Vous êtes sur la page 1sur 116

Standard Form Number: SF-INFR-01

Revised on: July 28, 2004


APPROVED BUDGET FOR THE CONTRACT
CONSTRUCTION OF SENIOR CITIZEN'S BLDG.
BANGUED, ABRA
Project Name and Location
Stations:
Length:
MARK-UPS
TOTAL MARK-UP
ESTIMATED IN PERCENT
DESCRIPTION QUANTITY UNIT
DIRECT COST
ITEM NO. OCM[1] PROFIT % VALUE
(1) (2) (3) (4) (5) (6) (7) (9) (10)
PART II OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 1.00 l.s. 4,323.48 15.00% 10.00% 25.00% P 1,080.87
B.7 Occupational Safety and Health Program 4.00 month 13,927.60 10.00% 10.00% P 1,392.76
PART A EARTHWORK
803 (1) a Structure Excavation 75.00 cu.m. 41,026.12 15.00% 10.00% 25.00% P 10,256.53
803 (4) Gravel Fill 33.73 cu.m. 26,195.09 15.00% 10.00% 25.00% P 6,548.77
804 (1) a Embankment 75.00 cu.m. 5,080.08 15.00% 10.00% 25.00% P 1,270.02
PART B PLAIN AND REINFORCED CONCRETE WORK
900(1)c2 Reinforced Concrete (Footing, WF and Slab on Fill) 46.80 cu.m. 169,489.96 15.00% 10.00% 25.00% P 42,372.49
900(1)c4 Reinforced Concrete (Column) 10.40 cu.m. 41,885.07 15.00% 10.00% 25.00% P 10,471.27
900 ( 1 )c6 Reinforced Concrete (RB-1 & RB-2) 10.02 cu.m. 23,007.59 15.00% 10.00% 25.00% P 5,751.90
902(1) Reinforcing Steel(Deformed) 9818.80 kgs. 234,578.65 15.00% 10.00% 25.00% P 58,644.66
1044(1) Forms and Falseworks 1.00 l.s. 135,381.88 15.00% 10.00% 25.00% P 33,845.47
PART C FINISHING
1043(2) a CHB Non Load Bearing Wall - 100mm 67.00 sq.m. 25,154.49 15.00% 10.00% 25.00% P 6,288.62
1043(2) b CHB Non Load Bearing Wall - 125mm 222.00 sq.m. 102,435.60 15.00% 10.00% 25.00% P 25,608.90
1027(1) Cement Plaster Finish 550.00 sq.m. 179,509.55 15.00% 10.00% 25.00% P 44,877.39
1047(3) Structural Steel, furnished, and fabricated - Purlins 849.50 kgs. 53,816.33 15.00% 10.00% 25.00% P 13,454.08
1047(2) Structural Steel, furnished, fabricated, and erected - Truss 1727.50 kgs. 109,145.55 15.00% 10.00% 25.00% P 27,286.39
1003(1) a1 Ceiling (4.5mm Fiber Cement Board) 266.00 sq.m. 60,155.21 15.00% 10.00% 25.00% P 15,038.80
1008 (1) Aluminum Glass Windows/Doors 37.20 sq.m. 120,368.21 15.00% 10.00% 25.00% P 30,092.05
1010(2)b Doors (Wood Panel) 7.56 sq.m. 40,056.13 15.00% 10.00% 25.00% P 10,014.03
1013(1) Metal Roofing - Prepainted Long Span 291.20 sq.m 171,273.87 15.00% 10.00% 25.00% P 42,818.47
1018(1) Tiles and Trims (Toilet) 34.30 sq.m. 37,897.52 15.00% 10.00% 25.00% P 9,474.38
1018(2) Tiles - Vitrified Floor Tile (main flr.) 190.00 sq.m. 181,955.41 15.00% 10.00% 25.00% P 45,488.85
1032(1)a1 Painting Works - Masonry and Fiber Cement Painting 550.00 sq.m. 97,750.13 15.00% 10.00% 25.00% P 24,437.53
1035(1) Furring Channel-Double Furring System 266.00 ln.m. 60,889.08 15.00% 10.00% 25.00% P 15,222.27
1001 (1) a Pipe - 50mm diameter PVC 20.00 ln.m. 3,806.05 15.00% 10.00% 25.00% P 951.51
1001 (1) a3 Pipe - 100mm diameter PVC 8.00 ln.m. 4,522.02 15.00% 10.00% 25.00% P 1,130.50
1001 (1) a2 Pipe - 75mm diameter PVC 42.00 ln.m. 11,304.12 15.00% 10.00% 25.00% P 2,826.03
1002 (5) a1 Polyprophylene Random Copolymer (PPR-C) Pipes - 1/2" 50.00 pcs. 11,480.26 15.00% 10.00% 25.00% P 2,870.06
1002(9) diam. Closet
Water PN10 2.00 set 13,091.32 15.00% 10.00% 25.00% P 3,272.83
1002(5)f1 Lavatory, Wall Hung. Complete 2.00 sets 7,774.74 15.00% 10.00% 25.00% P 1,943.68
1002(12) Tissue Holder 2.00 pcs. 703.75 15.00% 10.00% 25.00% P 175.94
1002(13) Stainless Kitchen Sink 1.00 pc. 5,630.04 15.00% 10.00% 25.00% P 1,407.51
1201 (4)d Valves and Fittings 1.00 pcs. 523.75 15.00% 10.00% 25.00% P 130.94
1201(4)e Floor Drain 2.00 pcs. 763.75 15.00% 10.00% 25.00% P 190.94
PART D ELECTRICAL
1100(7)f1 Polyvinyl Chloride Pipes (PVC)-20mm 300.00 meters 17,303.56 15.00% 10.00% 25.00% P 4,325.89
1100(14) Octagonal Junction Box metal 32.00 pcs. 3,176.42 15.00% 10.00% 25.00% P 0.30
1100(15) Utility Boxes metal 28.00 pcs. 2,678.74 15.00% 10.00% 25.00% P 669.68

1101(1)a2 Electrical Wire - 3.5mm TWG/THHN 4.00 roll 17,572.43 15.00% 10.00% 25.00% P 4,393.11
1101(1)a3 Electrical Wire - 5.5mm TWG/THHN 1.00 roll 5,800.60 15.00% 10.00% 25.00% P 1,450.15
1101(1)a4 Electrical Wire - 10.0mm TWG/THHN 20.00 meter 1,506.44 15.00% 10.00% 25.00% P 376.61
1101(3) Tumbler Switch 6.00 set 1,894.35 15.00% 10.00% 25.00% P 473.59
1101(6) Duplex Convenience Receptacles 23.00 set 8,407.66 15.00% 10.00% 25.00% P 2,101.92
1102(1)b Panelboard Circuit Breaker Type - LPA Flush Mounted, 1.00 set 14,645.97 15.00% 10.00% 25.00% P 3,661.49
1103(1)a1 Compact NEMA 1 Enclosure
Flourescent Lamp (CFL) 9.00 sets 6,058.15 15.00% 10.00% 25.00% P 1,514.54
1200(4)A7 Package Type Airconditioning Unit (PACU)-Ceiling Mounted 4.00 sets 166,768.40 0.00% P -
Inverter

PREPARED/SUBMITTED BY:

JONATHAN T. BOBITA CHOPIN P. BACARRA RONALDO O. SAPONGEN ERNESTO B. BELMES


ENGINEER II ENGINEER II ENGINEER II ENGINEER II
ROVED BUDGET FOR THE CONTRACT
TION OF SENIOR CITIZEN'S BLDG.
BANGUED, ABRA
Project Name and Location

Contract Duration: 120 CD

TOTAL
TOTAL COST UNIT COST
VAT[3] INDIRECT COST

(11) (12) (13) (14)


OTHER GENERAL REQUIREMENTS
P 270.22 P 1,351.09 P 5,674.57 P 5,674.57
P 766.02 P 2,158.78 P 16,086.38 P 4,021.59
EARTHWORK
P 2,564.13 P 12,820.66 P 53,846.78 P 717.96
P 1,637.19 P 8,185.96 P 34,381.05 P 1,019.30
P 317.51 P 1,587.53 P 6,667.61 P 88.90
PLAIN AND REINFORCED CONCRETE WORK
P 10,593.12 P 52,965.61 P 222,455.57 P 4,753.32
P 2,617.82 P 13,089.09 P 54,974.16 P 5,285.98
P 1,437.97 P 7,189.87 P 30,197.46 P 3,013.72
P 14,661.17 P 73,305.83 P 307,884.48 P 31.36
P 8,461.37 P 42,306.84 P 177,688.72 P 177,688.72
FINISHING
P 1,572.16 P 7,860.78 P 33,015.26 P 492.77
P 6,402.23 P 32,011.13 P 134,446.73 P 605.62
P 11,219.35 P 56,096.74 P 235,606.29 P 428.38
P 3,363.52 P 16,817.60 P 70,633.94 P 83.15
P 6,821.60 P 34,107.99 P 143,253.54 P 82.93
P 3,759.70 P 18,798.50 P 78,953.72 P 296.82
P 7,523.01 P 37,615.07 P 157,983.28 P 4,246.86
P 2,503.51 P 12,517.54 P 52,573.67 P 6,954.19
P 10,704.62 P 53,523.08 P 224,796.95 P 771.97
P 2,368.59 P 11,842.97 P 49,740.49 P 1,450.16
P 11,372.21 P 56,861.07 P 238,816.48 P 1,256.93
P 6,109.38 P 30,546.92 P 128,297.05 P 233.27
P 3,805.57 P 19,027.84 P 79,916.92 P 300.44
P 237.88 P 1,189.39 P 4,995.44 P 249.77
P 282.63 P 1,413.13 P 5,935.15 P 741.89
P 706.51 P 3,532.54 P 14,836.65 P 353.25
P 717.52 P 3,587.58 P 15,067.84 P 301.36
P 818.21 P 4,091.04 P 17,182.36 P 8,591.18
P 485.92 P 2,429.60 P 10,204.34 P 5,102.17
P 43.98 P 219.92 P 923.68 P 461.84
P 351.88 P 1,759.39 P 7,389.42 P 7,389.42
P 32.73 P 163.67 P 687.43 P 687.43
P 47.73 P 238.67 P 1,002.43 P 501.21
ELECTRICAL
P 1,081.47 P 5,407.36 P 22,710.93 P 75.70
P 992.33 P 992.63 P 4,169.05 P 130.28
P 167.42 P 837.10 P 3,515.84 P 125.57

