% PM
01.05.10 PAVIMENTO RIGIDO CONCRETO FC=280KG/CM2 E=0.20CM
01.05.11 PAVIMENTO RIGIDO ENCOFRADO Y DESENCOFRADO
01.06 PINTURA
01.06.01 PINTURA ESMALTE Y BARNIZ EN CARPINTERIA
01.06.02 PINTURA ESMALTT CARPINTERIA METALICA
01.07 OBRAS COMPLEMENTARIAS
01.07.01 JUNTA DT CONSTRUCCION CON TEKNOPORT
01.07.02 JUNTAS ASFALTICAS PAVIMENTO RIGIDO
02 INSTALACIONDE AREAS VERDES YEQUIP AMIENTO BASICO DEL ORNATO
02.01 AREAS VERDES
02.01.01 LLENADO DE IARDINERA CON TIERRA DE CHACRA
02.01.02 ADQUISICION E INSTALACION DE SEMILLA RAYGRASS
02.01.03 ADQUISICION E INSTALACION DE ARBOLES ORNAMENTALES
02.01.04 ADQUISICION E INSTALACION DE ESPECIES FLORALES
02.01.05 CERCO METALICO JARDINES
02.01.06 MALLA DE PROTECCION ARBOLES ORNAMENTALES
02.02 EQUIPAMIENTO
02.02.01 CONFECCION E INSTALACION DE FIGURAS ALEGORICAS
02.02.01.01 EXTRACCION DE PIEDRA P/TALLAR
EXTRACION DE PIEDRA PARA EN CANTERA
02.02.01.02 SELECCIN Y APILAMIENTO OE PIE DRA
02.02.01.03 CARGUIO OE PIEDRA
02.02.01.04 TRANSPORTE DE PIEDRA P/TALLAR
TRASLADO DE PIEDRA PARA TALLAR EN CANTERA
02.02.01.05 TALLADO DE FIGURAS ALEGORICAS
02.02.02 ADQUISICION E INSTALACION DE EQUIPOS
02.02.02.01 ADQUISICION E INSTALACION OE CADENA ORNAMENTAL DE FF
02.02.02.02 ADQUISICION E INSTALACION DE PAPELERAS METALICAS
02.02.02.03 ADQUISICION E INSTALACION DE LUMINARIAS DE PISO
2.3.- PLANILLA DE METRADOS DIARIOS

N DE
UND CANT. LARGO ANCHO ALTO SUPERF. PARCIAL
VEC

UND
M2
M2 1.00 1.00 4.00 3.00 12.00
M2 1.00 1.00 3.00 1.50 4.50
M2 1.00 1.00 3.00 2.50 7.50
M
M 1.00 1.00 85.00 85.00
GLB
KG
M3
M3
KM
M2

M2
M2

M2
M2

M3
M3
M3
M3
M3
M3
M2

M3
M3
M3
M3

M3
M3
M3
M3

M2

M2
M2
M2
M2
M2
M2
M3
M2
M3
M3
M2

M2
M2

M
M

M3 0.00
M2 0.00
UND 0.00
UND 0.00
M 0.00
UND 0.00

M3
M3 1.00 1.00 1.50 1.20 3.00 5.40
M3
M3
M3
M3 1.00 1.00 1.50 1.20 3.00 5.40
M3

UND
UND
UND
TOTAL UND

24.00 M2

85.00 M
M3
M2
UND
UND
M
UND

M3

M3
2.3.- PLANILLA DE ME

ITEM DESCRIPCION
02.03 INSTALACIONES ELECTRICAS

02.03.01 SERVICIO DE REPARACION SISTEMA ELECTRICO INC/MATERIALES

02.03.02 SERVICIO OE REPARACION SISTEMA DE BOMBEO INC/MATERIALES

02.04 SISTEMA DE AGUA FRIA Y CONTRA INCENDIO

02.04.01 SERVICIO OE REPARACION SISTEMA RIEGO ASPERSION INC / MATERIALES

02.05 EMPALME A REO DE ALCANTARILLADO


02.05.01 RED DE EMPALME
02.05.01.01 EXCAVACION DE TERRENO TUB 6". 8' MASIA1 ML
02.05.01.02 CAMA DE APOVO
02.05.01.03 TUBERIA PVC ISO ZOOMM S-25 UF
02.05.01.04 COLOCACION DE CAMA DF ARENA H=0.20M
02.05.01.05 RELLENO COMPACTADO ZAN1A
02.05.01.06 CONEXIN A RED DE DESAGE
02.05.02 BUZON
02.05.02.01 ACERO ESTRUCTURAl PARA LOSA TAPA BUZON
02.05.02.02 ENCOBRADO DESENCOFRADO LOSA TAPA BUZON
02.05.02.03 CONCRETO FC=210 KG/CM2 PARA LOSAS TAPA I1U7.0N
02.05.02.04 MEDIA CAA DC A' CONCRfTO K.-1 75 K6/CM? ACAVAOO POUDO
02.06 RED DE AGUA PLUVIALES
02.06.01 EXCAVACION D ZANJA PAI1A DfttNAJC
02.06.02 CONCRETO CANALETAS FC=210 kg/cm2
02.06.03 ENCOFRDO CANALETA 0,30X0.30 M INCLUYL TARRAIEO
02.06.04 ELIMINACION DE MATERIAI EXEDENTE
02.07 SEALIZACION
02.07.01 EXCAVACION DE HOYO PARA POSTE
02.07.02 CONCRETO PARA COLOCACION DE POSTE f'c=?.10 kA:m2
02.07.03 POSTE DE FIERRO GALVANIZADO
02.07.04 SEAL PREVENTIVA
02.07.05 SEAL REGLAMENTARIA
02.07.06 SEALES INFORMATIVAS URBANA
02.07.07 MARCAS EN H PAVIMENTO *
02.07.08 PINTADO DE SARDINELES
02.08 REPOSICION DE CAIAS DE DESAGE EN VEREDAS
02.08.01 REPOSICION DE CAJAS DE AGUA EN VEREDAS
02.08.02 REPOSICION DE CAJAS OE DESAGE ENVEREDAS
02.08.03 DISEO DE MEZCLAS
02.08.04 ROTURA DE BRIQUETAS
02.08.05 PRUEBAS OE CONTROL DE COMPAC'TACION
02.08.06 LIMPIEZA DURANTE LA EJECUCION DE LA OBRA
02.08.07 CURADO CON AGUA
03 MITIGACION AMBIENTAL Y DE RIESGOS
03.01 MITIGACION DE IMPACTO AMBIENTAL
03.02 MITIGACION DE RIESGOS DE DESASTRES
2.3.- PLANILLA DE METRADOS DIARIOS

N DE
UND CANT. LARGO ANCHO ALTO SUPERF. PARCIAL
VEC

GLB

GLB

GLB

M
M
M
M2
M
PTO

KG
UND
M3
M2

M
M3
M2
M3

UND
M3
UND
UND
UND
UND
M2
M2

UND
UND
UND
UND
UND
DIA
M2

GLB
GLB
TOTAL UND
2.3.- PLANILLA DE ME

ITEM DESCRIPCION
01 PAVIMENTACIN DE PISTAS V VEREDAS
01.01 OBRAS PROVISIONALES
01.01.01 TRANSPORTE DE PERSONAL OBRERO A CANTERA
LINTERNA PANORMICA A 500 MTS DE ALCANCE
01.02 SEGURIDAD Y SALUD
ELABORACIN, IMPLEMENTACIN Y ADMINISTRACIN DEL PLAN DE SEGURIDAD Y
01.02.01
SALUD
01.02.01.01 EN EL TRABAJO
EQUIPO DE PROTECCION INDIVIDUAL
CASCO DE SEGURIDAD COLOR AZUL (05) COLOR ANARANJADO 35) COLOR AMARILLO
(10) - SEGURA
CORTAVIENTOS CON FORRO POLAR PARA CASCOS DE SEGURIDAD COLOR AZUL-
NACIONAL
OVEROL DRILL EN DOS PIEZASICAMISA Y PANTALON) COLOR AZUL CON CINTA
REFLECTIVA
CON TOGOTIPO INSTITUCIONAL DRILL ' . ...
OVEROL CON FORRO POLAR EN DOS PIEZAS (CAMISA* PANTALN COLOR AZUL CON
CINTA

REFLECTABA CON LOGOTIPO INSTITUCIONAL NACIONAL EN TELA DRILL)- NACIONAL

LENTES DE SEGURIDAD COLOR CLAROS (SEGN NORMA VIGENTE) SPRO

LENTES DE SEGURIDAD COLOR OSCUROS(SEGN NORMA VIGENTE) SPRO

GUANTES DE SABANA PARA OPERARIO (SEGN NORMA VIGENTE). SPRO

GUANTES DE CUERO REFORZADOS TRIPLE COSTURA ISEGN NORMA VIGENTE)-


NACIONAT

GUANTES DE JEBE N9 ALTOS (SEGN NORMA VIGENTE)-P80TEX


SOTAS DE JEBE-NACIONAL
T
R ESPIRADOR ES RE USABLES DE MEDIA CARA PARA POLVO DE UNA VIA CON
CARTUCHO

'(SEGN. NORMA VIGENTEL -KAMASA TAPONES DE OIDO -GLUTE

FRANELA COLOR VERDF. Y ROIO X 60 MTS -SAN JACINTO

BOTIQUIN (INCLUYE MF.DICAMEN IOS) 0! PAQUETES DE GUANTES QUIRURGICOS

CAMILLA RIGIDA PARA HERIDOS

01.02.01.02 EQUIPOS DE PROTECCION COLECTIVA

LINTERNA PANORAMICA A SOO MTS DI ALCANQ

01.02.01.03 SEALIZACION TEMPORAL DE SEGURIDAD


01.02.01.04 CAPACITACION EN SEGURIDAD Y SALUD

CHARLAS DE INDUCCION AL PERSONAL OBRERO (SEG. Y SALUDI

CHARLAS DE INDUCCION AL PERSONAL OBRERO (SEG. Y SALUD)

01.02.01.05 EXAMENES MEDICOS PRE-OCUPACIONALES

EXAMEN MEDICO OCUPACIONAL (PSICOLOGIA,OFTALMOLOGIA)


EXAMEN MEDICO OCUPACIONAL (PSICOLOGIA,OFTALMOLOGIA)

REGISTRO DE DOCUMENTACION DEL SISTEMA DE GESTION DE LA SEG, Y SALUD EN


01.02.01.06
EL TRABAJO.
01.03 PREPARACIN DE PIEDRA
01.03.01 EXTRACCION DE PIEDRA EN CANTERA

EXTRACCION DE PIEDRA EN CAN1ERA (ACUMULACION DE PIEDRAS)

EXTRACCION DE PIEDRA EN CANTERA (ACUMULACION DI PIEDRAS)

01.03.02 ACOPIO DE PIEDRA EN CANTERA

ACOPIO DE PIEDRA EN CANTERA (DISTANCIA DE 120 MI DE LA CANTERA)

ACOPIO D PIEDRA EN CANTERA (DISTANCIA DE 120 ML DE LA CANTERA)

01.03.03 CARGUIO DE PIEDRA PARA TRASLADO

CARGUO DE PIEDRA PARA U TRASLADO CORRESPONDIENTE . ..


