Vous êtes sur la page 1sur 29

Risk Management

Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary. Risk Management
Operators and contractors should implement proactive risk management programs. Risk is a
product of uncertainty. With the accumulation of relevant experience in the industry, risk can
be mitigated. When entering a new area of development, extending the limits of current
technology, or undertaking a new contractual commitment, new risks are introduced. Risk
management should be applied early and continue through the project.
Employees, contractor personnel, operators and other participants should be indoctrinated
with an awareness of the risks faced by the project within their sphere of involvement, and the
mitigation measures available to them. Adequate resources should be committed to the
mitigation of risk and responsibilities formally assigned.
6.2.1 Risk Analysis In The Project Phases
6.2.1.1 Phase 1, Feasibility Study
Identify alternative concepts for screening.
Evaluate relative capital cost and operating costs for each concept.
Identify areas where technology development may be necessary.

Vous aimerez peut-être aussi