Vous êtes sur la page 1sur 14

Advances of Deep Foundations, Kikuchi, Otani, Kimura, Morikawa (eds), 101-114 (2007)

Current design practice for axially loaded piles and piled rafts in
Germany
C. Vrettos
Division of Soil Mechanics and Foundation Engineering, Technical University of Kaiserslautern,
67663 Kaiserslautern, Germany

ABSTRACT: The new generation of German DIN standards for geotechnical works adopted the philosophy
of the Eurocode EC7 introducing the limit state design approach. A summary of the relevant national
standards for pile design and construction is given. The design rules and the respective code provisions are
presented in detail, both for ultimate and serviceability limit states. Two illustrative pile design examples are
described. The second part of the paper provides an overview of the guideline contents for the design and
construction of piled raft foundations.

1 INTRODUCTION denotes the design value of the action effects and Rd


Traditional pile design in Germany was based on the denotes the design value of the resistance.
A review with focus on practical aspects and
global safety factor approach that uses a lumped
factor applied notionally to either the ultimate design methods is given by Kempfert et al. (2003).
strength or the applied load. This is deemed to The Working Group 2.1 on Piles of the German
Geotechnical Society (DGGT) is presently preparing
account for all the uncertainties inherent in the
a detailed report with recommendations covering all
design. This was the philosophy of the German DIN
standards until recently. The general code for major aspects of piling technology, design methods,
geotechnical design referring to the permissible and quality control.
loading of foundation soils was the DIN 1054:1976- In the following, the basic design principles of
the Eurocode and the relevant DIN standards as
11 issued in 1976. The standards for piles were the
applied to axially loaded pile foundations are
DIN 4014:1990-03 for bored piles, DIN 4026:1975-
08 for driven piles and DIN 4128:1983-04 for presented and two illustrative examples are given to
grouted piles. demonstrate the application of the new DIN
standards. Furthermore, the design principles for
In the frame of harmonisation of industrial
piled raft foundations that constitute a novel
standards within the European Union the member
states agreed to adjust their national codes to the foundation system for settlement-sensitive high-rise
building are given.
Eurocodes within a specified period of time. The
introduction of the Structural Eurocodes established
the limit state design (LSD) approach. A limit state
2 CODES AND DESIGN FUNDAMENTALS
is usually defined as any limiting condition beyond
which the structure ceases to fulfil its intended 2.1 Eurocodes and DIN standards
function. Limit state design considers the
While Eurocodes (EC) 2, 3, 4, 5, 6, and 9 refer to a
performance of a structure, or structural elements, at
given construction material (reinforced concrete,
each limit state. Typical limit states are strength,
steel, etc.), EN 1990 (Basis of design), Eurocode 1
serviceability, stability, fatigue. Different factors are
(Actions), Eurocode 7 (Geotechnical design) and
applied to loads and material strengths to account for
Eurocode 8 (Earthquake resistance) are relevant to
their different uncertainty. The new DIN standards
all types of construction, irrespective of the material
generation adopted that principle assuring
used. Eurocode 7 (EC7) consists of two parts:
compatibility with the Eurocodes.
EN 1997-1 Geotechnical design Part 1: General
The ultimate limit states are verified by applying
rules, and EN 1997-2 Geotechnical design Part 2:
partial factors to the main variables of the
Ground investigation and testing. Part 1 describes in
calculation model, and by verifying that the
a general form the principles for geotechnical design
fundamental inequality Ed Rd is fulfilled, where Ed
in the frame of the LSD concept as applied to the
calculation of the geotechnical actions on the - DIN EN 1538:2000 Execution of special
structural elements in contact with the ground geotechnical works - Diaphragm walls. This
(footings, piles, basement walls, etc.), as well as to document includes cast in situ concrete diaphragm
the deformations and resistances of the ground walls, precast concrete diaphragm walls, and
submitted to the actions from the structures. Pile reinforced slurry walls.
foundations are treated there in Section 7. Some - DIN 4126: Stability analysis of diaphragm walls.
detailed design rules or calculation models, i.e. Some additional ISO-standards that are
formulae or diagrams, are given only in Annexes developed specifically for piles are not expected to
that are informative except Annex A that is be introduced officially by the building control
mandatory in the normative sense. Annex A defines authority in Germany.
the partial factors for ultimate limit state in Standards that concern the public safety need in
persistent and transient design situations Germany approval by the building control authority.
(fundamental combinations), as well as correlation In this spirit and in order to enable the introduction
factors for the characteristic values of pile bearing of European standards that are often less binding in
capacity. The numerical values for the partial or content than the German ones, special technical
correlation factors are merely recommended values. reports (DIN-Fachberichte) are prepared as
These values can be changed in the National Annex application documents containing the necessary
to EN 1990-1, which is published by each country. additional provisions that render the European
Part 2 of EC 7 makes the link between the design standard more precise. Presently, only the DIN -
requirements of Part 1, in particular Section 3 Fachbericht 129:2005-02 Application document to
Geotechnical data, and the results of a number of DIN EN 1536:1999-06, Execution of special
laboratory and field tests. The standardisation of the geotechnical works - Bored piles is published, the
tests themselves is published by the TC 341 of CEN. other reports being in preparation.
All field and laboratory tests common in At the end of 2004 a two year period started
geotechnical practice are treated. A number of during which the National Annex (NA) to EC7-1
informative Annexes with examples of correlations had to be prepared. This Annex will contain the
and derivations of values of geotechnical parameters values of the design parameters required by EC7-1.
from field test results are included. At the same time a five-year period started at the end
In Germany pile design is presently specified in of which the EC7-1 in combination with the NA
the DIN 1054:2005-01, issued in the year 2005 that EC7-1 will be introduced nationwide removing all
replaced the old DIN 1054:1976-11. In addition, pile inconsistencies of national codes with respect to
design is regulated by the DIN EN 1997-1:2005-10 EC7-1.
that is the German version EC7-1. For steel piles the For the transition period a number of national
DIN EN 1993-5 (EC3-5) also applies. standards have been prepared that are concurrently
The following standards that establish the general valid with the new ones. In that sense the old
principles for the construction of the various pile standard for geotechnical design DIN 1054:1976-11