01.03.04 CORTE Y PERFILADO DE ADOQUINES DE PIEDRA 2SX1-4J9 CM
01.03.05 INSTALACIN DE ADOQUINES DE PIEDRA 25X14X9 CM

01.03.06 MOVILIZACIN Y DESMOVILIZACIN DE PIEDRA CANTERA A OBRA

MOVILIZACIN Y DESMOVILIZACIN DI PIEDRA CANTERA A OBRA


2.3.- PLANILLA DE METRADOS DIARIOS

N DE
UND CANT. LARGO ANCHO ALTO SUPERF. PARCIAL
VEC

DIA
DIA 1.00 1.00 total 22.00 22.00

GLB

UND 1.00 32.00 PRECIO 9.00 288.00

UND 1.00 33.00 PRECIO 9.00 297.00

UND 1 00 1.00 PRECIO 15.00 15.00

PRECIO

UND 1.00 33.00 PRECIO 35.00 1155.00

UND 1.00 1.00 PRECIO 8.00 8.00

UNO 1.00 34.00 PRECIO 8.00 272.00

PAR 1.00 7.00 PRECIO 8.50 59.50

PAR 1.00 50.00 PRECIO 9.00 450.00

PAR 1.00 2.00 PRECIO 14.00 28.00


PAR 1.00 0 00 PRECIO 30.00

UND 1.00 19.00 PRECIO 14.00 266.00

1.00 33.00 PRECIO 1.00 33.00

ROLLO 1 00 1.00 PRECIO 300.00 300.00

UND 1.00 1.00 PRECIO 250.00 250.00

UND 1 00 1.00 PRECIO 250.00 250.00

GLB

GLB 1.00 0.30 PRECIO 712.71 213.81

GLB
GLB

GLO 1.00 0.50 PRECIO 1870.00 935.00

GLB 1.00 0.50 PRECIO 1870.00 935.00

GLB PRECIO

GIB 1.00 0.08 PRECIO 120.00 9.60


GLB 1.00 0.08 PRECIO 121.00 9.68

GLB

M2

M2 17.00 1.00 AREA 32.00 544.00

M2 4.00 1.00 AREA 22.00 88.00

M2

M2 17.00 1.00 AREA 32.00 544.00

M2 4.00 1.00 AREA 22.00 88.00

M2

M2
M2
M2

VJE

DIA 1.00 1.00 TOTAL 10.00 10.00


TOTAL UND

22.00 DIA

3671.50 GLB

213.81 GLB

1889.28 GLB
632.00 M2

632.00 M2

10.00 VIAJE
2.4.- VALORIZACION FISICO DE OBRA - EXPED
PROYECTO : "MEJORAMIENTO DEL SERVICIO DE INFRAESTRUCTURA DE CALLES DE LA LOC
ING. RESIDENTE : ING. ROBERTO NINCA GARCIA
ING.INSPECTOR : ING. ROMULO JULIO CHOQUE ARMUTO
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE DE SAN CRISTOBAL CALACOA
MODALIDAD : ADMINISTRACIN DIRECTA

SEGN EXPEDIENTE TECNICO


ANTERIOR
ITEM DESCRIPCIN
COSTO
UND METRADO PARCIAL (S/.) METRADO MONTO VALORIZ. %
UNITARIO (S/.)

01 PAVIMENTACIN OE PISTAS Y VEREDAS


01.01 OBRAS PROVISIONALES
01.01.01 CARTEL DE IDENTIFICACION DE OBRAS DE 3.6X2.4D M UND 1.00 1,345.89 1,345.89 0.00 S/. 0.00 0.00%
01.01.02 CASETA ADICIONAL P/GUARDIANIA 1/O DEPOSITO M2 40.00 86.49 3,459.60 0.00 S/. 0.00 88.20%
01.01.03 CERCO DE PROTPITLON DE MALLA ARPILLERA M 200.00 18.89 3,778.00 0.00 S/. 0.00 42.50%
01.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 2.00 1,343.42 2,686.84 0.00 S/. 0.00 0.00%
01.01.05 TRANSPORTE DE CEMENTO KG 5,872.00 5.94 34,879.68 0.00 S/. 0.00 0.00%
01.01.06 TRANSPORTE 0 MATERIALES MOQUEGUA-CALACOA M3 10,000.00 0.23 2,300.00 0.00 S/. 0.00 0.00%
01.01.07 TRANSPORTE DE AGREGADOS MOQUEGUA. OBRA M3 832.00 154.12 128,227.84 0.00 S/. 0.00 0.00%
01.01.08 TRANSPORTELE PIEDRA ALTO TRANSITO AREQUIPA CALACOA J375 KM 193.00 336.19 64,884.67 0.00 S/. 0.00 0.00%
01.01.09 APERTURA DE VIAS DE ACCESO PROVICIONAL M2 0.17 7,252.87 1,232.99 0.00 S/. 0.00 0.00%
01.02 TRABAJOS PRELIMINARES
01.02.01 TRAZO Y REPLANTEO M2 4,213.59 1.46 6,151.84 0.00 S/. 0.00 0.00%
01.02.02 TRAZO V REPLANTEO DURANTE LA EJECUCION DE OBRA M2 8,427.18 1.25 10,533.98 0.00 S/. 0.00 0.00%
01.03 MOVIMIENTO DE TIERRAS
01.03.01 DEMOLICION DE OBRAS DE CONCRETO
01.03.01.01 DEMOLICION DE VEREDAS DE CONCRETO M2 2.18 133.53 291.10 0.00 S/. 0.00 0.00%
01.03.01.02 DEMOLICION ESTRUCTURAS DE CONCRETO M2 15.28 124.93 1,908.93 0.00 S/. 0.00 0.00%
01.03.02 ELIMINACION DE MATERIAL EXEOENTE
01.03.02.01 CARGUIO DE MATERIAL EXCEDENTE DE DEMOLICIONES M3 4.19 112.20 470.12 0.00 S/. 0.00 0.00%
01.03.02.02 CORTE SUPERFICIAL DE SUBRASANTE HASTA 0.20M M3 1,248.83 5.17 6,456.45 0.00 S/. 0.00 0.00%
01.03.02.03 PERFILADO Y COMPACTADO DE SUBRASANTE M3 4,213.59 7.54 31,770.47 0.00 S/. 0.00 0.00%
01.03.02.04 AFIRMADO DE 1" PARA VEREDAS COMPACTADO M3 567.80 13.65 7,750.47 0.00 S/. 0.00 0.00%
01.03.02.05 CARGUIO DE MATERIAL EXCEDENTE DE CORTE M3 974.66 5.11 4,980.51 0.00 S/. 0.00 0.00%
01.03.02.06 TRANSPORTE DE MATERIAL EXECEDENTE DE CORTE M3 974.66 6.58 6,413.26 0.00 S/. 0.00 0.00%
01.03.02.07 NIVELACION Y COMPACTADO DE MAT. BASE PREVIO AL PAVIMENTO M2 3,645.78 7.09 25,848.58 0.00 S/. 0.00 0.00%
01.03.03 EXTRACCION PREPARACION DE MATERIAL BASE
01.03.03.01 EXTRACCION DE CANTERA MATERIAL BASE M3 795.65 6.91 5,497.94 0.00 S/. 0.00 0.00%
01.03.03.02 ZARANDEADO DE MATERIAL DE PRESTAMO M3 795.65 7.11 5,657.07 0.00 S/. 0.00 0.00%
01.03.03.03 CARGUIO DE MATERIALDE PRESTAMO (BASEI M3 795.65 3.27 2,601.78 0.00 S/. 0.00 0.00%
01.03.03.04 TRANSPORTE A LA OBRA MATERIAL BASE M3 795.65 8.80 7,001.72 0.00 S/. 0.00 0.00%
01.03.04 EXTRACCION PREPARACION TIERRA DE CHACRA
01.03.04.01 EXTRACCION DE CANTERA TIERRA OE CHACRA M3 21.56 37.65 811.73 0.00 S/. 0.00 0.00%
01.03.04.02 ZARANDEO DE MATERIAL TIERRA DE CHACRA M3 21.56 10.87 234.36 0.00 S/. 0.00 0.00%
01.03.04.03 CARGUIO DE TIERRA OE CHACRA M3 15.09 8.79 132.64 0.00 S/. 0.00 0.00%
01.03.04.04 TRANSPORTE A LA OBRA I1ERRA DT CHACRA M3 15.09 11.81 178.21 0.00 S/. 0.00 0.00%
01.04 OBRAS DE CONCRETO SIMPLE
01.04.01 FALSO PISO DE 4" DE CONCRETO 1:10 M2 7.90 49.00 387.10 0.00 S/. 0.00 0.00%
01.05 PISOS, PAVIMENTOS V VEREDAS
01.05.01 PISO DE PIEDRA LAJA E=5.0CM M2 7.90 204.87 1,618.47 0.00 S/. 0.00 0.00%
01.05.02 VEREDA ASENT. PIEDRA SELECCIONADA Y HABILITADA FC=175 KG/CM2 372.00 89.54 33,308.88 0.00 S/. 0.00 0.00%
01.05.03 VEREDA ENCOFRADO Y DESENCOFRADO M2 167.75 47.36 7,944.64 0.00 S/. 0.00 0.00%
01.05.04 VEREDA RIGIDA DE CONCRETO DE 4" M2 49.20 130.46 6,418.63 0.00 S/. 0.00 0.00%
01.05.05 VEREDA DE PIEDRA LAJA E- 5CTN M2 92.21 219.48 20,238.25 0.00 S/. 0.00 0.00%
01.05.06 PISO DE APAREJO AMERICANO DE PIEDRA LAJA GRANITO M2 20.00 199.96 3,999.20 0.00 S/. 0.00 0.00%
01.05.07 LOSA OE CONCRETO F'C"210 KG/CM2 E =0.T0M M3 135.29 400.54 54,189.06 0.00 S/. 0.00 0.00%
01.05.08 COLOCACION DE ADOQUINES DE PIEDRA PARA TRANSITO ALTO M2 2,020.47 342.72 692,455.48 0.00 S/. 0.00 0.00%
01.05.09 CONCRETO FC=210 KG/CM2 + 60% PM M3 84.67 400.53 33,912.88 0.00 S/. 0.00 0.00%
01.05.10 PAVIMENTO RIGIDO CONCRETO FC=280KG/CM2 E=0.20CM M3 186.47 429.92 80,167.18 0.00 S/. 0.00 0.00%
01.05.11 PAVIMENTO RIGIDO ENCOFRADO Y DESENCOFRADO M2 234.19 113.65 26,615.69 0.00 S/. 0.00 0.00%
01.06 PINTURA
01.06.01 PINTURA ESMALTE Y BARNIZ EN CARPINTERIA M2 57.60 15.99 921.02 0.00 S/. 0.00 0.00%
01.06.02 PINTURA ESMALTT CARPINTERIA METALICA M2 30.00 11.56 346.80 0.00 S/. 0.00 0.00%
01.07 OBRAS COMPLEMENTARIAS
01.07.01 JUNTA DT CONSTRUCCION CON TEKNOPORT M 1,990.21 4.66 9,274.38 0.00 S/. 0.00 0.00%
01.07.02 JUNTAS ASFALTICAS PAVIMENTO RIGIDO M 1,990.21 8.01 15,941.58 0.00 S/. 0.00 0.00%
02 INSTALACIONDE AREAS VERDES YEQUIP AMIENTO BASICO DEL ORNATO
02.01 AREAS VERDES
02.01.01 LLENADO DE IARDINERA CON TIERRA DE CHACRA M3 15.09 28.72 433.38 0.00 S/. 0.00 0.00%
02.01.02 ADQUISICION E INSTALACION DE SEMILLA RAYGRASS M2 5.00 15.50 77.50 0.00 S/. 0.00 0.00%
02.01.03 ADQUISICION E INSTALACION DE ARBOLES ORNAMENTALES UND 14.00 37.11 519.54 0.00 S/. 0.00 0.00%
02.01.04 ADQUISICION E INSTALACION DE ESPECIES FLORALES UND 300.00 7.47 2,241.00 0.00 S/. 0.00 0.00%
02.01.05 CERCO METALICO JARDINES M 265.25 27.99 7,424.35 0.00 S/. 0.00 0.00%
02.01.06 MALLA DE PROTECCION ARBOLES ORNAMENTALES UND 14.00 389.72 5,456.08 0.00 S/. 0.00 0.00%
02.02 EQUIPAMIENTO
02.02.01 CONFECCION E INSTALACION DE FIGURAS ALEGORICAS
02.02.01.01 EXTRACCION DE PIEDRA P/TALLAR M3 40.00 439.55 17,582.00 0.00 S/. 0.00 46.53%
02.02.01.02 SELECCIN Y APILAMIENTO OE PIE DRA M3 30.00 390.66 11,719.80 0.00 S/. 0.00 0.00%
02.02.01.03 CARGUIO OE PIEDRA M3 30.00 18.99 569.70 0.00 S/. 0.00 0.00%
02.02.01.04 TRANSPORTE DE PIEDRA P/TALLAR M3 30.00 188.50 5,655.00 0.00 S/. 0.00 62.03%
02.02.01.05 TALLADO DE FIGURAS ALEGORICAS M3 12.00 8,260.00 99,120.00 0.00 S/. 0.00 0.00%
DE OBRA - EXPEDIENTE FINAL
CALLES DE LA LOCALIDAD DE CALACOA, DISTRITO DE SAN CRISTOBAL, CALACOA - MARISCAL NIETO - MOQUEGUA"

