Vous êtes sur la page 1sur 1

Gantt Chart -Hemant Kumar

Day Highlight: 1 Plan Duration Actual Start % Complete Actual (beyond plan) % Complete (beyond plan)

PLANNED PLANNED ACTUAL ACTUAL PERCENT


TASKS START DURATION START DURATION COMPLETE Days
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60

Portofolio 1 5 1 4
25%

Question1 100%
1 6 1 6

Question 2 35%
2 4 2 5

Question 3 10%
4 8 4 6
Question 4 85%
4 2 4 8
Question 5 85%
4 3 4 6

Logo Design 50%


5 4 5 3

Design a logo 60%


5 2 5 5

Logo Rationale 75%


5 2 5 6

Incorporate logo in project 100%


6 5 6 7

Advertisement flyer 60%


6 1 5 8

Developing the layout 0%


9 3 9 3

Adding key features 50%


9 6 9 7

Data dictionary 0%
9 3 9 1
1%
Develop customers information 9 4 8 5
80%
Make data dictionary 10 5 10 3

Data Base 0%
11 2 11 5
Develop database using data
0%
dictionary 12 6 12 7
0%
Produce a report 12 1 12 5

Mail Merge 0%
14 5 14 6

Develop a letter 44%


14 8 14 2

Mail Merge database information 0%


14 7 14 3

Spreadsheet 12%
15 4 15 8

Develop stock list 5%


15 5 15 3

Include necessary formulas 0%


15 8 15 5

Portofolio 50%
16 28 16 30
50%
Question 6 16 28 16 30
50%
Question 7 16 28 16 30
50%
Question 8 16 28 16 30
50%
Question 9 16 28 16 30

Page 1 of 1

Vous aimerez peut-être aussi