Hyperbaric Welding - The Zawtika Project is a gas field development

project located in the Gulf of Moattama, Myanmar.


Zawtika The development area covers Block M9 and small
portion of Block M11, owned by Myanmar Oil & Gas
Enterprise (MOGE). The field lies approximately 300
Project: km south of Yangon and 290 km west of Tavoy on
Zawtika Development Project the Myanmar coast and the average water depth is
approximately 135-160 meters. (relative to LAT).
Phase 1A
Zawtika Development Phase 1A consists of ZPQ (Processing
Client: platform integrated with Living Quarter module), a bridged-link
PTTEP International Limited wellhead platform WP1, two remote wellhead platforms WP2
and WP3, associated intra-field sealines, offshore and onshore
Location: gas export to connect to the PTT gas pipeline at Ban-I-Tong,
Onshore Operating Center (ZOC), Block Valve #1 and #2
ZPQ Platform, Gulf of Moattama, (ZBV1 and ZBV2), and Metering Station (ZMS).
Myanmar
Overview
Kreuz Subsea was the subcontractor for the diving activities for
Zawtika Project Phase 1A. The scope includes installation of 18
diameter rigid spool and 2 joints of dry hyperbaric welding for
28 diameter spool.

The 18 and 28 spools were prefabricated onshore in


Myanmar and transported to site using a materials barge. The
18 closing spools were fabricated and hydrotested after the
metrology had been done.

The hyperbaric welding for 28 Spool was performed at 138m


water depth inside the special enclosure structure called
Welding Habitat. Two (2) Pipe Handling Frames were also
utilized to align the 28 Spool to the Riser and Pipeline.

Detailed scope of work


1. Stinger Checks and other air diving support for 28 Pipeline
Installation
2. Two (2) joints of Hyperbaric Welding on the 28" Diameter
Spool connecting between Riser at ZPQ Platform and
Pipeline at 138m water depth
3. Installation of four (4) nos. of 18 Diameter Spools
connecting between Riser at ZPQ Platform and Pipeline at
138m water depth
4. Install six (6) nos. of Flange Protector on the 18 Diameter
spools
5. Removal of three (3) Riser Supports
6. Installation of seven (7) nos. of 28 Spool Bend Protection
7. Abandon Pipeline Recovery and Concrete Mattress
Installation

In order to ensure the safety, quality, and efficiency of the work,


all Diver-Welders hired by Kreuz Subsea had to be qualified at
the National Hyperbaric Center in Aberdeen, Scotland prior to
Installation Vessel: mobilization.
Kreuz Subsea chartered third party DP DSV
for the project
Project Type:
Subsea Construction
Water Depth:
130 - 140 MSW
Commencement Date: Location:
Approximately 300km
September 2012 south of Yangon and 290km
west of Tavoy on the
THAILAND
Myanmar coast.
Completion Date:
m
January 2014 ~230k