ID Task Name Duration Start Finish Predecessors

December 11 February 1 March 21 May 11 July 1 August 21 October 11 December 1 January 21 March 11 May 1 June 21 August 11 October 1 November 21 January 11 March 1 April 21 June 11 August 1
12/20 1/10 1/31 2/21 3/13 4/3 4/24 5/15 6/5 6/26 7/17 8/7 8/28 9/18 10/9 10/30 11/20 12/11 1/1 1/22 2/12 3/5 3/26 4/16 5/7 5/28 6/18 7/9 7/30 8/20 9/10 10/1 10/22 11/12 12/3 12/24 1/14 2/4 2/25 3/18 4/8 4/29 5/20 6/10 7/1 7/22 8/12
1 Project Milestone Summery 460 days Sun 11/6/16 Sun 8/12/18
2 Project start (Zero Date) 0 days Sun 11/6/16 Sun 11/6/16 11/6
3 Project engg, Completion 0 days Fri 9/1/17 Fri 9/1/17 21,30 9/1
4 Project Procurement Completion 0 days Fri 5/4/18 Fri 5/4/18 58 5/4
5 Project Mechanical Completion 0 days Fri 6/15/18 Fri 6/15/18 89 6/15
6 Project Completion 0 days Sun 8/12/18 Sun 8/12/18 96 8/12
7 Engineering 215 days Mon 11/7/16 Fri 9/1/17
8 Process Engineering 65 days Mon 11/7/16 Fri 2/3/17
9 Review Basic Engineering Package 20 days Mon 11/7/16 Fri 12/2/16 2
10 Prepare & Issue PFDs 10 days Mon 12/5/16 Fri 12/16/16 9
11 Prepare & Issue P & IDs 25 days Mon 12/19/16 Fri 1/20/17 10
12 Prepare & Issue Equipment Data S 10 days Mon 1/23/17 Fri 2/3/17 11
13 Mechanical Engineering 160 days Mon 1/23/17 Fri 9/1/17
14 Prepare & Issue Equipment Layout 20 days Mon 1/23/17 Fri 2/17/17 11,10
15 Prepare & Issue GAD 40 days Mon 4/3/17 Fri 5/26/17 23
16 Prepare & Issue ISO 60 days Mon 5/29/17 Fri 8/18/17 15
17 Prepare & Issue MR - Compressor 10 days Mon 2/6/17 Fri 2/17/17 12
18 Prepare & Issue MR - Heat Exchang 10 days Mon 2/6/17 Fri 2/17/17 12
19 Prepare & Issue Preliminary MTO 15 days Mon 5/29/17 Fri 6/16/17 15
20 Prepare & Issue MRs for Bulk Piping Items10 days Mon 6/19/17 Fri 6/30/17 19
21 Prepare Final MTO 10 days Mon 8/21/17 Fri 9/1/17 16
22 Civil Engineering 45 days Mon 2/20/17 Fri 4/21/17
23 Prepare & Issue Plot Plan 30 days Mon 2/20/17 Fri 3/31/17 14
24 Prepare & Issue Equipment Fdn. Dr 15 days Mon 4/3/17 Fri 4/21/17 23
25 Electrical & Instrumentation Enginee 160 days Mon 1/23/17 Fri 9/1/17
26 Prepare & Issue SLD 40 days Mon 1/23/17 Fri 3/17/17 11
27 Prepare & Issue Area Classification Drgs. 20 days Mon 5/29/17 Fri 6/23/17 26,15
28 Prepare & Issue E & I Cable Layouts 20 days Mon 6/26/17 Fri 7/21/17 27
29 Prepare & Issue MTO for E & I 10 days Mon 7/24/17 Fri 8/4/17 28
30 Prepare & Issue MRs for E & I Bulk i 20 days Mon 8/7/17 Fri 9/1/17 29
31 Procurement 315 days Mon 2/20/17 Fri 5/4/18
32 Procurement of Equipment 315 days Mon 2/20/17 Fri 5/4/18
33 Procurement-Compressor 265 days Mon 2/20/17 Fri 2/23/18
34 Prepare & Issue Inquiry 10 days Mon 2/20/17 Fri 3/3/17 17
35 Receive Bids 30 days Mon 3/6/17 Fri 4/14/17 34
36 Prepare TBA 15 days Mon 4/17/17 Fri 5/5/17 35
37 Prepare CBA 5 days Mon 5/8/17 Fri 5/12/17 36
38 Prepare & Issue LOI 10 days Mon 5/15/17 Fri 5/26/17 37
39 Prepare & Submit Vendor Drawi 30 days Mon 5/29/17 Fri 7/7/17 38
40 Procure - Raw Material 40 days Mon 7/10/17 Fri 9/1/17 39
41 Manufacturing 100 days Mon 9/4/17 Fri 1/19/18 40
42 Factory Acceptance Test (FAT) 10 days Mon 1/22/18 Fri 2/2/18 41
43 Packaging & Despatch 5 days Mon 2/5/18 Fri 2/9/18 42
44 Delivery at Site 10 days Mon 2/12/18 Fri 2/23/18 43
