Vous êtes sur la page 1sur 17

APRIL

1, 2017
SRSA ROVER

PRESENTED BY: JOSH DOCKER, JACK ZANDE, HUDSON BEST, NATHAN


MINDERMAN, ZAC THOMAS, KEN LEE


TABLE OF CONTENTS
Srsa Rover .................................................................................................................................................................................................... 0
Drawings ....................................................................................................................................................................................................................... 2
Top View ................................................................................................................................................................................................................................ 2
Side View ............................................................................................................................................................................................................................... 3
Front View ............................................................................................................................................................................................................................. 4
Exploded View ....................................................................................................................................................................................................................... 5
Bolt lock ................................................................................................................................................................................................................................. 6
Hinge ..................................................................................................................................................................................................................................... 7
Gant chart ..................................................................................................................................................................................................................... 8
Method ......................................................................................................................................................................................................................... 9
Budget ......................................................................................................................................................................................................................... 11
Risk Management Plan ................................................................................................................................................................................................ 12
Tender EvaluaCon Criteria ............................................................................................................................................................................................ 14
Criteria Summary ................................................................................................................................................................................................................. 14
CommunicaQon ................................................................................................................................................................................................................... 15
Availability ........................................................................................................................................................................................................................... 15
Competency ........................................................................................................................................................................................................................ 16
Safety ................................................................................................................................................................................................................................... 16

4/1/2017 1
SRSA

DRAWINGS
TOP VIEW




















4/1/2017 2
SRSA

SIDE VIEW

4/1/2017 3
SRSA

FRONT VIEW





















4/1/2017 4
SRSA

EXPLODED VIEW

4/1/2017 5
SRSA

BOLT LOCK

4/1/2017 6
SRSA

HINGE

4/1/2017 7
SRSA


GANT CHART


Green Designers And Contractors
Blue Designers
Yellow Contractors

4/1/2017 8
SRSA


METHOD

Step Action Completion Criteria Diagram


1. To construct the chassis of the vehicle firstly cut 3 Ensure that the frame is
Chassis pieces of wood with a tenon saw or drop saw to square at the cross member
lengths of (305mm, 305mm and 77.5mm), Using the Ensure that the frame is
3 pieces of wood assemble them to form a H shape. parallel with the top edges
To secure the frame first glue the wood using perpendicular.
generous portions of glue, once dry using 1 screw Ensure to use counter
(45mm length) per joint to fully secure use a drill or sinking screws
screwdriver. Then drill 4 holes of diameter 5mm in Use screws of length 45mm
the frame in the locations designated by the
drawings for the axle to be inserted into.
2. Axle The axle consists of a threaded piece of metal Ensure no glue enters the
running through a hollow piece of tubing fixed tube
securely through the frame. To secure the axle first Ensure the tube is centred
cut two pieces of hollow tubing (158mm) with a Ensure the tube is square
hacksaw, using glue secure the tube through the Ensure not to tighten nuts
pre-drilled holes and apply glue to any gaps around Ensure that the thread of the
the tube. To fix the shaft inside the axle use 4 nuts nuts match the thread of the
threading them loosely onto the rod. rod
3. 3D print the wheels using the given blueprints in Print the wheels in ABS type
Wheels drawings. Push the rod through all 4 wheels material
fastening with lock nuts. Ensure the wheels are not
wobbling
Ensure the nuts are tight
Ensure that the outside and
inside nuts of each wheel
grips the wheel so both
wheels spin simultaneously.
Ensure the lock nuts thread
4/1/2017 9
SRSA

matches the thread of the


rod
4. Bottle The bottle cage consists of a pipe on a hinge to Ensure hinge lines up to
Cage allow access. Cut the piece of PVC piping using a allow the cage to swing
hacksaw to a length of 220mm, to attach the hinges Ensure glue and screws hold
first rule a line on the pipe showing where the hinge strong without cracking the
will run. Using screws (4mm diameter, 12mm length) wood.
one side of the hinges to the pipe. Insert the bottle Use small screws (may be
cage in to the frame ensuring that the hinges line up included in packaging of
with the side of the frame. hinge)
Then glue the hinge to the side of the frame insuring Ensure the pin of the hinge
to hold pressure on the join to ensure the glue holds sits on the edge of the frame
strong. Through the holes in the hinge screw the (bottle cage will not fit if pin
hinge plate to the frame for added strength. is over hanging)
5 Cage Attach the dead bolt hinge lock to the opposing side Ensure that the hinge lock
Lock of the pipe using screws (included in packaging) and will reach the pipe
a screwdriver/drill driver. Close the bottle cage and Ensure the bolt will enter the
make a marking where the bolt will hit the pipe when pipe holding it firm with
it is set between the two side pieces of chassis. minimal movement.
Using a drill piece that corresponds with the size of
the extending bolt drill a hole in the pipe on the
centre of the marking.

