Académique Documents
Professionnel Documents
Culture Documents
1. SCOPE...........................................................................................................................
2. REFERENCE ..................................................................................................................
3. DEFINITION .................................................................................................................
4. RESPONSIBLITIES ........................................................................................................
5. EXECUTION ORGANIZATION ........................................................................................
6. WORK PROCEDURE.....................................................................................................
7. QUALITY REQUIREMENT ...........................................................................................
8. SUBMITTALS..............................................................................................................
9. APPENDIX..................................................................................................................
WORK METHOD STATEMENT
1. SCOPE
2. REFERENCE
referenced and comply with the latest edition of the codes and
standards listed below,
(d) ASTM D1556 Standard Test Method for Density and Unit Weight
of Soil in Place by
Table
Relative Density
(i) ASTM D4318 Liquid Limit, Plastic Limit and Plasticity Index of
Soils
(SITE PREPARATION-WGP)
Page 4 of 16
clay:
Sieve Size
Percent Passing
in (6.25mm)
100
project.
3.4. Contract or Contract Documents
Any and all documents, including design drawings, which Saudi Aramco
has transmitted or
3.5. Contractor
passing the No. 16 sieve (1.18 mm) and usually containing less
than 10% soil particles
(SITE PREPARATION-WGP)
Page 5 of 16
3.9. Marl
from clay to gravel sizes and often include cobble and boulder sized
pieces.
3.10. Rocks
3.11. SABKHA
4. RESPONSIBLITIES
4.1. Construction Manager [CM]
execute and supervise each and every work. The basic functions
of the Construction
- Construction Management
Implement the Project Quality Plan to the project and Direct responsible
in quality and
establish the ITP, manage the inspection of the work and review the activity of
the Quality
every stage of the activities as to the codes and standards and procedures and
deliver the
technical advice to the construction team to keeping the quality
requirement. All the
inspection activity shall record as per the designated checklist submit to QCS
and raise the
Ensure all work permits are available prior to commencement of any work as
per
areas for any unsafe conditions. Liaise with Field Supervisors and
Foremen that
5. EXECUTION ORGANIZATION
principal.
Description Qty
Responsible
Construction Manager 1
Preparation Work
HSE Supervisor 2
Preparation Work
Direct responsible in Safety for the
Site
HSE Officer 4
Preparation Work
(SITE PREPARATION-WGP)
Page 8 of 16
DEVELOPMENT
-TBM Installation
-Setting Out
-Extraction & Stockpiling
-Remove Trees
EXCAVATION
EMBANKMENT
-Cuttings
-Foundation Treatment
-Subgrade Preparation
-Placement & Compaction
-Replacement[If required]
-Final Grading
COMPLETION
-Final Inspection
of
FILL/SUBGRADE
----------------------- Page 13-----------------------
6. WORK PROCEDURE
away along with SAR line CTW 110 under construction as shown in
Appendix 10.1.
6.1.1. Development of Borrow-pit
6.1.2. Stockpiling
- Cohesiveness Soil : 1V : 2H
- Cohesive-less Soil : 1V : 3H
ASTM D4318
4253/4254
The Survey Control Point endorsed by the Company shall be the Temporary
Bench Mark
(TBM) which will be confirmed by Third Party Survey Service Provider and
confirmation
report submit to the Company for approval in prior to all Setting out of the Site
Preparation
- Location of Embankment:
- Elevation in Grade:
6.2.2. Demolition
other similar structure that will obstruct the development works of the
project must be
asphalt pavement up to the base coarse level. The unsuitable material should
be disposed
at designated area(Please see section 9.1 Borrow pit and Disposal area)
6.2.3. Cleaning & Grubbing
Clearing and grubbing shall consist of the removal and disposal of all trees,
stumps, roots,
logs, shrubs, grass, weeds, fallen timber and other surface litter,
wherever they occur
within the right-of-way and within such other areas as directed and staked out
by the PMT.
of stumps
(b) Excavation shall be made to the lines, grades and cross sections as to
the IFC drawing.
(c) Side slope of excavation shall be cut true and straight and shall be
graded to the cross
at least 1 roller width beyond the design edge of the slope and then
trimming back to
(e) The surface of existing ground after excavated and stripped shall be
the Subgrade
6.3. Embankment
The embankment usually refers to an earthen structure that is used to raise up
above the
Structure Foundation.
30(thirty)cm.
(b) Fill material shall be placed in lifts not exceeding 200 mm (8 in) in loose
depth. Fill
compaction equipment.
(c) For foundation for asphalt and concrete pavement subgrades, fill shall
be compacted
(e) If clean sand or dune sand is used for fill, surface protection will be
required. A cap
the No. 200 sieve. The capping material shall have a maximum liquid
limit of 35 and a
(SITE PREPARATION-WGP)
Page 12 of 16
7. QUALITY REQUIREMENT
8. SUBMITTALS
Representative
8.1. Reports including all laboratory and field test logs and comments,
Field
test reports shall include density and moisture content test logs
indicating
following:
8.1.1. Bi-weekly.
8.2. Borrow (Fill) Materials and Water Sources and test results of all
borrow
according to SAES-A-114.
(b) Indicate whether or not any components will remain after filling or
backfilling.
(c) Provide plans, sketches and/or detail along with calculations.
removal.
(SITE PREPARATION-WGP)
Page 13 of 16
9. APPENDIX
(SITE PREPARATION-WGP)
Page 14 of 16
Disposal Area
(SITE PREPARATION-WGP)
Page 15 of 16
9.2.1 SATIP-A-114-01
Construction.
PROJECT TITLE:
WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR
INSPECTION RESPONSIBILITY
TASK / ACTIVITY
REMARKS
CNTRCTR
ARAMCO
2.1 SAIC-A-1002
W S cap materials for the first 2 delivery days, and once
3.0 INSTALLATION
3.1 SAIC-A-1003
W S
Inspection 1004
5 occurrences thereafter.
SAIC-A-
1005
SAIC-A-
1006
4.0 PRE-COMMISSIONING
GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require
100 % participation by Saudi Aramco Site Inspection Personnel. After this period,
Saudi Aramco Inspection may adjust
attendance.
LEGEND
W Witness Inspection/Test RH
Review and Approval of Documents
S Surveillance I 100%
Contractor Inspection