P 1,098.28 P 5,491.39 P 23,063.82 P 5,765.95


P 362.54 P 1,812.69 P 7,613.29 P 7,613.29
P 94.15 P 470.76 P 1,977.20 P 98.86
P 118.40 P 591.98 P 2,486.34 P 414.39
P 525.48 P 2,627.40 P 11,035.06 P 479.79
P 915.37 P 4,576.86 P 19,222.83 P 19,222.83
P 378.63 P 1,893.17 P 7,951.32 P 883.48
P 8,338.42 P 8,338.42 P 175,106.82 P 43,776.70
P 2,894,968.31

APPROVED:

ERNESTO B. BELMES LORETO B. DACOROON


ENGINEER II CARETAKER
1.00 -
2.00 5,674.57 - 5,674.57

3.00 16,086.38 - 16,086.38


4.00 - - -

5.00 53,846.78 -
6.00 34,381.05 -
7.00 6,667.61 -
8.00 - -
9.00 222,455.57 -
10.00 54,974.16 -
11.00 30,197.46 - 30,197.46
12.00 307,884.48 - 307,884.48
13.00 177,688.72 - 177,688.72
16.00 - -
35.00 33,015.26 -
36.00 134,446.73 -
17.00 235,606.29 - 235,606.29

18.00 70,633.94 - 70,633.94

19.00 143,253.54 -
20.00 78,953.72 -
21.00 157,983.28 -
22.00 52,573.67 -
23.00 224,796.95 -
24.00 49,740.49 -
25.00 238,816.48 - 238,816.48
26.00 128,297.05 - 128,297.05
27.00 79,916.92 - 79,916.92
28.00 4,995.44 - 4,995.44
29.00 5,935.15 -
30.00 14,836.65 -
31.00 15,067.84 -
32.00 17,182.36 -
33.00 10,204.34 - 10,204.34

34.00 923.68 -
37.00 7,389.42 -
38.00 687.43 -
39.00 1,002.43 -
51.00 - -
41.00 22,710.93 - 22,710.93
42.00 4,169.05 -

43.00 3,515.84 -
44.00 23,063.82 -
45.00 7,613.29 -
46.00 1,977.20 - 1,977.20
47.00 2,486.34 - 2,486.34
48.00 11,035.06 - 11,035.06
49.00 19,222.83 - 19,222.83
50.00 7,951.32 -
52.00 175,106.82 -
2,894,968.31
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Cordillera Administrative Region
OFFICE OF THE DISTRICT ENGINEER
Bangued, Abra

PROGRAM OF WORK

Region : C.A.R. Roadbed Width :na


District : ABRA DEO Pavement Width :na
Name of Project : Bridge Width :na
CONSTRUCTION OF SENIOR CITIZEN'S BLDG.
Type of Structure :Multi-Purpose Building
Road Section ID : Type of Superstructure :Reinforced Concr
Section : Type of SubStructure :Reinforced Concrete
Location : BANGUED, ABRA No. of Span : ____na____ No. of Piers :
Appropriation : P3,000,000.00
Source of Fund : BEFF-(BATCH 13) Dimension :
Classification ### No. of Storeys : 2
Station Limits : No. of Classrooms :
Net Length :
Thickness : No. of Days to Complete 120
Width
Starting Date : Upon release of funds
ITEMS OF WORK EQUIPMENT
ITEM
TO BE DONE % DESCRIPTION
PART II OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 0.196%
B.7 Occupational Safety and Health Program 0.556% Plate Compactor
PART A EARTHWORK Backhoe
803 (1) a Structure Excavation 1.860% Dumptruck
803 (4) Gravel Fill 1.188% Elec. Drill
804 (1) a Embankment 0.230% One Bagger Mixer
PART B PLAIN AND REINFORCED CONCRETE WORK Welding Machine
900(1)c2 Reinforced Concrete (Footing, WF and Slab on Fill) 7.684% Jackhammer
900(1)c4 Reinforced Concrete (Column) 1.899%
900 ( 1 )c6 Reinforced Concrete (RB-1 & RB-2) 1.043%
902(1) Reinforcing Steel(Deformed) 10.635%
PART C FINISHING
1047(3) Structural Steel, furnished, and fabricated - Purlins 2.440%
1047(2) Structural Steel, furnished, fabricated, and erected - Truss 4.948%
1003(1) a1 Ceiling (4.5mm Fiber Cement Board) 2.727%
1008 (1) Aluminum Glass Windows/Doors 5.457%
1010(2)b Doors (Wood Panel) 1.816%
1013(1) Metal Roofing - Prepainted Long Span 7.765%
1018(1) Tiles and Trims (Toilet) 1.718%
1018(2) Tiles - Vitrified Floor Tile (main flr.) 8.249%
1027(1) Cement Plaster Finish 8.138%
1032(1)a1 Painting Works - Masonry and Fiber Cement Painting 4.432%
1035(1) Furring Channel-Double Furring System 2.761%
1043(2) a CHB Non Load Bearing Wall - 100mm 1.140%
1043(2) b CHB Non Load Bearing Wall - 125mm 4.644%
1044(1) Forms and Falseworks 6.138%
1001 (1) a Pipe - 50mm diameter PVC 0.173%
1001 (1) a3 Pipe - 100mm diameter PVC 0.205%
1001 (1) a2 Pipe - 75mm diameter PVC 0.512%
1002 (5) a1 Polyprophylene Random Copolymer (PPR-C) Pipes - 1/2" diam. PN10 0.520%
1002(9) Water Closet 0.594%
1002(5)f1 Lavatory, Wall Hung. Complete 0.352%
1002(12) Tissue Holder 0.032%
1002(13) Stainless Kitchen Sink 0.255%
1201 (4)d Valves and Fittings 0.024%
1201(4)e Floor Drain 0.035%
PART D ELECTRICAL
1100(7)f1 Polyvinyl Chloride Pipes (PVC)-20mm 0.784%
1100(14) Octagonal Junction Box metal 0.144%
1100(15) Utility Boxes metal 0.121%
1101(1)a2 Electrical Wire - 3.5mm TWG/THHN 0.797%
1101(1)a3 Electrical Wire - 5.5mm TWG/THHN 0.263%
1101(1)a4 Electrical Wire - 10.0mm TWG/THHN 0.068%
1101(3) Tumbler Switch 0.086%
1101(6) Duplex Convenience Receptacles 0.381%
1102(1)b Panelboard Circuit Breaker Type - LPA Flush Mounted, NEMA 1 Enclosure 0.664%
1103(1)a1 Compact Flourescent Lamp (CFL) 0.275%
1200(4)A7 Package Type Airconditioning Unit (PACU)-Ceiling Mounted Inverter 6.049%
100.000%
ESTIMATED COST OF PROPOSED WORK
ITEM DESCRIPTION
UNIT QUANTITY UNIT COST
PART II OTHER GENERAL REQUIREMENTS - - -
B.5 Project Billboard / Signboard l.s. 1.00 5,674.57
B.7 Occupational Safety and Health Program month 4.00 4,021.59
PART A EARTHWORK - - -
803 (1) a Structure Excavation cu.m. 75.00 717.96
803 (4) Gravel Fill cu.m. 33.73 1,019.30
804 (1) a Embankment cu.m. 75.00 88.90
PART B PLAIN AND REINFORCED CONCRETE WORK - - -
900(1)c2 Reinforced Concrete (Footing, WF and Slab on Fill) cu.m. 46.80 4,753.32
900(1)c4 Reinforced Concrete (Column) cu.m. 10.40 5,285.98
900 ( 1 )c6 Reinforced Concrete (RB-1 & RB-2) cu.m. 10.02 3,013.72
902(1) Reinforcing Steel(Deformed) kgs. 9,818.80 31.36
PART C FINISHING - - -
1047(3) Structural Steel, furnished, and fabricated - Purlins kgs. 849.50 83.15
1047(2) Structural Steel, furnished, fabricated, and erected - Truss kgs. 1,727.50 82.93
1003(1) a1 Ceiling (4.5mm Fiber Cement Board) sq.m. 266.00 296.82
1008 (1) Aluminum Glass Windows/Doors sq.m. 37.20 4,246.86
1010(2)b Doors (Wood Panel) sq.m. 7.56 6,954.19
1013(1) Metal Roofing - Prepainted Long Span sq.m 291.20 771.97
1018(1) Tiles and Trims (Toilet) sq.m. 34.30 1,450.16
1018(2) Tiles - Vitrified Floor Tile (main flr.) sq.m. 190.00 1,256.93
1027(1) Cement Plaster Finish sq.m. 550.00 428.38
1032(1)a1 Painting Works - Masonry and Fiber Cement Painting sq.m. 550.00 233.27
1035(1) Furring Channel-Double Furring System ln.m. 266.00 300.44
1043(2) a CHB Non Load Bearing Wall - 100mm sq.m. 67.00 492.77
1043(2) b CHB Non Load Bearing Wall - 125mm sq.m. 222.00 605.62
1044(1) Forms and Falseworks l.s. 1.00 177,688.72
1001 (1) a Pipe - 50mm diameter PVC ln.m. 20.00 249.77
1001 (1) a3 Pipe - 100mm diameter PVC ln.m. 8.00 741.89
1001 (1) a2 Pipe - 75mm diameter PVC ln.m. 42.00 353.25
Polyprophylene Random Copolymer (PPR-C) Pipes - 1/2" diam.
1002 (5) a1 pcs. 50.00 301.36
PN10
1002(9) Water Closet set 2.00 8,591.18
1002(5)f1 Lavatory, Wall Hung. Complete sets 2.00 5,102.17
1002(12) Tissue Holder pcs. 2.00 461.84
1002(13) Stainless Kitchen Sink pc. 1.00 7,389.42
1201 (4)d Valves and Fittings pcs. 1.00 687.43
1201(4)e Floor Drain pcs. 2.00 501.21
PART D ELECTRICAL - - -
1100(7)f1Polyvinyl Chloride Pipes (PVC)-20mm meters 300.00 75.70
1100(14)Octagonal Junction Box metal pcs. 32.00 130.28
1100(15)Utility Boxes metal pcs. 28.00 125.57
1101(1)a2Electrical Wire - 3.5mm TWG/THHN roll 4.00 5,765.95
1101(1)a3Electrical Wire - 5.5mm TWG/THHN roll 1.00 7,613.29
1101(1)a4Electrical Wire - 10.0mm TWG/THHN meter 20.00 98.86
1101(3)Tumbler Switch set 6.00 414.39
1101(6)Duplex Convenience Receptacles set 23.00 479.79
Panelboard Circuit Breaker Type - LPA Flush Mounted, NEMA 1
1102(1)b set 1.00 19,222.83
Enclosure
1103(1)a1 Compact Flourescent Lamp (CFL) sets 9.00 883.48
Package Type Airconditioning Unit (PACU)-Ceiling Mounted
1200(4)A7 sets 4.00 43,776.70
Inverter