4/1/2017 10
SRSA

BUDGET

Materials Units Unit costings Costs Sourcing


required
Wood (40mm x 40mm) 65cm $1.60 per 1m length $1.04 Curtin
Threaded Rod (4mm) 40cm $0.87per 1m length $0.35 Curtin
Nuts (4mm) 8 $0.05 for 1 unit $0.40 Curtin
Timber Screws (4mm) (length 12mm) 4 $0.02 for 1 unit $0.08 Curtin
Hollow Round Bar (5mm internal with 2mm 35cm $7.54 per 1m $2.64 Curtin
a thickness)
PVC Pipe (75mm) 20cm $7.55 per 1m $1.51 Bunnings
Hinge (65mm nickel plated) 2 $6.88 for 2 units $6.88 Bunnings
Sliding Bolt Lock (with included screws) 1 $0.64 for 1 unit $0.64 Bunnings
Chassis Screws (45mm Gold Passivated 2 $4.20 for 15 units $0.56 Bunnings
Wafer Head Timber Screws)
Hinge Screws (zinc plated hinge-long 4 $4.20 for 45 units $0.37 Bunnings
thread timber screws 10mm)
3D Printed Wheels 4 Wheels $0.03 per gram approx $6.00 Curtin
Glue (araldite) $0.80 per gram approx $2 Curtin
Total Cost $22.47

4/1/2017 11
SRSA


RISK MANAGEMENT PLAN
In a working environment, people will always be exposed to risks and hazards and can have both physical and mental
consequences if not dealt with correctly. The purpose of a risk management plan is to ensure the safety of those involved projects.
There is a duty of care that all engineers must abide by to ensure that all practices are safe for all those involved.

A hazard (according to Prof Nicoleta Maynard in week 3 lecture powerpoint) is a physical situation with potential for human injury, damage to
our environment or even in some cases both. A hazard is a source to which risks can stem from. In order to assess hazards we can
identify potential sources that would cause this injury or damage.

Whereas a risk (according to Prof Nicoleta Maynard in week 3 lecture powerpoint) is the chance of something happening that could cause a
specific level of harm to people, property or environment. To assess risk, we can analyse mechanisms by which these undesired
events could occur. When assessing risks, engineers need to consider both the likelihood and severity of each situation. By doing
so they can implement mitigation to reduce the risk involved in the project. Each risk must be properly assessed to ensure that the
safety of those involved is kept as a main priority. However, there will always be residual risk involved in all projects which cannot
be avoided no matter what mitigations are put in place.

A good source used to assess the risk of situations is by comparing the likelihood against the consequences or severity. This was
introduced as the risk matrix and is shown below. By using this matrix, engineers can assess risks ranging from low to extreme and
this can help them find ways of prevention or mitigation in order to reduce the risk and uphold safety in the work place.

4/1/2017 12
SRSA

Hazard Risk Consequences Likelihood Mitigation Residual Risk Comments


DESIGN The group doesnt see
each other everyday
Poor Due to our weekly group
Hold weekly Group which could result in
communicatio Achieving in an meetings we have been able to
Not properly Meetings. some mis-
n between inaccurate or Unlikely easily allocate roles for each
allocating tasks. Assign a group communication. However
group unfinished design. group member helping us
leader. the weekly meetings
members. keeping us on track.
move this risk down to
rare.
Assign a group
leader. Motivation may be lost as
Once again due to the constant
Not completing Come to a unanimous the semester progresses
group meetings we were easily
Unmotivated Bad group the report on time decision as to what however this is very
able to decide what we wanted
or Lazy group morale and low or submitting work Possible the group wants to unlikely as all members
to achieve in the assignment.
members. work ethic. that isnt up to achieve. of our group show
Ensuring all work got completed
standard. A contract that all consistent signs of
to an acceptable standard.
members can be kept motivation.
accountable for.
Materials not Ensure that sufficient Mistakes are still possible
Rover not working A large amount of research has
being available research is to be made where the
Poor Design to the been done by our group to
for construction Possible undertaken so that designers werent aware.
Choices. expectations of ensure we use proper material
or dont work as the design is up to the However the mitigation
the client. and construction methods.
intended. clients standards. makes this Unlikely.
CONSTRUCTION Could penetrate
There will still be dust
Physical injury peoples eyes or
Dust and and wood in the air which All builders will be required to
to those cause issues Wear safety glasses
Wood chips in Possible could seep through the abide by the safety guidelines to
involved in breathing resulting and face masks.
the Air mask however any cause ensure no physical harm.
construction. in serious physical
of injury becomes rare.
damage.
Physical injury Use hand tools or Still using sharp material If a person does not feel
Dangerous Physical injury
such as cuts or or less dangerous so they will have to comfortable with powered tools,
Power to those
permanent Possible equipment. proceed with caution. there is no issue with using hand
tools(Drop involved in
damage such as Workers require Risk of injury becomes held tools, powered ones are
saw) construction.
losing fingers. experience. rare. just faster.
Still possible for mistakes
Poor Not completing Consistent weekly The designers of our group will
to be made whether they
Communicati the project in Not being up to meetings to ensure ensure that our rover is built in
communicate
on between the way that it the clients Unlikely that the two parties the way that we intended it to be
consistently or not.
designers and was intended to standards. are in the same frame by constantly meeting with the
However this becomes
builders be. of mind. builders.
very rare.

