PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 1 of 15
Handling SRCC Documentation and Distribution
Issue Date February 10, 2016
Contents Page
1. Purpose
2. Scope
3. Associated Procedures
2
4. Definitions
5. Responsibilities
6. Procedure
7. Appendices
1. Purpose
The purpose of this procedure is to outline the responsibilities of SZC and other
personnel under the control of SZC to formally notify the issuance of a SRCC on a
relevant plant system or work area.
2. Scope
This procedure applies to each Section Manager within SZC for their scope of supply
at Tanjung Bin Power Station Site. Sub-contractors shall work to this procedure
under the direction of the involved Section Manager and will be subject to
surveillance and or audit.
3. Associated Procedures
4. Definitions
SRCC: Safety Rules Clearance Certificate, the means by which all parties will be
advised that plant or equipment is to be energized for the first time and from which
point it is mandatory to have access to that plant or equipment using the SZC safety
documentation.
Energised: System or part system that has been made live with electricity, fluid
pressure, air pressure, stored energy (filling), hazard substances and any means,
which may have the potential to harm.
5. Responsibilities
The responsibilities within this procedure are connected totally with the safe working
of personnel within or adjacent to a specified work face, plant system, or area where
specified equipment is to be energised and therefore has the potential to harm.
The responsibility is directly with the SZC Site Manager and partner Site Managers
to ensure that all potential affected parties are formally notified of the SRCC
procedure and of specific SRCCs that have been issued. This responsibility is then
passed to the Sub-contractor management to ensure that all manpower at or near
the specified work face is aware of the potential hazard and that a SRCC has been
issued.
For personnel who are not considered in a supervisory role, they will not receive
SRCCs, therefore training is required for the various recipients of the SRCC in terms
of what is required to be done upon receipt. Such personnel shall treat all installed
plant/apparatus as in service and under the Safety Rules unless the individual has
received confirmation from the responsible party.
6. Procedure
a) Attach the Signature Proforma (See Appendix C) to the front of the SRCC;
b) Identify from the SRCC the work unit/location of the plant/apparatus and
compare with the standard distribution from the Matrix Distribution Sheet
(See Appendix B);
c) Mark onto the Signature Proforma in the tick-box provided the required
distribution;
d) Note the current date, time and SRCC number in the SZC SRCC File
Register;
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 5 of 15
Handling SRCC Documentation and Distribution
Issue Date February 10, 2016
e) Pass the SRCC and Signature Proforma to the SZC Site Manager or in his
absence the Commissioning Manager to verify the distribution;
f) Upon return of the SRCC and Signature Proforma from the SZC Site
Manager or Field Operation Leader with the confirmed distribution, copy the
SRCC document into the required number of copies;
h) The Signature Proforma must be signed by all no later than 1700 hours of the
same working day (SRCCs received on Saturday shall be received by 1700
hours on Monday.) If the Signature has not been returned, identify its
location, retrieve and obtain outstanding signature;
i) Enter into SZC File Register the date and time received;
j) On a weekly basis, the SZC File Register must be cross checked with the
filed Signature Proformas to ensure good record keeping is being
maintained; (Partners Quality Manager will audit every month)
k) All distribution recipients must ensure that the SRCC is distributed onwards in
hardcopy format to immediate subordinates, sub-contractors, vendor
representatives and other appropriate persons working in or near the
specified work face.
7. Appendixes
A SRCC Pro-formas
C Signature Proforma
I hereby give notice that the plant/apparatus scheduled below is ready to be made
live/charged with working fluid/put into service and all subsequent work is to be conducted
under the terms of the Tanjung Bin Power Plant Safety Rules.
ID Ref.
Description
Location
Type of System
I confirm that the plant/apparatus listed above is required to be SRCCs and I authorise their
being made live/charged with the working fluid/put into service after complete processing of
this SRCC.
I confirm I have ensured with all involved parties that the Plant/Apparatus listed above is
ready to be SRCCs and all necessary terminal points listed above are made safe, locked
and tagged.
Initials
ID Description SRCC No. Name
(*Note)
* Note:- I authorise the terminal points of previous SRCCs listed above and locked by myself or by my nominated deputy, to be
released.
PERMIT OFFICE
I confirm this SRCC has completed its process as required and the plant/apparatus
identified on page 1 may be made live/charged with the working fluid/put into service from
Date _____________________ Time _______________
All keys are secured in a SRCC Key bar under control of the
Permit Office and will remain secured until released by a subsequent SRCC
I acknowledge receipt of this SRCC and will fulfil my responsibility to ensure all relevant
personnel, sub contractors and all their relevant personnel under my control are informed
that this SRCC is being issued and that all subsequent work on the detailed plant/apparatus
must be conducted under the Terms of the Tanjung Bin Power Plant Safety Rules.
RJ MALAKOFF
SZC
ZELAN
ISHI POWER
TOS ENERGY
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 10 of 15
Handling SRCC Documentation and Distribution
Issue Date February 10, 2016
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 11 of 15
Handling SRCC Documentation and Distribution
Issue Date February 10, 2016
APPENDIX B
Construction Mag.
Assis. Mag.
E & C Leader
Mechanical Leader
Instrument Leader
Engineering
COMMISSIONING
QA/QC
PLANNING
AREAS
Later
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 12 of 15
Handling SRCC Documentation and Distribution
Issue Date February 10, 2016
CODE
Construction Mag.
E & C Leader
Mechanical Leader
Instrument Leader
Engineering
COMMISSIONING
Assis. Mag.
PLANNING
QA/QC
AREAS
OKI PULP & PAPER MILL Project No. P-OkiPL1
PROJECT
[OKIPL1] Document No. P-OkiPL1-100-01-FRM-XXX
Revision 00
Page 13 of 15
Handling SRCC Documentation and Distribution
Issue Date February 10, 2016
APPENDIX C
Acknowledge this SRCC by signing and dating where indicated and pass on immediately to
another person on the list. The last person to sign is to immediately return to the issuer as
indicated below.
SRCC Document
SZC
Site Manager
SZC
Site Manager