systems are issued as German versions of European that is based on the global safety factor approach
codes (EN): will be withdrawn an the end of 2007 being replaced
- DIN EN 1536:1999 Execution of special by the DIN 1054:2005-01 that is based on the partial
geotechnical works - Bored piles safety factor concept. A supplement standard
- DIN EN 12794:2005 Precast concrete products - DIN 1054:~2007 to be issued in 2007 will contain
Foundation piles. It covers both single length and solely specifications compatible to EC7-1. The
segmental piles for which the larger transverse DIN 1054 will be redrawn at the earliest in 2009.
dimension is not more than 1.5 times the smaller
transverse dimension.
2.2 Limit states
- DIN EN 12699:2001 Execution of special
geotechnical works - Displacement piles. This Two limit states are considered when undertaking a
document covers piles driven using impact, limit state design for foundations: ultimate (ULS)
vibration, pressing, screwing or a combination of and serviceability limit states (SLS).
these methods. The ultimate limit state governs the safety of a
- DIN EN 14199:2005 Execution of special structure against collapse or excessive deformation
geotechnical works Micropiles. This covers piles of a foundation leading to the collapse of the
with outside diameter smaller than 300 mm for structure it supports. It should have a very low
bored piles and smaller than 150 mm for probability of occurrence. In DIN 1054:2005 it is
displacement piles. referred to as GZ 1 and is further divided into three
Since diaphragm wall elements are often used in cases depending on the failure mechanism involved:
the sense of pile foundations the following - GZ 1A: Loss of equilibrium of structure or ground
construction standards are also relevant: without failure of the ground (uplift, buoyancy,
hydraulic heave, internal erosion, piping)
- GZ 1B: Failure of structure/structural element or combining EK 1 and SK 1, LF 2 by combining
failure of the ground supporting the structure either EK 2 and SK 1 or EK 1 and SK 2. Partial
(sliding, bearing resistance failure of foundations, safety factors are defined for the particular load
failure of piles, retaining walls, anchors etc.) cases. LF 3 when resulting as combination of EK 3
- GZ 1C: Loss of global stability induced by failure and SK 3 may require unit valued partial safety
of the ground and/or supporting elements such as factors for actions and resistances. Numerical values
anchors or nails for the partial safety factors for pile foundations are
The serviceability limit state, denoted by GZ 2 in given in the following sections of the paper.
DIN 1054:2005, governs situations beyond which Basic for the design are the characteristic values
specified functions of a structure or structural for actions and resistances denoted by the index k.
elements can no longer be satisfied, e.g. They are obtained from experiments, measurements,
deformation, settlement or vibration exceeding calculations or experience by considering the type of
specific values under normal working conditions. structure and design method, the quality and size of
The analysis usually involves the estimation of sample, and the sensitivity of the particular
deformation. parameter. The characteristic values of actions are
Eurocode EC7 defines the following limit states multiplied while these of the resistances are divided
in place of the states GZ1A, GZ1B, and GZ1C of the by appropriate partial safety factors. The resulting
DIN 1054:2005: EQU, STR, GEO, UPL, HYD values are the so-called design values denoted by the
denoting equilibrium, internal failure of index d.
structure, geotechnical failure, uplift, and
hydraulic failure, respectively. This implies that
2.4 Partial safety factors
for compatibility the state GEO has to be split into
two sub-cases GEO-1 and GEO-2. Due to the novelty of limit state design in most of
the European countries and the wide variety of soil
2.3 Actions and resistances conditions, soil testing and design methods, EC 7
allows for three different so-called Design
DIN 1054:2005 considers design situations for Approaches (DA 1, DA 2 and DA 3) when assessing
specific combinations of combinations of actions Rd and Ed for persistent and transient situations. The
EK 1 to EK 3 and safety classes of resistances SK 1
selection of the design approach and of the values of
to SK 3 yielding load cases 1 to 3 (LF 1 to LF 3).
More specifically it distinguishes between: the partial factors is left to national determination.
Combinations of actions (EK): Discussion and comparisons of results using the 3
- Regular combination of actions (EK 1): Permanent DAs may be found in Frank et al. (2004). The basic
and variable actions which occur regularly during principle for the selection of design approach in
the lifetime of the structure; Germany was to maintain the safety level of the
- Rare combination of actions (EK 2): Actions of former global safety factor approach.
EK1 plus rare or onetime actions;
- Exceptional combination of actions (EK 3):
Actions of EK1 plus exceptional actions occurring 3 PILE DESIGN ACCORDING TO
at the same time, e. g. accidents, earthquakes or DIN 1054:2005
other catastrophic events.
3.1 General
Conditions of safety classes of resistances (SK):
- SK 1: Conditions valid for the lifetime of the In pile design it is distinguished between internal
structure; and external bearing capacity. The former refers to
- SK 2: Conditions valid during repair or check against failure of the pile material (concrete,
construction of the structure or of nearby steel etc) itself while the latter refers to bearing
structures; capacity check of the ground supporting the pile.
- SK 3: Conditions which may most likely occur According to DIN 1054:2005 this corresponds for
only once or never during the life time of the piles to the ultimate limit state GZ 1B (in EC7-1:
structure. STR for the internal, GEO-2 for the external bearing
Load cases: capacity). For tension piles the Limit state GZ 1A of
- Load case 1 (LF 1): Permanent or temporary DIN 1054:2005 (UPL in EC7-1) has to be checked
design situations during the lifetime of the in addition.
structure;
- Load case 2 (LF 2): Temporary design situations
3.2 Actions
during construction or repair;
- Load case 3 (LF 3): Accidental design situations. For piles it is distinguished between:
The relevant combinations are defined in - Foundation loads, e.g. from the superstructure
DIN 1054:2005. For example, LF 1 is obtained by building;
- Soil-specific loads (e.g. from downdrag, bending the pile load test results. For intermediate values a
due to settlement, lateral earth pressure); linear interpolation is applied.
- Dynamic and cyclic loads.
Table 1. Correlation factor in dependence on the number of
From these characteristic actions one obtains the pile load tests N and the dispersion of the measured values
characteristic loads Ek on the piles: according to DIN 1054:2005.
FG,k and FQ,k, and, HG,k and HQ,k, from permanent
(index G) and variable loads (index Q) on the Correlation factor
Number Average value Minimum value
pile head in axial and transverse horizontal direction, of tests N R1m R1m, min
respectively, as well as bending moments MG,k and
s N / R1m = 0 s N / R1m = 0.25
MQ,k, due to various permanent and variable actions.
1 - - 1.15
All these loads have to be transferred to the 2 1.05 1.10 1.05
ground fulfilling the internal and external capacity >2 1.00 1.05 1.00
check.

