Description of works:

Fabrication of [ 3 x 1 x 1 : (16 sq. m)] hexagonal mesh type 100mm x 120 mm G


wire 12 swg, mesh wire 10 swg and selvedged wire 8 swg , including rolling, cutti
palcing in position including stretching, forming compartments; tying with bracin
providing and filling stone / boulder in gabion boxes / mattresses etc. including d
specification.
Spec. cl. No: 2401

Labour (A) Material (B)


Norms No.
Type Unit Qty. Rate Amount Type Unit

Fabrication of box: Activity no : 24.01.01

Mesh wire(10
0.63 340.20 kg
SWG)
Skilled md 540.00

Selvedge
0.28 106.40 kg
wire(8 SWG)
Unskilled md 380.00
Filling of stones : Activity no : 24.02.04

0.75 405.00 Block stone m3


Skilled md 540.00

2.25 855.00 Bond stone m3


Unskilled md 380.00
Tying of lids: Activity no : 24.02.01

Binding
1.04 395.20 m3
wire(12 SWG)
Unskilled md 380.00
Sub total of A = 2101.80 Sub to
Sub total of A +B + C = 7942.03 Contractor's ove

Description of works:
Fabrication of [ 2 x 1 x 1 : (11sq. m)] hexagonal mesh type 100mm x 120 mm G
wire 12 swg, mesh wire 10 swg and selvedged wire 8 swg , including rolling, cutti
palcing in position including stretching, forming compartments; tying with bracin
providing and filling stone / boulder in gabion boxes / mattresses etc. including d
Spec. cl. No: 2401 specification.

Labour (A) Material (B)


Norms No.
Norms No.
Type Unit Qty. Rate Amount Type Unit

Fabrication of box: Activity no : 24.01.02.2


Skilled md 0.34 540.00 183.60 Mesh wire (12 SWG) Kg
Unskilled md 0.15 380.00 57.00 selvedge wire(8 SWG) Kg
Filling of stones : Activity no : 24.02.04

0.50 270.00 Block stone m3


Skilled md 540.00

1.50 570.00 Bond stone m3


Unskilled md 380.00
Tying of lids: Activity no : 24.02.01

Binding
0.75 285.00 m3
wire(12 SWG)
Unskilled md 380.00
Sub total of A = 1365.60 Sub to
Sub total of A +B + C = 5370.78 Contractor's ove

Description of works:
Fabrication of [ 1.5 x 1 x 1 : (161sq. m)] hexagonal mesh type 100mm x 120 mm
wire 12 swg, mesh wire 10 swg and selvedged wire 8 swg , including rolling, cutti
palcing in position including stretching, forming compartments; tying with bracin
providing and filling stone / boulder in gabion boxes / mattresses etc. including d
Spec. cl. No: 2401 specification.

Labour (A) Material (B)


Norms No.
Type Unit Qty. Rate Amount Type Unit

Fabrication of box: Activity no : 24.01.02.2


Skilled md 0.28 540.00 151.20 Mesh wire (12 SWG) Kg
Unskilled md 0.12 380.00 45.60 selvedge wire(8 SWG) Kg
Filling of stones : Activity no : 24.02.04

0.38 202.50 Block stone m3


Skilled md 540.00

1.13 427.50 Bond stone m3


Unskilled md 380.00
Tying of lids: Activity no : 24.02.01

Binding
0.68 258.40 m3
wire(12 SWG)
Unskilled md 380.00
Sub total of A = 1085.20 Sub to
Sub total of A +B + C = 4311.15 Contractor's ove

Fabrication of hexagonal mesh type 100mm x 120 mm Gabion boxes / mattresses with diaph
selvedged wire 8 swg , including rolling, cutting and weaving ; assembling Gabion boxes ma
compartments; tying with bracing wires and tie wires; tying down the lid complete; and prov
etc. including dressing, beding, bonding and all transporation as per specification.

Box size Unit Qty. Amount


1.5 x 1 x1 Box m3 1.5 4957.82
2 x 1 x 1 Box m 3
2 6176.40
3 x 1 x 1 Box m3 3 9133.33
Total : 20267.55
Average (1m3) 3118.09
type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with binding
g , including rolling, cutting and weaving ; assembling Gabion boxes mattresses,
tments; tying with bracing wires and tie wires; tying down the lid complete; and
attresses etc. including dressing, beding, bonding and all transporation as per Unit : 1
box

Material (B) Equipment (C)


Qty. Rate Amount Type Unit Qty. Rate Amount
Necessary
testing of 2% of M.C. 114.51
materials

35.10 91.00 3194.10

3.90 91.00 354.90

3.00 609.70 1829.10

0.30 609.70 182.91

1.81 91.00 164.71

Sub total of B = 5725.72 Sub total of C = 114.51


Contractor's overhead expenses 15% = 1191.30 Unit Rate = 9133.33

type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with binding
g , including rolling, cutting and weaving ; assembling Gabion boxes mattresses,
tments; tying with bracing wires and tie wires; tying down the lid complete; and
attresses etc. including dressing, beding, bonding and all transporation as per Unit : 1
box

Material (B) Equipment (C)


Qty. Rate Amount Type Unit Qty. Rate Amount
Necessary
testing of 2% of M.C. 78.53
materials
24.15 91.00 2197.65
2.96 91.00 269.36

2.00 609.70 1219.40

0.20 609.70 121.94

1.30 91.00 118.30

Sub total of B = 3926.65 Sub total of C = 78.53


Contractor's overhead expenses 15% = 805.62 Unit Rate = 6176.40

esh type 100mm x 120 mm Gabion boxes / mattresses with diapharagms, with binding
g , including rolling, cutting and weaving ; assembling Gabion boxes mattresses,
tments; tying with bracing wires and tie wires; tying down the lid complete; and
attresses etc. including dressing, beding, bonding and all transporation as per Unit : 1
box

Material (B) Equipment (C)


Qty. Rate Amount Type Unit Qty. Rate Amount
Necessary
testing of 2% of M.C. 63.25
materials
19.75 91.00 1797.25
2.70 91.00 245.70

1.50 609.70 914.55

0.15 609.70 91.45

1.25 91.00 113.75


Sub total of B = 3162.70 Sub total of C = 63.25
Contractor's overhead expenses 15% = 646.67 Unit Rate = 4957.82

es / mattresses with diapharagms, with binding wire 12 swg, mesh wire 10 swg and
mbling Gabion boxes mattresses, palcing in position including stretching, forming
Unit : 1 m3
he lid complete; and providing and filling stone / boulder in gabion boxes / mattresses
er specification.