PROJECT MANAGEMENT

REVEALED
TRAINING BOOK
SECOND EDITION
BY IO4PM
www.io4pm.org

COPYRIGHT INTERNATIONAL ORGANIZATION FOR PROJECT MANAGEMENT


Dedication
To all of the IO4PM students, thank you for inspiring us, keeping us focused, and making
sure we do our best to help you grow in your career with your skills and knowhow. Without
you, your engagement and your loyal support, IO4PM could not come where it is today.
TABLE OF CONTENTS CLICKABLE
WELCOME ........................................................................................................................6
ABOUT IO4PM - INTERNATIONAL ORGANIZATION FOR PROJECT MANAGEMENT ...........7
WHAT IS PROJECT MANAGEMENT? ...................................................................................8
ORGANIZATIONAL INFLUENCES AND PROJECT LIFECYCLE ...............................................12
PROJECT MANAGEMENT PROCESSES..............................................................................15
ROLES IN PROJECT MANAGEMENT ..................................................................................19
SCOPE MANAGEMENT ....................................................................................................27
TIME MANAGEMENT .......................................................................................................42
COST MANAGEMENT ......................................................................................................57
QUALITY MANAGEMENT .................................................................................................65
HUMAN RESOURCES MANAGEMENT ...............................................................................77
COMMUNICATIONS MANAGEMENT..................................................................................90
RISK MANAGEMENT .......................................................................................................98
PROCUREMENT MANAGEMENT.....................................................................................109
STAKEHOLDER MANAGEMENT......................................................................................125
Thank you ..................................................................................................................131
WELCOME
Hi! Im Jenny. Therefore, we wrote for you Project Management
Revealed and brought it for your service!
I love that you are taking your time to read your
Project Management book. I want to briey share We are absolutely condent that Project Manage-
with you why we wanted to write this book for you ment Revealed will make you procient in Project
and how you can get the best use out of it. Management, so that you will have an outstanding
opportunity to love Project Management and keep
Within the context of our Project Management on taking the tangible benets of being a Project
certication programs we made a thorough research Management professional.
in Project Management education space.
Take some coee to enjoy and some paper to
The conclusion was: We failed to nd one single take your notes, and spend some quiet time to
textbook, we could sincerely recommend to our read your Project Management book!
students!
Afterwards you will have a great understanding
We talked to our successful students and found out about Project Management domain and be prepared
that, almost none of the Project Management books to pass your Project Management certication exam.
in the market could really help them make a smooth You will be ready to deliver great products and
entry to Project Management. Signicant number of services to your clients and employers and to build
Project Management books in the marketplace claim your bright career and future!
that they cover all details of Project Management,
but what they are not telling is that, they don't have Jenny Evans
understandable, clear and logical content to help Chief Operations Lead
their readers comprehend and most importantly love IO4PM - International Organization for
Project Management! Project Management

6
ABOUT IO4PM - INTERNATIONAL ORGANIZATION FOR PROJECT MANAGEMENT
IO4PM is an independent institute which helps pay expensive fees for the one way prot-driven
organisations and professionals get accredited with Project Management Certication Programs of other
worldwide renowned and valid Project Management Certication Entities.
certication programs and prove their competence
in Project Management domain. We empower IO4PM aims to remove the barriers set in front of
professionals worldwide to build their careers, and the Project Management Practitioners in developed
companies to create and sell their outstanding and emerging markets by saving them from paying
products and services. unreasonable fees for Project Management Classro-
om Trainings and Project Management Certication
Your Accredited Project Manager, Accredited Prog- Examinations before they certify their knowhow in
ram Manager, Accredited Product Manager, Accredi- Project Management.
ted Service Manager, Accredited Project Quality
Manager and Accredited Project Requirements Moreover, feel free to check out "What makes Your
Analyst Certication Programs have proven their Certication Programs Best of the Industry?" section
worldwide Acceptance and Reputation by being the on our www.io4pm.org web portal to read why we
choice of more than 535'000 Project Management perform and serve you far more better than our
Practitioners in 143 Countries. competition.

Project Management is a set of open Product and IO4PM provides 6 major online Project Manage-
Service Delivery Frameworks, and yet before IO4PM ment Certication Programs which are designed by
was established, there used to be no reasonable way our consortium of renowned business and people
for Project Management Practitioners like yourself to Leaders, coaches, mentors, experts and authorities
obtain Project Management Certications and to from all major industries. You can check your Project
prove your competence in Project Management Management Certication Programs from this List of
domain. Project Management Practitioners had to Project Management Certications.

7
WHAT IS PROJECT MANAGEMENT? cost, quality, human resources, communication, risk,
procurement and stakeholder management.

DEFINITION OF A PROJECT
A project is a temporary eort to create unique
product, service or result. A project has a denite
start and end.

A project management plan is created by a project


manager. This plan requires buy-ins from all
stakeholders. The plan should be realistic, time-
bound and achievable.

OPERATIONAL WORK
An organization can either have operational work or
project work. The dierence between operational
Project Management and Program Management
work and project work is that the operational work is
High Level Overview
always ongoing whereas project work has a denite
end.