3.3 Characteristic resistances The use of the correlation factor was not
customary in Germany and is a compromise with
It is customary in Germany to determine the axial respect to the future introduction of the Eurocode.
pile resistances not via calculation methods but on The values of the correlation factor in the
the basis of
DIN 1054:2005 are different from those given in the
- Static load tests
- Dynamic load tests EC7-1 in combination with the National Annex, cf.
- Empirical correlations Frank (2006). The procedure defined in the DIN
basically corresponds to the experience in Germany
with the global safety factor concept.
3.4 Pile resistance from static load tests In the event where the limiting resistance is not
Following the DIN 1054:2005, when piles are explicitly identified from the measured resistance vs.
designed from static load tests the measured settlement curve it is assumed that it occurs at a
resistance values R1m,j are obtained from the in-situ settlement of
experimental resistance vs. settlement/heave curves
(RSC/RHC). From these data one then determines s1 = 0.10 Db (3)
the characteristic RSC/RHC curves that are the basis
for the design and the capacity check. where Db is the diameter of the pile base.

3.4.1 Characteristic resistance for ULS 3.4.2 Characteristic resistance for SLS
Characteristic values of resistance for the limit state The transfer of the rules defined in Table 1 to the
GZ 1 are obtained from the measured ones R1m,j by derivation of characteristic resistance vs. settlement
dividing them with a correlation factor . This curves (RSC) for the serviceability limit state could
corresponds to the recommendation given in EC7-1. produce undesirable jumps in the characteristic
The characteristic value R1,k is obtained as the RSC. DIN 1054:2005 recommends a qualified
minimum of the pile load test results according to weighting of the results of pile tests at the SLS
equation (1): enabling the derivation of a characteristic RSC that
should be continuous.
R1,k = Min {R1m ,min / ; R1m / } (1) A practicable solution is the following: If the
measured RSC show relatively uniform dispersion
with values smaller than s N / R1m = 0.25 or
where R1m,min and R1m are the minimum and average
s N / Rm = 0.25 a single correlation factor is
values of measured resistance, respectively, is the determined using the average value Rm , whereas for
correlation factor as given in Table 1, and
values larger than 0.25 the correlation factor is
determined using Rm, min . Only for non-uniform
i =1( R1m R1m, j ) 2 /( N 1)
N
sN = . (2)
dispersion with values lying below and above the
limiting value 0.25 would jumps in the curve be
If more than one pile contributes to the load transfer produced. A meaningful correction is then applied to
to the ground, e.g. when using a rigid pile cap, and if the experimental curve that has to be verified by a
the dispersion coefficient s N / R1m 0.25 , it is geotechnical expert.
allowed to use from Table 1 the average value R1m of
3.4.3 Static axial load tests CASE and TNO formulae and the CAPWAP
The performance of pile tests of static or dynamic TNOWave, respectively. In the Rapid Load Test the
nature is standardised in Germany in the direct method is performed by means of the
Recommendations for Static and Dynamic Pile Tests Unloading Point Method. This procedure is however
of the German Geotechnical Society, Working not allowed by the DIN 1054:2005.
Group 2.1, DGGT (1998).
One pile test should be carried out for each
Table 2. Increase of correlation factor according to Table 1
uniform subsoil condition, whereas for foundations when evaluating dynamic pile load tests.
with more than hundred piles two pile tests are
recommended. For sensitive buildings and buildings 1) Calibration on static pile load tests
of geotechnical category GK 3 (for the definition of Location of pile Analysis procedure Increase
GK see below) the number of pile tests is defined in test
cooperation with the geotechnical expert. For Same site Extended method None
micropiles DIN 1054:2005 requires at least 2 piles to (e.g. CAPWAP)
be tested, at minimum at 3% of all piles. Direct Method = 0.10
The testing load shall be large enough in order to (e.g. CASE-formula)
reach the limit state GZ1 fulfilling one of the Different project Extended method = 0.05
following criteria: Direct method = 0.15
a) Limiting settlement: 2) Deduction from general empirical values = 0.15
R g1 = R ( s g ) (only extended method permitted)
Note: When applying the correlation factors from Table 1 to
with sg = 0.1D whereby D is the pile diameter for dynamic load tests, the double number of tests must be
uniform cylindrical piles, the diameter of the pile available in the first column in Table 1 (e.g. static N = 1,
base for piles with widened base, and the equivalent dynamic N = 2).
pile diameter (same area) for piles with rectangular
cross section. 3.6 Pile resistance from empirical correlations
b) Creeping behaviour:
R g1 = R ( k s ) This applies mainly to bored piles and corresponds
to the traditional practice followed in Germany.
where ks is an individually specified amount of
Characteristic values for base resistance qb,k and
creep.
shaft friction at each layer qs,k,i are directly
With respect to the necessary instrumentation
separate monitoring of shaft and base resistance is determined from values of soil parameters using
required when soil is strongly nonhomogeneous, appropriate charts and tables. The variation of pile
shaft resistance after reaching peak value drops to a resistances with settlement s underlying the design
much lower residual value, and when strict criteria procedure is depicted in Figure 1, with Rk(s), Rb,k (s),
are imposed on limiting displacement values. In and Rs,k(s) denoting the characteristic values of
standard cases recording of pile head settlement is total, base, and shaft resistance of the pile,
considered sufficient. respectively. The characteristic axial pile resistance
is
3.5 Pile resistance from dynamic load tests Rk ( s ) = Rb,k ( s ) + Rs ,k ( s ) = qb,k Ab + q s ,k ,i As ,i (4)
i
Under certain circumstances DIN 1054:2005 allows where Ab and As,i are the pile base area and shaft
the determination of pile resistances from dynamic surface in layer i.
load tests. Correlation factors have also to be
In Figure 1 sg denotes the limiting settlement with
considered as given in Table 1. The required number
s g = 0.10 Db
of dynamic tests as well as the increase in the value
of the factors is summarized in Table 2 in that is set equal to the settlement at the ultimate limit
dependence on the available data from comparable state GZ 1.
static tests and the testing procedure used. For the pile settlement at the SLS the relevant
With respect to the data reduction procedure it is parameter is the pile shaft diameter Ds.
distinguished between direct and extended methods. The limiting settlement for the mobilisation of
The former are based on one-dimensional wave shaft resistance is defined by the following equation
propagation theory and allow the direct on-site with settlements given in [cm] and resistance in
estimation of the bearing capacity reached, while the [MN]:
latter incorporate the complete model of the pile s sg = 0.50 Rs , k ( s sg ) + 0.50 3.00 (5)
embedded in the soil. Typical examples are the
Table 4. Pile base resistance for bored piles in cohesive soils
according to DIN 1054:2005.