FECHA DE INICIO : 06 DE OCTUBRE DEL 2015


FECHA DE TRMINO : EJECUCION

EJECUCION REAL A DICIEMBRE 2015


SALDO
ACTUAL ACUMULADO

METRADO MONTO VALORIZ. % METRADO MONTO VALORIZ. % METRADO MONTO VALORIZ. %

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 1.00 S/. 1,345.89 100.00%
24.00 S/. 2,075.76 60.00% 24 S/. 2,075.76 60.00% 16.00 S/. 1,383.84 40.00%
85.00 S/. 1,605.65 42.50% 85 42.50% 115.00 S/. 3,778.00 57.50%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 2.00 S/. 2,686.84 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 5,872.00 S/. 34,879.68 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 10,000.00 S/. 2,300.00 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 832.00 S/. 128,227.84 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 193.00 S/. 64,884.67 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 0.17 S/. 1,232.99 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 4,213.59 S/. 6,151.84 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 8,427.18 S/. 10,533.98 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 2.18 S/. 291.10 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 15.28 S/. 1,908.93 100.00%
S/. 0.00 #DIV/0! 0 S/. 0.00 #DIV/0! 0.00 S/. 0.00 #DIV/0!
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 4.19 S/. 470.12 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 1,248.83 S/. 6,456.45 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 4,213.59 S/. 31,770.47 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 567.80 S/. 7,750.47 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 974.66 S/. 4,980.51 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 974.66 S/. 6,413.26 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 3,645.78 S/. 25,848.58 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 795.65 S/. 5,497.94 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 795.65 S/. 5,657.07 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 795.65 S/. 2,601.78 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 795.65 S/. 7,001.72 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 21.56 S/. 811.73 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 21.56 S/. 234.36 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 15.09 S/. 132.64 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 15.09 S/. 178.21 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 7.90 S/. 387.10 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 7.90 S/. 1,618.47 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 372.00 S/. 33,308.88 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 167.75 S/. 7,944.64 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 49.20 S/. 6,418.63 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 92.21 S/. 20,238.25 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 20.00 S/. 3,999.20 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 135.29 S/. 54,189.06 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 2,020.47 S/. 692,455.48 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 84.67 S/. 33,912.88 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 186.47 S/. 80,167.18 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 234.19 S/. 26,615.69 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 57.60 S/. 921.02 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 30.00 S/. 346.80 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 1,990.21 S/. 9,274.38 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 1,990.21 S/. 15,941.58 100.00%

0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 15.09 S/. 433.38 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 5.00 S/. 77.50 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 14.00 S/. 519.54 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 300.00 S/. 2,241.00 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 265.25 S/. 7,424.35 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 14.00 S/. 5,456.08 100.00%

5.40 S/. 2,373.57 13.50% 5.4 S/. 2,373.57 13.50% 34.60 S/. 15,208.43 86.50%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 30.00 S/. 11,719.80 100.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 30.00 S/. 569.70 100.00%
5.40 S/. 1,017.90 18.00% 5.4 S/. 1,017.90 18.00% 24.60 S/. 4,637.10 82.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 12.00 S/. 99,120.00 100.00%
2.4.1.- VALORIZACION FISICO DE OBRA - ADIC
PROYECTO : "MEJORAMIENTO DEL SERVICIO DE INFRAESTRUCTURA DE CALLES DE LA LOC
ING. RESIDENTE : ING. ROBERTO NINCA GARCIA
ING.INSPECTOR : ING. ROMULO JULIO CHOQUE ARMUTO
ENTIDAD EJECUTORA : MUNICIPALIDAD DISTRITAL DE DE SAN CRISTOBAL CALACOA
MODALIDAD : ADMINISTRACIN DIRECTA

SEGN EXPEDIENTE TECNICO


ANTERIOR
ITEM DESCRIPCIN
COSTO
UND METRADO PARCIAL (S/.) METRADO MONTO VALORIZ. %
UNITARIO (S/.)

01 PAVIMENTACIN DE PISTAS V VEREDAS


01.01 OBRAS PROVISIONALES
01.01.01 TRANSPORTE DE PERSONAL OBRERO A CANTERA DIA 60.00 482.14 28,928.40 0.00 S/. 0.00 0.00%
01.02 SEGURIDAD Y SALUD
01.02.01 ELABORACIN, IMPLEMENTACIN Y ADMINISTRACIN DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO
01.02.01.01 EQUIPO DE PROTECCION INDIVIDUAL GLB 1.00 26,360.00 26,360.00 0.00 S/. 0.00 0.00%
01.02.01.02 EQUIPOS DE PROTECCION COLECTIVA GLB 1.00 712.71 712.71 0.00 S/. 0.00 0.00%
01.02.01.03 SEALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1,726.00 1,726.00 0.00 S/. 0.00 0.00%
01.02.01.04 CAPACITACION EN SEGURIDAD Y SALUD GLB 2.00 1,870.00 3,740.00 0.00 S/. 0.00 0.00%
01.02.01.05 EXAMENES MEDICOS PRE-OCUPACIONALES GLB 30.00 120.00 3,600.00 0.00 S/. 0.00 0.00%
01.02.01.06 REGISTRO DE DOCUMENTACION DEL SISTEMA DE GESTION DE LA SE
GLB 1.00 3,500.00 3,500.00 0.00 S/. 0.00 0.00%
01.03 PREPARACIN DE PIEDRA
01.03.01 EXTRACCION DE PIEDRA EN CANTERA M2 2,020.47 38.30 77,384.00 0.00 S/. 0.00 0.00%
01.03.02 ACOPIO DE PIEDRA EN CANTERA M2 2,020.47 32.28 65,220.77 0.00 S/. 0.00 0.00%
01.03.03 CARGUIO DE PIEDRA PARA TRASLADO M2 2,020.47 22.84 46,147.53 0.00 S/. 0.00 0.00%
01.03.04 CORTE Y PERFILADO DE ADOQUINES DE PIEDRA 2SX1-4J9 CM M2 2,020.47 50.92 102,882.33 0.00 S/. 0.00 0.00%
01.03.05 INSTALACIN DE ADOQUINES DE PIEDRA 25X14X9 CM M2 2,020.47 171.51 346,530.81 0.00 S/. 0.00 0.00%
01.03.06 MOVILIZACIN Y DESMOVILIZACIN DE PIEDRA CANTERA A OBRA VJE 60.00 843.46 50,607.60 0.00 S/. 0.00 0.00%