BREAKDOWN OF EXPENDITURES ( ESTIMATE ) %


1. LABOR P 447,622.47 14.921 A. TOTAL PROJECT COST
2. MATERIALS 1,695,612.54 56.520 ( DIRECT / INDIRECT )
3. EQUIPMENT EXPENSES 97,480.12 3.249 B. ENG'G. & ADMIN. OH
4. INDIRECT COST ( OCM, PROFITS, TAX, VAT): 654,253.18 21.808 C. SURVEY PREPARATION
5. SOIL TESTING: D. ROW /SITE ACQUISITION
5. ENG'G. & ADM. OVERHEAD 105,000.00 3.500 SOIL TESTING
6. CONST. CONTINGENCIES 31.69 0.001 E. CONST. CONTINGENCIES
7. GENDER & DEVELOPMENT F. GENDER & DEVELOPMENT
8. COST OF RIGHT OF WAY G. COST OF RIGHT OF WAY
9. RA 9206 H. RA 9206
10. YOUTH & INFRA DEVELOPMENT I. BUDGET RESERVE
11. BUDGET RESERVE J. YOUTH & INFRA DEVELOPMENT
TOTAL P 3,000,000.00 100.00 K. APPROPRIATION

Prepared By: C Submitted By:

JUAN ANTONIO E. FLORENTINO CHONA LUISA A. RAMOS


ARCHITECT II CHIEF, Planning & Design Section
Checked By: Approved:

EMMANUEL T. COLLADO LORETO B. DACOROON


ENGINEER II ASSISTANT DISTRICT ENGINEER
(CARETAKER)
Republic of the Philippines
NT OF PUBLIC WORKS AND HIGHWAYS
dillera Administrative Region
CE OF THE DISTRICT ENGINEER
Bangued, Abra

ROGRAM OF WORK

m.

Multi-Purpose Building
,Steel
Reinforced Concrete
na

c.d.

NEEDED

1
1
1
2
1
1
2
ESTIMATED COST OF PROPOSED WORK
TOTAL COST
-
5,674.57
16,086.38
-
53,846.78
34,381.05
6,667.61
-
222,455.57
54,974.16
30,197.46
307,884.48
-
70,633.94
143,253.54
78,953.72
157,983.28
52,573.67
224,796.95
49,740.49
238,816.48
235,606.29
128,297.05
79,916.92
33,015.26
134,446.73
177,688.72
4,995.44
5,935.15
14,836.65
15,067.84
17,182.36
10,204.34
923.68
7,389.42
687.43
1,002.43
-
22,710.93
4,169.05
3,515.84
23,063.82
7,613.29
1,977.20
2,486.34
11,035.06
19,222.83
7,951.32
175,106.82

P 2,894,968.31

105,000.00

-
31.69

J. YOUTH & INFRA DEVELOPMENT


P 3,000,000.00

CHONA LUISA A. RAMOS


CHIEF, Planning & Design Section

LORETO B. DACOROON
ASSISTANT DISTRICT ENGINEER
(CARETAKER)
SUMMARY OF ESTIMATES

ITEM LABOR MATERIALS EQ. RENTALS


PART II OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 737.71 3,512.00 73.77
B.7 Occupational Safety and Health Program 3,332.00 10,262.40 333.20
PART A EARTHWORK
803 (1) a Structure Excavation 37,296.47 - 3,729.65
803 (4) Gravel Fill 5,108.90 20,575.30 510.89
804 (1) a Embankment 3,947.35 - 1,132.73
PART B PLAIN AND REINFORCED CONCRETE WORK
900(1)c2 Reinforced Concrete (Footing, WF and Slab on Fill) 7,922.69 147,152.00 14,415.27
900(1)c4 Reinforced Concrete (Column) 7,295.52 32,656.00 1,933.55
900 ( 1 )c6 Reinforced Concrete (RB-1 & RB-2) 8,337.74 11,084.07 3,585.77
902(1) Reinforcing Steel(Deformed) 33,762.62 182,938.40 17,877.63
1044(1) Forms and Falseworks 30,856.44 101,439.80 3,085.64
PART C FINISHING
1043(2) a CHB Non Load Bearing Wall - 100mm 7,570.58 16,826.85 757.06
1043(2) b CHB Non Load Bearing Wall - 125mm 30,856.44 68,493.52 3,085.64
1027(1) Cement Plaster Finish 114,417.78 53,650.00 11,441.78
1047(3) Structural Steel, furnished, and fabricated - Purlins 5,730.48 43,675.00 4,410.85
1047(2) Structural Steel, furnished, fabricated, and erected - Tr 9,012.59 86,470.00 13,662.96
1003(1) a1 Ceiling (4.5mm Fiber Cement Board) 7,504.74 51,900.00 750.47
1008 (1) Aluminum Glass Windows/Doors 11,243.83 108,000.00 1,124.38
1010(2)b Doors (Wood Panel) 2,051.03 37,800.00 205.10
1013(1) Metal Roofing - Prepainted Long Span 27,758.79 140,739.20 2,775.88
1018(1) Tiles and Trims (Toilet) 7,947.74 29,155.00 794.77
1018(2) Tiles - Vitrified Floor Tile (main flr.) 18,595.83 161,500.00 1,859.58
1032(1)a1 Painting Works - Masonry and Fiber Cement Painting 20,627.39 71,760.00 5,362.74
1035(1) Furring Channel-Double Furring System 8,753.71 51,260.00 875.37
1001 (1) a Pipe - 50mm diameter PVC 769.14 2,960.00 76.91
1001 (1) a3 Pipe - 100mm diameter PVC 256.38 4,240.00 25.64
1001 (1) a2 Pipe - 75mm diameter PVC 1,794.65 9,330.00 179.47
1002 (5) a1 Polyprophylene Random Copolymer (PPR-C) Pipes - 1/ 2,641.14 8,575.00 264.11
1002(9) Water Closet 992.11 12,000.00 99.21
1002(5)f1 Lavatory, Wall Hung. Complete 704.31 7,000.00 70.43
1002(12) Tissue Holder 185.23 500.00 18.52
1002(13) Stainless Kitchen Sink 1,481.85 4,000.00 148.19
1201 (4)d Valves and Fittings 185.23 320.00 18.52
1201(4)e Floor Drain 185.23 560.00 18.52
PART D ELECTRICAL
1100(7)f1 Polyvinyl Chloride Pipes (PVC)-20mm 7,094.15 9,500.00 709.41
1100(14) Octagonal Junction Box metal 880.38 2,208.00 88.04
1100(15) Utility Boxes metal 704.31 1,904.00 70.43
1101(1)a2 Electrical Wire - 3.5mm TWG/THHN 2,884.03 14,400.00 288.40
1101(1)a3 Electrical Wire - 5.5mm TWG/THHN 132.37 5,655.00 13.24
1101(1)a4 Electrical Wire - 10.0mm TWG/THHN 92.21 1,405.00 9.22
1101(3) Tumbler Switch 922.14 880.00 92.21
1101(6) Duplex Convenience Receptacles 3,319.70 4,756.00 331.97
1102(1)b Panelboard Circuit Breaker Type - LPA Flush Mounted 3,269.06 11,050.00 326.91
1103(1)a1 Compact Flourescent Lamp (CFL) 2,307.41 3,520.00 230.74
1200(4)A7 Package Type Airconditioning Unit (PACU)-Ceiling Moun 6,153.09 160,000.00 615.31
TOTAL P 447,622.47 P 1,695,612.54 P 97,480.12

Total Project Cost =


(3 .5% ) Engineering Overhead Cost =
APPROPRIATION =
Contingencies=
MARK UP VAT TOTAL COST QUANTITY UNIT DURATION UNIT COST

1,080.87 270.22 5,674.57 1.00 l.s. 8.00 5,674.57


1,392.76 766.02 16,086.38 4.00 month 960.00 4,021.59

10,256.53 2,564.13 53,846.78 75.00 cu.m. 75.00 717.96


6,548.77 1,637.19 34,381.05 33.73 cu.m. 14.00 1,019.30
1,270.02 317.51 6,667.61 75.00 cu.m. 12.00 88.90

42,372.49 10,593.12 222,455.57 46.80 cu.m. 19.00 4,753.32


10,471.27 2,617.82 54,974.16 10.40 cu.m. 14.00 5,285.98
5,751.90 1,437.97 30,197.46 10.02 cu.m. 16.00 3,013.72
58,644.66 14,661.17 307,884.48 9,818.80 kgs. 54.00 31.36
33,845.47 8,461.37 177,688.72 1.00 l.s. 70.00 177,688.72

6,288.62 1,572.16 33,015.26 67.00 sq.m. 21.00 492.77


25,608.90 6,402.23 134,446.73 222.00 sq.m. 70.00 605.62
44,877.39 11,219.35 235,606.29 550.00 sq.m. 183.00 428.38
13,454.08 3,363.52 70,633.94 849.50 kgs. 13.00 83.15
27,286.39 6,821.60 143,253.54 1,727.50 kgs. 25.00 82.93
15,038.80 3,759.70 78,953.72 266.00 sq.m. 20.00 296.82
30,092.05 7,523.01 157,983.28 37.20 sq.m. 52.00 4,246.86
10,014.03 2,503.51 52,573.67 7.56 sq.m. 8.00 6,954.19
42,818.47 10,704.62 224,796.95 291.20 sq.m 77.00 771.97
9,474.38 2,368.59 49,740.49 34.30 sq.m. 31.00 1,450.16
45,488.85 11,372.21 238,816.48 190.00 sq.m. 42.00 1,256.93
24,437.53 6,109.38 128,297.05 550.00 sq.m. 44.00 233.27
15,222.27 3,805.57 79,916.92 266.00 ln.m. 26.00 300.44
951.51 237.88 4,995.44 20.00 ln.m. 3.00 249.77
1,130.50 282.63 5,935.15 8.00 ln.m. 1.00 741.89
2,826.03 706.51 14,836.65 42.00 ln.m. 7.00 353.25
2,870.06 717.52 15,067.84 50.00 pcs. 15.00 301.36
3,272.83 818.21 17,182.36 2.00 set 8.00 8,591.18
1,943.68 485.92 10,204.34 2.00 sets 4.00 5,102.17
175.94 43.98 923.68 2.00 pcs. 1.00 461.84
1,407.51 351.88 7,389.42 1.00 pc. 8.00 7,389.42
130.94 32.73 687.43 1.00 pcs. 1.00 687.43
190.94 47.73 1,002.43 2.00 pcs. 1.00 501.21
0
4,325.89 1,081.47 22,710.93 300.00 meters 23.00 75.70
0.30 992.33 4,169.05 32.00 pcs. 5.00 130.28
669.68 167.42 3,515.84 28.00 pcs. 4.00 125.57
4,393.11 1,098.28 23,063.82 4.00 roll 8.00 5,765.95
1,450.15 362.54 7,613.29 1.00 roll 1.00 7,613.29
376.61 94.15 1,977.20 20.00 meter 1.00 98.86
473.59 118.40 2,486.34 6.00 set 5.00 414.39
2,101.92 525.48 11,035.06 23.00 set 18.00 479.79
3,661.49 915.37 19,222.83 1.00 set 16.00 19,222.83
1,514.54 378.63 7,951.32 9.00 sets 9.00 883.48
- 8,338.42 175,106.82 4.00 sets 24.00 43,776.70
P 515,603.74 P 138,649.44 P 2,894,968.31

P 2,894,968.31
105,000.00
P 3,000,000.00
31.69
5,674.57 -
16,086.38 -
0 0
53,846.78 -
34,381.05 -
6,667.61 -
0 0
222,455.57 -
54,974.16 -
30,197.46 -
307,884.48 -
177,688.72 -
0 0
33,015.26 -
134,446.73 -
235,606.29 -
70,633.94 -
143,253.54 -
78,953.72 -
157,983.28 -
52,573.67 -
224,796.95 -
49,740.49 -
238,816.48 -
128,297.05 -
79,916.92 -
4,995.44 -
5,935.15 -
14,836.65 -
15,067.84 -
17,182.36 -
10,204.34 -
923.68 -
7,389.42 -
687.43 -
1,002.43 -
0 0
22,710.93 -
4,169.05 -
3,515.84 -
23,063.82 -
7,613.29 -
1,977.20 -
2,486.34 -
11,035.06 -
19,222.83 -
7,951.32 -
175,106.82 -

2,894,968.31

OK PRE!