Pile base resistance qb,k


Relative pile
at an average shear strength cu,k of
head settlement
s/Ds and s/Db the undrained soil in [MPa]
0.10 0.20
0.02 0.35 0.90
0.03 0.45 1.10
0.10 (= sg) 0.80 1.50
Intermediate values are obtained by linear
interpolation. For bored piles with widened base values
shall be
reduced to 75%

Table 5. Pile shaft resistance for bored piles in cohesionless


Figure 1: Elements of characteristic resistance vs. settlement soils according to DIN 1054:2005.
curves for bored piles according to DIN 1054:2005.
Average tip resistance of Ultimate value qs,k of pile
CPT in [MPa] shaft friction in [MPa]
When determining the characteristic axial pile 0 0
resistance vs. heave curve for bored piles it is set 5 0.040
10 0.060
s sg , tension = 1.30 s sg . (6) 15 0.120
Intermediate values are obtained by linear interpolation
The informative Annex B to DIN 1054:2005
summarizes empirical correlations as determined
from a large number of static pile load tests both for Table 6. Pile shaft resistance for bored piles in cohesive soils
pile shaft and pile base resistance. They are valid for according to DIN 1054:2005.
bored piles with diameter Db or Ds from 0.30 to Shear strength cu,k of Ultimate value qs,k of pile
3.00 m that are embedded at least over 2.50 m in undrained soil in [MPa] shaft friction in [MPa]
bearing layer. These empirical values are given in 0.025 0
dependence on the CPT tip cone resistance qc for 0.10 0.040
0.20 0.060
cohesionless and on the characteristic value of Intermediate values are obtained by linear interpolation
undrained shear strength for cohesive soils cu,k,
respectively, cf. Tables 3 to 6. When applied for
estimating the pile base resistance the tip cone Table 7. Pile base and pile shaft resistance for bored piles in
resistance of the CPT is usually determined as an rock according to DIN 1054:2005.
average value over a depth from 1D above to 4D Uniaxial compression Pile base Pile shaft
below the pile base for pile diameters D 0.6 m, and strength qb,k resistance qb,k friction qs,k
1D above to 3D below the pile base for D > 0.6 m. in [MPa] in [MPa] in [MPa]
For pile shaft friction the average over a layer with 0.50 1.50 0.08
small scatter in the data is taken. Values for rocks 5.00 5.00 0.50
are reproduced in Table 7. 20.00 10.00 0.50
Intermediate values are obtained by linear interpolation
Table 3. Pile base resistance for bored piles in cohesionless
soils according to DIN 1054:2005. For displacement piles and micropiles equation (4)
Pile base resistance qb,k in [MPa] is valid accordingly, however only for the limit state
Relative pile at an average tip cone resistance qc GZ 1.
head settlement of the CPT
s/Ds and s/Db in [MPa] R1, k ( s ) = Rb1, k ( s ) + Rs1, k ( s ) =
10 15 20 25
0.02 0.70 1.05 1.40 1.75
= qb1,k Ab + qs1,k ,i As,i (7)
i
0.03 0.90 1.35 1.80 2.25
0.10 (= sg) 2.00 3.00 3.50 4.00 Some recommended empirical values are
Intermediate values are obtained by linear summarized in Annex C and D of DIN 1054:2005.
interpolation. For bored piles with widened base values
shall be reduced to 75%
3.7 Bearing capacity check for axial loading F2, d R2, d = R2, k (11)
In limit state GZ 1 the characteristic values of the
loads imposed by the superstructure on the piles Crucial to the serviceability is the estimation of the
Fk are multiplied by the partial factors on actions to differential settlements between the individual piles
obtain the design values: within a pile group or between supports consisting
of single piles or pile groups. They may result in an
F1, d = Fk , G G + Fk ,Q Q (8) ultimate limit state for the superstructure. The
amount of differential settlement s depends mainly
on the pile type and the absolute settlement s2.
where G and Q are the partial safety factors for
Typical values for s/s2 range from 1/3 for bored
unfavourable permanent and variable actions,
piles to 1/4 for displacement pile foundations.
respectively. The partial factors depend on the load
The method suggested by the DIN 1054:2005 is
case (LF 1 to LF 3) considered as given in Table 8.
schematically shown in Figure 2 with s2,k denoting
the allowable settlement, as defined e.g. from the
Table 8. Partial safety factors for actions for the ultimate limit structural analysis of the superstructure. The
state GZ1B according to DIN 1054:2005. restraint inducing differential settlement is estimated
as
Action Factor LF1 LF2 LF3
Permanent G 1.35 1.20 1.00
Unfavorable variable Q 1.50 1.30 1.00 s2, k = s2, k (12)

whereby the factor depends on the pile installation


The design value of the pile resistance is determined method, the soil stratigraphy, and the position of the
from equation (9) using the partial safety factor for piles within the foundation system and shall be
pile resistance R as given in Table 9: determined in agreement with a geotechnical expert.
In absence of specific investigations a first estimate
R1, d = R1, k / R (9) = 0.15 is often used in practice.

