Académique Documents
Professionnel Documents
Culture Documents
Stable workforce
1) Which of the following is a benefit that arises from using a chase strategy in production planning
opposed to a production leveling strategy?
Stable workforce
Explanation
In a chase strategy, a company manufactures only enough to meet demand which leads to
little or no finished goods inventory and hence lower inventory carrying cost than in a
production leveling strategy.
2) A car factory has on average ten weeks of work in process (WIP) inventory, annual costs of goods
sold are $50.000.000, sales revenue is $130.000.000 and the manufacturing lead time is 6 Weeks.
Assuming that the factory works 350 days a year what is the average dollar value of the work in
process (WIP)?
$5.000.000
$2.000.000
$10.000.000
$3.085.142
2) A car factory has on average ten weeks of work in process (WIP) inventory, annual costs of goods
sold are $50.000.000, sales revenue is $130.000.000 and the manufacturing lead time is 6 Weeks.
Assuming that the factory works 350 days a year what is the average dollar value of the work in
process (WIP)?
$5.000.000
$2.000.000
$10.000.000
$3.085.142
Explanation
Work in process (WIP) is part of the costs of goods sold (COGS). Production costs like labor,
materials and overhead are applied to WIP throughout the entire manufacturing process
and the value of WIP is therefore estimated to be half of the final value (COGS).
Weekly Cost of Goods Sold = $50,000,000 per year/ 50 weeks per year= $1.000,000/week
MRP stands for materials requirement plan whereas MRP II stands for manufacturing
resource plan
3) What is the difference between MRP and MRP II?
MRP stands for materials requirement plan whereas MRP II stands for manufacturing
resource plan
Explanation
MRP II stands for manufacturing resource plan. The term MRP II is used to distinguish the
manufacturing resource plan (MRP II) from the materials requirement plan (MRP).
4) A flow process layout is also called
Stream layout
Project layout
Product layout
Progress layout
4) A flow process layout is also called
Stream layout
Project layout
Product layout
Progress layout
Explanation
Flow process layouts are often called product layouts due to the limited range of products
such systems are generally set up for.
5) In forecasting, the mean absolute deviation (MAD) can be used for which of the following
purposes?
The mean absolute deviation (MAD) determines the absolute variability of a data set.
While a total error could sum up to zero due to different error directions the MAD measure
the variability by calculating the total error ignoring the plus and minus signs.
Certico
CPIM Exam Prep