3,000,000.00
-
ITEM 1100(7)f1 : Polyvinyl Chloride Pipes (PVC)-20mm
Unit of Measurement= meters Quantity= 300.00
Output= 40.5 ln.m./hr. Duration= 22.22
Say 23.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 23 71.95
Skilled 3 23 52.06
Unskilled 2 23 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost 1 23
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
20mm diameter PVC Pipe meters 300 31.67
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1100(14) : Octagonal Junction Box metal


Unit of Measurement= pcs. Quantity= 32.00
Output= 7 pcs./hr. Duration= 4.57
Say 5.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 5 71.95
Skilled 2 5 52.06
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost 1 5
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
4x4 Octagonal Junction Box pcs. 32 33.00
PVC Adapter pcs. 128 9.00
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
ITEM 1100(15) : Utility Boxes metal
Unit of Measurement= pcs. Quantity= 28.00
Output= 7 pcs./hr. Duration= 4.00
Say 4.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 4 71.95
Skilled 2 4 52.06
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools
10% of Labor Cost 1 4
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:

2x4 Utility Box pcs. 28 32.00


PVC Adapter pcs. 112 9.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1101(1)a2 : Electrical Wire - 3.5mm TWG/THHN


Unit of Measurement= roll Quantity= 4.00
Output= 75 lm./hr. Duration= 8.00
Say 8.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 8 71.95
Skilled 4 8 52.06
Unskilled 2 8 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1 100
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
3.5mm THHN Wire rolls 4 3,600.00
Electrical Tape pcs 4 35.00
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
ITEM 1101(1)a3 : Electrical Wire - 5.5mm TWG/THHN
Unit of Measurement= roll Quantity= 1.00
Output= 18.75 lm./hr. Duration= 0.05
Say 1.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:

Skilled 1 1 52.06
Unskilled 1 2 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1 100
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
5.5mm THHN Wire rolls 1.00 5,550.00
Electrical Tape pcs 3 35.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1101(1)a4 : Electrical Wire - 10.0mm TWG/THHN


Unit of Measurement= meter Quantity= 20.00
Output= 18.75 lm./hr. Duration= 1.07
Say 1.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Skilled 1 1 52.06
Unskilled 1 1 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1 100
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
8.0mm THHN Wire meters 20.00 65.00
Electrical Tape pcs 3 35.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1101(3) : Tumbler Switch


Unit of Measurement= set Quantity= 6.00
Output= 1.25 set/hr. Duration= 4.80
Say 5.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Skilled 2 5 52.06
Unskilled 2 5 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1

Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
Tumbler Switch Two-Gang set 1.00 130.00
Tumbler Switch One-Gang set 5.00 150.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1101(6) : Duplex Convenience Receptacles


Unit of Measurement= set Quantity= 23.00
Output= 1.25 set/hr. Duration= 18.40
Say 18.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Skilled 2 18 52.06
Unskilled 2 18 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
Duplex Convenience Outlet set 18.00 167.00
ACU outlet set 5.00 350.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1102(1)b : Panelboard Circuit Breaker Type - LPA Flush Mounted, NEMA 1 Enclosure
Unit of Measurement= set Quantity= 1.00
Output= Duration= 16.00
Say

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 16 71.95
Skilled 1 16 52.06
Unskilled 2 16 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:

Minor Tools 10% of Labor Cost 1

Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:

60AMP Bolt-on Type Main Circuit Breaker (Koten) set 1.00 550.00
15AMP Bolt-on Type Branch Circuit Breaker (Koten) set 3.00 450.00
20AMP Bolt-on Type Main Circuit Breaker (Koten) set 2.00 450.00
30AMP Bolt-on Type Main Circuit Breaker (Koten) set 5.00 450.00
Panel Board Cabinet (Flush Type) set 1.00 6,000.00
14-Knock Out Holes , 12-Branches and 1-Main,
grounding terninal, neutral bus bar
32mm.0 Entrance cap set 1.00 100.00
32mm.0 RSC elbow set 3.00 95.00
32mm.0 RSC coupling set 3.00 50.00
32mm.0 Rigid steel conduit set 2.00 500.00

Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
ITEM 1103(1)a1 : Compact Flourescent Lamp (CFL)
Unit of Measurement= sets Quantity= 9.00
Output= 1.0 set/hr. Duration= 9.00
Say 9.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:

Foreman 1 9 71.95
Skilled 2 9 52.06
Unskilled 2 9 40.15

Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:

Minor Tools 10% of Labor Cost 1 100

Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:

2-40 Watts Compact Flourescent Lamp (CFL) sets 24.00 110.00


2-20 Watts Compact Flourescent Lamp (CFL) sets 8.00 110.00

Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
ITEM 1200(4)A7 : Package Type Airconditioning Unit (PACU)-Ceiling Mounted Inverter
Unit of Measurement= sets Quantity= 4.00
Output= set/hr. Duration= 24.00
Say 24.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:

Foreman 1 24 71.95
Skilled 2 24 52.06
Unskilled 2 24 40.15

Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:

Minor Tools 10% of Labor Cost 1 100

Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:

Air Conditioner Inverter Type 2.0hp 220V (Ceiling


mounted, split) sets 4.00 40,000.00

Sub-Total for 3
Direct Cost
OCM/CP
VAT 5%
ITEM COST
TOTAL UNIT COST
hours
hours

Amount

1,654.88
3,592.31
1,846.96
P 7,094.15

Amount

709.41
P 709.41

Amount

9,500.00
P 9,500.00
P 17,303.56
P 4,325.89
P 1,081.47
P 22,710.93
P 75.70

hours
hours

Amount

359.76
520.63
P 880.38

Amount

88.04
P 88.04

Amount

1,056.00
1,152.00
P 2,208.00
P 3,176.42
P 794.10
P 198.53
P 4,169.05
P 130.28
hours
hours

Amount

287.81
416.50
P 704.31

Amount

70.43
P 70.43

Amount

896.00
1,008.00
P 1,904.00

P 2,678.74
P 669.68
P 167.42
P 3,515.84
P 125.57

hours
hours

Amount

575.61
1,666.00
642.42
P 2,884.03

Amount

288.40
P 288.40

Amount

14,400.00
140.00
P 14,400.00
P 17,572.43
P 4,393.11
P 1,098.28
P 23,063.82
P 5,765.95

hours
hours

Amount

52.06
80.30
P 132.37

Amount

13.24
P 13.24

Amount

5,550.00
105.00
P 5,655.00

P 5,800.60
P 1,450.15
P 362.54
P 7,613.29
P 7,613.29

hours
hours

Amount

52.06
40.15
P 92.21

Amount

9.22
P 9.22

Amount

1,300.00
105.00
P 1,405.00

P 1,506.44
P 376.61
P 94.15
P 1,977.20
P 98.86

hours
hours

Amount

520.63
401.51
P 922.14

Amount

92.21

P 92.21

Amount

130.00
750.00
P 880.00

P 1,894.35
P 473.59
P 118.40
P 2,486.34
P 414.39

hours
hours

Amount

1,874.25
1,445.45
P 3,319.70

Amount

331.97
P 331.97

Amount

3,006.00
1,750.00
P 4,756.00

P 8,407.66
P 2,101.92
P 525.48
P 11,035.06
P 479.79

hours
hours

Amount

1,151.22
833.00
1,284.84
P 3,269.06

Amount

326.91

P 326.91

Amount

550.00
1,350.00
900.00
2,250.00
6,000.00

100.00
285.00
150.00
1,000.00

P 11,050.00
P 14,645.97
P 3,661.49
P 915.37
P 19,222.83
P 19,222.83
hours
hours

Amount

647.56
937.13
722.72

P 2,307.41

Amount

230.74

P 230.74

Amount

2,640.00
880.00

P 3,520.00
P 6,058.15
P 1,514.54
P 378.63
P 7,951.32
P 883.48
hours
hours

Amount

1,726.83
2,499.00
1,927.26

P 6,153.09

Amount

615.31

P 615.31

Amount

160,000.00

P 160,000.00
P 166,768.40
P -
P 8,338.42
P 175,106.82
P 43,776.70
Name of Project: CONSTRUCTION OF SENIOR CITIZEN'S BLDG.
Location: BANGUED, ABRA
DETAILED UNIT PRICE ANALYSIS
ITEM B.5 : Project Billboard / Signboard
Unit of Measurement= l.s. Quantity= 1.00
Output= Duration= 8.00 hours
Say 8.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Skilled 1 8 52.06 416.50
Unskilled 1 8 40.15 321.21
Sub-Total for 1 P 737.71
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools 10% of Labor Cost 1 73.77
Sub-Total for 2 P 73.77
Name and Specification Unit Quantity Unit Cost Amount
2. Materials:
A. For DPWH Standard Billboard:
Computer generated tarpaulin signs sq.ft. 32 50.00 1,600.00
Lumber bd.ft. 36 42.00 1,512.00
Common Nails Assorted kg. 1 80.00 80.00
1/4" Ordinary Plywood pcs. 1 320.00 320.00
Sub-Total for 3 P 3,512.00
Direct Cost P 4,323.48
OCM/CP 25% P 1,080.87
VAT 5% P 270.22
ITEM COST P 5,674.57
TOTAL UNIT COST P 5,674.57