Table 9. Partial safety factors for pile resistances for the R 2,k R 1,k R R 2,k R 1,k R
ultimate limit state GZ 1B according to DIN 1054:2005. s2,k min
s 2,k 2s 2,k
s 2,k
Pile resistance Factor LF1-LF3 Secant for
spring coefficient
Resistance in compression from s 2,k max
Pc 1.20
pile load test s1,k Rk s1,k Rk
Resistance in tension from pile
Pt 1.30
load test
s s
Resistance in compression and
(a) (b)
tension from empirical P 1.40
correlations
Figure 2. Resistance of single pile R2,k at SLS from a
characteristic resistance vs. settlement curve according to
DIN 1054:2005 for small (a) and considerable (b) expected
Finally, the bearing capacity for the ultimate limit differential settlements between piles.
state is checked requiring

F1, d R1, d (10) 3.9 Pile groups


Note that for load case LF 1, that describes Due to the interaction of piles in a pile group the
persistent situations, the average partial factor for resistance vs. settlement curves of the individual
actions G,Q 1.4, and the partial factor for piles are different than those of the single isolated
resistance R 1.4 when pile resistance is pile strongly depending also on the position within
determined from empirical correlations. This yields the group. It may also happen that for large
1.4 1.4 2.0, that corresponds to the value of the settlements the resistance of the piles in a group is
traditional global safety factor. larger than that of the isolated single pile. At
working loads conditions, however, a group pile will
settle more than the single one. Although the
3.8 Serviceability check for axial loading application of computational method for the
The serviceability check for limit state GZ 2 requires assessment of resistance vs. settlement curve is not
allowed by the DIN 1054:2005 the prediction of
group behaviour is feasible only by means of an micropiles (Annex D of DIN 1054:2005) or increase
appropraite mechanical model. This in turn is by 50% the shaft resistance values of conventional
difficult to be defined due to the influence of the bored piles given in the tables above.
installation method, and of the prevailing soil Resistance of tension piles shall be determined
conditions. A practicable solution consists in using solely by static load tests, exept for the case that a
the resistance curve for a single pile and applying a certified geotechnical expert allows it.
theoretical model that describes as close as possible
the group effects. In this sense, a distinction between 4 GROUND INVESTIGATION FOR PILES
bored and displacement piles is necessary. While the
installation for displacement piles makes the reliable The results of the ground investigation shall be
prediction of group effects almost impossible due to sufficient to provide information for the proper
the induced soil displacement, the carefull installation of piles according to the respective
installation of bored piles affects the gound to a DIN EN construction standards. The extent of these
much lesser extent. In general, due to the pre- investigations depend according to DIN 4020:2003-
stressing of the soil between the piles and the 9 Geotechnical investigations for civil engineering
influence of the induced driving energy the expected purposes on the geotechnical category of the
settlement of displacement piles will be smaller than project and are set-up in detail by a geotechnical
that of bored piles. The distance, beyond which the expert.
interaction two neighboring piles becomes According to DIN 1054:2005 foundations are
classified into the geotechnical categories (GK)
negligible is often set equal to 6 to 8 pile diameters.
whereby the lowest category GK1 is not applicable
DIN 1054:2005 does not require for pile groups to piles.
the verification of bearing capacity. An alternative GK 2 is relevant e.g. when pile settlement is
approach is based on the suggestions of EC7 and important for the structural system, pile resistance is
examines two failure mechanisms: i) compressive determined from empirical correlations and simple
and pull-out resistance of the piles individually, and soil conditions, or negative friction is expected. The
ii) compressive or pull-out failure of the piles and highest category GK 3 includes among other
the soil contained between them acting as a block. situations with highly loaded piles at low values of
For the prediction of settlements and the verification permissible settlements and/or shaft and base
of serviceability a number of computational methods grouting, estimation of resistance from empirical
are available in the literature that should be used correlations at difficult soil conditions, piled-raft
with engineering judgement because of the difficulty foundations, and cyclically loaded piles when
in assessing the effects of pile ground geometry, soil sufficient experience is not available for the
properties, and pile cap stiffness. For pile particular type of pile. The depth of investigation is
defined by the DIN 4020:2003.
foundations consisting of end-bearing piles the total
Bearing capacity of cohesionless soils should be
settlement may be calculated by adding the parts due determined on the basis of the tip resistance of the
to the settlement of an equivalent deep sited raft CPT. Correlations between qc and the blow count
foundation at the level of the pile base, and the numbers N of SPT or Dynamic Probing Heavy
settlement of the individual piles. The calcualtion of (DPH), e.g.
differential settlements, that are crucial to potential
distortion of the superstructure, requires, however, qc (CPT) N10 (DPH)
more elaborate methods.
or other correlations based on the relative density
have been proven in practice.
3.10 Special pile types The undrained shear strength of cohesive soils is
Shaft-grouted bored piles are often used to enhance usually determined from undrained triaxial tests and
shaft resistance in soils of low relative density or verified by empirical relations based on soil
soft consistency and also as remedial measure when consistency or CPT results. For soft soils the field
the vicinity of the pile is disturbed due to the pile vane tests is also used.
construction. Often, base-grouting is also performed
for increasing load carrying capacity. Grouting is
carried out using tube-a-manchette in stages after 5 DESIGN EXAMPLES FOR PILES
casting the bored piles. Site-specific instrumented
5.1 Pile design from empirical correlations
trial piles are usually carried out to confirm the
design parameters and verify the construction The example is taken from the DIN 4014:1990-03.
method. For preliminary design one may use the We consider an axially loaded bored pile to be
empirical relations for shaft resistance of grouted designed from the empirical correlations given in the
Annex B of DIN 1054:2005. Pile geometry, soil depth of 3D (here 3D = 2.70m) below the pile base
stratigraphy, and soil properties are given in level. From the CPT-profile an average value of
Figure 3. The clay layer is characterized by the qc,m = 17.5 MPa is obtained.
undrained shear strength cu.k while for the sandy By applying the numerical values given in
layer the profile of the CPT tip cone resistance is Table 3 for qc,m we get the settlement-dependent
given. First, the depth profile of the CPT is divided values of the pile base resistance as summarized in
into sublayers of constant cautious estimates of the
Table 11.
average values.
q c [MPa] Table 11. Pile base resistance for design example.
0 5 10 15 2 0 25
Relative settlement qb,k Rb,k (s)
Fill
s/D [MPa] [MN]
2.2 m 2 0.02 1.225 0.784
0.03 1.575 1.008
Clay cu,k = 0.1 MPa
Depth below ground surface [m]