4/1/2017 13
SRSA

TESTING Even with it secured


Ensure that the
The rover Unable to perform there is always a risk of it
Poor techniques used to Our group will ensure we
breaks or testing and not be not being handled
Transportatio Rare transport the rover supervise and trust the way in
becomes up to the clients correctly by those who
n Process are safe and have it which our rover is transported.
defective expectations transport it making this
properly secured.
risk extremely rare.
Slipping causing
injury or the body
Slipping or of the rover If rain does become an issue our
Test the rover indoors By testing the rover
damaging the becomes group is still confident that the
Rain Unlikely or under sufficient indoors this risk becomes
wooden body of defective where rover will be able to perform to
cover. impossible.
the rover. the shape of wood the clients standards.
was affected by
the water.
Life at uni can become
busier towards the end of
On the day the Hold consistent group As a group we all work well
semester. With an
rover is tested, it meetings and also together and have meetings on
Project increased workload, we
Poor time does not perform ensure the designers a regular basis. When it comes
incomplete on Unlikely still many be pushed for
management to the clients are keeping up to to testing and construction we
testing day. time. However with
standards or is date on the progress will ensure we stick to our
these constant meetings
defective. of rover being built. schedule.
this becomes risk
becomes rare.

TENDER EVALUATION CRITERIA


CRITERIA SUMMARY

Criteria Title Criteria Details Mark

Communication Communicates via facebook messenger and/or email. /30

Availability Available for Designer-contractor meetings /30

Competency Experience using power tools /20

Safety Relevant safety equipment must be provided and used /20

4/1/2017 14
SRSA

COMMUNICATION

To ensure a worry free construction phase, a clear line of communication must always be open. This line of communication will be used to
bring up queries, concerns and suggestions. To achieve this SRSA requires that tenderers are able to provide and use either facebook
messenger or email.

0 15 30

Tenderers are not able to use Tenderers are able to Tenderers reply within the hour
Facebook messenger to communicate via facebook (during working hours
communicate, and reply later messenger and/or reply to communicate via facebook
than 24 hours to emails. emails within 24hrs. messenger and/or reply to
emails within 24hrs.


AVAILABILITY

For a smooth and effective construction phase, it is crucial to not only have open communications via email and messenger but also have a set
one hour, weekly meeting time in which both parties; designers and contractors are available to meet up in order to talk progress, ideas and
concerns. Having regular meetings will not only facilitate clear communication between designers and contractors but will also establish an
element of consistency throughout the construction phase which will work to eliminate the burden of time constraints, and promote positive time
management. The times that are made available for meetings are as follows:
Monday 3:00 -> 4:00pm
Wednesday 1:00 -> 2:00pm

0 15 30

Not a single One or more representatives are One or more representatives


representative is able to able to attend weekly design- are able to attend weekly
attend weekly design- contractor meetings for at least design-contractor meetings for
contractor meetings. one of the provided provided two of the provided provided
times. times.

4/1/2017 15
SRSA

COMPETENCY

To guarantee an efficient and effective construction phase SRSA requests that not only must tenderness submit their perceived level of
competency, but also their experience alongside as proof of capability. Proof of competency can include but is not limited to:
An attached school report displaying the class and grade received for classes in which power tools were used ie. Metalwork, woodwork,
systems technology etc.
A picture of any project worked on where power tools were demanded ie. A mug holder, a bird house or simply any project requiring
power tools.
Any other file the tenderers deem acceptable proof may also be submitted as proof, but ultimately it will come down to the judgement of
the SRSA to see if the proof will be deemed acceptable or not.

0 10 20

Tenderers have zero Tenderers have proof that Tenderers have proof that they are
proof of competency. they are capable of using a capable of using both a power drill
power drill. and a saw.

SAFETY

Health and safety are a universal must, to ensure that the construction phase runs smoothly, with as much mitigation to risk as possible SRSA
requests that contractors follow safe work practises.

0 10 20

Contractors refuse to provide Contractors provide and Contractors provide and agree
and wear safety glasses and agree to use either safety to use both safety glasses and
steel toe boots. glasses or steel toed boots. steel toed shoes.

4/1/2017 16
SRSA

Vous aimerez peut-être aussi