ITEM B.7 : Occupational Safety and Health Program


Unit of Measurement= month Quantity= 4.00
Output= Duration= 960.00 man-days
Designation No. of Person No. of Hours Hourly Rate Amount
1. Labor:
Safety Officer (Part Time) 1 64 52.06 3,332.00
Sub-Total for 1 P 3,332.00
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools 10% of Labor Cost 1 333.20
Sub-Total for 2 P 333.20

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
A. Personal Protective Equipment (PPE)
Safety Shoes man-days 960 7.67 7,363.20
Safety Helmet man-days 960 0.25 240.00
Safety Gloves man-days 960 2.77 2,659.20
Sub-Total for 3 P 10,262.40
Direct Cost P 13,927.60
OCM/CP 10% P 1,392.76
VAT 5% P 766.02
ITEM COST P 16,086.38

Page 40
TOTAL UNIT COST P 4,021.59

Page 41
ITEM 803 (1) a : Structure Excavation
Unit of Measurement= cu.m. Quantity= 75.00
Output= 1 cu.m./hr. Duration= 75.00 hours
Say 75.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 75 71.95 5,396.34
Skilled 2 75 52.06 7,809.38
Laborer 8 75 40.15 24,090.75
Sub-Total for 1 P 37,296.47

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 1.00 3,729.65
Sub-Total for 2 P 3,729.65

Name and Specification Unit Quantity Unit Cost Amount


3. Materials:

Sub-Total for 3 P -

Direct Cost P 41,026.12


OCM/CP 25% P 10,256.53
VAT 5% P 2,564.13
ITEM COST P 53,846.78
TOTAL UNIT COST P 717.96

ITEM 803 (4) : Gravel Fill


Unit of Measurement= cu.m. Quantity= 33.73
Output= 2.365 cu.m./hr. Duration= 14.26 hours
Say 14.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 14 71.95 1,007.32
Skilled 1 14 52.06 728.88
Unskilled 6 14 40.15 3,372.71
Sub-Total for 1 P 5,108.90

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 1 510.89
Sub-Total for 2 P 510.89

Name and Specification Unit Quantity Unit Cost Amount

3. Materials:
3/4 Gravel cu.m. 33.73 610.00 20,575.30
Sub-Total for 3 P 20,575.30
Direct Cost P 26,195.09
OCM/CP 25% P 6,548.77
VAT 5% P 1,637.19
ITEM COST P 34,381.05
TOTAL UNIT COST P 1,019.30

Page 42
Page 43
ITEM 804 (1) a : Embankment
Unit of Measurement= cu.m. Quantity= 75.00
Output= 6.225 cu.m./hr. Duration= 12.05 hours
Say 12.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 6 71.95 431.71
Skilled 2 6 52.06 624.75
Unskilled 6 12 40.15 2,890.89
Sub-Total for 1 P 3,947.35

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 1 394.73
Plate Compactor 1 6 123.00 738.00
Sub-Total for 2 P 1,132.73

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
Additional Common Borrow cu.m. 200.00 -

Sub-Total for 3 P -

Direct Cost P 5,080.08


OCM/CP 25% P 1,270.02
VAT 5% P 317.51
ITEM COST P 6,667.61
TOTAL UNIT COST P 88.90

ITEM 900(1)c2 : Reinforced Concrete (Footing, WF and Slab on Fill)


Unit of Measurement= cu.m. Quantity= 46.80
Output= 2.49 cu.m./hr. Duration= 18.80 hours
Say 19.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 19 71.95 1,367.07
Skilled 2 19 52.06 1,978.38
Unskilled 6 19 40.15 4,577.24
Sub-Total for 1 P 7,922.69

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
One Bager Mixer 1 19 172.00 3,268.00
Concrete Vibrator 1 19 545.00 10,355.00
Minor Tools 10% of Labor Cost 1 792.27
Sub-Total for 2 P 14,415.27

Page 44
Page 45
Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
40 Kgs. Portland Cement bags 422.00 250.00 105,500.00
Washed Sand cu.m. 23.40 560.00 13,104.00
Washed Gravel cu.m. 46.80 610.00 28,548.00
Sub-Total for 3 P 147,152.00

Direct Cost P 169,489.96


OCM/CP 25% P 42,372.49
VAT 5% P 10,593.12
ITEM COST P 222,455.57
TOTAL UNIT COST P 4,753.32

ITEM 900(1)c4 : Reinforced Concrete (Column)


Unit of Measurement= cu.m. Quantity= 10.40
Output= 0.765 cu.m./hr. Duration= 13.59 hours
Say 14.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 14 71.95 1,007.32
Skilled 4 14 52.06 2,915.50
Unskilled 6 14 40.15 3,372.71
Sub-Total for 1 P 7,295.52

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
One Bager Mixer 1 7 172.00 1,204.00
Minor Tools 10% of Labor Cost 1 729.55
Sub-Total for 2 P 1,933.55

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
40 Kgs. Portland Cement bags 93.60 250.00 23,400.00
Washed Sand cu.m. 5.20 560.00 2,912.00
Washed Gravel cu.m. 10.40 610.00 6,344.00
Sub-Total for 3 P 32,656.00

Direct Cost P 41,885.07


OCM/CP 25% P 10,471.27
VAT 5% P 2,617.82
ITEM COST P 54,974.16
TOTAL UNIT COST P 5,285.98

ITEM 900 ( 1 )c6 : Reinforced Concrete (RB-1 & RB-2)


Unit of Measurement= cu.m. Quantity= 10.02
Output= 0.656 cu.m./hr. Duration= 15.27 hours
Say 16.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 16 71.95 1,151.22
Skilled 4 16 52.06 3,332.00
Unskilled 6 16 40.15 3,854.52
Sub-Total for 1 P 8,337.74

Page 46
Page 47
Name and Capacity No. of Units No. of Hours Hourly Rate Amount

Minor Tools 10% of Labor Cost 1 833.77


One Bager Mixer 1 16 172.00 2,752.00
Sub-Total for 2 P 3,585.77

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:

a. Second Floor Beam cu.m. 15.36


40 Kgs. Portland Cement bags 140.00 71.95 10,073.18
Washed Sand cu.m. 7.64 52.06 397.61
Washed Gravel cu.m. 15.27 40.15 613.29
Sub-Total for 3 P 11,084.07

Direct Cost P 23,007.59


OCM/CP 25% P 5,751.90
VAT 5% P 1,437.97
ITEM COST P 30,197.46
TOTAL UNIT COST P 3,013.72

ITEM 1003(1) a1 : Ceiling (4.5mm Fiber Cement Board)


Unit of Measurement= sq.m. Quantity= 266.00
Output= 5.1 Duration= 20.00 hours
Say 20.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 16 71.95 1,151.22
Skilled 3 16 52.06 2,499.00
Unskilled 6 16 40.15 3,854.52
Sub-Total for 1 P 7,504.74

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 1 20 750.47 750.47

Sub-Total for 2 P 750.47

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
4.5mm thick Fiber Cement Board pcs. 102 400.00 40,800.00
1'x2' PPGI Air vent pcs. 12 500.00 6,000.00
1" Metal Black Screw pcs. 5,100 1.00 5,100.00
Sub-Total for 3 P 51,900.00

Direct Cost P 60,155.21


OCM/CP 25% P 15,038.80
VAT 5% P 3,759.70
ITEM COST P 78,953.72
TOTAL UNIT COST P 296.82

Page 48
Page 49
ITEM 1008 (1) : Aluminum Glass Windows/Doors
Unit of Measurement= sq.m. Quantity= 37.20
Output= 0.72 sq.m./hr. Duration= 51.67 hours
Say 52.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 52 71.95 3,741.47
Skilled 2 52 52.06 5,414.50
Unskilled 1 52 40.15 2,087.87
Sub-Total for 1 P 11,243.83

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 1 52 1,124.38 1,124.38
Sub-Total for 2 P 1,124.38

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
Aluminum framed Sliding Doors & Window
(Powder Coated) with 6mm thk bronze glass and sq.m. 27.60 2,800.00 77,280.00
Insect Screen

Aluminum framed Swing Doors & Window


(Powder Coated) with 6mm thk bronze glass and sq.m. 9.60 3,200.00 30,720.00
8 Insect Screen
Sub-Total for 3 P 108,000.00

Direct Cost P 120,368.21


OCM/CP 25% P 30,092.05
VAT 5% P 7,523.01
ITEM COST P 157,983.28
TOTAL UNIT COST P 4,246.86

ITEM 1010(2)b : Doors (Wood Panel)


Unit of Measurement= sq.m. Quantity= 7.56
Output= 0.4726 sq.m./man.hr. Duration= 8.00 hours
Say 8.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 8 71.95 575.61
Skilled 2 8 52.06 833.00
Unskilled 2 8 40.15 642.42
Sub-Total for 1 P 2,051.03

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 205.10
Sub-Total for 2 P 205.10

Page 50
Page 51
Name and Specification Unit Quantity Unit Cost Amount

2. Materials:

D1- 0.90x2.10 m.Mahogany Panel door on 50x150mm.thk


8 Mahogany jamb w/ complete accessories sq.m. 7.56 5,000.00 37,800.00

note: complete set (with 75x200m door jamb, hinges,barrel bolt,


dead bolt,door knob and paint finished) see detail

Sub-Total for 3 P 37,800.00

Direct Cost P 40,056.13


OCM/CP 25% P 10,014.03
VAT 5% P 2,503.51
ITEM COST P 52,573.67
TOTAL UNIT COST P 6,954.19

ITEM 1013(1) : Metal Roofing - Prepainted Long Span


Unit of Measurement= sq.m Quantity= 291.20
Output= 4.15 sq.m./hr. Duration= 76.49 hours
Gutter/Flashing/Ridgeroll= 21.25 ln.m./hr. Say 77.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 77 71.95 5,540.25
Skilled 4 77 52.06 16,035.25
Unskilled 2 77 40.15 6,183.29
Sub-Total for 1 P 27,758.79

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 1 76 2,775.88 2,775.88
Sub-Total for 2 P 2,775.88

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:

Gauge 26 Pre-painted Rib-type PPGI Sheet(Long Span) ln.m. 299.00 370.00 110,630.00
Gauge 24 Pre-painted Ridge Roll ln.m. 22.60 168.00 3,796.80
Gauge 24 Pre-painted End Flassing(2.44m) ln.m. 26.80 168.00 4,502.40
Gauge 24 Pre-painted Gutter (2.44m) ln.m. 45.00 168.00 7,560.00
2"Self Drilling Screw (Tekscrew) pcs. 3,500.00 2.50 8,750.00
5/32" Blind rivets boxes 4.00 800.00 3,200.00
Touch-up paint lit. 2.00 150.00 300.00
Roof Sealant lit. 5 400.00 2,000.00
Sub-Total for 3 P 140,739.20

Direct Cost P 171,273.87


OCM/CP 25% P 42,818.47
VAT 5% P 10,704.62
ITEM COST P 224,796.95
TOTAL UNIT COST P 771.97

Page 52
Page 53
ITEM 1018(1) : Tiles and Trims (Toilet)
Unit of Measurement= sq.m. Quantity= 34.30
Output= 1.12 sq.m./hr. Duration= 30.63 hours
Say 31.00 hours
Designation No. of Person No. of Hours Hourly Rate Amount
1. Labor:
Foreman 1 31 71.95 2,230.49
Skilled 2 31 52.06 3,227.88
Unskilled 2 31 40.15 2,489.38
Sub-Total for 1 P 7,947.74

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools-10% of Labor Cost 1 31 794.77 794.77
Sub-Total for 2 P 794.77

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
300x300mm Tiles sq.m. 34.30 850.00 29,155.00
note: with tile trim, adhesive and tile grout and cement
base
Sub-Total for 3 P 29,155.00

Direct Cost P 37,897.52


OCM/CP 25% P 9,474.38
VAT 5% P 2,368.59
ITEM COST P 49,740.49
TOTAL UNIT COST P 1,450.16

ITEM 1018(2) : Tiles - Vitrified Floor Tile (main flr.)