4 0.10 3.250 2.080


5.2 m 10.2 m
6 Since the values for pile resistances given in the
qc,2 = 7 MPa
Annex B of DIN 1054:2005 are already
characteristic ones, the correlation factor does not
Sand 8
need be considered.
qc,3 = 11 MPa
The characteristic resistance vs. settlement curve
10 is finally determined by the addition of the two
0.90 m resistance components, as depicted in Figure 4 with
12 qc,4 = 17.5 MPa 3D the numerical values given in Table 12.

Table 12. Pile resistance in dependence on pile head settlement


14 for design example.
Relative Pile head
Rs,k (s) Rb,k (s) Rk (s)
Figure 3. Design situation for example of pile design from settlement settlement
[MN] [MN] [MN]
empirical correlations: soil profile, CPT tip resistance, and pile s/D [cm]
geometry. ssg 1.2 1.357 0.509 1.866
0.02 1.8 1.357 0.784 2.141
From Table 5 and 6 one obtains the ultimate values 0.03 2.7 1.357 1.008 2.365
0.10 9.0 1.357 2.080 3.437
of pile shaft friction for sand and clay, and with the
mantle area the pile shaft resistance values Rs,k,i as
listed in Table 10.

Table 10. Ultimate values for pile shaft friction for design
example

Layer i As,i cu,k,i qc,i qs,k,i Rs,k,i


[m] [m2] [MPa] [MPa] [MPa] [MN]
2.20 - 5.20 8.48 0.10 0.040 0.339
5.20 - 7.70 7.07 7.00 0.056 0.396
7.70 - 10.20 7.07 11.00 0.088 0.622
Rs ,k = 1.357

From the ultimate value of pile shaft friction Rs,k we


obtain using equation (5) the settlement for the
mobilisation of shaft friction ssg in [cm] with Rs,k in
[MN]

s sg = 0.50 Rs,k + 0.50 = 1.20 cm . Figure 4. Resistance vs. settlement curve from empirical
correlations for the design example

In order to determine the pile base resistance Rb,k an


average value of the soil strength is derived over a
5.2 Pile design from static pile load test results Table 13. Results of two pile load tests together with the
derived numerical values of the characteristic resistance vs.
The pile foundation as depicted in Figure 5 with a settlement curves for a flexible and a rigid structural system.
pile diameter D = 0.90 m, permanent load
FG,k = 1.20 MN and variable load FQ,k = 0.60 MN is s [cm] 0 1 2 4 6 9
considered. The results of the two pile load tests Rm,min [MN] 0 1.60 2.20 3.15 3.60 3.95
carried out are given as values Rm,min and Rm,max in Rm,max [MN] 0 1.80 2.65 3.50 4.00 4.40
Table 13. The settlement giving the limit load is Rm [MN] 0 1.70 2.43 3.33 3.80 4.18
defined according to equation (3) as s1 = 0.190 cm = flex [-] 1.05 1.05 1.05 1.05 1.05
9 cm. The prescribed allowable pile settlement is Rk,flex [MN] 0 1.52 2.10 3.00 3.43 3.76
s2 = 2.0 cm. s N / Rm [MN] 0 0.08 0.13 0.07 0.07 0.08
rigid [-] 1.07 1.08 1.07 1.07 1.07
FG,k = 1.20 MN Rk,rigid [MN] 0 1.59 2.25 3.12 3.57 3.92
FQ,k = 0.60 MN

Resistance R [MN]
0 2 4 6
0

Rk,rigid
-2 Rk,flex
Pile D = 0.90 m Rm,max
Settlement s [cm] Rm,min
-4
Figure 5. Design situation for example of pile design from
static load tests
-6
5.2.1 Characteristic pile resistance
The characteristic pile resistance vs. settlement
curve is determined according to DIN 1054:2005 as -8
follows. If it is assumed that the load from the
superstructure is not distributed to more than one
pile (i.e. load transfer from weak to strong -10
piles), the design departs from a flexible pile cap,
and the characteristic values of the resistance vs. Figure 6. Derivation of characteristic resistance vs. settlement
settlement curve is determined from the minimum curves form the pile load tests.
values of the test results Rm,min. The correlation
factor is = 1.05, cf. Table 1. The resulting pile
resistance is given in Table 13 and Figure 6.
E1, d = GG , k G + FQ , k Q =
If on the other hand the pile cap is rigid enabling the
redistribution of pile loads, the characteristic pile = 1.2 1.35 + 0.6 1.50 = 2.52 MN
resistance is allowed to be determined from the
average value from all pile tests conducted. For R1, d = R1, k / Pc = 3.76 / 1.20 = 3.14 MN > 2.52 MN
relative values of the data dispersion s N / Rm 0.25
the correlation factor is obtained by linear
b) Load distribution by rigid cap (rigid system):
interpolation and is applied to the entire resistance
vs. settlement curve thus avoiding discontinuities in
the curve. The resulting resistance vs. settlement E1,d = 2.52 MN
curve is depicted in Figure 6 with the numerical R1, d = R1, k / Pc = 3.92 / 1.20 = 3.27 > 2.52 MN
values summarized in Table 13.
5.2.3 Serviceability check
5.2.2 Bearing capacity check From the characteristic loads F2,k resulting from the
At the ultimate limit state GZ 1B the condition structural analysis we have
E1,d R1,d
E2,d = E2,k = FG,k + FQ,k = 1.20 + 0.60 = 1.80 MN