RESUMEN VALORIZADO
COSTO DIRECTO S/. 757,340.15 S/. 0.00 0.00%
GASTOS GENERALES S/. 98,454.22 S/. 0.00 0.00%
GASTOS DE SUPERVISIN S/. 37,867.01 S/. 0.00 0.00%
GASTOS DE ADMINISTRACIN S/. 53,013.81 S/. 0.00 0.00%
GASTOS DE LIQUIDACIN S/. 15,146.80 S/. 0.00 0.00%
GASTOS DE EXPEDIENTES TECNICOS S/. 13,370.99 S/. 0.00 0.00%
TOTAL VALORIZADO S/. 975,192.98 100.00% S/. 0.00 0.00%
O DE OBRA - ADICIONAL N 01
CALLES DE LA LOCALIDAD DE CALACOA, DISTRITO DE SAN CRISTOBAL, CALACOA - MARISCAL NIETO - MOQUEGUA"

FECHA DE INICIO : 06 DE OCTUBRE DEL 2015


FECHA DE TRMINO : EJECUCION

EJECUCION REAL A DICIEMBRE 2015


SALDO
ACTUAL ACUMULADO

METRADO MONTO VALORIZ. % METRADO MONTO VALORIZ. % METRADO MONTO VALORIZ. %

22.00 S/. 10,607.08 36.67% 22 S/. 10,607.08 36.67% 38.00 S/. 18,321.32 363.33%

0.14 S/. 3,690.40 14.00% 0.14 S/. 3,690.40 14.00% 0.86 S/. 22,669.60 786.00%
0.30 S/. 213.81 30.00% 0.3 S/. 213.81 30.00% 0.70 S/. 498.90 870.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 1.00 S/. 1,726.00 1000.00%
0.50 S/. 935.00 25.00% 0.5 S/. 935.00 25.00% 1.50 S/. 2,805.00 1075.00%
0.15 S/. 18.00 0.50% 0.15 S/. 18.00 0.50% 29.85 S/. 3,582.00 1199.50%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 1.00 S/. 3,500.00 1300.00%

632.00 S/. 24,205.60 31.28% 632 S/. 24,205.60 31.28% 1,388.47 S/. 53,178.40 1468.72%
632.00 S/. 20,400.96 31.28% 632 S/. 20,400.96 31.28% 1,388.47 S/. 44,819.81 1568.72%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 2,020.47 S/. 46,147.53 1700.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 2,020.47 S/. 102,882.33 1800.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 2,020.47 S/. 346,530.81 1900.00%
0.00 S/. 0.00 0.00% 0 S/. 0.00 0.00% 60.00 S/. 50,607.60 2000.00%

S/. 60,070.85 7.93% S/. 60,070.85 7.93% S/. 697,269.30 92.07%


S/. 7,809.21 S/. 7,809.21 S/. 90,645.01
S/. 2,703.19 S/. 2,703.19 S/. 34,863.47
S/. 600.71 S/. 600.71 S/. 48,808.85
S/. 2,703.19 S/. 2,703.19 S/. 13,945.39
S/. 1,501.77 S/. 1,501.77 S/. 12,310.43
S/. 75,388.92 7.93% S/. 75,388.92 7.93% S/. 897,842.45 92.07%
2.5.- MEMORIA DESCRIPTIVA VALORIZADA (EXPEDIEN

01 PAVIMENTACION DE PISTAS Y VEREDAS


01.01 OBRAS PROVISIONALES
01.01.02 CASETA ADICIONAL P/ GUARDIANIA Y/O DEPOSITO

Esta partida comprende la construccin provisional de ambientes para instalar un Almacn y Guardian
las necesidades de la obra, para garantizar la seguridad y correcto almacenaje de los materiales y herr

En el presente mes se ha ejecutado la partida con el siguiente detalle:


PROGRAMADO U.M. ANTERIOR ACTUAL
METRADO M2 24
PRESUPUESTO 0.00 2,075.76

01.01.03 CERCO DE PROTECCION DE MALLA ARPILLERA


Esta partida comprende la construccin y colocacin de cerco de malla arpillera y sus puertas que son
que delimitan el rea de costruccin u otros ambientes necesarios para la seguridad y control durante l
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR ACTUAL
METRADO M 0 85
PRESUPUESTO 0.00 1605.65

02.02.01 CONFECCION E INSTALACION DE FIGURAS ALEGORICAS


02.02.01.01 EXTRACCION DE PIEDRA P/ TALLAR
Esta partida consiste en la extraaccion de piedra de cantera para transporte de piedra para tallar.
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR ACTUAL
METRADO M3 0 5.4
PRESUPUESTO 0.00 1,017.90

12.02.01.04 TRANSPORTE DE PIEDRA P/TALLAR


Esta partida consiste en la extraccin, seleccin y apilamiento, carguio y transporte de piedra para talla
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M. ANTERIOR ACTUAL
METRADO m3 '0 5.4
PRESUPUESTO 0/00 1,017.90
SCRIPTIVA VALORIZADA (EXPEDIENTE)

mbientes para instalar un Almacn y Guardiana de acuerdo a


y correcto almacenaje de los materiales y herramientas.

ACUMULADO % AVAN. ACUM.


24 60.00
1,605.65

erco de malla arpillera y sus puertas que son elentos de cierre


ecesarios para la seguridad y control durante la ejecucin de la obra

ACUMULADO % AVAN. ACUM.


85 42.50
1,605.65

era para transporte de piedra para tallar.

ACUMULADO % AVAN. ACUM.


5.4 18.00
1,017.90

ento, carguio y transporte de piedra para tallar.

ACUMULADO % AVAN. ACUM.


5.4 18
1,017.90
2.5.- MEMORIA DESCRIPTIVA VALORIZAD

01.00 PAVIMENTOS DE PISTAS Y VEREDAS


01.01 OBRAS PROVISONALES
01.01.01 TRANSPORTE DE PERSONAL OBRERO A CANTERA
Esta partida comprende traslado de personal obrero a cantera y traslado de materiales y herramie
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR
METRADO DIA 0
PRESUPUESTO 0.00

01.02.01.01 EQUIPO DE PROTECCION INDIVIDUAL


Esta partida comprende la entrega de equipos de proteccion individual de los obreros como: casco
guantes, zapatos, chalecos, lentes, cortavientos, ropa de trabajo y otros
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR
METRADO GLB 0
PRESUPUESTO 0.00

01.02.01.02 EQUIPO DE PROTECCION COLECTIVA


Esta partida comprende la entrega de equipos de seguridad al guardian de la obra como: linterna,
audible de seguridad y otros
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR
METRADO GBL 0
PRESUPUESTO 0.00

01.02.01.04 CAPACITACION TEMPORAL DE SEGURIDAD


Esta partida comprende capacitacion, charlas de seguridad, capacitacion de instrucciones en el tra
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR
METRADO GLB 0
PRESUPUESTO 0.00

01.02.01.05 EXAMENES MEDICOS PRE-OCUPACIONALES


Esta partida comprende en dar atencion de examenes medicos ocupacionales, examenes psicolog
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR
METRADO GLB 0
PRESUPUESTO 0.00

01.03 PREPARACION DE PIEDRA


01.03.01 EXTRACCION DE PIEDRA EN CANTERA
Esta partida comprende en extraer piedra en cantera, el trabajo conciste en empiezar herramienta
barretas, picos, palas, carretilla
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR
METRADO M2 0
PRESUPUESTO 0.00

01.03.02 ACOPIO DE PIEDRA EN CANTERA


Esta partida comprende en juntar la piedra en cantera, el trabajo conciste en emplear herramienta
barretas, picos, palas, carretilla.
En el presente mes se ha ejecutado la partida con el siguiente detalle:
PROGRAMADO U.M ANTERIOR
METRADO M2
PRESUPUESTO 0.00
ORIA DESCRIPTIVA VALORIZADA (ADICIONAL N 01)

era y traslado de materiales y herramientas

ACTUAL ACUMULADO % AVAN. ACUM.


22 22 36.67
10,607.08 10,607.08

on individual de los obreros como: casco de seguridad,

ACTUAL ACUMULADO % AVAN. ACUM.


0.139 0.139 14.00
3,664.04 3,664.04

d al guardian de la obra como: linterna, megafonos, alarma

ACTUAL ACUMULADO % AVAN. ACUM.


0.3 0.3 30.00
213.81 213.81

d, capacitacion de instrucciones en el trabajo, charlas de induccion a obreros

ACTUAL ACUMULADO % AVAN. ACUM.


0.5 0.5 25.00
935.00 935.00

dicos ocupacionales, examenes psicologia, examenes de oftalmologia

ACTUAL ACUMULADO % AVAN. ACUM.


0.15 0.15 0.50
18.00 18.00

abajo conciste en empiezar herramientas manuales como:

ACTUAL ACUMULADO % AVAN. ACUM.


632 632 31.28
24,205.60 24,205.60

abajo conciste en emplear herramientas manuales como:

ACTUAL ACUMULADO % AVAN. ACUM.