Unit of Measurement= sq.m. Quantity= 190.00
Output= 4.5 sq.m./hr. Duration= 42.22 hours
Say 42.00 hours
Designation No. of Person No. of Hours Hourly Rate Amount
1. Labor:
Foreman 1 42 71.95 3,021.95
Skilled 4 42 52.06 8,792.78
Unskilled 4 42 40.15 6,781.10
Sub-Total for 1 P 18,595.83
Name and Capacity No. of Units No. of Hours Hourly Rate Amount
2. Equipment:
Minor Tools 10% of Labor Cost 1 42 1,859.58 1,859.58
Sub-Total for 2 P 1,859.58
Name and Specification Unit Quantity Unit Cost Amount
2. Materials:
600x600mm Vitrified Tiles sq.m. 190.00 850.00 161,500.00
note: with tile trim, adhesive and tile grout and cement
base
Sub-Total for 3 P 161,500.00

Direct Cost P 181,955.41


OCM/CP 25% P 45,488.85
VAT 5% P 11,372.21
ITEM COST P 238,816.48
TOTAL UNIT COST P 1,256.93
Page 54
Page 55
ITEM 1027(1) : Cement Plaster Finish
Unit of Measurement= sq.m. Quantity= 550.00
Output= 3 sq.m./hr. Duration= 183.33 hours
Say 183.00 hours
Designation No. of Person No. of Hours Hourly Rate Amount
1. Labor:
Foreman 1 183 71.95 13,167.08
Skilled 6 183 52.06 57,164.63
Unskilled 6 183 40.15 44,086.07
Sub-Total for 1 P 114,417.78

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools
10% of Labor Cost 1 183 11,441.78 11,441.78
Sub-Total for 2 P 11,441.78

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:

40 kg. Cement bags 181.00 250.00 45,250.00


Fine sand cu.m. 15.00 560.00 8,400.00
note:(16mm thick plaster average)
Sub-Total for 3 P 53,650.00

Direct Cost P 179,509.55


OCM/CP 25% P 44,877.39
VAT 5% P 11,219.35
ITEM COST P 235,606.29
TOTAL UNIT COST P 428.38

ITEM 1032(1)a1 : Painting Works - Masonry and Fiber Cement Painting


Unit of Measurement= sq.m. Quantity= 550.00
Output= 12.5478 sq.m./hr. Duration= 43.83 hours
Say 44.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 22 71.95 1,582.93
Skilled 6 44 52.06 13,744.50
Unskilled 3 44 40.15 5,299.97
Sub-Total for 1 P 20,627.39

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Steel Scaffoldings w/ Flatform 12 22.00 12.50 3,300.00
Minor Tools 10% of Labor Cost 1 2,062.74
Sub-Total for 2 P 5,362.74

Page 56
Page 57
Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
Concrete Surface: Sq.m. 550.0
Concrete Neutralizer Gal. 24.00 420.00 10,080.00
Patching compoud Gal. 18.00 320.00 5,760.00
Flat Latex Primer Gal. 24.00 500.00 12,000.00
Semi-Gloss Latex Gal. 21.00 520.00 10,920.00
Latex Tinting colors pint 6.00 100.00 600.00
Ceiling Surface: Sq.m. 266.00
Glazing Putty Gal. 11.00 420.00 4,620.00
Flat Wall Enamel Gal. 11.00 580.00 6,380.00
Enamel Quick Dry Gal. 14.00 580.00 8,120.00
Paint Thinner pint 4.00 300.00 1,200.00
Tinting Color pint 4.00 100.00 400.00
9" Roller brush Pcs. 10.00 55.00 550.00
Pan Pcs. 6.00 95.00 570.00
Pallet knives Pcs. 6.00 50.00 300.00
4" Paint brush Pcs. 6.00 85.00 510.00
#80 3M Sand paper Ft. 150.00 65.00 9,750.00
Sub-Total for 3 P 71,760.00
Direct Cost P 97,750.13
OCM/CP 25% P 24,437.53
VAT 5% P 6,109.38
ITEM COST P 128,297.05
TOTAL UNIT COST P 233.27

ITEM 1035(1) : Furring Channel-Double Furring System


Unit of Measurement= ln.m. Quantity= 266.00
Output= 10.5 Duration= 25.33 hours
Say 26.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 26 71.95 1,870.73
Skilled 2 26 52.06 2,707.25
Unskilled 4 26 40.15 4,175.73
Sub-Total for 1 P 8,753.71

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools
10% of Labor Cost 1 26 875.37
Sub-Total for 2 P 875.37

Page 58
Page 59
Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
L20x20 Wall Angle (2.44m) pcs. 92 80.00 7,360.00
Double Metal Furring (5.0m) pcs. 112 170.00 19,040.00
Carrying Channel (5.0m) pcs. 51 165.00 8,415.00
1" self tapping screw pcs. 5,451 1.00 5,451.00
1/8"x1" Tox with screw pcs. 332 2.00 664.00
1/8x1/2" Blind Rivets box 4 600.00 2,400.00
W-Clip pcs. 462 15.00 6,930.00
Consumables (drill bit,screw bit,riveter,c-clamp etc.) lot 1 1,000.00 1,000.00
Sub-Total for 3 P 51,260.00
Direct Cost P 60,889.08
OCM/CP 25% P 15,222.27
VAT 5% P 3,805.57
ITEM COST P 79,916.92
TOTAL UNIT COST P 300.44

ITEM 1043(2) a : CHB Non Load Bearing Wall - 100mm


Unit of Measurement= sq.m. Quantity= 67.00
Output= 3.1875 sq.m./hr. Duration= 21.02 hours
Say 21.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 21 71.95 1,510.98
Skilled 4 21 52.06 4,373.25
Unskilled 2 21 40.15 1,686.35
Sub-Total for 1 P 7,570.58

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools
10% of Labor Cost 1 21 757.06
Sub-Total for 2 P 757.06

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:

100mm thick CHB Non-load Bearing pcs. 879 10.00 8,793.75


40 kg. Cement bags 26 250.00 6,599.50
Fine Sand (Class C) cu.m. 3 560.00 1,433.60

Sub-Total for 3 P 16,826.85

Direct Cost P 25,154.49


OCM/CP 25% P 6,288.62
VAT 5% P 1,572.16
ITEM COST P 33,015.26
TOTAL UNIT COST P 492.77

Page 60
ITEM 1043(2) b : CHB Non Load Bearing Wall - 125mm
Unit of Measurement= sq.m. Quantity= 222.00
Output= 3.1875 sq.m./hr. Duration= 69.65 hours
Say 70.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 70 71.95 5,036.59
Skilled 4 70 52.06 14,577.50
Unskilled 4 70 40.15 11,242.35
Sub-Total for 1 P 30,856.44

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools
10% of Labor Cost 1 70 3,085.64
Sub-Total for 2 P 3,085.64

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
125mm thick CHB Non-load Bearing pcs. 2,914 12.00 34,965.00
40 kg. Cement bags 120 250.00 29,938.78
Fine Sand cu.m. 6 560.00 3,589.74

Sub-Total for 3 P 68,493.52

Direct Cost P 102,435.60


OCM/CP 25% P 25,608.90
VAT 5% P 6,402.23
ITEM COST P 134,446.73
TOTAL UNIT COST P 605.62
ITEM 1044(1) : Forms and Falseworks
Unit of Measurement= l.s. Quantity= 1
Output= Duration= 70.00 hours
Say 70.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 70 71.95 5,036.59
Skilled 4 70 52.06 14,577.50
Unskilled 4 70 40.15 11,242.35
Sub-Total for 1 P 30,856.44

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools
10% of Labor Cost 1 70 3,085.64
Sub-Total for 2 P 3,085.64

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
A. Formworks
1/2" Ordinary Plywood (4x8ft) - Two(2) Uses pcs. 28 620.00 17,360.00
Good Lumber (multiple uses) bd.ft. 1,862 42.00 78,199.80
Assorted Naills kgs 74 80.00 5,880.00
Page 61
Sub-Total for 3 P 101,439.80

Direct Cost P 135,381.88


OCM/CP 25% P 33,845.47
VAT 5% P 8,461.37
ITEM COST P 177,688.72
TOTAL UNIT COST P 177,688.72

Page 62
ITEM 902(1) : Reinforcing Steel(Deformed)
Unit of Measurement= kgs. Quantity= 9,818.80
Output= 179.5125 kgs./hr. Duration= 54.70 hours
Say 54.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 54 71.95 3,885.37
Skilled 6 54 52.06 16,868.25
Unskilled 6 54 40.15 13,009.01
Sub-Total for 1-Grade 40 P 33,762.62

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 5% of Labor Cost 1 675.25
Bar Cutter 1 14 219.75 2,966.63
Bar Bender 1 41 351.50 14,235.75
Cargo Truck 1 1,102.00 -
Sub-Total for 2 P 17,877.63

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
910 pcs-10mm diam. Reinforcing Steel bars kgs. 3,367.00 36.00 121,212.00
280 pcs-16mm diam. Reinforcing Steel bars kgs. 1,492.40 36.00 53,726.40
GI Wire #16 kgs. 100.00 80.00 8,000.00
Total kgs. 4,859.40
Sub-Total for 3 P 182,938.40

Direct Cost P 234,578.65


OCM/CP 25% P 58,644.66
VAT 5% P 14,661.17
ITEM COST P 307,884.48
TOTAL UNIT COST P 31.36

ITEM 1047(3) : Structural Steel, furnished, and fabricated - Purlins


Unit of Measurement= kgs. Quantity= 849.50
Output= 61.92 kgs./hr. Duration= 13.72 hours
Say 13.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 13 71.95 935.37
Skilled 4 13 52.06 2,707.25
Unskilled 4 13 40.15 2,087.87
Sub-Total for 1 P 5,730.48