has to be verified. For load case LF 1 we have: The allowable characteristic pile resistance in the
a) Independently acting piles (flexible system): serviceability limit state is obtained from Figure 6:
R2,d = R2,k = 2.10 MN > 1.80 MN (flexible system) individual piles and between pile and raft as
schematically shown in Figure 7. Back analysis of a
R2,d = R2,k = 2.25 MN > 1.80 MN (rigid system) static pile test is commonly used to verify the
assumptions of the model and the values of the
Hence, for both cases the SLS check is fulfilled. parameters.
The serviceability limit check can be also
performed via the pile settlement: From Figure 6 we Ftot,k
obtain for the characteristic pile load F2,k = 1.80 MN
the settlement for a flexible system s2 = 1.50 cm,
while for a rigid system s2 = 1,30. Both values are
smaller than the allowable settlement of 2.00 cm.
(x,y)
Rpile,k,1 Rpile,k,j
6 PILED RAFT FOUNDATIONS
6.1 General and design methods
Piled rafts are a new foundation concept for
important high-rise buildings and have been
successfully used in Germany since the beginning of (x,y)
the 90s, Katzenbach et al. (2000). This foundation
type is a viable alternative to conventional pile or
raft foundations in competent ground. The combined z
foundation is able to support the applied axial
loading with an appropriate factor of safety at a
tolerable level of settlement under working loads. qs,1(z)
The implementation of this foundation type led to an qs,j(z)
abolishment of complicated settlement-correction qb,1 qb,j
techniques. During the last years the computational
methods available in combination with Interactions: 1 Pile -soil
measurements on real projects allowed the realistic 2 Pile-pile
modelling of the complicated bearing behaviour of 3 Raft-soil
that composite foundation system. The bearing 4 Pile-raft
behaviour is described by means of the pile raft
coefficient pr that defines what amount of the total Figure 7. Interactions in a piled raft foundation (Hanisch et al.,
force Ftot,k is carried by the piles. Hence, pr ranges 2001).
from 0 for a raft to 1 for a pile foundation. Due to
the strong nonlinearity of the pile bearing behaviour The design work consists in estimating the
the pile raft coefficient depends on the stress level deformation behaviour of the composite system and
and accordingly also on the amount of settlement of the distribution of the load into its two components,
the piled raft foundation. The piles can be loaded up pile group and raft. The available methods may be
to their ultimate bearing capacity, and are spaced divided into i) approximate analytical, ii)
strategically to achieve a more uniform settlement approximate numerical, and iii) refined numerical,
thus reducing sectional forces in the raft and leading the choice being dictated by the importance of the
to a more economical solution. project. An overview is given by Poulos (2001).
This new foundation concept has been introduced The aim of the design process is to optimize the
very recently in the DIN 1054:2005 in Section 8.5.5. position and the geometry of the piles. The solution
For the design reference is made to the of the soil-structure interaction problem is obtained
corresponding guideline (Hanisch et al., 2001) and by means of a pseudo-coupled procedure that is
to the fact that a project specific approval by the based on an interaction between the designers of the
building control authority is required. superstructure and the foundation system, resp. The
The guideline requires the computational model interface in this design procedure is defined in terms
applied to be able to simulate: i) the bearing of the modulus of subgrade reaction for the raft and
behaviour of a single pile taking into account the the spring coefficients for the individual piles.
shearing along the pile shaft and the compression at For the preliminary design, where different
the pile base, and ii) the interaction effects between foundation alternatives are compared, a flexible
simplified method is required to assess the influence - Homogeneous soil conditions with no abrupt
of the pile group configuration and of the soil changes in soil stiffness;
parameters. An approximate method that is an - Foundation loaded at its center of gravity with no
extension of the method outlined by dynamic effects.
Randolph (1994) has been presented by the author It should be noticed that the check of the external
(Vrettos, 2006). The method allows the bearing capacity of the individual piles is not
accommodation of the variable pile distance and required.
length as well as the different stiffness of central,
peripheral, and corner piles. 6.2.2 Internal bearing capacity
For the final design a nonlinear finite element All foundation elements shall be checked against
analysis with an appropriate soil model is usually material failure for all relevant combinations of
carried out for important projects. In the past, the actions. In particular, piles shall be designed for
majority of these calculations used an elastoplastic compression combined with bending and shear,
Drucker/Prager cap model mainly due to the fact tension during construction stages, and downdrag.
that this formulation is already implemented in The raft shall be checked for bending, shear, and
numerical codes. punching shear at the slab-column and slab-pile
connections.
The partial resistances of raft and piles depend on
6.2 Ultimate Limit State
the stress level induced by the actions. Therefore it
The guideline for piled rafts adopted the limit state is required that the pile raft coefficient pr be
design philosophy and distinguishes for limit state calculated both for the ultimate and the
GZ 1 between external and internal bearing capacity. serviceability limit state. The sectional forces of the
The methodology defined by the EC7-1 for piles can raft and of the piles are computed for the load
not be directly applied to piled rafts. distribution on piles and raft corresponding to the
pile raft coefficient. The more unfavourable results
6.2.1 External bearing capacity are then used for the structural design.
The calculation of the resistance vs. settlement
curves for the overall foundation system is carried
out using a computational model accounting for the 6.3 Serviceability Limit State
interaction effects and applying a global safety
Checking is carried out for limit state GZ 2 in
factor to the characteristic values of actions. analogy to the bearing capacity check by setting for
the partial safety factor a value equal to 1.
n
Fk ,i R1,tot,k (13)
6.3.1 External serviceability
i =1
The requirements of serviceability of the system are
with equal to 2.0, 1.75, and 1.50 for load case fulfilled when
LF 1, LF 2, and LF 3, respectively.
Assessment of the characteristic value of the total n
resistance R1,tot,k is made on the basis of the induced
E Fk ,i C .