45 Procurement-Heat Exchanger 315 days Mon 2/20/17 Fri 5/4/18
46 Prepare & Issue Inquiry 10 days Mon 2/20/17 Fri 3/3/17 18
47 Receive Bids 30 days Mon 3/6/17 Fri 4/14/17 46
48 Prepare TBA 15 days Mon 4/17/17 Fri 5/5/17 47
49 Prepare CBA 5 days Mon 5/8/17 Fri 5/12/17 48
50 Prepare & Issue LOI 10 days Mon 5/15/17 Fri 5/26/17 49
51 Open L/C 10 days Mon 5/29/17 Fri 6/9/17 50
52 Prepare & Submit Vendor Drawi 30 days Mon 6/12/17 Fri 7/21/17 51
53 Procure - Raw Material 40 days Mon 7/24/17 Fri 9/15/17 52
54 Manufacturing 100 days Mon 9/18/17 Fri 2/2/18 53
55 Factory Acceptance Test (FAT) 10 days Mon 2/5/18 Fri 2/16/18 54
56 Packaging & FOB 15 days Mon 2/19/18 Fri 3/9/18 55
57 Shipping & Custom Clearance 30 days Mon 3/12/18 Fri 4/20/18 56
58 Delivery at Site 10 days Mon 4/23/18 Fri 5/4/18 57
59 Procurement of Bulk Items 155 days Mon 7/3/17 Fri 2/2/18
60 Procurement - Piping Bulk Items 145 days Mon 7/3/17 Fri 1/19/18
61 Prepare & Issue Inquiry 10 days Mon 7/3/17 Fri 7/14/17 20
62 Receive Bids 20 days Mon 7/17/17 Fri 8/11/17 61
63 Prepare TBA 15 days Mon 8/14/17 Fri 9/1/17 62
64 Prepare CBA 5 days Mon 9/4/17 Fri 9/8/17 63
65 Prepare & Issue LOI 5 days Mon 9/11/17 Fri 9/15/17 64
66 Manufacturing 40 days Mon 9/18/17 Fri 11/10/17 65
67 Packaging & Despatch 5 days Mon 11/13/17 Fri 11/17/17 66
68 Delivery at Site 10 days Mon 11/20/17 Fri 12/1/17 67
69 Repeat Order Final MTO Piping items 40 days Mon 9/4/17 Fri 10/27/17 21
70 Manufacturing & Delivery at Site 60 days Mon 10/30/17 Fri 1/19/18 69
71 Procurement - E & I Bulk Items 110 days Mon 9/4/17 Fri 2/2/18
72 Prepare & Issue Inquiry 10 days Mon 9/4/17 Fri 9/15/17 30
73 Receive Bids 20 days Mon 9/18/17 Fri 10/13/17 72
74 Prepare TBA 15 days Mon 10/16/17 Fri 11/3/17 73
75 Prepare CBA 5 days Mon 11/6/17 Fri 11/10/17 74
76 Prepare & Issue LOI 5 days Mon 11/13/17 Fri 11/17/17 75
77 Manufacturing 40 days Mon 11/20/17 Fri 1/12/18 76
78 Packaging & Despatch 5 days Mon 1/15/18 Fri 1/19/18 77
79 Delivery at Site 10 days Mon 1/22/18 Fri 2/2/18 78
80 Construction 300 days Mon 4/24/17 Fri 6/15/18
81 Construction of Civil Work 15 days Mon 4/24/17 Fri 5/12/17
82 Construct Fdn for Compressor 10 days Mon 4/24/17 Fri 5/5/17 24
83 Construct Fdn for Heat Exchanger 15 days Mon 4/24/17 Fri 5/12/17 24
84 Mechanical Work 95 days Mon 1/22/18 Fri 6/1/18
85 Install Compressor 20 days Mon 2/26/18 Fri 3/23/18 82,44
86 Install Heat Exchangers 20 days Mon 5/7/18 Fri 6/1/18 58,83
87 Fabrication & Erection of Pipe Rake & Pipe90 days Mon 1/22/18 Fri 5/25/18 16,68,70
88 Electrical & Instrumentation Works 60 days Mon 3/26/18 Fri 6/15/18
89 E & I Cabling & Erection Of E & I Item 60 days Mon 3/26/18 Fri 6/15/18 79,85
90 Hookup, Testing & Pre Commisioning 40 days Mon 3/26/18 Fri 5/18/18
91 Hookup, Testing & Pre Commisioning 40 days Mon 3/26/18 Fri 5/18/18
92 Hookup, & Tie-ins 10 days Mon 3/26/18 Fri 4/6/18 85
93 Loop Checking & Testing 15 days Mon 4/9/18 Fri 4/27/18 92
94 Precommissioning 15 days Mon 4/30/18 Fri 5/18/18 93
95 Commissioning & Startup 20 days Mon 5/21/18 Fri 6/15/18
96 Commissioning & Startup 20 days Mon 5/21/18 Fri 6/15/18 94

Project: Project1fgf Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Sun 12/18/16 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress