Schedule of Rates - 2008

Item Item Description Unit Rate(Rs.)


Code
Zone - Tripura
Chapter Name - Civil
Category - Earthwork, Erosion Control and
3.1 Excavation in soil by manual means - -- --
3.1.1 Excavation in Roadway cutting in soil by using manual means including loading in truck and cum 79.60
carrying of cut earth to embankment site with all lifts and lead upto 1000 m as per MoRT&H
Technical Specification clauses of section 300.
3.1.2 Excavation in Roadway cutting in soil by using manual means and carrying of cut earth to cum 45.30
embankment site with all lifts and lead upto 20 m as per MoR&TH Technical Specification
clauses of section 300.
3.2 Excavation in ordinary rock by manual means -- --
3.2.1 Excavation in Roadway cutting in ordinary rock by using manual means including loading in cum 104.80
truck and carrying of cut earth to embankment site with all lifts and lead upto 1000 m as per
MoRT&H Technical Specification clauses of section 300.
3.2.2 Excavation in Roadway cutting in ordinary rock by using manual means and carrying of cut cum 70.40
earth to embankment site with all lifts and lead upto 50 m as per MoRT&H Technical
Specification clauses of section 300.
3.3 Excavation in Soil with Dozer with lead upto 100 m. - Excavation for roadway in soil by cum 64.60
mechanical means with Dozer including cutting and pushing the earth to site of embankment
upto a distance of 100 m ( average lead of 50 metres ), including trimming bo
3.4 Excavation in ordinary rock with Dozer with lead upto 100 m. - Excavation for roadway in cum 108.80
ordinary rock by mechanical means with Dozer including cutting and pushing the earth to site
of embankment upto a distance of 100 m ( average lead of 50 metres ), inc
3.5 Excavation in hard rock ( requiring blasting ) with disposal upto 1000 m.- Excavation for cum -674.10
roadway in hard rock ( requiring blasting ) by drilling, blasting and breaking, trimming bottom
and side slopes in accordance with requirements of lines, grades and

Designed By e-Governance Solutions Group,C-DAC Page:1


Schedule of Rates - 2008

3.6 Excavation in Soil using Hydraulic Excavator CK 90 and Tippers with disposal upto 1000 m - cum 31.20
Excavation for roadwork in soil with hydraulic excavator of 0.9 cum bucket capacity including
cutting and loading in tippers, trimming bottom and side slopes in acc
3.7 Excavation in ordinary rock using Hydraulic Excavator CK 90 and Tippers with disposal upto cum 41.30
1000 m - Excavation for roadwork in ordinary rock with hydraulic excavator of 0.9 cum bucket
capacity including cutting and loading in tippers, trimming bottom and
3.8 Excavation in hard rock ( blasting prohibited ) using Hydraulic Excavator CK 90 and Tippers -- --
with disposal upto 1000 m- Excavation for roadwork in hard rock ( blasting prohibited ) with
hydraulic excavator of 0.9 cum bucket capacity including cutting and l
3.8.1 By Mechanical Means cum -574.70
3.8.2 By Manual Means cum -434.10
3.9 Excavation in hard rock ( controlled blasting ) with disposal upto 1000 m.- Excavation for cum -547.40
roadway in hard rock with controlled blasting by drilling, blasting and breaking, trimming
bottom and side slopes in accordance with requirements of lines, grades a
3.10 Excavation in Marshy Soil- Excavation for roadway in marshy soil with hydraulic excavator 0.9 cum 37.70
cum bucket capacity including cutting and loading in tippers and disposal with all lifts and lead
upto 1000 m trimming of bottom and side slopes in accordance wi
3.11 Removal of Unsuitable Soil with Disposal upto 1000 m - Removal of unsuitable soil including cum 31.50
excavation, loading and disposal upto 1000 m lead with all lifts but excluding compaction
ground supporting embankment / subgrade, replacement by suitable soil, w
3.12 Presplitting of Rock excavation slopes - Carrying out excavation in hard rock to achieve a sqm 116.70
specified slope of the rock face by controlled use of explosives and blasting accessories in
properly aligned and spaced drill holes, collection of the excavated ro
3.13 Excavation for structures - Earth work in excavation of foundation of structures as per drawing -- --
and technical specification, including setting out, construction of shoring and bracing, removal
of stumps and other deleterious matter, dressing of sides and
3.13.1 Ordinary soil -- --
3.13.1.1 By manual means ( upto 3 m depth ) cum 96.60
3.13.1.2 By mechanical means ( upto 3 m depth ) cum 25.70
Designed By e-Governance Solutions Group,C-DAC Page:2
Schedule of Rates - 2008