(14)
i =1
total settlement, i.e. the point at which the settlement
starts to increase at a higher rate. The effects E dependent on the actions Fk,i are
If the check is not performed by an adequate computed by an adequate model based on
realistic computational model it is allowed in simple characteristic values of the material properties.
cases to calculate the total resistance R1,tot,k by means The resistance parameter C is in most cases the
of the characteristic value of the base resistance of tolerable settlement of the piled raft foundation. It is
the foundation raft, i.e. ignoring the vertical bearing defined e.g. from the requirements referring to
capacity of the piles. Dowel resistance of the piles connections of service pipes in the building, the
along the failure surface may be considered in the settlement of adjacent buildings, or the bending and
analysis. tilting of the superstructure itself. In practice, for the
Simple cases are defined as follows: serviceability of elevators but also for optical
- Geometrically uniform piled raft, i.e. identical pile reasons tilting shall be limited to 1:1000. It should
length and diameter, constant pile spacing, also be noted that according to observations - even
rectangular or circular raft, overhang of less than for homogeneous soil conditions, symmetrical
three pile diameters at the edges of the raft; building and loading - differential settlements may
reach values in the order of 30% to 50% of the total - Verification of the computational model and the
settlement. assumptions made regarding soil parameters;
DIN 1054:2005 specifies for the serviceability - Timely detection of critical situations;
check a value of the safety factor for the actions - Observation of the evolution of settlements during
equal to 1.0 both for permanent and variable loads. the construction.
However, relevant for serviceability are the The program includes measurement of:
settlement-inducing loads. It is therefore - Load-settlement behaviour of the foundation by
recommended here when consolidation effects are geodetic methods;
of minor importance to reduce the permanent load - Load share between raft and piles by recording
of the superstructure by the own-weight of the soil-raft contact pressure and pile loads;
foundation slab and to add in absence of detailed - The bearing behaviour of typical piles (central,
information 30% of the variable load. edge, corner) comprising the pile head and pile base
force as well as the distribution of skin friction along
6.3.2 Internal serviceability the pile shaft;
Piles have to be checked for the allowable crack - The variation of soil deformation with depth.
width. The raft has to be checked in addition for the In simple cases measuring only the load-
amount of differential settlements that may lead to settlement behaviour will be sufficient.
structural distortion of the superstructure.

7 CONCLUSIONS
6.4 Checking of design and supervision of
construction
The adoption of the Eurocodes by the national DIN
Design and construction shall be approved by a standards resulted in important changes in the design
geotechnical expert particularly qualified for this philosophy with a unified set of principles for all
job. The following works have to be done: geotechnical design. It motivates a systematic
-Examination of the ground investigations and thought about uncertainty in soil parameters and
laboratory testing program and the interpretation of makes clear distinction between ultimate and
the results serviceability limit states. In German standards the
- Plausibility check of the characteristic values of basic principle for selecting numerical values for the
soil parameters used in the computational model partial safety factors is maintaining the safety level
- Examination of the computational model adopted of the former global safety concept. The
for the design and of the numerical results using an methodology for piles outlined in the
independent calculation method DIN 1054:2005 standard follows past experience
- Set-up and supervision of the monitoring program, and provides guidance by specifying pile resistances
and verification of design assumptions against field for a variety of pile types and soil conditions.
observations. The design methodology for piled rafts is
The construction of the piled raft foundation shall embedded in the limit state design philosophy.
be supervised by a geotechnical expert assigned by Design work requires the close cooperation between
the client and approved by the building control the structural and the geotechnical engineer in order
authority. to optimize the foundation with respect to the
It should be noted that for quality control settlements and construction costs.
purposes the DIN requires that designs be subjected
to review by checking engineers who need a
special official registration. However, responsibility
for the design remains with the design engineer. REFERENCES

DGGT - German Geotechnical Society 1998. Recommen-


6.5 Monitoring dations of the Working Group 2.1 on Static and Dynamic
The bearing behavior and the load transfer have to Pile Testing (in German).
Frank, R. 2006. Design of pile foundations following
been monitored under the supervision of a qualified Eurocode 7, Proc. XIII Danube-European Conference,
geotechnical expert. Monitoring may comprise the Ljubljana.
excavation, the foundation and the adjacent
buildings. The monitoring program is an
indispensable component of the safety concept and
serves the following needs:
Frank, R., Bauduin, C., Driscoll, R., Kavvadas, M., Krebs
Ovesen, N., Orr, T. and Schuppener, B. 2004. Designers
Guide to EN 1997: Geotechnical design-General rules.
London: Thomas Telford.
Hanisch, J., Katzenbach, R. and Knig, G. 2001. Kombinierte
Pfahl-Plattengrndungen. Berlin: Ernst & Sohn.
Katzenbach, R., Arslan, U., and Mooramann, C. 2000. Piled
raft foundation projects in Germany. In J.A. Hemsley (ed.),
Design Applications of Raft Foundations: 323-391.
London: Thomas Telford.
Kempfert, H.-G., Eigenbrod, K. D. and Smoltczyk U. 2003.
Pile Foundations. In U. Smoltczyk (ed.), Geotechnical
Engineering Handbook, 3: 83:227: Berlin: Ernst &
Sohn/Wiley.
Poulos, H.G. 2001. Piled raft foundations Design and
applications, Geotechnique 50(2): 95-113.
Randolph, M.F. 1994. Design methods for pile groups and
piled rafts. Proc. 13th Int. Conf. Soil Mech. Found. Engng.,
New Delhi, 5: 61-82.
Vrettos, C. 2006. Ein Nherungsverfahren zur Berechnung von
Pfahl-Plattengrndungen mit unregelmiger Geometrie. In
F. Rackwitz (ed.), Entwicklungen in der Bodenmechanik,
Bodendynamik und Geotechnik: 303-312. Berlin: Springer.

Vous aimerez peut-être aussi