Académique Documents
Professionnel Documents
Culture Documents
Based on AXELOS PRINCE2 material. Reproduced under licence from AXELOS Limited. All rights reserved.
Based on AXELOS PRINCE2 material. Material is reproduced under licence from AXELOS Limited. All rights reserved.
PRINCE2 is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.
AXELOS is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.
Copyright 2014, Simplilearn, All rights reserved.
1 The Swirl logo is a trade mark of AXELOS Limited, used under the permission of AXELOS Limited. All rights reserved. Copyright 2014, Simplilearn, All rights reserved.
Objectives
After completing Explain the challenges faced by an organisation during project management
this lesson, you will
be able to: Define a project
A project is a temporary organization that is created for the purpose of delivering one or more
business products according to an agreed Business Case.[1]
Characteristics of project are as follows:
Each project has definite start date and an intended end date which makes all projects temporary in
Temporary
nature.
The resources from various units with multiple skillsets are involved in the project. This makes all the
Cross-functional
projects cross-functional.
Uncertainty Each project has its own share of risks. Hence, there is an uncertainty in each project.
Project management is the planning, delegating, monitoring and control of all aspects of the project,
and the motivation of those involved, to achieve the project objectives within the expected
performance targets for time, cost, quality, scope, benefits and risks.[2]
It is a generic methodology that can be applied to any project in any industry or domain.
Any product specific development methodology can be integrated with management aspect of
PRINCE2.
As per PRINCE2, the Project Managers need to control the following six aspects or variables of a
project:
The project has to be affordable and, though initially there may be a particular budget, there will be
Cost
many factors which can lead to overspending and, perhaps, some opportunities to cut costs.
Timescales The next most-frequent question asked of a Project Manager, is the timescale of a project.
Finishing on time and within budget is not enough if the result of the project is not functional. In
Quality
PRINCE2 terms, the projects products must be fit for purpose.
If the scope is not known, then the various parties involved in a project may end up talking at cross-
Scope
purposes.
Risks All projects entail risks, however the amount of acceptable risk should be predefined.
The Project Manager has to have a clear understanding of the purpose of the project as an investment
Benefits
and make sure that what the project delivers is consistent with achieving the desired return.
The PRINCE2 is a project management methodology that includes four integrated elements of
principles, themes, processes and the project environment.
PROJECT ENVIRONMENT
PRINCE2 THEMES
PRINCE2 PRINCIPLES
Figure 1.2 PRINCE2 Manual. The structure of PRINCE2. Copyright AXELOS Limited 2013. Material is reproduced under
licence from AXELOS. All rights reserved.
a. Performance
b. Reliability
c. Scope
d. Ease of use
a. Performance
b. Reliability
c. Scope
d. Ease of use
Answer: c.
Explanation: Scope is an aspect of project performance that needs to be managed.
a. Quality
b. Role descriptions
c. Processes
d. Product descriptions
a. Quality
b. Role descriptions
c. Processes
d. Product descriptions
Answer: c.
Explanation: Processes is one of the four integrated elements within PRINCE2. The other
elements are themes, principles and the project environment.
Answer: b.
Explanation: All the benefits are not realised during project life cycle, they may also be
realised after the project is over. For example, a product marketing campaign project may
result into increased sales of the product even after the campaign is over.
Answer: d.
Explanation: PRINCE2 does not provide: specialist aspects such as industry specific
activities, detailed techniques such as earned value analysis and leadership and
motivational skills.
a. Temporary
b. Cross-functional
c. Continuous production
d. Uncertainty
a. Temporary
b. Cross-functional
c. Continuous production
d. Uncertainty
Answer: c.
Explanation: Continuous production is not a feature that distinguishes a project from
business as usual. The five characteristics of a project that distinguishes itself from business
as usual are: change, temporary, cross-functional, unique and uncertainty.
Here is a quick Project is defined as a temporary organisation that is created for the
recap of what we
purpose of delivering one or more business products according to an agreed
have learnt in this
lesson: Business Case
As per PRINCE2, Cost, Timescales, Quality, Scope, Risks and Benefits are
the six aspects of any project that need to be controlled
Based on AXELOS PRINCE2 material. Material is reproduced under licence from AXELOS Limited. All rights reserved.
PRINCE2 is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.
AXELOS is a [registered] trade mark of AXELOS Limited, used under permission of AXELOS Limited. All rights reserved.
The Swirl logo is a trade mark of AXELOS Limited, used under the permission of AXELOS Limited. All rights reserved.
22 Copyright2014,
Copyright 2014, Simplilearn,
Simplilearn, All rights
All rights reserved.
reserved.
References
[1] Based on Managing Successful Projects with PRINCE2, by AXELOS. Introduction, What makes projects
different?
[2] Based on Managing Successful Projects with PRINCE2, by AXELOS. Introduction, Why have a project
management method?