632 632 31.28
20,400.96 20,400.96
2.1.- RESUMEN DE AVANCE DE OBRA D

"MEJORAMIENTO DEL SERVICIO DE INFRAESTRUCTURA


PROYECTO
- MARISCAL NIETO - MOQUEGUA"
E.EJECUTORA MUNICIPALIDAD DISTRITAL DE SAN CRISTOBAL CALACO
MODALIDAD ADMINISTRACION DIRECTA
MONTO DE LA OBRA S/. 2'097,932.40
FECHA DE INICIO DE LA OBRA 06 DE OCTUBRE DEL 2015
PLAZO DE EJECUCION 180 DIAS DE CALENDARIO

MODALIDAD DE EJECUCION:
ADMINISTRACION DIRECTA
EXPEDIENTE TCNICO REFORMULADO PARA CULMINAR OBRA:
S/. 890,301.66 Nuevos soles

VALOR
PROGRAMADO
N de Quin. Del Monto % Ejecucin %
informe informe S/. Programada Acumulado
Inicio 0.00%
1.0 OCTUBRE 108567.31 6.66% 6.66%
2.0 NOVIEMBRE 512504.93 31.46% 38.12%
3.0 DICIEMBRE 250816.44 15.39% 53.51%
4.0 ENERO 397071.50 24.37% 77.88%
5.0 FEBRERO 178482.43 10.95% 88.84%
6.0 MARZO 170158.93 10.44% 99.28%
7.0 ABRIL 11684.12 0.72% 100.00%

Total a la Fecha S/. 1,629,285.66 100.00%


AVANCE DE OBRA DE OBRA "CURVA S"

DE INFRAESTRUCTURA DE CALLES DE LA LOCALIDAD DE CALACOA, DISTRITO DE SAN CRISTOBAL, CALACOA


"
AN CRISTOBAL CALACOA
DEPARTAMENTO :MOQUEGUA
PROVINCIA :MARISCAL NIETO
DISTRITO :SAN CRISTOBAL - CALACOA
LUGAR :CALACOA
ING. RESIDENTE :ING. ROBERTO NINCA GARCIA
ING.INSPECTOR :ING. ROMULO JULIO CHOQUE ARMUTO

PLAZO DE EJECUCIN:
: 180 DIAS CALENDARIOS
ASIGNACIN PRESUPUESTAL:
S/. 1'000,000.000 Nuevos soles ao15

VALORIZACION DE OBRA
FISICO EJECUTADO FINANCIERO EJECUTADO
Monto Porcentaje % Porcentaje %
MontoS/.
S/. de ejecucin Acumulado de ejecucin Acumulado
0.00% 0.00%
84265.38 5.17% 5.17% 180864.63 8.62% 8.62%

S/. 84,265.38 5.17% S/. 180,864.63 8.62%


3.1.- RESUMEN FINACIERO
NOVIEMBRE - 2015.
APROBADO
N DESCRIPCION Anterior
TOTAL % % TOTAL %
1.00 COSTO DIRECTO 1,629,265.66 0.00 0.00%
262324 personal 351602.12 100.00% 0.00 0.00%
262325 bienes y/o materiales 1054993.54 100.00% 0.00 0.00%
262326 Servicios. 222,670.00 100.00% 0.00 0.00%
2.00 COSTOS INDIRECTOS 468,666.74 0.00 0.00%
a GASTOS DE DIRECCION TECNICA 211,804.54 100.00% 0.00 0.00%
262324 personal 167,699.89 100.00% 0.00 0.00%
262325 bienes y/o materiales 9,966.50 100.00% 0.00 0.00%
262325 Servicios. 34,138.15 100.00% 0.00 0.00%
b GASTOS DE SUPERVICION 81,463.28 100.00% 0.00 0.00%
c GASTOS DE LIQUIDACION 32585.31 100.00% 0.00 0.00%
d GASTOS DE ADMINISTRACION 114,048.60 100.00% 0.00 0.00%
e GASTOS DE ELAB. DE EXP. TECNICO 28,765.01 100.00% 0.00 0.00%
TOTAL 2,097,932.40 100% 0.00 0.00%
1.- RESUMEN FINACIERO
NOVIEMBRE - 2015.
EJECUTADO
Actual Acumulado Saldo
TOTAL % TOTAL % TOTAL %
141,811.75 141,811,75 1,487,453.91
57,375.00 16.32% 57,375.00 16.32% 294,227.12 83.68%
53,276.75 5.05% 53,276.75 5.05% 1,001,716.79 94.95%
31,160.00 13.99% 31,160.00 13.99% 191,510.00 86.01%
39,052.88 39,052.88 429,613.86
22,198.17 10.48% 22,198.17 10.48% 189,606.37 89.52%
21,488.17 12.81% 21,488.17 12.81% 146,211.72 87.19%
750.00 7.53% 750.00 7.53% 9,216.50 92.47%
0.00% 0.00% 34,138.15 100.00%
16,854.71 20.69% 16,854.71 20.69% 64,608.57 79.31%
0.00% 0.00% 32,585.31 100.00%
0.00% 0.00% 114,048.60 100.00%
0.00% 0.00% 28,765.01 100.00%
180,864.63 8.62% 180,864.63 8.62% 1,917,067.77 91.38%
3.1.1 .- RECUR

DOC BASE
MESES
TIPO N

OCTUBRE O/S 65
OCTUBRE O/S 65
OCTUBRE O/S 414
OCTUBRE O/S 414
OCTUBRE O/S 421
OCTUBRE O/S 421
OCTUBRE O/S
OCTUBRE O/S
OCTUBRE O/S
OCTUBRE O/S
OCTUBRE O/S 422
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 393
OCTUBRE O/C 394
OCTUBRE O/C 395
OCTUBRE O/C 395
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
OCTUBRE O/C 398
3.1.1 .- RECURSOS UTILIZADOS (COSTO DIRECTO Y COSTO INDIRECTO)

DESCRIPCION UND

SERGEO E.I.R.L.
ESTUDIO DE PIEDRA SERV.
PARE PINO FREDY
TRASLADO DE MATERIAL DE JULIACA CALACOA SERV.
MUNICIPALIDAD DISTRITAL DE SAN CRISTOBAL CALACOA
MUNICIPALIDAD DISTRITAL DE SAN CRISTOBAL CALACOA SERV.
FLORES MAMANI NICACIO MANUEL
TRASLADO DE PERSONAL OBRERO OBRA SERV.
CERRATO MAMANI JENNY ISIDORA
MUNICIPALIDAD DISTRITAL DE SAN CRISTOBAL CALACOA SERV.
PARE PINO FREDY
EMP DE SERV MULTIPLES DAYRA SYJ S.R.L
CASCO DE SEGURIDAD COLOR AZUL (05) COLOR ANARANJADO (35) COLOR AMARILLO (10) UND.
CORTAVIENTOS CON FORRO POLAR PARA CASCO DE SEGURIDAD COLOR AZUL - NACIONAL UND.
OVEROL DRILL EN DOS PIEZAS (CAMISA Y PANTALON) COLOR AZUL CON CINTA REFLECTIVA UND.
OVEROL CON FORRO POLAR EN DOS PIEZAS (CAMISA Y PANTALON COLOR AZUL CON CINTA REFLECTIVA UND.
LENTES DE SEGURIDAD CLAROS (SEGN NORMA VIGENTE) - SPRO UND.
LENTES DE SEGURIDAD OSCUROS ( SEGN NORMA VIGENTE) - SPRO UND.
ZAPATOS DE SEGURIDAD PARA PERSONAL OBRERO (SEGN NORMA VIGENTE) SCALDOR PAR
GUANTES DE BADANA PARA OPERARIO (SEGN NORMA VIGENTE) NACIONAL PAR
GUANTES DE CUERO REFORZADOS TRIPLE COSTURA (SEGN NORMA VIGENTE) - NACIONAL PAR
GUANTES DE GEBE N 9 ALTOS (SEGN NORMA VIGENTE) - PROTEX PAR
BOTAS DE JEBE - NACIONAL PAR
RESPIRADORES REUSABLES DE MEDIA CARA PARA POLVO DE UNA VIA CON CARTUCHO UND.
TAPONES DE OIDOS - GLUTE UND.
FRANELA COLOR VERDE Y ROJO X 60 MTS - SAN JACINTO ROLLO
ROMERO TORRES JUANA PAULA
AGRO RIEGO TECNIFICADO LAS AMERICAS DEL SUR S.R.L.
TANQUE DE AGUA DE 1100 LTS INC. ACSESORIOS - ROTOPLAS UND.
EMP DE SERV MULTIPLES DAYRA SYJ S.R.L
CLAVOS P/ MADERA C/C DE 2'' - PRODAC KILOG
CLAVOS P/ MADERA C/C DE 3'' - PRODAC KILOG
CLAVOS P/ MADERA DE 4'' - PRODAC KILOG
CLAVOS PARA CALAMINA - PRODAC KILOG
ALAMBRE NEGRO #8 - ACEROS AREQUIPA KILOG
ALAMBRE NEGRO #16 - ACEROS AREQUIPA KILOG
FIERRO CORRUGADO DE 1/2'' (PUESTO EN OBRA) - ACEROS AREQUIPA VARILLA
ADITIVO PLASTIFICANTE Y REDUCTOR DE AGUA - CHEMA PLAST GALONES
ADITIVO ACELERANTE DE FRAGUA - SIKA GALONES
SOLVENTE PARA LACA PROTECTORA - CHEMA GALONES
LACA PROTECTORA ENCOFRADO P/ CONCRETO - CHEMA GALONES
YESO DE 25 KG - NACIONAL BLS.
CALAMINA GALVANIZADA DE 0.80M X 3.60M X 0.24MM - TORTUGA UND.
LINTERNA PANORAMICA A 500 MTS DE ALCANCE EFECTIVO RECARGABLE DE 6 VOLTIOS UND.
MALLA ARPILLERA DOBLE ANCHO 2.00 X 100 MTS - NACIONAL ROLLO
TO DIRECTO Y COSTO INDIRECTO)

BRUTO P.U. CANT PARCIAL COSTO TOTAL

3,860.00
3860.00 1.00 3860.00
1,800.00
1800.00 1.00 1800.00
10000.00
10000.00 1.00 10000.00
2800.00
2800.00 1.00 2800.00
9900.00
9900.00 1.00 9900.00
2,800.00
8,310.00
9.00 50.00 450.00
9.00 50.00 450.00
15.00 60.00 900.00
35.00 60.00 2100.00
8.00 25.00 200.00
8.00 50.00 400.00
60.00 50.00 3000.00
8.50 100.00 850.00
9.00 100.00 900.00
14.00 25.00 350.00
30.00 12.00 360.00
14.00 50.00 700.00
1.00 50.00 50.00
300.00 2.00 600.00
720.5
1,040.00
520.00 2.00 1040.00
7,507.50
6.00 20.00 120.00
6.00 40.00 240.00
6.00 10.00 60.00
6.00 20.00 120.00
6.00 30.00 180.00
6.00 20.00 120.00
28.00 20.00 560.00
29.50 25.00 737.50
37.50 50.00 1875.00
30.00 4.00 120.00
140.00 10.00 1400.00
11.50 20.00 230.00
25.00 35.00 875.00
45.00 2.00 90.00
390.00 2.00 780.00
3.1.1.- RECUR

DOC BASE
MESES
TIPO N"

OCTUBRE O/C 399


OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 399
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
OCTUBRE O/C 400
3.1.1.- RECURSOS UTLIZADOS (COSTO DIRECTO Y COSTO INDIRECTO)

DESCRIPCION UND.