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 1 573.05
Welding Machine 1 61.95 61.95 3,837.80
Cut-off Machine 1 4.00 30.00 120.00
Sub-Total for 2 P 4,410.85

Page 63
Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
90 pcs.1.0mm, 2x3" C-purlins kgs. 648.00 50.00 32,400.00
13 pcs. 1.0mm, 2x10" C-purlins kgs. 201.50 50.00 10,075.00
Red Lead Primer gal. 3 400.00 1,200.00
Welding Rod kgs. 43.00 110.00 4,730.00
Sub-Total for 3 P 43,675.00

Direct Cost P 53,816.33


OCM/CP 25% P 13,454.08
VAT 5% P 3,363.52
ITEM COST P 70,633.94
TOTAL UNIT COST P 83.15

ITEM 1047(2) : Structural Steel, furnished, fabricated, and erected - Truss


Unit of Measurement= kgs. Quantity= 1,727.50
Output= 68 kgs./hr. Duration= 25.40 hours
Say 25.00 hours

Designation No. of Person No. of Hours Hourly Rate Amount

1. Labor:
Foreman 1 25 71.95 1,798.78
Skilled 4 25 52.06 5,206.25
Unskilled 2 25 40.15 2,007.56
Sub-Total for 1 P 9,012.59

Name and Capacity No. of Units No. of Hours Hourly Rate Amount

2. Equipment:
Minor Tools 10% of Labor Cost 1 901.26
Welding Machine 1 206 61.95 12,761.70
Sub-Total for 2 P 13,662.96

Name and Specification Unit Quantity Unit Cost Amount

2. Materials:
80 pcs 3/16"x2x2 Angle Bar kgs. 1,240.00 40.00 49,600.00
25 pcs 3/16"x2x2 Angle Bar kgs. 287.50 40.00 11,500.00
10 mm.thk, Base plate kgs. 200.00 40.00 8,000.00
Welding Rod kgs. 87.00 110.00 9,570.00
Red Lead Primer gal. 8 400.00 3,200.00
Assorted Sizes Paint Brush l.s. 1 1000.00 1,000.00
16mmx450 A307 Anchor Bolt pc. 36 100.00 3,600.00
Sub-Total for 3 P 86,470.00

Direct Cost P 109,145.55


OCM/CP 25% P 27,286.39
VAT 5% P 6,821.60
ITEM COST P 143,253.54
TOTAL UNIT COST P 82.93

Page 64
ITEM 1001 (1) a : Pipe - 50mm diameter PVC
Unit of Measurement= ln.m. Quantity= 20.00
Output= 6.2625 ln.m./hr. Duration= 3.19
Say 3.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 3 71.95
Skilled 2 3 52.06
Unskilled 2 3 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
50mm PVC Pipe Series 600 ln.m. 20.00 100.00
63mm 90deg. PVC elbow pcs. 6.00 45.00
63mm Sanitary Tee pcs. 5.00 60.00
63mm P-Trap pcs. 2.00 120.00
Solvent Cement cc 100.00 1.50
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1001 (1) a3 : Pipe - 100mm diameter PVC


Unit of Measurement= ln.m. Quantity= 8.00
Output= 6.2625 ln.m./hr. Duration= 1.28
Say 1.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 1 71.95
Skilled 2 1 52.06
Unskilled 2 1 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Page 65
Name and Specification Unit Quantity Unit Cost

2. Materials:
100mm PVC Pipe Series 600 ln.m. 8.00 200.00
100mm PVC -90 deg. Elbow Series 600 pcs 2.00 95.00
100mm PVC -Santary Tee Series 600 pcs 4.00 195.00
100mmx50mm PVC -Tee Adapter Series 600 pcs 6.00 165.00
100mm Cleanout with Plug Series 600 pcs 4.00 95.00
Solvent Cement cc 200.00 1.50
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1001 (1) a2 : Pipe - 75mm diameter PVC


Unit of Measurement= ln.m. Quantity= 42.00
Output= 6.2625 ln.m./hr. Duration= 6.71
Say 7.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 7 71.95
Skilled 2 7 52.06
Unskilled 2 7 40.15
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
75mm PVC Pipe Series 600 ln.m. 42.00 165.00
75mm PVC 90 deg. elbow Series 600 pcs 30.00 70.00
Solvent Cement cc 200.00 1.50
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

Page 66
ITEM 1002 (5) a1 : Polyprophylene Random Copolymer (PPR-C) Pipes - 1/2" diam. PN10
Unit of Measurement= pcs. Quantity= 50.00
Output= 3.40 pc./hr. Duration= 14.80
Say 15.00
Designation No. of Person No. of Hours Hourly Rate
1. Labor:
Foreman 1 15.00 71.95
Skilled 2 15.00 52.06
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
PPR Pipes - 1/2"diam.x4.00m PN10 pcs. 50.00 100.00
1/2"0 Coupling pcs. 50.00 25.00
1/2"0 Elbow pcs. 20.00 30.00
1/2"0 Tee pcs. 8.00 35.00
1/2"0 male / female adaptor pcs. 7.00 165.00
1/2"0 Union paatente pcs. 1.00 80.00
1/2"x3" Nipple pcs. 7.00 30.00
Sub-Total for 3
Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST
ITEM 1002(9) : Water Closet
Unit of Measurement= set Quantity= 2.00
Output= 0.25 pc./hr. Duration= 8.00
Say
Designation No. of Person No. of Hours Hourly Rate
1. Labor:
Foreman 1 8 71.95
Skilled 1 8 52.06
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
Water Closet 1.6gpf Including Fittings with
accessories (Elongated) American Std. or sets 2.00 6,000.00
Equivalent
Sub-Total for 3

Direct Cost
OCM/CP 25%
Page 67
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1002(5)f1 : Lavatory, Wall Hung. Complete


Unit of Measurement= sets Quantity= 2.00
Output= 0.50 pc./hr. Duration= 4.00
Say 4.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 4 71.95
Skilled 2 4 52.06
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
Lavatory Including Fittings and Accessories
(American Std. or Equivalent) sets 2.00 3,500.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1002(12) : Tissue Holder


Unit of Measurement= pcs. Quantity= 2.00
Output= 2.00 pc./hr. Duration= 1.00
Say 1.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 1 71.95
Skilled 2 1 56.64
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
Ceramic Tissue Holder pcs. 2.00 250.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
Page 68
TOTAL UNIT COST

ITEM 1002(13) : Stainless Kitchen Sink


Unit of Measurement= pc. Quantity= 1.00
Output= 0.13 pc./hr. Duration= 8.00
Say 8.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 8 71.95
Skilled 2 8 56.64
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:

Stainless counter sink with Lever Type Faucet and pcs. 1.00 4,000.00
Stainless Drain
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1201 (4)d : Valves and Fittings


Unit of Measurement= pcs. Quantity= 1.00
Output= 2.00 pc./hr. Duration= 0.50
Say 1.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 1 71.95
Skilled 2 1 56.64
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
1/2" Gate Valve pcs. 1.00 320.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
Page 69
VAT 5%
ITEM COST
TOTAL UNIT COST

ITEM 1201(4)e : Floor Drain


Unit of Measurement= pcs. Quantity= 2.00
Output= 2.00 pc./hr. Duration= 1.00
Say 1.00

Designation No. of Person No. of Hours Hourly Rate

1. Labor:
Foreman 1 1 71.95
Skilled 2 1 56.64
Sub-Total for 1

Name and Capacity No. of Units No. of Hours Hourly Rate

2. Equipment:
Minor Tools 10% of Labor Cost 1
Sub-Total for 2

Name and Specification Unit Quantity Unit Cost

2. Materials:
4x4" Stainless Steel Floor Drain pcs. 2.00 280.00
Sub-Total for 3

Direct Cost
OCM/CP 25%
VAT 5%
ITEM COST
TOTAL UNIT COST

Page 70
hours
hours

Amount

215.85
312.38
240.91
P 769.14

Amount

76.91
P 76.91

Amount

2,000.00
270.00
300.00
240.00
150.00
P 2,960.00

P 3,806.05
P 951.51
P 237.88
P 4,995.44
P 249.77

hours
hours

Amount

71.95
104.13
80.30
P 256.38

Amount

25.64
P 25.64

Page 71
Amount

1,600.00
190.00
780.00
990.00
380.00
300.00
P 4,240.00

P 4,522.02
P 1,130.50
P 282.63
P 5,935.15
P 741.89

hours
hours

Amount

503.66
728.88
562.12
P 1,794.65

Amount

179.47
P 179.47

Amount

6,930.00
2,100.00
300.00
P 9,330.00

P 11,304.12
P 2,826.03
P 706.51
P 14,836.65
P 353.25

Page 72
hours
hours
Amount

1,079.27
1,561.88
P 2,641.14

Amount

264.11
P 264.11

Amount

5,000.00
1,250.00
600.00
280.00
1,155.00
80.00
210.00
P 8,575.00
P 11,480.26
P 2,870.06
P 717.52
P 15,067.84
P 301.36

hours
hours
Amount

575.61
416.50
P 992.11

Amount

99.21
P 99.21

Amount

12,000.00

P 12,000.00

P 13,091.32
P 3,272.83
Page 73
P 818.21
P 17,182.36
P 8,591.18

hours
hours

Amount

287.81
416.50
P 704.31

Amount

70.43
P 70.43

Amount

7,000.00
P 7,000.00

P 7,774.74
P 1,943.68
P 485.92
P 10,204.34
P 5,102.17

hours
hours

Amount

71.95
113.28
P 185.23

Amount

18.52
P 18.52

Amount

500.00
P 500.00

P 703.75
P 175.94
P 43.98
P 923.68
Page 74
P 461.84

hours
hours

Amount

575.61
906.24
P 1,481.85

Amount

148.19
P 148.19

Amount

4,000.00

P 4,000.00

P 5,630.04
P 1,407.51
P 351.88
P 7,389.42
P 7,389.42

hours
hours

Amount

71.95
113.28
P 185.23

Amount

18.52
P 18.52

Amount

320.00
P 320.00

P 523.75
P 130.94
Page 75
P 32.73
P 687.43
P 687.43

hours
hours

Amount

71.95
113.28
P 185.23

Amount

18.52
P 18.52

Amount

560.00
P 560.00

P 763.75
P 190.94
P 47.73
P 1,002.43
P 501.21

Page 76
I. HAULING COST OF FINE/COARSE AGGREGATES
HAULING DISTANCE = 5 KMS.