3.13.2 Ordinary Rock ( not requiring blasting ) -- --


3.13.2.1 By manual means ( upto 3 m depth ) cum 120.80
3.13.2.2 By mechanical means ( upto 3 m depth ) cum 34.50
3.13.3 Hard Rock ( requiring blasting ) -- --
3.13.3.1 By manual means ( upto 3 m depth ) cum 257.00
3.13.4 Hard Rock ( blasting prohibited) -- --
3.13.4.1 By manual means ( upto 3 m depth ) cum 335.20
3.13.5 Marshy soil -- --
3.13.5.1 By manual means ( upto 3 m depth ) cum 250.00
3.13.5.2 By mechanical means ( upto 3 m depth ) cum 101.20
3.14 Scarifying Existing Granular Surface to a Depth of 50 mm by manual means - Scarifying sqm 11.20
Existing Granular Surface by manual means to a Depth of 50 mm and disposal of scarified
material with all lifts and leads upto 1000 m as per MoRT&H Technical Specifica
3.15 Scarifying Existing Bituminous Surface to a Depth of 150 mm by Mechanical Means - sqm 2.60
Scarifying Existing bituminous Road Surface by mechanical means to a Depth of 150 mm and
disposal of scarified material with all lifts and leads upto 1000 m as per MoRT&H T
3.16 Construction of Embankment with Material Obtained from Borrow Pits - Construction of cum 132.90
embankment with approved material obtained from borrow pits with all lifts, transporting to site,
spreading, grading to required slope and compacting to meet requirement
3.17 Construction of Embankment with Material deposited from Roadway Cutting - Construction of cum 87.80
Embankment with approved materials deposited at site from roadway cutting and excavation
from drain and foundation of other structures graded and compacted to meet
3.18 Construction of Subgrade and Earthen Shoulders - Construction of subgrade and earthen cum 132.90
shoulders with approved material obtained from borrow pits with all lifts and leads, transporting
to site , spreading, grading to required slope and compacted to meet re
3.19 Compacting Original Ground - -- --
3.19.1 Compacting original ground supporting subgrade - Loosening of the ground upto a level of 500 cum 50.10
mm below the subgrade level, watered, graded and compacted in layers to meet requirement
of Tables 300.2 for subgrade construction as per MoRT&H Technical Specifi
Designed By e-Governance Solutions Group,C-DAC Page:3
Schedule of Rates - 2008

3.19.2 Compacting original ground supporting embankment - Loosening, Levelling and Compacting cum 27.60
original ground supporting embankment to facilitate placement of first layer of embankment,
scarified to a depth of 150 mm, mixed with water at OMC and then compacted b
3.20 Stripping, Storing and relaying of Top soil - Stripping, storing of top soil by road side at 15 m cum 79.40
interval and re-application on embankment slopes, cut slopes and other areas in localities
where the available embankment material is not conducive to plant
3.21 Stripping, Storing and Relaying Top Soil from Borrow Areas in Agricultural Fields - Stripping of cum 38.80
top soil from borrow areas located in agriculture fields, storing at a suitable place, spreading
and relaying after taking the borrow earth to maintain fertil
3.22 Turfing with Sods - Furnishing and laying of the live sods of perennial turf forming grass on sqm 29.60
embankment slope , verges or other locations shown on the drawing or as directed by the
Engineer including preparation of ground, fetching of sods and watering a
3.23 Seeding and Mulching - Preparation of seed bed on previously laid top soil, furnishing and sqm 102.30
placing of seeds, fertilizer, mulching material, applying bituminous emulsion at the rate of 0.23
litres per sqm and laying and fixing jute netting, including water
3.24 Surface Drains in Ordinary Soil - Construction of unlined surface drains of average -- --
cross-sectional area 0.4 sqm in ordinary soil to specified lines, grades, levels and dimensions
as per MoRT&H Technical Specification clauses of section 300. Excavated mat
3.24.1 Mechanical Means mtr 40.00
3.24.2 Manual Means mtr 24.20
3.25 Surface Drains in Ordinary Rock - Construction of unlined surface drain of average -- --
cross-sectional area 0.4 sqm in ordinary rock to specified lines, grades, levels and dimensions
as per approved design and MoRT&H Technical Specification clauses of section
3.25.1 Mechanical Means mtr 81.20
3.25.2 Manual Means mtr 36.20
3.26 Surface Drains in Hard Rock - Rate per metre may be worked out based on quantity of hard -- --
rock as per design. For rate of hard rock cutting, refer relevant item in this chapter.