MAMANI CHURA GIULANA TESSY


ARCHIVADOR CHICO DE PALANCA LOMO ANCHO GRIS - ARTESCO UND.
ARCHIVADOR GRANDE DE PALANCA LOMO ANCHO GRIS - ARTESCO UND.
BANDEJA DE METAL DE DOCUMENTOS DE OFICINA (2CUERPOS) - ARTESTO UND.
BORRADOR DE DIBUJO BLANCO - F. CASTELL UND.
CINTA DE EMBALAJE GRANDE TRANSPARENTE - OVE UND.
CINTA SCOOH INCLUYE DISPENSADOR - OVE UND.
CLIPS MEDIANO - ARTESCO CAJA
CORRECTOR - LIQUID PAPER UND.
CUADERNO CHICO CUADRICULADO ANILLADO DE 100 HOJAS - ATLAS UND.
CUADERNO DE OBRA 100 FOLIOS AUTOCALCABLE - NACIONAL UND.
CUADERNO GRANDE CUADRICULADO ANILLADO DE 200 HOJAS - NACIONAL UND.
UNION UNIVERSAL DE 1/2'' P/ AGUA PVC - EPS UND.
UNION UNIVERSAL DE 1/2'' P/ AGUA PVC - EPS UND.
ESCALIMETRO - MAPEEL UND.
FASTENER X 100 UND - ARTESCO UND.
FILE A-4 X 25 UND - GRAFI UND.
GRAPAS - ARTESCO CAJA
LAPICERO TINTA LIQUIDA (AZUL ROJO Y NEGRO) - PILOT CAJA
LAPICEROS TINTA SECA (AZUL ROJO Y NEGRO) - PILOT CAJA
LAPIZ PORTAMINAS ROTRING 0.5 MM UND.
LIBRETAS TOPOGRAFICAS - NACIONAL UND.
MOTA PARA PIZARRA - ARTESCO UND.
PAPEL BOND A-1 ATLAS ROLLO
PAPEL BOND A-3 ATLAS MILLAR
PAPEL BOND A-4 DE 75 GRS - XEROX MILLAR
PAPEL BOND A-4 DE 75 GRS COLOR CELESTE MILLAR
PAPEL BOND A-4 DE 75 GRS COLOR VERDE MILLAR
PAPEL BOND A-4 DE 75 GRS COLOR ROJO, CELESTE, VERDE PLIEGO
PERFORADOR GRANDE - F. CASTELL UND.
PIZARRA ACRILICA 1.20 X 2.40 MTRS UND.
PLUMONES ACRILICOS (AZUL, NEGRO, ROJO) - F.CASTELL UND.
POSIT - LOVE UND.
REGLA GRANDE DE 30 CM METALICA - LOVE UND.
RESALTADOR COLOR VERDE Y AMARILLO - F. CASTELL CAJA
SACAGRAPAS - ARTESCO UND.
TABLEROS DE PLASTICO CON SUJETADOR - ARTESCO UND.
TIJERA GRANDE - F. CASTELL UND.
VINIFAN GRANDE TRANSPARENTE TIPO OFICIO - ARTESCO UND.
SELLOS POR FIRMA AUTOMATICO - TRODAT UND.
TAMPON COLOR NEGRO MODELO CIRCULAR UND.
CONO DVD - PRINCO CIENTO
LAPICEROS TINTA INDELEBLE - F. CASTELL UND.
CARTUCHO THONER IMPRESORA LASER 78 A -HP UND.
BIDON DE AGUA MINERAL 20 LTS - SAN LUIS UND.
O DIRECTO Y COSTO INDIRECTO)

COSTO
BRUTO P.U. CANT PARCIAL
TOTAL

3,353.75
5.50 5.00 27.50
6.00 5.00 30.00
39.00 1.00 39.00
1.00 6.00 6.00
6.00 4.00 24.00
12.00 2.00 24.00
3.00 4.00 12.00
6.00 6.00 36.00
2.00 5.00 10.00
73.00 3.00 219.00
18.00 5.00 90.00
14.00 3.00 42.00
35.00 1.00 35.00
10.00 1.00 10.00
6.00 2.00 12.00
7.00 4.00 28.00
3.50 0.50 1.75
42.00 2.00 84.00
24.00 2.00 48.00
12.00 5.00 60.00
10.00 2.00 20.00
3.50 1.00 3.50
40.00 2.00 80.00
50.00 1.00 50.00
25.00 10.00 250.00
40.00 2.00 80.00
40.00 2.00 80.00
0.50 20.00 10.00
25.00 1.00 25.00
200.00 1.00 200.00
42.00 2.00 84.00
12.00 5.00 60.00
8.00 2.00 16.00
30.00 1.00 30.00
3.00 2.00 6.00
11.00 4.00 44.00
10.00 2.00 20.00
10.00 5.00 50.00
30.00 2.00 60.00
25.00 1.00 25.00
75.00 1.00 75.00
3.50 2.00 7.00
250.00 4.00 1000.00
24.00 10.00 240.00
3.1.1.- RECURSOS UTILIZADOS (COSTO DIRECTO Y COSTO INDIRECT
DOC BASE
MESES DESCRIPCION
TIPO N"

OCTUBRE O/C 400 CERRATO MAMANI JENNY ISIDORA


OCTUBRE O/C 400 BALDE DE PLASTICO DE 5 GLN - USADOS
OCTUBRE O/C 400 BOMBA (SURTIDOR DE COMBUSTIBLE DE METAL) - TRUPER
OCTUBRE O/C 400 BROCHAS DE 3"-TORO
OCTUBRE O/C 400 SOGA DE NYLON 3/4" - IMPORTADA
OCTUBRE O/C 400 CILINDRO DE 55 GLN DE PLASTICO ABIERTO CON TAPA- NACIONAL
OCTUBRE O/C 400 CILINDRO DE 55 GLN DE METAL - NACIONAL
OCTUBRE O/C 400 CIZALLA MANUAL DE 18" - TRUPER
OCTUBRE O/C 400 CORDEL DE NYLON N 80 X 100 MT.
OCTUBRE O/C 400 EXTENCION'DE 50 MTS CABLE N 12 - INDECO
OCTUBRE O/C 400 HOJAS DE SIERRA N3 18 - SANFLEX
OCTUBRE O/C 400 HOJAS DE SIERRA Na 24 - SANFLEX
OCTUBRE O/C 400 LAMPA CON PUNTA REDONDA - TRAMONTINA
OCTUBRE O/C 400 LIJA N2 60 - HEBRALIC
OCTUBRE O/C 400 LIJA N2 80 - HEBRALIC
OCTUBRE O/C 400 MANGERA DE NIVEL 1/2 TRANSPARENTE DE BUENA CALIDAD - NACIONAL
OCTUBRE O/C 400 MANGERA DE 3/4" REFORZADO
OCTUBRE O/C 400 PISTOLA DE CALAFATEO PARA APLICAR ADITIVO - SIKA
OCTUBRE O/C 400 PLASTICO DOBLE ANCHO DE 2.00 MTS.
OCTUBRE O/C 400 ROMANA DE 12 KG - VIKINGO
OCTUBRE O/C 400 ROMANA DE 25 KG - VIKINGO
OCTUBRE O/C 400 GALONES DE PLASTICO X 10 GLN
OCTUBRE O/C 400 EMBUDO DE METAL GRANDE PICO DE LORO - NACIONAL
OCTUBRE O/C 400 MOLDES BRIQUETERAS - NACIONAL
OCTUBRE O/C 400 CONO DE ABRAMS INCLUYE BASTIDOR - NACIONAL
OCTUBRE O/C 400 INDUSTRIA COMERCIAL DEL SUR UNIDOS SOCIEDAD ANONIMA CERRADA - INCOSUR
OCTUBRE O/C 400 ALICATE DE MANO - IMPORTADO
OCTUBRE O/C 400 ARCOS DE SIERRA - IMPORTADO
OCTUBRE O/C 402 BARRETA EXAGON^L DE 1" )fT.5 MTS ,
OCTUBRE O/C 402 BUGU1 C/COJINETE PARA TRABAJO PESADO - TRUPPER
OCTUBRE O/C 402 ARNES DE SEGURIDAD C/DOBLE LINEA DE VIDA - FERRO AMERICANO
OCTUBRE O/C 402 CINCEL DE PUNTA 5/8" X 30 CM - ACEROS
OCTUBRE O/C 402 CINCEL PUNTA PLANA DE 5/8" X 30 CM - ACEROS
OCTUBRE O/C 402 COMBO DE 10 LIBRAS - SHUBERTH
OCTUBRE O/C 402 COMBO DE 4 LIBRAS - UYUSTOOLL
OCTUBRE O/C 402 MACHETE TIPO SABLE - IMPORTADO
OCTUBRE O/C 402 MARTILLO GRANDE - STANLEY
OCTUBRE O/C 402 PICOS-SHUBERTH
OCTUBRE O/C 402 PLOMADA GRANDE - NACIONAL
OCTUBRE O/C 402 RASTRILLO C/MANGO DE MADERA - TRUPPER
OCTUBRE O/C 402 WINCHA METRICA DE 5 MTS - UYUSTOOLL
OCTUBRE O/C 402 WINCHA METRICA DE 50 MTS - STANLEY
OCTUBRE O/C 402 WINCHA METRICA DE 8 MTS - STANLEY
ADOS (COSTO DIRECTO Y COSTO INDIRECTO)
COSTO
UND. BRUTO P.U. CANT PARCIAL
TOTAL

