Daily Report

Project Name: KBK Project


Project Code: 03 YG 00400 Report Date : 11-May-2017 Thursday No. of Day 650 Report No. DPR-344
Project Start Date 2015-8-1 Contract Period 458 Calendar Day AM PM Fine
Weather
Estimate Completion Date 2016-10-31 Remain Period (192) Calendar Day 6~8 8~10 10 ~12 13~15 15~17 17~19 Rain
Work Force
M&E Site Survey Office General Crane Crane
Trades PM PE SAE Site Engr QA/QC QS Admin Safety Security Geotech Welder Steel Worker
engineer Store or Staff Workers Operator Helper
Today 1 1 1 1 1 1 1 2 1 3 3 13
Helper Manson Steel
Trades M&E Operator (ACP) Manson Carpenter Total
(ACP) worker Supervisior
Today 1 2 32
Machine & Equipments onsite
Description previous Today Cum. Remarks Description previous Today Cum. Remarks Description previous Today Cum. Remarks
70 Ton Crane 1 1 1 1.5 Hp Submer; pump 4 4 4 19KW Welding Box 6 6 6
Sheet pile machine 0 0 0 1 Hp Motor pump 1 1 1
3"x3" Air Compressor 1 1 1 1.5 Hp Motor pump 1 1 1
165 KVA Generator 0 1 1 2Hp Pressure pump 0 0 0
Material Delivery On Site
Quantity Quantity Quantity
Description Unit Description Unit Description Unit Remarks
Today Total Today Total Today Total
165 KVA Generator (UPG site) No 1 1

FO-OP-01 REV-00 Page: 1/2


Daily Report

Project Name: KBK Project


QC - Test Sampling
Item Remarks

Test
Sample
Taken

LTI Free Day UA,UC Near Miss FAI MTC LTA Daily TBT
HSE Conducted By
Safety Officer
Works Carried out Details
Trades Of Work Location Remark
1 Steel beam installation work at 7th to 8th floor At grid (C-D)
2 Welding work at column and beam joint 3th floor at grid (C-D) & 8th floor at grid (D-E)
3 Check alignment and fit bolt & nuts 5th floor , grid (C-D) & 10th floor , grid (D-E)
4 Prepare access road to come site office
5 Housekeeping work
6 Staircase-A installation work at 6th to 8th Floor At grid (C-D)
7 Prepare to install safety net at working area
Special Event

Visitors Site
Purpose
on site Instruction

Project Manager Project Engineer Prepare By: Site Engineer


Name U Khin Maung Myint Name Name Aye Wit Yee Soe
Signature Signature Signature

FO-OP-01 REV-00 Page: 2/2


KBK Project
Site Progress Photo
Date: 11.05.2017

Staircase-A installation work ( 6th to 8th Floor)

Steel structure installation work at 7th and 8th Floor


Welding work at column and beam joint

Prepare access road