1 DUMPTRUCK WITH A CAPACITY OF 4 CU.M.


LOADING TIME = 5 MINS.
UNLOADING TIME = 1 MINS.
SLACK TIME = 6 MINS.
12 MINS.

LOADED TRIP = 5 KMS. X 60 MINS/HR = 20 MINS


15 KPH

UNLOADED TRIP = 5 KMS. X 60 MINS/HR = 15 MINS


20 KPH

TOTAL TIME = 47 MINS

NO OF HRS./TRIP = 47 = 0.78 HOURS


60 MINS./HR.

Equipment Rental:
1- Dumptruck 6-8 tons, 4 cu.m. P 807.00 /hour
P 6,456.00 /day

TOTAL COST PER TRIP = P 6,456.00 X 0.78 = P 839.28


6 HRS.
SAY P 839.00

HAULING COST PER CU.M. = P 839.00 = P 209.75 /CU.M.


4 SAY P 210.00 /CU.M.

FOR FINE AGGREGATES:


Pick-up price= P 350.00 /cu.m. (processed material)
Hauling cost= P 210.00
P 560.00
say 560.00

FOR COARSE AGGREGATES:


Pick-up price= P 400.00 /cu.m. (processed material)
Hauling cost= P 210.00
P 610.00
say 610.00

FOR Gravel pea:


Pick-up price= P 400.00 /cu.m. (processed material)
Hauling cost= P 210.00
P 610.00
say 610.00
II. PRODUCTION COST OF BOULDERS

PICKING & STOCK PILING FROM RIVER BED


LABOR CAPACITY= 2 CU.M./DAY
EMPLOYING 7 LABORERS= 14 CU.M./DAY
LABOR RATE ( P 194.70 X 7)= P 1,362.90 / DAY
PRODUCTION COST OF BOULDERS
PRODUCTION COST = P 1,362.90
14

= P 97.35 /CU.M.

II. HAULING COST OF BOULDERS


HAULING DISTANCE = 17 KMS.
USING 1 PAYLOADER
1 DUMPTRUCK WITH A CAPACITY OF 4 CU.M.

LOADING TIME = 5 MINS.

UNLOADING TIME = 1 MINS.


SLACK TIME = 2 MINS.
8 MINS.

LOADED TRIP = 17 KMS. X 60 MINS/H = 68 MINS


15 KPH

LOADED TRIP = 17 KMS. X 60 MINS/H = 51 MINS


20 KPH

TOTAL TIME = 127 MINS

NO OF HRS./TRIP = 127 = 2.12 HOURS


60 MINS./HR.

COST OF 1 DUMPTRUCK = P 5,672.00 X 2.12 = ###


8 HRS.

COST OF 1 PAYLOADER = P 6,648.00 X 5 = P 69.25


8 (60 MINS./HR)

TOTAL = ###

UNIT COST = P 1,572.33 + P 97.35 = P 490.43 /CU.M.


4 SAY P 490.00 /CU.M.

Quantity of conc.to be formed: #REF! Cu.m.


PAINTING ( 2-Coats )
Wall Area: 0 Sq.m.
Ceiling Area: 80 Sq.m.
Total Area: 80 Sq.m.
Duration: 1 C.D.
A. MATERIALS
Description of Material/sQuantity Unit
Boysen Flat La 0 Gal.
Boysen Quick 5 Gal.
Paint Thinner 10 Gal.
Concrete Neutr 0 Gal.
Sand paper 28 Pcs.
Concrete Putty 0 Lit.
Wood Paste fil 3 Lit.
Transhipment 0.5 Trip
Material cost
VAT
Mark-up

B. LABOR
Manpower NO. Rate/Day
Construction 1 P 277.30
Painter 3 P 209.90
Laborer 3 P 194.70
Labor Cost
VAT
Mark-up

Total Item Cost


Unit Cost
Total Adjusted Cost

PAINTING #REF! #REF!

PAINTING 1 80.00
II. HAULING COST OF BUILDING MATERIALS
Equipment Rental:
1- Dumptruck 6-8 tons, 4 cu.m. P 807.00 /hour
P 6,456.00 /day

Manpower:
6-Laborers @ P 25.00/man hr. P 150.00 /hour
P 1,200.00 /day

Loading Time: 20.00 minutes


Unloading Time: 20.00 minutes
Slack Time: 6.00 minutes
Total 46.00 minutes

Travel Velocity:
Loaded: 15.00 Kph
Unloaded: 20.00 Kph
Distance: 0.00 Km.
Loaded: 0.00 km. X 60.00 Min./hour
15.00 Kph
= 0.00 minutes

Unloaded: 0.00 km. X 60.00 Min./hour


20.00 Kph
= 0.00 minutes

Total= 46.00 minutes


0.77 hours

Hauling Cost of Building Materials:


Equipment Rental:
6-Laborers @ P 25.00/man hr. P 150.00 /hour x 0.77 = P 115.00
1-Dumptruck (5.00 cu.m.) P 807.00 /hour x 0.77 = P 618.70
Total = P 733.70 per trip
Capacity of 1-unit Dumptruck= 4 cu.m.
6.0 Tons= 6000 Kgs.
5 Cu.yard= 1687.5 Bd.ft
4"CHB 500 Pcs./trip

Hauling Cost of 40 kg.Portland cement:


6000 kgs./ 40 kgs.per bag = 150 bags/trip

= P 733.70 per trip


150 bags/trip
P 4.89 Pick-up at Site
4.89 /bag P 250.00 P 254.89

Hauling Cost per kilograms:


= P 733.70 per trip
6000 Kgs.
P 0.12 /Kgs. Pick-up at Site
0.12 P 36.00 P 36.12

Hauling Cost per Bd.Ft.:


= P 733.70 per trip
1687.5 Bd.ft
P 0.43 /Bd.Ft. Pick-up at Site
0.43 P 36.00 P 36.43

Hauling Cost per CHB.:


= P 733.70 per trip
500 Pcs./trip 4" Chb
P 1.47 /Pcs. Pick-up at Site
1.47 P 9.00 P 10.47
5" Chb
Pick-up at Site
P 11.00 P 12.47

Hauling Cost of Structural Steel:


= P 733.70 per trip
6000 Kgs.
P 0.12 /Kgs. Pick-up at Site
0.12 43.8 P 44.00

GITW # 16
= P 733.70 per trip
6000 Kgs.
0.1222833333 /Bd.Ft. Pick-up at Site
0.12 60 P 60.12
Total Cost
#REF!

#REF!
#REF!
#REF!
#REF!

Total cost
#REF!

#REF!
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

MARK-UP
#REF!
#REF!

P -
P -
P -
P -
P -
#REF! #REF!
#REF!
#REF!

#REF!
TIMESPOT SCHEDULE

Name of Project : Err:509


Location : Nangalisan, Tuba, Benguet
Type of Materials : Cement
Source of Materials : Baguio City
Ave. Hauling Distance : 1 kms.
distance speed
Time of Travel w/o Load: 1 x 60 / 20 = 3 mins.
Time of Travel w/ Load : 1 x 60 / 15 = 4 mins.
Time of Loading : Manual = 60 mins.
Time of Unloading : Manual = 60 mins.
Slack Time : = 5 mins.
Cycle Time = 132 mins.

No. of Trips per day : 8*60/ 132 = 3.64 trips say = 4 trip / day
Vehicle Used / Capacity of Truck : Dumptruck / 200 bags
Volume Hauled per day : 4 trips x 200 bags = 800 bags

LABOR :
No. of Laborers : 5
Rate per day : P317.84
No. of Days : 1
P1,589.20

RENTAL :
Equipment Used : Dumptruck
Rate per day : P4,847.00
No. of days : 1
P4,847.00

For Cement
Total Cost : P 6,436.20
Unit Cost : 8.05
Cost at Source : P 250.00 /bag
Manual Hauling :
Actual Cost : 258.05 /bag
say P 258.00 /bag
TIMESPOT SCHEDULE

Name of Project : Err:509


Location : Nangalisan, Tuba, Benguet
Type of Materials : Sand, Gravel
Source of Materials : Baguio City
Ave. Hauling Distance 23 km.
distance speed
Time of Travel w/o Load: 23 x 60 / 20 = 69 mins.
Time of Travel w/ Load : 23 x 60 / 15 = 92 mins.
Time of Loading : Payloader = 10 mins.
Time of Unloading : Dumptruck = 2 mins.
Slack Time : = 5 mins.
Cycle Time = 178 mins.

No. of Trips per day : 8*60/ 178 = 2.70 trips say = 3.0 trip / day
Vehicle Used / Capacity of Truck : Dumptruck / 4.5 cu.m.
Volume Hauled per day : 3 trips x 4.5 cu.m. = 13.5 cu.m.

LABOR :
No. of Laborers :
Rate per day :
No. of Days :

RENTAL :
Equipment Used : Dumptruck
Rate per day : P4,847.00
No. of days : 1
P4,847.00

FOR AGGREGATES: SAND


Total Cost : P4,847.00
Unit Cost : 359.04
Cost @ Source : 910.00
Actual Cost : 1,269.04
say 1,269.00 /cu.m.

GRAVEL
Total Cost : P4,847.00
Unit Cost : 359.04
Cost @ Source : 885.00
Actual Cost : 1,244.04
say 1,244.00 /cu.m.
TIMESPOT SCHEDULE

Name of Project : Err:509


Location : Nangalisan, Tuba, Benguet
Type of Materials : RSB, Structural Steel
Source of Materials : Baguio City
Ave. Hauling Distance : 23 km.
distance speed
Time of Travel w/o Load: 23 x 60 / 20 = 69 mins.
Time of Travel w/ Load : 23 x 60 / 15 = 92 mins.
Time of Loading : Manual = 30 mins.
Time of Unloading : Manual = 30 mins.
Slack Time : = 5 mins.
Cycle Time = 226 mins.

No. of Trips per day : 8*60/ 226 = 2.12 trips say = 2 trip / day
Vehicle Used / Capacity of Truck : Dumptruck / 5,000 kgs.
Volume Hauled per day : 2 trips x 5,000 kgs. = 10000 kgs.

RSB
LABOR : CAPABILITY
No. of Laborers : 5
Rate per day : P317.84
No. of Days : 1
P1,589.20

RENTAL :
Equipment Used : Dumptruck
Rate per day : P4,847.00
No. of days : 1
P4,847.00

RSB
Total Cost : P6,436.20
Unit Cost : 0.64
Cost @ Source ### 38.00 /kg.
Actual Cost : 38.64
say 38.60 /kg.

Structural Steel
Total Cost : P6,436.20
Unit Cost : 0.64
Cost @ Source ### 48.00 /kg.
Actual Cost : 48.64
say 48.60 /kg.
263
250
13
298
302
4
302
250
52
5.25 4
5.65 7.06
29.6625 28.24

Vous aimerez peut-être aussi