Vous êtes sur la page 1sur 2

Important Notice

Polly Trottenberg, Commissioner


The NYCDOT Division of Bridges is continuing component rehabilitation of
the Queensboro Bridges 21st St. exit ramp. To facilitate construction
activities, a full closure of the 21st St. ramp will begin May 21, 2017 through
June 30, 2017. The ramp closure will take place Sunday night through Friday
morning between the hours of 11:00 p.m. and 5:30 a.m. . Please see detour
map on the following page.

Ed Koch
Queensboro
Bridge
( 21 Street exit ramp
upper deck)

Community Board No. 2

Queens

May 2017

Google Maps 2017

Full Closure 21st St. Ramp (upper deck)


Sunday Friday
11:00 p.m. 5:30 a.m.
May 21 through June 30

Questions regarding this project may be directed to Community Liaison Kisha


Dasent, at 917-558-5370 or via e-mail at manqensi9@gmail.com. For all NYC non-
emergency services, including inquiries regarding NYCDOT construction projects,
dial 311. Be prepared to give your name, borough, the project number (HBCR01C),
your city. your needs. and a return phone number.
your number.
Important Notice
Polly Trottenberg, Commissioner
Detour Map for 21st St. Ramp

Ed Koch
Queensboro
Bridge
( 21 Street exit ramp
upper deck)

Community Board No. 2

Queens
Google maps 2017
May 2017
= Closure = Detour Route
Detour Instructions
1. Proceed passed closed ramp to Thomson Ave.
2. Make a right on Thomson Ave. and continue to Jackson
Ave.
3. Turn left on to Jackson Ave.
4. Then a quick right hand turn on to 45th Ave.
5. Continue to 21st. street.

Questions regarding this project may be directed to Community Liaison Kisha


Dasent, at 917-558-5370 or via e-mail at manqensi9@gmail.com. For all NYC non-
emergency services, including inquiries regarding NYCDOT construction projects,
your city. your needs. dial 311. Be prepared to give your name, borough, the project number (HBCR01C),
your number. and a return phone number.