Designed By e-Governance Solutions Group,C-DAC Page:4


Schedule of Rates - 2008

3.27 Sub-Surface Drains with perforated pipe - Construction of subsurface drain with perforated mtr 702.40
pipe of 100 mm internal diameter of metal / asbestos cement/ cement concrete / PVC, closely
jointed, perforations ranging from 3 mm to 6 mm depending upon size of m
3.28 Aggregate Sub-Surface Drains - Construction of aggregate sub-surface drain 300 mm x 450 mtr 336.10
mm with aggregates conforming to table 300.4, as per MoRT&H Technical Specification
clauses of section 300. (excavated material to be utilised in roadway.)
3.29 Underground Drain at Edge of Pavement - Construction of an underground drain 1 m x 1 m mtr 4125.80
(inside dimensions) lined with RCC M-20, 100 mm thick and covered with RCC slab 100 mm in
thickness on urban roads as per MoRT&H Technical Specification.
3.30 Preparation and surface treatment of formation - Preparation and surface treatment of sqm 1.50
formation by removing mud and slurry, watering to the extent needed to maintain the desired
moisture content, trimming to the required line, grade, profile and rolling w
3.31 Construction of rock fill embankment - Construction of rock fill embankment with broken hard cum 46.50
rock fragments of size not exceeding 300 mm laid in layers not exceeding 500 mm thick
including filling of surface voids with stone spalls, blinding top layer wit
3.32 Excavation in soil in hilly area by mechanical means -- --
3.32.1 For disposal upto 1000 m - Excavation in soil in hilly area by mechanical means including cum 74.90
cutting and trimming of side slopes and disposing of excavated earth with all lifts and lead upto
1000 metres as per MoRT&H Technical Specification clauses of sectio
3.32.2 For disposal in the valley side. - Excavation in soil in hilly area by mechanical means including cum 46.60
cutting and trimming of side slopes and disposing of excavated earth with all lifts in the barren
valley side as per MoRT&H Technical Specification clauses o
3.33 Excavation in ordinary rock ( not requiring blasting ) in hilly area by mechanical means -- --
3.33.1 For disposal upto 1000 m - Excavation in ordinary rock ( not requiring blasting ) in hilly area by cum 112.20
mechanical means including cutting and trimming of side slopes and disposing of excavated
earth with all lifts and lead upto 1000 metres as per MoRT&H Techn
3.33.2 For disposal in the valley side - Excavation in ordinary rock ( not requiring blasting ) in hilly cum 72.70
area by mechanical means including cutting and trimming of side slopes and disposing of
excavated earth with all lifts in the barren valley side as per MoRT&
Designed By e-Governance Solutions Group,C-DAC Page:5
Schedule of Rates - 2008

3.34 Excavation in hard rock ( requiring blasting ) with disposal upto 1000 m. - Excavation for cum 166.40
roadway in hard rock ( requiring blasting ) by drilling, blasting and breaking, trimming bottom
and side slopes in accordance with requirements of lines, grades and
3.35 Work in Urban Roads - The cost of earth work in urban roads in habited area will be -- --
comparatively higher due to following reasons:
3.36 Construction of Embankment with Flyash available from coal or lignite burning Thermal Plants cum 96.30
as waste material. - Construction of embankment with Flyash conforming to table 1 of IRC: SP:
58 - 2001 obtained from coal or lignite burning thermal power statio

Designed By e-Governance Solutions Group,C-DAC Page:6