CONSTRUCTION METHOD JETTY HERA

Plan Heras EPC of Tank Farm Terminal & Facilities Timor Leste
Step 1. Temporary Jetty & Temporary Acces to Piling
Step 2 Piling ( pemancangan)

2.1 Driving from Land side ( Dia. 355.6 mm)


2.2 Piling Sea Side Main Jetty & Dolphin ( Dia. 610.0 mm)
Step 3. Pile Cut Off
Step 6. Instal Precast Pile Cap Main Catwalk
Step 7. Instal Formwork Mooring & Breasting Dolphin
Step 8. Pile Head Treatment Concrete
Step 9. Formwork & Pouring Concrete Dolphin
Step 10. Install Precast Pile Cap Main Platform
Step 11. Pouring Concrete PHT and Cap
Step 12. Instal Precast Beam Main Platform
Step 13. Pouring Concrete Slab Main Platform
Step 14. Instal Catwalk
Step 15. Instal Last Catwalk