LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD

AUMENTO DE % POR AREAS INACCESIBLES


VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)

OBRAS INICIALES
BONOS FIANZAS, TIMBRES, SEGUROS % Global 3.83% 5.18% 4.50% 7.11% 6.98% 5.85% 5.85% 5.63% 5.85% 5.49%
PERMISO DE CONSTRUCCIN % Global 1.49% 2.01% 1.75% 2.77% 2.71% 2.28% 2.10% 2.19% 2.10% 2.14%
CASETA DE CONSTRUCCIN Global 850.00 1150.00 1000.00 1580.00 1550.00 1300.00 1200.00 1250.00 1200.00 1220.00
SERVICIO TEMPORAL DE AGUA POTABLE Global 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SERVICIO TEMPORAL DE ELECTRICIDAD Y TELFONO Global 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
CORTE (SUELO NORMAL) m3 7.65 10.35 9.00 14.22 13.95 11.70 10.80 11.25 10.80 10.98
CORTE (EN ROCA) m3 157.25 212.75 185.00 292.30 286.75 240.50 222.00 231.25 222.00 225.70
RELLENO COMPACTADO m2 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
LETRERO DE METAL Unitario 425.00 575.00 500.00 790.00 775.00 650.00 600.00 625.00 600.00 610.00
Placa de marmolina (13 x 17) Unidad 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00
DEMOLICIN DE LAS ESTRUCTURAS EXISTENTES: 0.00 0.00 0.00 0.00 0.00 0.00
TECHOS m2 4.68 6.33 5.50 8.69 8.53 7.15 6.60 6.88 6.60 6.71
PAREDES m2 4.68 6.33 5.50 8.69 8.53 7.15 6.60 6.88 6.60 6.71
COLUMNAS Y VIGAS m2 6.38 8.63 7.50 11.85 11.63 9.75 9.00 9.38 9.00 9.15
PISOS DE MADERA m2 9.78 13.23 11.50 18.17 17.83 14.95 13.80 14.38 13.80 14.03
PAVIMENTOS m2 4.68 6.33 5.50 8.69 8.53 7.15 6.60 6.88 6.60 6.71
SISTEMA ELCTRICO Unitario 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

DRENAJES PLUVIALES
CABEZAL Y ZAMPEADO (Alcantarillado) Gl 561.00 759.00 660.00 1042.80 1023.00 858.00 792.00 825.00 792.00 805.20
CAJA PLUVIAL (C.I) Unitario 140.25 189.75 165.00 260.70 255.75 214.50 198.00 206.25 198.00 201.30
MEDIA/CAA DE HORM. Y ZAMPEADO 12 DIA ml 26.35 35.65 31.00 48.98 48.05 40.30 37.20 38.75 37.20 37.82
MEDIA/CAA DE HORM. Y ZAMPEADO 14 DIA ml 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
TRAGANTE PLUVIAL Unidad 93.50 126.50 110.00 173.80 170.50 143.00 132.00 137.50 132.00 134.20
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
CMARA DE INSPECCIN (MAN HOLE) Unidad 153.00 207.00 180.00 284.40 279.00 234.00 216.00 225.00 216.00 219.60
TUBERA DE HORMIGN DE 15 DIA ml 45.05 60.95 53.00 83.74 82.15 68.90 63.60 66.25 63.60 64.66
TUBERA DE HORMIGN DE 18 DIA ml 56.10 75.90 66.00 104.28 102.30 85.80 79.20 82.50 79.20 80.52
TUBERA DE HORMIGN DE 24 DIA ml 102.00 138.00 120.00 189.60 186.00 156.00 144.00 150.00 144.00 146.40
TUBERA DE HORMIGN DE 30 DIA ml 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00
ZAMPEADO A FINAL DE CAA Unidad 55.25 74.75 65.00 102.70 100.75 84.50 78.00 81.25 78.00 79.30
CANAL DE HORMIGN MAS LOSETAS ml 23.38 31.63 27.50 43.45 42.63 35.75 33.00 34.38 33.00 33.55

FUNDACIONES

EXCAVACIN Y RELLENO (Pared, muro, columnas, etc.)


m3 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30

EXCAVACIN Y RELLENO (Pared, muro, columnas, etc.)


ROCA m3 157.25 212.75 185.00 292.30 286.75 240.50 222.00 231.25 222.00 225.70

CORRIDAS DE PARED CON REFUERZO m3 297.50 402.50 350.00 553.00 542.50 455.00 420.00 437.50 420.00 427.00
CORRIDAS DE PARED SIN REFUERZO m3 191.25 258.75 225.00 355.50 348.75 292.50 270.00 281.25 270.00 274.50
CORRIDAS CON REFUERZO PARA MURO DE BLOQUES
REFORZADO m3 216.75 293.25 255.00 402.90 395.25 331.50 306.00 318.75 306.00 311.10

BLOQUES DE 6 CON REFUERZO m2 42.50 57.50 50.00 79.00 77.50 65.00 60.00 62.50 60.00 61.00
BLOQUES DE 6 SIN REFUERZO m2 27.20 36.80 32.00 50.56 49.60 41.60 38.40 40.00 38.40 39.04
MURO DE HORMIGN REFORZADO Y ZAPATA m3 382.50 517.50 450.00 711.00 697.50 585.00 540.00 562.50 540.00 549.00
MURO DE BLOQUES DE 6 RELLENO CON REFUERZO m2 46.75 63.25 55.00 86.90 85.25 71.50 66.00 68.75 66.00 67.10
MURO DE BLOQUES DE 8 RELLENO CON REFUERZO m2 51.85 70.15 61.00 96.38 94.55 79.30 73.20 76.25 73.20 74.42
VIGA ANTISSMICA m3 369.75 500.25 435.00 687.30 674.25 565.50 522.00 543.75 522.00 530.70
ZAPATA Y PEDESTAL DE COLUMNAS m3 340.00 460.00 400.00 632.00 620.00 520.00 480.00 500.00 480.00 488.00
RELLENO DE MATERIALES SELECTO BAJO PISO (Incluye
capa de piedra) m3 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30

HORMIGN ESTRUCTURAL
COLUMNAS ESTRUCTURAL m3 340.00 460.00 400.00 632.00 620.00 520.00 480.00 500.00 480.00 488.00
COLS. DE AMARRE DE HORMIGN REFORZADO m3 297.50 402.50 350.00 553.00 542.50 455.00 420.00 437.50 420.00 427.00
VIGAS DEL TECHO Y DE AMARRE m3 340.00 460.00 400.00 632.00 620.00 520.00 480.00 500.00 480.00 488.00
VIGAS Y BANDAS DE HORM. ESTRUC. m3 382.50 517.50 450.00 711.00 697.50 585.00 540.00 562.50 540.00 549.00
DINTELES Y ALFEIZAR m3 255.00 345.00 300.00 474.00 465.00 390.00 360.00 375.00 360.00 366.00
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)

