Académique Documents
Professionnel Documents
Culture Documents
From (25 -55) % of purchased equipment cost Ref [5] A percent of 50%
:was taken
The installation cost = $ 65,797,140
Instrumentation and controls .3
Instrument cost installation - labor cost and expenses for auxiliarys
equipment's and material constitute the major portion of the capital
investment required for instrumentation. This cost depends on the amount of
control required. It is between (8-50) % of the purchased cost for all
.equipment's
.The value 40% was taken
Therefore, the instrumentation cost = $ 52,637,712
Piping .4
The cost of piping covers labors, valves, fittings, pipe, supports and
other items involved in the complete erection of all piping used directly in the
.process
The cost as a percent from purchased = 75% Therefore, the cost of piping = $
98,695,710
Electrical installation .5
The cost of electrical installation consists: Primary of installation labor and
material for power and lighting with building services lighting usually included
.under the heading of building and service costs
The cost amount to (10-40) % of purchased equipment cost. The value of 30%
.was taken
Therefore, the cost of electrical installation = $ 39,478,284
.B. Building, process and auxiliary
The cost amount to (10-70) % of purchased equipment cost. The value of
.40% is the best percent for this plant
Therefore, the building cost = $52,637,712
C. Services facilities and Yard improvements
The cost about (40-100) % of purchased equipment cost, the value of 60%
of purchased equipment cost = $78,956,568
D. Land
The cost range as a percent of the equipment purchased cost is (4-8) %. The value of
5 % was used. Therefore, the land cost = $ 6,579,714
II. Indirect costs (IC) = Expenses which are not directly involved with
material and labor o f actual installation of complete facility (15-35%) of fixed-
.capital investment) REF [5]
Table (5-2) the indirect investment
FCI = $ 901,330,684.9
labor .1 (TPC)$0.15
Insurance.2 (FCI)$0.005
:Where
=Operati OL
labor. FCI plant overhead cost:(0.15 (TPC)$0.15 ng
TPC).C =$
901,330,684.9
TCI = $ 1,060,389,041
$ hr Btu
7.16
MMBtu year 8000 hr 47031.64
$
year 2,693,972,339
$
ton The NGL e price is equal = 467.6
4 Ib hr 1 Ton $ $
3.8760 10 8000 468 =647,845,71.43
hr year 2240 Ib Ton year
$
Ton The C5+ e price is equal = 507.5
4 Ib hr 1 Ton $ $
3.1620 10 hr 8000 year 2240 Ib 507.5 Ton =573,112,50 year
25
C .F
=106.7 = Rate of return (DCFROR)
T .C . I
T .C . I
Payback period = C .F = 1 Months & 7 Dyes