5,502.00
UND. 10.00 15.00 150.00 '
UND. 120.00 1.00 120.00
UND. 8.00 8.00 64.00
METRO 4.80 40.00 192.00
UND. 130.00 10.00 1,300.00
UND. 80.00 5.00 400.00
UND. 75.00 1.00 75.00
UND. 15.00 2.00 30.00
UND. 82.00 5.00 410.00
UND. 6.20 10.00 62.00
UND. 6.20 10.00 62.00
UND. 27.00 15.00 405.00
UND. 1.50 30.00 45.00
UND. 1.50 30.00 45.00
METRO 1.60 20.00 32.00
METRO 3.50 200.00 _ 700.00
UND. 200.00 2.00 400.00
METRO 1.50 200.00 300.00
UND. 19.00 1.00 19.00
UND. 28.00 1.00 28.00
UND. 28.00 5.00 140.00
UND. 38.00 1.00 38.00
UND. 120.00 3.00 360.00
UND. 125.00 1.00 125.00
5,466.00
UND. 11.00 3.00 33.00
UND. 15.00 5.00 75.00
UND. 55.00 10.00 550.00
UNO. 155.00 15.00 2,325.00
UND. 220.00 3.00 660,00
UND. 14.00 5.00 70.00
UND. 14.00 5.00 70.00
UND. 45.00 5.00 225.00
UND. 23.00 16.00 368.00
UND. 21.00 2.00 42.00
UND. 25.00 4.00 100.00
UND. 27.00 15.00 405.00
UND. 15.00 3.00 45.00
UND. 23.00 10.00 230.00
UND. 10.00 5.00 50.00
UND. 58.00 1.00 58.00
UND. 32.00 5.00 160.00
3.1.1.- RECURSOS UTILIZADOS (COSTO DIRECTO Y COSTO INDIRE
DOC BASE
MESES DESCRIPCION
TIPO N"

OCTUBRE O/C 402 SERVICENTRO EL GALLITO S.C.R.LTDA.


OCTUBRE O/C 402 PETROLEO DIESEL B5
OCTUBRE O/C 402 GASOLINA DE 90 OCTANOS
OCTUBRE O/C 402 GASOLINA DE 84 OCTANOS
OCTUBRE O/C 402 SERVICIOS Y COMERCIALIZADO RA BORDA E.l.R.L.
OCTUBRE O/C 402 GIGANTOGRAFIA DE 2.40 X 3.60 MTS PARA CARTEL DE OBRA SEGUN MODELO (A TODO COLOf
OCTUBRE O/C 402 INVERSIONES BRAM1L"E.1.R.L.
OCTUBRE O/C 402 BOTIQUIN (INCLUYE MEDICAMENTOS^?. PAQUETES DE GUANTES QUIRURGICOSOl FRASCO DE
OCTUBRE O/C 402 CAMILLA RIGIDA PARA,.,HERIDOS
OCTUBRE O/C 402 HUACAN QUISPE RAMON ROBERTO
OCTUBRE O/C 406 ACEITE GRADO 40 PARA MEZCLADORA X 1/4 GLN.
OCTUBRE O/C 406 GRASA EP-2 MULTI PROPOSITOS X 450 GR - BISTONYK
OCTUBRE O/C 406 SALTA NEGOCIOS Y REPRESENTACIONES E.l.R.L.
OCTUBRE O/C 406 ZAPATOS DE SEGURIDAD PARA PERSONAL OBRERO (SEGUN NORMA VIGENTE) - MINER
OCTUBRE O/C 406 INDUSTRIAL MADERERA Y FERRETERIA MAVILA EMPRESA INDIVIDUAL DE RESPONSA
OCTUBRE O/C 406 TRIPLA Y LUPUNA 2.4X1.2X6MM
OCTUBRE O/C 406 TRIPLAY LUPUNA 2.4X1.2X19MM
OCTUBRE O/C 406 LISTONES DE 2"X 3" X 12'- TORNILLO
OCTUBRE O/C 406 LISTONES DE 2" X 4" X 12'- TORNILLO
OCTUBRE O/C 406 MADERA DE (1.5"X8"X10') - TORNILLO
OCTUBRE O/C 406 MADERA DE (2"X12"X10') - TORNILLO
OCTUBRE O/C 406 LISTONES DE 2" X 2" X 10 - TORNILLO
OCTUBRE O/C 406 PALOS DE EUCALIPTO D=3 X 3.00 MTS
OCTUBRE O/C 406 PALOS DE EUCALIPTO D=4X6.00 MTS
OCTUBRE O/C 406
OCTUBRE O/C 406 PLANILLA DE COSTO INDIRECTO DIRECCION TECNICA
OCTUBRE O/C 406 COORDINDOR DE OBRA
OCTUBRE O/C 406 PLANILLA DE CONTRATADOS
OCTUBRE O/C 411 PLANILLA DE ADMINISTRACION
OCTUBRE O/C 411 RESIDENTE DE OBRA
OCTUBRE O/C 411 ASISTENTE TECNICO
OCTUBRE O/C 411 ASISTENTE ADMINISTRATIVO
OCTUBRE O/C 413 CHOFER
OCTUBRE O/C 413 PLANILLA DE COI^O DIRECTO
OCTUBRE O/C 424 PEON
OCTUBRE O/C 424 PEON
OCTUBRE O/C 424 PEON
OCTUBRE O/C 427 PEON
OCTUBRE O/C 427 PEON
OCTUBRE O/C 427 PEON
DOS (COSTO DIRECTO Y COSTO INDIRECTO)
COSTO
UND. BRUTO P.U. CANT PARCIAL
TOTAL

9180.00
GALONES 10.80 850.00 9180.00
GALONES 13.60 0.00 0.00
GALONES 12.00 0.00 0.00
250.00
UND. 250.00 1.00 250.00
750.00
UND. 250.00 2.00 500.00
UND. 250.00 1.00 250.00
282.00
UND. 32.00 6.00 192.00
UND. 15.00 6.00 90.00
3250.00
UND. 65.00 50.00 3250.00
8415.00
PLANC 43.00 20.00 860.00
PLANC 108.00 5.00 540.00
UND. 33.00 20.00 660.00
UND. 44.00 20.00 880.00
UND;. 55.00 30.00 1650.00
UND. 100.00 30.00 3000.00
UND. 16.60 20.00 332.00
UND. 8.50 50.00 425.00
UND. 34.00 2.00 68.00

5,232.00 5,232.00
DA 432.00 4800.00 30.00 5232.00
PLLA 5,014.00 5,014.00
11,202.17 11,202.17
DIA 382.85 4253.89 30.00 4636.74
DIA 214.50 2386.33 30.00 2597.83
DIA 152.10 1690.00 26.00 1842.10
DIA 175.50 1950.00 30.00 2125.50
7,306.44 7,306.44
DIA 125.00 1347.23 23.00 1472.23
DIA 103.27 1112.94 19.00 1216.21
DIA 86.14 878.64 15.00 964.78
DIA 86.14 878.64 15.00 964.78
DIA 103.27 1112.94 19.00 1216.21
DIA 125.00 1347.23 23.00 1472.23
3.1.1.- RECURSOS UTILIZADOS (COSTO DIRECTO Y COSTO INDIRECT

DOC BASE
MESES DESCRIPCION
TIPO N"

OCTUBRE O/C 429 PLANILLA DE COSTO DIRECTO


OCTUBRE O/C 429 PEON
OCTUBRE O/C 430 PEON
OCTUBRE O/C 430 PEON
OCTUBRE O/C 430 PEON
OCTUBRE O/C 430 PEON
OCTUBRE O/C 430 PEON
OCTUBRE O/C 430 PEON
OCTUBRE O/C 430 OFICIAL
OCTUBRE O/C 430 PEON
OCTUBRE O/C 430 PEON
OCTUBRE O/C 430 OFICIAL
OCTUBRE O/C 430 PEON
OCTUBRE PLLA 320 PEON
OCTUBRE PLLA 320 PEON
NOVIEMBRE PLLA 285 PEON
OCTUBRE PLLA 309 PEON
OCTUBRE PLLA 309 PEON
OCTUBRE PLLA 309 PEON
OCTUBRE PLLA 309 PEON
OCTUBRE PLLA 309 PEON
OCTUBRE PLLA M67 PEON ; /
OCTUBRE PLLA M67 PEON - '>
OCTUBRE PLLA M67 PEON
OCTUBRE PLLA M67 PEON ~ ' ::
OCTUBRE PLLA M67 OPERARIO
OCTUBRE PLLA M67 OPERARIO
OCTUBRE PLLA M67 OFICIAL
OCTUBRE PLLA PEON
OCTUBRE PLLA PEON
OCTUBRE PLLA PEON
OCTUBRE PLLA PEON
OCTUBRE PLLA PEON
OCTUBRE PLLA PLANILLA DE COSTO INDIRECTO SUPERVISION
OCTUBRE PLLA JEFE DE SUPERVISION
OCTUBRE PLLA INSPECTOR DE OBRA
OCTUBRE PLLA ASISTENTE TECNICO
OCTUBRE PLLA TECNICO DE SEGURIDAD
OCTUBRE PLLA GIZA NINA ALEYDA JUANA
OCTUBRE PLLA ADQUISICION DE MATERIALES DE SEGURIDAD SUPERVISION
OCTUBRE PLLA LA GOMITA E.I.R.L.
OCTUBRE PLLA
OCTUBRE PLLA
OCTUBRE PLLA
ADOS (COSTO DIRECTO Y COSTO INDIRECTO)

COSTO
UND. BRUTO P.U. CANT PARCIAL
TOTAL

50,068,56 50,068.56
DIA 125.00 1,347.23 23.00 1,472.23
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 137.21 1,463.87 24.00 1,601.08
DIA 125.00 1,347.23 23.00 1,472.23
DIA 119.57 1,288.66 23.00 1,408.23
DIA 145.59 1,569.28 24.00 1,714.87
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 121 ..33 1,307.73 22.00 1,429.06
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 137.21 1,463.87 24.00 1,601.08
DIA 130.44 1,405.81 24.00 1,536.25
DIA 137.21 1,463.87 24.00 "1601.08
DIA 130.44 1,405.81 24.00 1,536.25
DIA 125.00 1,347.23 23.00 1,472.23
DIA 130.44 1,405.81 24.00 1,536.25
DIA . 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 163.80 1,765.44 24.00 1,929.24
DIA 163.80 1,765.44 24.00 1,929.24
DIA 145.59 1,569.28 24.00 1,714.87
DIA 131.49 1,402.88 23.00 1,534.37
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
DIA 130.44 1,405.81 24.00 1,536.25
14,760.41 14,760,41
DIA 448.50 4,983.33 31.00 5,431.83
DIA 380.25 4,225.00 31.00 4,605.25
DIA 273.00 3,033.33 31.00 3,306.33
DIA 117.00 1,300.00 31.00 1,417.00
990.00 990.00
COMP 0.00 990.00 31.00 990.00
1,104.30 1,104.30

180,864.63
3.1.2.- RECURSOS HUMANOS
1.00 COSTO DIRECTO
Oct-15
3.0.- G.G. Supervision
1 INSPECTOR DE OBRA MES 1.00 100.00% 7.00 4,300.00 30,100.00
2 PERSONAL DE SEGURIDAD MES 1.00 100.00% 6.00 2,800.00 16,800.00
3 ASISTENTE TECNICO MES 1.00 100.00% 4.00 3,000.00 12,000.00
4 ASISTENTE ADMINISTRATIVO MES 1.00 100.00% 4.00 2,500.00 10,000.00
SUB TOTAL 68,900.00
4.0.- G.G. liquidacion
1 LIQUIDADOR TCNICO MES 1.00 100.00% 2.00 4,300.00 8,600.00
2 LIQUIDADOR FINANCIERO MES 1.00 100.00% 2.00 4,000.00 8,000.00
3 ASISTENTE CONTABLE MES 1.00 100.00% 2.00 2,900.00 5,800.00
4 ASISTENTE TCNICO MES 1.00 100.00% 2.00 2,900.00 5,800.00
SUB TOTAL 28,200.00
5.0.- G.G. administracion
1 ADMINISTRADOR MES 1.00 100.00% 6.00 3,200.00 19,200.00
2 TESORERO MES 1.00 100.00% 6.00 2,500.00 15,000.00
3 COTIZADOR MES 1.00 100.00% 6.00 2,200.00 13,200.00
4 PLANILLERO MES 1.00 100.00% 6.00 2,200.00 13,200.00
5 SECRETARIA MES 1.00 100.00% .6.00 1,900.00 11,400.00
6 CHOFER MES 1.00 100.00% 4.00 2,300.00 9,200.00
SUBTOTAL 81,200.00

SUB TOTAL 695,481.29


NOTA: los valores de recursos humanos estan de acuerdo a las planillas de pago otorgadas por el area del personal.
2.- RECURSOS HUMANOS

1.00 10,037.08 1.00 10,037.08 6.00 20,062.92


1.00 1,417.00 1.00 1,417.00 5.00 15,383.00
1.00 3,306.33 1.00 3,306.33 3.00 8,693,67
1.00 1.00 3.00 10,000,00
0.00 14,760.41 14,760.41 54,139,159.00

2.00 8,600.00
2.00 8,000,00
2.00 5,800.00
2.00 5,800.00
0.00 0.00 0.00 28,200.00

1.00 6.00 19,200.00


1.00 6.00 15,000.00
1.00 6.00 13,200.00
1.00 6.00 13,200.00
1.00 22,325,61 22,325.61 6.00 10,925.61
1.00 6.00 9,200.00
0.00 22,325.51 22,325.61 58,874.39

0.00 115,909.19 115,909.19 579,672.10


3.1.2.- RECURSOS HUMANOS
1.00 COSTO DIRECTO
Oct-15
1.10 mano de obra calificada
PROGRAMADO SEGN EXPEDIENTE TECNICO.
ITEM DESCRIPCIN
: UND CANTIDAD P.U. PARCIAL
1 CAPATAZ. H.H. 1,331.69 17.50 23,304.56
2 OPERARIO. H.H. 3,896.05 15.82 61,635.48
03 OPERRADOR;DE EQUIPO PESADO H.H. 1,795.62 13.75 24,689.84:
4 OPERRADOR DE EQUIPO LIVIAN H.H. 354.72 13.75 4,877.34
5 TOPOGRAFO H.H. 224.58 14.00 3,144.18
6 CONTROLADOR H.H. 734.60 11.66 8,565.40
7 TECNICO LABORATORISTA H.H. 88.00 30.00 2,640.00
8 OFICIAL. H.H. 4,036.87 13.43 54,215.15

sub total 183,071.95


1.20 mano de obra no calificada
PROGRAMADO SEGN EXPEDIENTE TECNICO.
ITEM DESCRIPCIN
: UND CANTIDAD P.U. PARCIAL
1 PEON. H.H. 14,709.54 12.19 179,309.34
sub total 179,309.34

2 g.g. direccion tecnica


PROGRAMADO SEGN EXPEDIENTE TECNICO.
ITEM DESCRIPCIN
: UND CANTIDAD P.U. PARCIAL
1 JEFE DE AREA (INGENIERO) MES 1.00 100.00% 7.00 5,200.00 36,400.00
2 RESIDENTE DE OBRA MES 1.00 100.00% 7.00 4,300.00 30,100.00
3 ASISTENTE TECNICO. MES 1.00 100.00% 7.00 3,000.00 21,000.00
4 ASISTENTE ADMINISTRATIVO MES 1.00 100.00% 7.00 2,500.00 17,500.00
5 CHOFER MES 1.00 100.00% 6.00 2,300.00 13,800.00
6 ALMACENERO MES 1.00 100.00% 6.00 2,200.00 13,200.00
7 GUARDIAN MES 2.00 100.00% 12.00 1,900.00 22,800.00
sub total 154,800.00
cd + dt 517,181.29

15.- recursos utilizados - combustibles y lubricantes


PROGRAMADO SEGN EXPEDIENTE TECNICO.
ITEM DESCRIPCIN
: UND CANTIDAD P.U. PARCIAL
1 GASOLINA DE 90 OCTANOS GLN S/. 50.00 S/. 14.00 S/. 700.00
1 GASOLINA DE 84 OCTANOS GLN S/. 50.00 S/. 14.00 S/. 700.00
2 PETROLEO DIESEL D2 GLN S/. 5,600.00 S/. 13.00 S/. 72,800.00

COSTO TOTAL
.1.2.- RECURSOS HUMANOS

Oct-15

EJECUCIN REAL
SALDO
ANTERIOR ACTUAL ACUMULADO
CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL ; CANTIDAD PARCIAL
- - - 1,331.69 23,304.56
- - 1.00 3,858.48 1.00 3,858.48 3,895.05 57,777.00
- - - - 1,795.62 24,689.84
- - - - 354.72 4,877.34
- - - - 224.58 3,144.18
- - - - 734.60 8,565.40
- - - 88.00 2,640.00
- - 1.00 4,858.80 1.00 4,035.87 49,356.35

0.00 8,717.28 8,717.28 174,354.67

EJECUCIN REAL
SALDO
ANTERIOR ACTUAL ACUMULADO
CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL ; CANTIDAD PARCIAL
1.00 48,657.72 1.00 48,657.72 14,708.54 130,651.62
0.00 48,657.72 48,657.72 130,651.62
I

EJECUCIN REAL
SALDO
ANTERIOR ACTUAL ACUMULADO
CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL ; CANTIDAD PARCIAL
- - 7.00 36,400.00
- - 1.00 10,246.00 1.00 10,246.00 6.00 19,854.00
- - 1.00 4,636.74 1.00 4,636.74 6.00 16,363.26
- - 1.00 2,597.83 1.00 2,597.83 6.00 14,902.17
- - 1.00 1,842.10 1.00 1,842.10 5.00 11,957.90
- - 1.00 2,125.50 1.00 2,125.50 5.00 11,074.50
- - 12.00 22,800.00
0.00 21,448.17 21,448.17 133,351.83
0.00 78,823.17 78,823.17 438,358.12

EJECUCIN REAL
SALDO
ANTERIOR ACTUAL ACUMULADO
CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL ; CANTIDAD PARCIAL
S/. 0.00 S/. 13.60 S/. 0.00 S/. 50.00 S/. 700.00
S/. 0.00 S/. 50.00 S/. 700.00
S/. 0.00 S/. 0.00 S/. 0.00 S/. 50.00 S/. 10.80 S/. 540.00 S/. 5,550.00 S/. 72,260.00

S/. 73,660.00
ERVACIONES:

nte Resolucin de Alcalda N 241-2015-A/MDSC-C, de fecha 01/09/2015 y memorndum N 057-2015-SGlDU/MDSC- C, de la sub


urbano, para la obra "MEJORAMIENTO DEL SERVICIO DE LA INFRAESTRUCTURA DE CALLES, DE LA LOCALIDAD DE C
DE SAN CRISTOBAL - PROVINCIA MARISCAL NIETO - REGION MOQUEGUA"

esente obra se ejecutara con la Finalidad de ampliar el rea de pavimentacin, atender las necesidades de la poblacin y mejorar el or
considerando que las calles Lima, Calacoa, Ancahs y Arequipa I son vas perimetrales a la plaza principal y que las calles Jo
, Moquegua , lea y Arequipa II son vas secundarias; las mencionadas arterias son de transito liviano de mediana intensidad qUe p
stionamiento vial de ese sector de la localidad

o inicio a los trabajos reprgramados con fecha 06 de octubre del 2015.


o entrega de los EPP a todo el personal de obra.
sarrollaron actividades provisionales.
izaron trabajos de limpieza y a condicionalmente de zona de trabajo.
te el presente mes la obra est en Ejecucin por lo que tiene avance fsico, tambin se tuvo avance financiero el cual est debidament
en el presente informe del mes.

erificado en obra con la inspeccin la presencia de partidas nuevas por ejecutar como: extraccin de piedra en cantera. Y! acopio
da en la cantera

ta ejecutando los trabajos realizados en la cantera, esto se detala en el presente informe


CLUSIONES
nce fsico de la Obra Exp. 01 acumulado de la primera semana de trabajo es de 0.42 %, S/. 8,876.46
nce fsico adicional N 01 acumulado hasta el 31 de diciembre del 2015 es de 7.73 %, si. 75,388.92
neraron puestos de trabajo con personal de ambos sexos de la localidad de Caacoa.
EXPEDIENTE INICIAL
OMEN DACIONES

omienda al rea de abastecimientos el uso de los trminos de referencia que el Ing. Residente presenta junto con los requerimientos p
lemas con la calidad de los materiales que se adquieren y asi como tambin la calidad de los! servicios a ejecutar y no perjudicar el ava
bra. |

dad en la entrega de materiales segn Ordenes de Compra y Ordenes de Servicio