ESCALERA Y ESCALINATAS DE HORM. C/REF. S/TIERRA m3 263.50 356.50 310.00 489.80 480.50 403.00 372.00 387.50 372.00 378.20

LAV. FUENTE, BANCA, SOBRE DE HORM. m3 263.50 356.50 310.00 489.80 480.50 403.00 372.00 387.50 372.00 378.20
TORRE-HORM. TANQUE-H20 10,000 Gl 7820.00 10580.00 9200.00 14536.00 14260.00 11960.00 11040.00 11500.00 11040.00 11224.00
TORRE-HORM. TANQUE-H20 5,000 Gl 4420.00 5980.00 5200.00 8216.00 8060.00 6760.00 6240.00 6500.00 6240.00 6344.00

LOSA ESTRUCTURAL
ALEROS DE HORMIGN m3 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00
FUNDIDA EN SITIO (Vigueta y bloques) m2 127.50 172.50 150.00 237.00 232.50 195.00 180.00 187.50 180.00 183.00
FUNDIDA EN SITIO DE HORM. SLIDO m2 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00
LOSA DE ESCALERA m2 255.00 345.00 300.00 474.00 465.00 390.00 360.00 375.00 360.00 366.00
POSTENSADA m2 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00
HORM.LAM GALV. CARRIOLA MAS ACERO m2 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00
VIGUETAS PREFABRICADAS MAS BLOQUES m2 85.00 115.00 100.00 158.00 155.00 130.00 120.00 125.00 120.00 122.00
VIGUETAS DOBLE TEE m2 85.00 115.00 100.00 158.00 155.00 130.00 120.00 125.00 120.00 122.00

PAVIMENTOS 0.00 0.00


HORM. SIMPLE-ACERAS m2 42.50 57.50 50.00 79.00 77.50 65.00 60.00 62.50 60.00 61.00
PAVIMENTO ASFLTICO (Calle y estacionamiento) m2 19.55 26.45 23.00 36.34 35.65 29.90 27.60 28.75 27.60 28.06
PAVIMENTO DE HORMIGN (Calles y estacionamiento) m2 40.80 55.20 48.00 75.84 74.40 62.40 57.60 60.00 57.60 58.56
CORDON CUNETA ml 56.10 75.90 66.00 104.28 102.30 85.80 79.20 82.50 79.20 80.52
CORDON SIMPLE ml 25.50 34.50 30.00 47.40 46.50 39.00 36.00 37.50 36.00 36.60
PISOS DE HORM. PARA EDIFICIO ACABADO A LLANA m2 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
PISOS DE HORM. PASILLOS CUBIERTOS m2 19.13 25.88 22.50 35.55 34.88 29.25 27.00 28.13 27.00 27.45
DE HORM. REFORZADOS CON AC. TEMP. m2 29.75 40.25 35.00 55.30 54.25 45.50 42.00 43.75 42.00 42.70
HORM. SIMPLE (EDIFICIOS) PARA BALDOSAS m2 19.13 25.88 22.50 35.55 34.88 29.25 27.00 28.13 27.00 27.45
SOBREPISO DE HORM. 3 m2 7.65 10.35 9.00 14.22 13.95 11.70 10.80 11.25 10.80 10.98

PAREDES
BLOQUES DE 4 m2 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
BLOQUES DE 6 m2 19.13 25.88 22.50 35.55 34.88 29.25 27.00 28.13 27.00 27.45
BLOQUES DE 8 m2 22.53 30.48 26.50 41.87 41.08 34.45 31.80 33.13 31.80 32.33
BARANDA DE BLOQUEO DE 4 m2 19.13 25.88 22.50 35.55 34.88 29.25 27.00 28.13 27.00 27.45
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
BARANDA DE BLOQUEO DE 4+TUBOS, A/C. GALV. m2 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
RETAQUEO DE BLOQUES DE 4 m2 19.13 25.88 22.50 35.55 34.88 29.25 27.00 28.13 27.00 27.45
PARED DE PLYCEM CON ENTRAMADO DE METAL m2 37.40 50.60 44.00 69.52 68.20 57.20 52.80 55.00 52.80 53.68
PARED DE PLYCEM CON ENTRAMADO DE MADERA m2 26.35 35.65 31.00 48.98 48.05 40.30 37.20 38.75 37.20 37.82
PARED DE PLYWOOD 1/4 CON ENTRAMADO DE
m2 22.95 31.05 27.00 42.66 41.85 35.10 32.40 33.75 32.40 32.94
MADERA A/C
PARED DE PLYWALL CON ENTRAMADO CON MADERA m2 25.50 34.50 30.00 47.40 46.50 39.00 36.00 37.50 36.00 36.60

PARED DE GYPSUM BOARD + ENTRAMADO DE


m2 38.25 51.75 45.00 71.10 69.75 58.50 54.00 56.25 54.00 54.90
MADERA
PARED DE GYPSUM BOARD + ENTRAMADO DE METAL m2 52.28 70.73 61.50 97.17 95.33 79.95 73.80 76.88 73.80 75.03

PANELES TIPO CORTINA (SYSTEM TRUST). m2 27.20 36.80 32.00 50.56 49.60 41.60 38.40 40.00 38.40 39.04
BLOQUES DE VIDRIO (8x 8 x 3 1/8) m2 216.75 293.25 255.00 402.90 395.25 331.50 306.00 318.75 306.00 311.10
DE MADERA MACHIMBRADA EN A/C SOBRE
m2 59.50 80.50 70.00 110.60 108.50 91.00 84.00 87.50 84.00 85.40
ENTRAMADO
LAMINA DE M-2 m2 20.40 27.60 24.00 37.92 37.20 31.20 28.80 30.00 28.80 29.28

TRABAJO DE ACERO
BARANDA DE TUBOS DE A/C. GALV. ml 29.75 40.25 35.00 55.30 54.25 45.50 42.00 43.75 42.00 42.70
BARANDA DE TUBO DE A/C. GALV. MAS MALLA
m2 45.05 60.95 53.00 83.74 82.15 68.90 63.60 66.25 63.60 64.66
EXPANDIDA
CANAL DE DESAGES, PARA TECHOS ml 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
CERCHA TEJIDAS METLICAS ml 30.18 40.83 35.50 56.09 55.03 46.15 42.60 44.38 42.60 43.31
COLUMNA DE WIDE FLANGE ml 45.05 60.95 53.00 83.74 82.15 68.90 63.60 66.25 63.60 64.66
COLUMNA DE TUB. GAL + PLATO + ANCLAJE 3 x 3 Unidad 80.75 109.25 95.00 150.10 147.25 123.50 114.00 118.75 114.00 115.90
PARAPETO LAMINAS ZINC ESMALTADO+ESTRUCTURA
m2 26.78 36.23 31.50 49.77 48.83 40.95 37.80 39.38 37.80 38.43
CARRIOLAS
PARAPETO DE PLYCEM + ESTRUCTURA DE CARRIOLAS m2 42.50 57.50 50.00 79.00 77.50 65.00 60.00 62.50 60.00 61.00

PASA MANO DE TUBO DE A/C GALV. ml 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
MARCO RGIDO COMPLETO DE W/F ml 81.60 110.40 96.00 151.68 148.80 124.80 115.20 120.00 115.20 117.12
SOLAPA LISA ESMALTADA ml 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
TANQUE DE RESERVA DE 10.000 GLS. METAL Gl 12962.50 17537.50 15250.00 24095.00 23637.50 19825.00 18300.00 19062.50 18300.00 18605.00
TANQUE DE RESERVA DE 5.000 GLS. METAL Gl 6375.00 8625.00 7500.00 11850.00 11625.00 9750.00 9000.00 9375.00 9000.00 9150.00
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
TANQUE DE RESERVA DE 3.000 GLS. METAL Gl 4250.00 5750.00 5000.00 7900.00 7750.00 6500.00 6000.00 6250.00 6000.00 6100.00
TORRE DE AC. TANQUE DE 5.000 GLS. (PLASTICO) Gl
TORRE DE AC. TANQUE DE 3.000 GLS. (PLASTICO) Gl
TECHO DE EDIFICIOS (carr. cubierta, sost., alin., caball.,
m2 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
tirafondo, etc.)
TECHO DE COBERTIZO (carr., cubierta, sost., alin.,
m2 21.25 28.75 25.00 39.50 38.75 32.50 30.00 31.25 30.00 30.50
caball.,tirafondo, etc.)
CUBIERTA DE METAL ESMALTADO (solamente) m2 17.00 23.00 20.00 31.60 31.00 26.00 24.00 25.00 24.00 24.40
CARRIOLA, SOST., ALIN. ETC. (solamente) m2 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
CABALLETE DE A/C. ESMALTADO (solamente) ml 11.90 16.10 14.00 22.12 21.70 18.20 16.80 17.50 16.80 17.08
VENT. DE MALLA/ALUMINIO m2 11.48 15.53 13.50 21.33 20.93 17.55 16.20 16.88 16.20 16.47
BAJANTE PLUVIAL PARA CANAL DE DESAGE (PVC) ml 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
VENTILADOR DE TURBINA 24 DIMETRO Y BASE Unidad 488.75 661.25 575.00 908.50 891.25 747.50 690.00 718.75 690.00 701.50

VENT. DE MALLA EXPANDIDA MAS MARCO DE ACERO m2 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80

VIGAS DE WIDE FLANGE ml 85.00 115.00 100.00 158.00 155.00 130.00 120.00 125.00 120.00 122.00
TECHO (CARRIOLAS, CUBIERTAS, ETC.) CALIBRE 24 m2 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
CUBIERTA CALIBRE 24 (solamente) m2 22.95 31.05 27.00 42.66 41.85 35.10 32.40 33.75 32.40 32.94
GRADERAS m2 89.25 120.75 105.00 165.90 162.75 136.50 126.00 131.25 126.00 128.10
TINAQUERA DE ACERO Unidad 1054.00 1426.00 1240.00 1959.20 1922.00 1612.00 1488.00 1550.00 1488.00 1512.80
CHANEL 6X8.2 ml 30.18 40.83 35.50 56.09 55.03 46.15 42.60 44.38 42.60 43.31
DOBLE CARRIOLAS 2X8 [ ] ml 26.35 35.65 31.00 48.98 48.05 40.30 37.20 38.75 37.20 37.82
TECHO (CARRIOLAS, CUBIERTAS Y CABALLETE DE
m2 35.28 47.73 41.50 65.57 64.33 53.95 49.80 51.88 49.80 50.63
PANALIT, ETC.)

CIELO RASO
2' x 2' DE STYROPOR m2 19.55 26.45 23.00 36.34 35.65 29.90 27.60 28.75 27.60 28.06
2' x 2' DE FIBRA MINERAL m2 19.55 26.45 23.00 36.34 35.65 29.90 27.60 28.75 27.60 28.06
2' x 4' DE STYROPOR m2 19.55 26.45 23.00 36.34 35.65 29.90 27.60 28.75 27.60 28.06
2' x 2' DE FIBRA MINERAL m2 26.35 35.65 31.00 48.98 48.05 40.30 37.20 38.75 37.20 37.82
AISLANTE TRMICO LOW-E 1/4 DE ESP. m2 7.65 10.35 9.00 14.22 13.95 11.70 10.80 11.25 10.80 10.98
CELOTEX IMPORTADO DE 4' x 8' mas entram. De madera
m2 30.60 41.40 36.00 56.88 55.80 46.80 43.20 45.00 43.20 43.92
mas moldura. Ycubre junta
CELOTEX SUSPEND. + T DE ALUM. m2 20.40 27.60 24.00 37.92 37.20 31.20 28.80 30.00 28.80 29.28
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
DE METAL ESMALT. SOBRE CARRIOLAS m2 25.50 34.50 30.00 47.40 46.50 39.00 36.00 37.50 36.00 36.60
PLYCEM SUSPEND. EN T DE ALUM. m2 28.90 39.10 34.00 53.72 52.70 44.20 40.80 42.50 40.80 41.48
PLYCEM SUSPEND + ESTRUCTURA DE MAD. m2 28.90 39.10 34.00 53.72 52.70 44.20 40.80 42.50 40.80 41.48
PLYCEM SUSPEND + ESTRUCTURA DE MET. m2 28.90 39.10 34.00 53.72 52.70 44.20 40.80 42.50 40.80 41.48
GYPSUM BOARD + ESTRUCTURA DE MET. m2 23.80 32.20 28.00 44.24 43.40 36.40 33.60 35.00 33.60 34.16
GYPSUM BOARD + ESTRUCTURA DE MAD. m2 23.80 32.20 28.00 44.24 43.40 36.40 33.60 35.00 33.60 34.16
DE MADERA MACHIMBRADA m2 59.50 80.50 70.00 110.60 108.50 91.00 84.00 87.50 84.00 85.40
DE MALLA REPELLADA + ENTRAMADO DE METAL m2 25.50 34.50 30.00 47.40 46.50 39.00 36.00 37.50 36.00 36.60
PLYCEM EN ENTRAMADO DE CARRIOLA 3 m2 59.50 80.50 70.00 110.60 108.50 91.00 84.00 87.50 84.00 85.40
SUSPENDIDO-ESCAYOLA m2 29.75 40.25 35.00 55.30 54.25 45.50 42.00 43.75 42.00 42.70

PUERTAS COMPLETAS
ACERO DE 1.00 x 2.15 Unidad 250.75 339.25 295.00 466.10 457.25 383.50 354.00 368.75 354.00 359.90
ACERO DE 1.20 x 2.15 Unidad 272.00 368.00 320.00 505.60 496.00 416.00 384.00 400.00 384.00 390.40
ACERO DOBLE DE 1.50 x 2.15 Unidad 280.50 379.50 330.00 521.40 511.50 429.00 396.00 412.50 396.00 402.60
ACERO 1.00 x 2.15 + LUCETA CON MALLA EXPAND. Unidad 263.50 356.50 310.00 489.80 480.50 403.00 372.00 387.50 372.00 378.20
ACERO 1.50 x 2.15 + LUCETA CON MALLA EXPAND. Unidad 280.50 379.50 330.00 521.40 511.50 429.00 396.00 412.50 396.00 402.60
MADERA SLIDA DE 1.00 x 2.15 Unidad 195.50 264.50 230.00 363.40 356.50 299.00 276.00 287.50 276.00 280.60
MADERA SLIDA DOBLE 1.00 x 2.15 Unidad 242.25 327.75 285.00 450.30 441.75 370.50 342.00 356.25 342.00 347.70
MADERA (TIPO TABLERO) DE 1.00 x 2.15 Unidad 195.50 264.50 230.00 363.40 356.50 299.00 276.00 287.50 276.00 280.60
MADERA (TIPO TABLERO) DOBLE 1.50 x 2.15 Unidad 212.50 287.50 250.00 395.00 387.50 325.00 300.00 312.50 300.00 305.00
MADERA (TIPO TABLERO) + LUCETA 1.00 x 2.15 Unidad 136.00 184.00 160.00 252.80 248.00 208.00 192.00 200.00 192.00 195.20
MADERA (TIPO TABLERO) DOBLE + LUCETA 1.50 x 2.15 Unidad 212.50 287.50 250.00 395.00 387.50 325.00 300.00 312.50 300.00 305.00
MADERA (TIPO TABLERO) DE 0.80 x 2.15 Unidad 204.00 276.00 240.00 379.20 372.00 312.00 288.00 300.00 288.00 292.80
MADERA (TIPO TABLERO) DE 0.70 x 2.15 Unidad 182.75 247.25 215.00 339.70 333.25 279.50 258.00 268.75 258.00 262.30
MADERA (TIPO TABLERO) DE 0.70 x 1.50 Unidad 140.25 189.75 165.00 260.70 255.75 214.50 198.00 206.25 198.00 201.30

MADERA DE PLYWOOD DE 1/4 EN A/C + ENTRAMADO Unidad 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00

MADERA SLIDA + PERSIANAS Unidad 191.25 258.75 225.00 355.50 348.75 292.50 270.00 281.25 270.00 274.50
ENROLLABLE 4.50 x 2.40 Unidad 1113.50 1506.50 1310.00 2069.80 2030.50 1703.00 1572.00 1637.50 1572.00 1598.20
DE VIDRIO EN MARCOS DE ALUMINIO Unidad 306.00 414.00 360.00 568.80 558.00 468.00 432.00 450.00 432.00 439.20
DE VIDRIO EN MARCOS DE MADERA Unidad 221.00 299.00 260.00 410.80 403.00 338.00 312.00 325.00 312.00 317.20
DE MADERA PLEGABLES Unidad 1912.50 2587.50 2250.00 3555.00 3487.50 2925.00 2700.00 2812.50 2700.00 2745.00
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
DE MADERA PLEGABLES MAS PLYCEM Unidad 1870.00 2530.00 2200.00 3476.00 3410.00 2860.00 2640.00 2750.00 2640.00 2684.00
PUERTA CORREDIZAS DE ACERO 1.50 X 2.40 Unidad 935.00 1265.00 1100.00 1738.00 1705.00 1430.00 1320.00 1375.00 1320.00 1342.00
TABIQUES DIVIDISORIOS DE MADERA m2 76.50 103.50 90.00 142.20 139.50 117.00 108.00 112.50 108.00 109.80
MUEBLES
ADMINISTRACIN ml 161.50 218.50 190.00 300.20 294.50 247.00 228.00 237.50 228.00 231.80
BIBLIOTECA ml 174.25 235.75 205.00 323.90 317.75 266.50 246.00 256.25 246.00 250.10
COCINA ml 212.50 287.50 250.00 395.00 387.50 325.00 300.00 312.50 300.00 305.00
DEPOSITO ml 136.00 184.00 160.00 252.80 248.00 208.00 192.00 200.00 192.00 195.20
EDUCACIN FAMILIAR ml 212.50 287.50 250.00 395.00 387.50 325.00 300.00 312.50 300.00 305.00
LABORATORIO FSICA QUMICA ml 242.25 327.75 285.00 450.30 441.75 370.50 342.00 356.25 342.00 347.70
LABORATORIO DE CIENCIAS ml 242.25 327.75 285.00 450.30 441.75 370.50 342.00 356.25 342.00 347.70

TABLEROS
DE CARTN COMPRIMIDO CON MURAL DE CELOTEX Unidad 225.25 304.75 265.00 418.70 410.75 344.50 318.00 331.25 318.00 323.30
COMPUTO 1.20 x 1.80 color blanco, en marco de aluminio,
Unidad 263.50 356.50 310.00 489.80 480.50 403.00 372.00 387.50 372.00 378.20
para usar con marcador

VENTANAS
Persianas de paleta de vidrio+ operador en marco de aluminio
y malla contra insectos m2 93.50 126.50 110.00 173.80 170.50 143.00 132.00 137.50 132.00 134.20

VERJAS DE ACERO m2 46.75 63.25 55.00 86.90 85.25 71.50 66.00 68.75 66.00 67.10
BLOQUE ORNAMENTAL TIPO-PERSIANA-TROPICAL m2 28.05 37.95 33.00 52.14 51.15 42.90 39.60 41.25 39.60 40.26
BLOQUE ORNAMENTAL TIPO R m2 22.95 31.05 27.00 42.66 41.85 35.10 32.40 33.75 32.40 32.94
DE MALLA EXPANDIDA EN MARCO DE A/C m2 39.10 52.90 46.00 72.68 71.30 59.80 55.20 57.50 55.20 56.12
MALLA c/ insectos EN MARCOS DE ALUMINIO (SOLO) m2 19.55 26.45 23.00 36.34 35.65 29.90 27.60 28.75 27.60 28.06
VIDRIO FIJO EN MARCO DE ALUMINIO m2 80.75 109.25 95.00 150.10 147.25 123.50 114.00 118.75 114.00 115.90
VIDRIO EN MARCO DE ALUMINIO CORREDIZAS m2 182.75 247.25 215.00 339.70 333.25 279.50 258.00 268.75 258.00 262.30
VIDRIO FIJO EN MARCO DE MADERA m2 76.50 103.50 90.00 142.20 139.50 117.00 108.00 112.50 108.00 109.80
VIDRIO FIJO EN MARCO DE MADERA CON BISAGRAS m2 182.75 247.25 215.00 339.70 333.25 279.50 258.00 268.75 258.00 262.30
VENTANA DE PERSIANAS-PALETAS DE ALUMINIO m2 136.00 184.00 160.00 252.80 248.00 208.00 192.00 200.00 192.00 195.20
BLOQUES ORNAMENTALES-PANAFLEX m2 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80

ACABADOS
AZULEJOS DE 0.15 x 0.15 m2 31.45 42.55 37.00 58.46 57.35 48.10 44.40 46.25 44.40 45.14
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
BALDOSA TIPO TOCHO 0.30 x 0.30 de grano m2 31.45 42.55 37.00 58.46 57.35 48.10 44.40 46.25 44.40 45.14
MALLA REPELLADA m2 27.20 36.80 32.00 50.56 49.60 41.60 38.40 40.00 38.40 39.04
MOSAICO DE GRANO FINO P/BRILLADO m2 46.75 63.25 55.00 86.90 85.25 71.50 66.00 68.75 66.00 67.10
MOSAICO DE PASTA. m2 27.20 36.80 32.00 50.56 49.60 41.60 38.40 40.00 38.40 39.04
REPELLO LISO EN LOSA m2 7.65 10.35 9.00 14.22 13.95 11.70 10.80 11.25 10.80 10.98
REPELLO LISO m2 11.05 14.95 13.00 20.54 20.15 16.90 15.60 16.25 15.60 15.86
REPELLO RUSTICO m2 11.48 15.53 13.50 21.33 20.93 17.55 16.20 16.88 16.20 16.47
ZCALO DE TOCHO ml 11.05 14.95 13.00 20.54 20.15 16.90 15.60 16.25 15.60 15.86
ZCALO DE GRANO FINO P/BRILLADO ml 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
ZCALO DE MOSAICO DE PASTA ml 11.05 14.95 13.00 20.54 20.15 16.90 15.60 16.25 15.60 15.86
PISO DE CERMICA NACIONAL m2 55.25 74.75 65.00 102.70 100.75 84.50 78.00 81.25 78.00 79.30
PISO DE CERMICA IMPORTADA m2 114.75 155.25 135.00 213.30 209.25 175.50 162.00 168.75 162.00 164.70
PISO DE VINIL AMERICANOS (SIN ZCALO) m2 29.75 40.25 35.00 55.30 54.25 45.50 42.00 43.75 42.00 42.70
ZCALO DE VINIL ml 11.90 16.10 14.00 22.12 21.70 18.20 16.80 17.50 16.80 17.08
ZCALO DE MADERA ml 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
PISO DE MAD. MACHIMB + ESTRUCTURA DE MAD. m2 59.50 80.50 70.00 110.60 108.50 91.00 84.00 87.50 84.00 85.40

PINTURA
ACEITE (METAL) m2 4.04 5.46 4.75 7.51 7.36 6.18 5.70 5.94 5.70 5.80
VINLICA (INTERIOR Y EXTERIOR) m2 4.04 5.46 4.75 7.51 7.36 6.18 5.70 5.94 5.70 5.80
ANTICORRESIVA (ELEMENTOS METLICOS) m2 3.83 5.18 4.50 7.11 6.98 5.85 5.40 5.63 5.40 5.49
SURFASTIL (TECHOS) m2 7.65 10.35 9.00 14.22 13.95 11.70 10.80 11.25 10.80 10.98

ELECTRICIDAD

Sistema de Distribucin (incluye: cruceta, poste, corta circuito,


Unidad 6375.00 8625.00 7500.00 11850.00 11625.00 9750.00 9000.00 9375.00 9000.00 9150.00
fusibles, pararrayos,aisladores, retenida, herrajes, etc.)

Transformadores de potencia, tipo convencionales de 75KVA,


Unidad 4675.00 6325.00 5500.00 8690.00 8525.00 7150.00 6600.00 6875.00 6600.00 6710.00
7.6/13.2KV y 120/240 V.
Conductores y tubera de alimentacin del interruptor
Unidad 2550.00 3450.00 3000.00 4740.00 4650.00 3900.00 3600.00 3750.00 3600.00 3660.00
principal
Caja e Interruptor Principal, conductor batera a tierra, jaula de
Unidad 2125.00 2875.00 2500.00 3950.00 3875.00 3250.00 3000.00 3125.00 3000.00 3050.00
proteccin.
Tablero de distribucin, breakers, etc. Unidad 4165.00 5635.00 4900.00 7742.00 7595.00 6370.00 5880.00 6125.00 5880.00 5978.00
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)

Tablero de distribucin TD-1, TD-2, TD-3, TD-4, TD-2-2, TD-3-


Unidad 5525.00 7475.00 6500.00 10270.00 10075.00 8450.00 7800.00 8125.00 7800.00 7930.00
3, breakers, etc.
Tablero de circuito, breakers, etc. Unidad 4080.00 5520.00 4800.00 7584.00 7440.00 6240.00 5760.00 6000.00 5760.00 5856.00
tubera y Alimentadores Unidad 8075.00 10925.00 9500.00 15010.00 14725.00 12350.00 11400.00 11875.00 11400.00 11590.00
Caja de paso, -N-S-6-5 Unidad 199.75 270.25 235.00 371.30 364.25 305.50 282.00 293.75 282.00 286.70
Viga ducto de 3 tubo de 4 dimetro Unidad 1275.00 1725.00 1500.00 2370.00 2325.00 1950.00 1800.00 1875.00 1800.00 1830.00
Salida Monofsicas incluye: tubera, conductores, cajas,
Unidad 38.25 51.75 45.00 71.10 69.75 58.50 54.00 56.25 54.00 54.90
tomacorrientes, Interruptor, caja de molduras, etc.

Salida Bifasica incluye: tubera, conductores, cajas,


Unidad 55.25 74.75 65.00 102.70 100.75 84.50 78.00 81.25 78.00 79.30
tomacorrientes 250 V-15 A. Molduras cajas de molduras, etc.

Salidas Trifsicas incluye: tuberas, cajas, conductores, tuberas


Unidad 80.75 109.25 95.00 150.10 147.25 123.50 114.00 118.75 114.00 115.90
flexibles, etc.
Luminaria fluorescente de 2/32 tipo canal Unidad 42.50 57.50 50.00 79.00 77.50 65.00 60.00 62.50 60.00 61.00
Luminaria fluorescente de 2/32 embutido con reflectores de
Unidad 59.50 80.50 70.00 110.60 108.50 91.00 84.00 87.50 84.00 85.40
aluminio anodizado
Luminaria fluorescente de 2/17 tipo canal Unidad 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
Luminaria fluorescente tipo pared de 175 vatios Unidad 148.75 201.25 175.00 276.50 271.25 227.50 210.00 218.75 210.00 213.50
Roseta sencilla con luminaria tipo fluorescente compacta Unidad 21.25 28.75 25.00 39.50 38.75 32.50 30.00 31.25 30.00 30.50
Luminaria fluorescente de 2/59 tipo canal Unidad 76.50 103.50 90.00 142.20 139.50 117.00 108.00 112.50 108.00 109.80
Luminaria tipo cobra de 250 vatios Unidad 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00
Lmpara de Emergencia Unidad 42.50 57.50 50.00 79.00 77.50 65.00 60.00 62.50 60.00 61.00
Abanico de Techo tipo K.D.K de 56 Unidad 63.75 86.25 75.00 118.50 116.25 97.50 90.00 93.75 90.00 91.50
Fotocelda de 3000 VA, 125 V Unidad 38.25 51.75 45.00 71.10 69.75 58.50 54.00 56.25 54.00 54.90
Detector de Humo Unidad 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
Detector de Calor Unidad 29.75 40.25 35.00 55.30 54.25 45.50 42.00 43.75 42.00 42.70
Estacin Manual Unidad 72.25 97.75 85.00 134.30 131.75 110.50 102.00 106.25 102.00 103.70
Mini corneta Unidad 72.25 97.75 85.00 134.30 131.75 110.50 102.00 106.25 102.00 103.70
Panel de alarma de 4 zonas Unidad 425.00 575.00 500.00 790.00 775.00 650.00 600.00 625.00 600.00 610.00
Panel de alarma de 8 zonas Unidad 850.00 1150.00 1000.00 1580.00 1550.00 1300.00 1200.00 1250.00 1200.00 1220.00
Panel de alarma de 12 zonas Unidad 1241.00 1679.00 1460.00 2306.80 2263.00 1898.00 1752.00 1825.00 1752.00 1781.20
Panel de alarma de 380 puntos (digital) Unidad 8415.00 11385.00 9900.00 15642.00 15345.00 12870.00 11880.00 12375.00 11880.00 12078.00
Modulo direccionable de 25 puntos Unidad 106.25 143.75 125.00 197.50 193.75 162.50 150.00 156.25 150.00 152.50
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)

Salidas de alarma (incluye: moldura, cable, caja de moldura y


Unidad 42.50 57.50 50.00 79.00 77.50 65.00 60.00 62.50 60.00 61.00
accesorios de moldura)
Salida de alarma ( tubera, conector, codo, caja de paso, cable,
Unidad 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
etc)
Extintores 20A-120 BC Unidad 127.50 172.50 150.00 237.00 232.50 195.00 180.00 187.50 180.00 183.00
PLOMERA (INCLUYE: Artefactos, Accesorios, Instalaciones
CONEXIN DOMICILIARIO AGUAS / POTABLE ml 11.90 16.10 14.00 22.12 21.70 18.20 16.80 17.50 16.80 17.08
CONEXIN DOMICILIARIO AGUAS/NEGRAS ml 14.66 19.84 17.25 27.26 26.74 22.43 20.70 21.56 20.70 21.05
CONEXIN SISTEMA/DRENAJE C/BALOMPIE ml 17.85 24.15 21.00 33.18 32.55 27.30 25.20 26.25 25.20 25.62
CONEXIN SISTEMA/DRENAJE T/SEPTICO ml 17.85 24.15 21.00 33.18 32.55 27.30 25.20 26.25 25.20 25.62
CONEXIN TANQUE SPTICO ml 19.55 26.45 23.00 36.34 35.65 29.90 27.60 28.75 27.60 28.06
CONEXIN DE GAS BUTANO (SALIDA) ml 148.75 201.25 175.00 276.50 271.25 227.50 210.00 218.75 210.00 213.50
DESAGES DE PISO Unidad 85.00 115.00 100.00 158.00 155.00 130.00 120.00 125.00 120.00 122.00
GABINETE COMPLETO DE MANGUERAS Unidad 361.25 488.75 425.00 671.50 658.75 552.50 510.00 531.25 510.00 518.50
SALIDA DE LAVAMANOS Unidad 212.50 287.50 250.00 395.00 387.50 325.00 300.00 312.50 300.00 305.00
SALIDA SIAMESA CONTRA-INCENDIO Unidad 420.75 569.25 495.00 782.10 767.25 643.50 594.00 618.75 594.00 603.90
SALIDA DE FREGADOR Unidad 212.50 287.50 250.00 395.00 387.50 325.00 300.00 312.50 300.00 305.00
SALIDA DE INODOROS Unidad 233.75 316.25 275.00 434.50 426.25 357.50 330.00 343.75 330.00 335.50
SALIDA DE URINAL Unidad 212.50 287.50 250.00 395.00 387.50 325.00 300.00 312.50 300.00 305.00
SALIDA DE FUENTE DE AGUA FRA Unidad 340.00 460.00 400.00 632.00 620.00 520.00 480.00 500.00 480.00 488.00
SALIDA FUENTE INTEGRAL Unidad 297.50 402.50 350.00 553.00 542.50 455.00 420.00 437.50 420.00 427.00
SALIDA HMEDO CONTRA-INCENDIO ml 21.25 28.75 25.00 39.50 38.75 32.50 30.00 31.25 30.00 30.50
TIPO DE CEMENTO CHICA Unidad 85.00 115.00 100.00 158.00 155.00 130.00 120.00 125.00 120.00 122.00
FREGADOR CON LLAVE CON CUELLO DE GANSO Unidad 297.50 402.50 350.00 553.00 542.50 455.00 420.00 437.50 420.00 427.00
LLAVE TIPO SIAMESAS DE GAS Unidad 110.50 149.50 130.00 205.40 201.50 169.00 156.00 162.50 156.00 158.60
SISTEMA DE BOMBAS c/equipo completo y accesorios Unidad 4250.00 5750.00 5000.00 7900.00 7750.00 6500.00 6000.00 6250.00 6000.00 6100.00
TINA DE CEMENTO DOBLE Unidad 122.19 165.31 143.75 227.13 222.81 186.88 172.50 179.69 172.50 175.38
TINA DE LABORATORIO + llave cuello de ganzo Unidad 297.50 402.50 350.00 553.00 542.50 455.00 420.00 437.50 420.00 427.00
DUCHA - incluye ferretera y parrilla Unidad 148.75 201.25 175.00 276.50 271.25 227.50 210.00 218.75 210.00 213.50
SALIDA - calentador + artefacto/30 gal. Unidad 212.50 287.50 250.00 395.00 387.50 325.00 300.00 312.50 300.00 305.00

REPARACIN PLOMERA
INODORO
CAMBIO VLVULA T/B Unidad 14.88 20.13 17.50 27.65 27.13 22.75 21.00 21.88 21.00 21.35
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
CAMBIO DE KORKY CON CADENA Unidad 8.50 11.50 10.00 15.80 15.50 13.00 12.00 12.50 12.00 12.20
CAMBIO DE BALANCN T/B Unidad 3.40 4.60 4.00 6.32 6.20 5.20 4.80 5.00 4.80 4.88
CAMBIO DE BOYA Y VARILLA Unidad 5.10 6.90 6.00 9.48 9.30 7.80 7.20 7.50 7.20 7.32
CAMBIO DE SIFON Y TORNILLO ACOPLAR (hay que
Unidad 21.25 28.75 25.00 39.50 38.75 32.50 30.00 31.25 30.00 30.50
desmontar tanque)
CAMBIO DE FERRETERA COMPLETA (plstica) desmontar Unidad 21.25 28.75 25.00 39.50 38.75 32.50 30.00 31.25 30.00 30.50

CAMBIAR TANQUE C/F Unidad 53.76 72.74 63.25 99.94 98.04 82.23 75.90 79.06 75.90 77.17
CAMBIO DE TAZA Unidad 85.00 115.00 100.00 158.00 155.00 130.00 120.00 125.00 120.00 122.00
CAMBIO DE LLAVE DE ABASTO Y TUBO ABASTO Unidad 17.00 23.00 20.00 31.60 31.00 26.00 24.00 25.00 24.00 24.40
DESTAPAR INODORO Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30
DESMONTAR INODORO Y DESTAPARLO Unidad 21.25 28.75 25.00 39.50 38.75 32.50 30.00 31.25 30.00 30.50
CAMBIO DE KIT DE VLVULA T/B PLSTICA Unidad 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
TAPA DE TANQUE DE INODORO Unidad 21.25 28.75 25.00 39.50 38.75 32.50 30.00 31.25 30.00 30.50
TAPA PARA LETRINA DE PORCELANA Unidad 38.25 51.75 45.00 71.10 69.75 58.50 54.00 56.25 54.00 54.90
DESMONTAR INODORO Unidad 21.25 28.75 25.00 39.50 38.75 32.50 30.00 31.25 30.00 30.50
CAMBIO DE FLOXOMETRO Unidad 157.25 212.75 185.00 292.30 286.75 240.50 222.00 231.25 222.00 225.70
CAMBIO DE KIT DE FLUXOMETRO Unidad 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
CAMBIO DE SPUD Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30

LAVAMANOS
REINSTALAR LAVAMANOS CAIDO Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30
CAMBIAR LLAVE DE LAVAMANOS (varia precio) Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30
CAMBIO DE LLAVE ANGULO Y TUBO ABASTO Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30
CAMBIO ARANDELA 00 Y ASIENTO Unidad 4.25 5.75 5.00 7.90 7.75 6.50 6.00 6.25 6.00 6.10
CAMBIO CONEXIN P.O. PLUG Unidad 10.63 14.38 12.50 19.75 19.38 16.25 15.00 15.63 15.00 15.25
CAMBIO TROMPA PLSTICA Unidad 5.10 6.90 6.00 9.48 9.30 7.80 7.20 7.50 7.20 7.32
CAMBIO DE LAVAMANOS C/FERRETERIA Unidad 76.50 103.50 90.00 142.20 139.50 117.00 108.00 112.50 108.00 109.80
DESTAPARLO Unidad 10.20 13.80 12.00 18.96 18.60 15.60 14.40 15.00 14.40 14.64
CAMBIO DE LAVAMANOS S/FERRETERIA Unidad 55.25 74.75 65.00 102.70 100.75 84.50 78.00 81.25 78.00 79.30

FREGADOR
TRAMPA DE GRASA Unidad 85.00 115.00 100.00 158.00 155.00 130.00 120.00 125.00 120.00 122.00
CAMBIO LLAVE DOBLE FREGADOR (SEGN TIPO) Unidad 42.50 57.50 50.00 79.00 77.50 65.00 60.00 62.50 60.00 61.00
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
CAMBIO LLAVE ANGULO Y TUBO ABASTO Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30
CAMBIO CONEXIN ANCHA FREG. 1-1/2 x 3-1/2 Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30
CAMBIO CONEXIN DOBLE Y TAIL PIECE PVC Unidad 15.30 20.70 18.00 28.44 27.90 23.40 21.60 22.50 21.60 21.96
CAMBIO TRAMPA DE 1-1/2 Unidad 7.65 10.35 9.00 14.22 13.95 11.70 10.80 11.25 10.80 10.98
CAMBIO ARANDELA Y ASIENTO LLAVE DOBLE Unidad 4.25 5.75 5.00 7.90 7.75 6.50 6.00 6.25 6.00 6.10
DESTAPAR FREGADERO Unidad 8.50 11.50 10.00 15.80 15.50 13.00 12.00 12.50 12.00 12.20

URINAL
CAMBIAR FLUOXOMETRO Unidad 157.25 212.75 185.00 292.30 286.75 240.50 222.00 231.25 222.00 225.70
CAMBIAR KIT FLUOXOMETRO Unidad 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
CAMBIAR SPOLD Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30
CAMBIAR TRAMPA 11/2 PLSTICA Unidad 7.65 10.35 9.00 14.22 13.95 11.70 10.80 11.25 10.80 10.98
CAMBIAR TAIL PIECE 11/2 Unidad 7.65 10.35 9.00 14.22 13.95 11.70 10.80 11.25 10.80 10.98
CAMBIO LLAVE ANGULO 1/2 URINAL PISO. Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30
CAMBIO CUBRE COBRE 1/2 x 8 Unidad 14.66 19.84 17.25 27.26 26.74 22.43 20.70 21.56 20.70 21.05
DESTAPAR URINAL Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30

LAVAMANOS Y FUENTE INTEGRAL


CAMBIO DE LLAVE DE CHORRO Unidad 8.50 11.50 10.00 15.80 15.50 13.00 12.00 12.50 12.00 12.20
CAMBIO DE TRAMPA DE 2 PLSTICA Unidad 8.50 11.50 10.00 15.80 15.50 13.00 12.00 12.50 12.00 12.20
DESTAPAR Unidad 12.75 17.25 15.00 23.70 23.25 19.50 18.00 18.75 18.00 18.30

OTROS
DESTAPAR LNEA PRINCIPAL (varia x distancia) Gl 48.88 66.13 57.50 90.85 89.13 74.75 69.00 71.88 69.00 70.15
DESTAPAR LNEA DE SERVICIO SANITARIO Gl 29.75 40.25 35.00 55.30 54.25 45.50 42.00 43.75 42.00 42.70
LETRINA DE CEMENTO O PORCELANA Gl 63.75 86.25 75.00 118.50 116.25 97.50 90.00 93.75 90.00 91.50
REPARAR ESCAPE DE AGUA EN PISO O PARED (picar) Gl 48.88 66.13 57.50 90.85 89.13 74.75 69.00 71.88 69.00 70.15
SUSTITUIR TUB. COBRE 1/2 TIPO L (B/. 1.90 x pie) ml 5.10 6.90 6.00 9.48 9.30 7.80 7.20 7.50 7.20 7.32

CERCA DE SEGURIDAD
BLOQUES DE 4 R/LISO DE 8' ALTURA m2 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80

MALLA ciclone de 8`completa+repello liso en base de bloques. ml 51.00 69.00 60.00 94.80 93.00 78.00 72.00 75.00 72.00 73.20

BLOQUES DE 4 REPELLADA MAS MALLA CICLONE ml 42.50 57.50 50.00 79.00 77.50 65.00 60.00 62.50 60.00 61.00
LISTADO DE COSTOS UNITARIOS ESTIMADO POR ACTIVIDAD
AUMENTO DE % POR AREAS INACCESIBLES
VERAGUAS
BOCAS CHIRIQUI VERAGUAS (STA. COLON (DONOSO,
ACTIVIDADES UNIDAD 15%MIN. 15%MAX PROMEDIO SAN BLAS DARIEN A.COMARCAL A.COMARCAL
(NURUM, SANTA
CATALINA) STA. ISABEL)
FE)
PORTONES DE MALLA CICLONE Unidad 29.75 40.25 35.00 55.30 54.25 45.50 42.00 43.75 42.00 42.70
0.00 0.00 0.00 0.00 0.00 0.00 0.00
GRAMA 0.00 0.00 0.00 0.00 0.00 0.00 0.00
TIPO CHORRERA m2 2.98 4.03 3.50 5.53 5.43 4.55 4.20 4.38 4.20 4.27
TIPO JAPONESA m2 3.83 5.18 4.50 7.11 6.98 5.85 5.40 5.63 5.40 5.49

TANQUES SPTICOS Y OTROS SISTEMAS


Tanque sptico, campo de drenaje, pozo ciego, cmara de
inspeccin Gl 4250.00 5750.00 5000.00 7900.00 7750.00 6500.00 6000.00 6250.00 6000.00 6100.00

Tanque sptico y filtro biolgico Gl 5100.00 6900.00 6000.00 9480.00 9300.00 7800.00 7200.00 7500.00 7200.00 7320.00
Campo de Filtracin, cmara de inspeccin y pozo ciego (L.
2805.00 3795.00 3300.00 5214.00 5115.00 4290.00 3960.00 4125.00 3960.00 4026.00
Mnima 100 mts)
Campo de Drenaje m/l 25.50 34.50 30.00 47.40 46.50 39.00 36.00 37.50 36.00 36.60
Pozo ciego Unidad 340.00 460.00 400.00 632.00 620.00 520.00 480.00 500.00 480.00 488.00
cmara de inspeccin Unidad 170.00 230.00 200.00 316.00 310.00 260.00 240.00 250.00 240.00 244.00
0.00 0.00 0.00 0.00 0.00
MISCELNEOS 0.00 0.00 0.00 0.00 0.00
Asta de Bandera y Pedestal Gl 1275.00 1725.00 1500.00 2370.00 2325.00 1950.00 1800.00 1875.00 1800.00 1830.00
Poste de canasta de baloncesto, tablero, red, pedestal (fijo) Gl 850.00 1150.00 1000.00 1580.00 1550.00 1300.00 1200.00 1250.00 1200.00 1220.00
Torre de canasta de baloncesto, tablero, aro, red movible Unidad 1275.00 1725.00 1500.00 2370.00 2325.00 1950.00 1800.00 1875.00 1800.00 1830.00
Tubos Galvanizados para red de Voleibol Unidad 63.75 86.25 75.00 118.50 116.25 97.50 90.00 93.75 90.00 91.50
Gabinete para llaves Unidad 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Llorones de PVC Unidad 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Llorones de Acero Galvanizado Unidad 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Cubierta de Panaletas m2 34.00 46.00 40.00 63.20 62.00 52.00 48.00 50.00 48.00 48.80
Cubierta de Panalit ondulado m2 25.50 34.50 30.00 47.40 46.50 39.00 36.00 37.50 36.00 36.60
Construccin de modulo de 4 letrinas (incluye cubiculos y
1700.00 2300.00 2000.00 3160.00 3100.00 2600.00 2400.00 2500.00 2400.00 2440.00
loza, etc.)
Piso de madera machambrada + estructura 2 x 6 m2 55.25 74.75 65.00 102.70 100.75 84.50 78.00 81.25 78.00 79.30

Cepillado, limpieza, sellado, reatornillado y pintado de techo m2 6.80 9.20 8.00 12.64 12.40 10.40 9.60 10.00 9.60 9.76

LIMPIEZA Y ORNATO
Limpieza General 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00