WHAT IS A PROGRAM?
WHAT IS PROJECT MANAGEMENT?
A group of projects is termed as a Program. There
Project Management is not about managing people
are several projects carried out in an organization
alone. Project management can be divided into
and managing these projects independently
dierent process groups and knowledge areas.
becomes a challenge for the organization. Hence, a
Process groups include initiating, planning,
group of related projects is combined together in a
executing, monitoring and controlling, and closing.
program.
Knowledge areas include integration, scope, time

8
PROJECT MANAGEMENT OFFICE
The project management oce (PMO) is a centrali-
zed department that manages projects. The PMO
can:
Central location and authority for providing
policies, methodologies and templates for
managing projects within the organization
Relationship between Program and Projects Trains individuals in project management
within the organization
Assists them with project management tools
WHAT IS A PORTFOLIO? Provide project managers for dierent
A portfolio includes a group of programs and projects, these project managers and the PMO
individual projects that are implemented to achieve a oce are responsible for the results of those
specic strategic business goal. projects

The project management oce is a department of


many individuals. The PMO has responsibilities such
as:
Manage needs and interconnectedness bet-
ween projects
Provide resources
Participate in project review meetings
Monitor compliance with organizational pro-
cesses
Provide templates
Relationship between Portfolio, Program and Provide centralized communication about
Projects projects

9
Be a part of change control board If these knowledge areas are managed well, they can
Help prioritize projects help in successfully achieving the project objectives.

BUSINESS VALUE You can also use a Project Charter to articulate the
Business value is dened as the total sum of tangible need of the project eectively. Below is a sample
and intangible elements of a business i.e. the total template of a Project Charter.
value of the business. Monetary assets, xtures,
stockholders, equity, utility are some of the examples
of tangible elements. Intangible elements include
goodwill, reputation, brand recognition, public
benet, trademarks, etc. Eective management of
ongoing operations help in creating value for the
business. All organizations, prot driven or non-
prot organizations are focused on attaining
business value for their activities.

OBJECTIVES
The project objectives are dened in a project
Project Charter Example
charter. A project is considered as complete when
the objectives of the project are met. A project is
terminated if the project objectives are not met.
MANAGEMENT BY OBJECTIVES (MBO)
Objectives may be dened at a high-level initially,
MBO is a management philosophy with three steps:
however, will be dened in detail as the project
Establish clear, concise, well-articulated and
progresses. Project manager is responsible to
realistic objectives
achieve project objectives. Quality management, risk
Periodic reviews required to check if objectives
management, stakeholder management, scope
are met
management all has an impact on project objectives.

10
Implement corrective actions wherever the project. The project may fail if stakeholders are
deviations are observed not informed, their inputs are not solicited or their
needs and expectations are not satised. A project
CONSTRAINTS manager is required to analyze and manage
Constraints can be in the area of time, cost, risk, stakeholder s needs and levels of inuence
scope, quality, resources, customer satisfaction and throughout the lifecycle of the project.
others. Constrains help evaluate competing
demands. The priority of each constraint is set by the
management. A change to one constrain can have an
impact to other constraints of the project.

Project inevitably goes through many changes due to


the competing demands we were talking about
earlier. Each change request goes through a change
request process. A project manager has to evaluate
these changes and identify the impact on all the
constraints of the project through integrated change
control process.

S TA K E H O L D E R S A N D S TA K E H O L D E R
MANAGEMENT
Stakeholders can be project managers, sponsors,
team members, project management oce, portfolio
managers, program managers, functional managers,
and sellers. Basically, stakeholders are those
individuals, groups or organizations that are Project Constraints
positively or negatively impacted by the product or

11
ORGANIZATIONAL INFLUENCES AND
PROJECT LIFECYCLE
ORGANIZATIONAL STRUCTURE
A project operates within people, process and
technology of an organization. Projects have an
impact on the culture, policies, procedures and other
aspects of an organization. The organizational
structure has a major inuence on the execution of
the project. The organizational structure decides the
resources, communication methods and other Functional Project Organization
aspects of project management.

Dierent types of organizational structures include: PROJECT-CENTRIC ORGANIZATION


In a project-centric organization environment, the
FUNCTIONAL ORGANIZATION entire company is organized by projects, and the
This is the most common form of an organization. project manager is in control of the projects.
Organizational departments are grouped by areas of Individuals or employees are assigned to projects
specialization within dierent functions. In these and report into a project manager. Once the project
organizations, projects generally occur in silo is over, they need to be assigned to another project.
environments, i.e. within the same function. Team Communication primarily occurs within the same
members complete the project work over and above project.
their responsibilities to normal departmental work.
Communication primarily occurs within the same
function.

12
Weak Matrix Project Organization
Project Centric Project Organization

MATRIX ORGANIZATION
In a matrix organization, the team members report
into two bosses: the functional manager and the
project manager. Communication goes from team
members to both bosses. The matrix organization is
created to get the best potential from both
functional and project-centric types of organizational
structure. Team members have departmental work
and they also do project work.

Balanced Matrix Project Organization

13
LIFE CYCLE
A progression through a series of developmental
stages is termed as a lifecycle.

PRODUCT LIFE CYCLE


The product life cycle starts at the conception of a
new product and ends at its withdrawal.

PROJECT LIFE CYCLE


A project life cycle is required to be executed to
produce the deliverables of the project. The life cycle
of a project can span from initiation phase to its
Strong Matrix Project Organization closure phase and may involve some additional or
some reduced steps varying from industry to
industry.
Depending on the strength of the matrix organiza-
tion, the power or level of authority varies between PROJECT MANAGEMENT PROCESS
the project manager and the functional manager. In A project management process includes Initiating,
a strong matrix organization, the power remains with Planning, Executing, Monitoring and Controlling, and
the project manager. In a weak matrix organization, Closing process groups.
the power remains with the functional manager. The
project manager is considered to be a coordinator or LESSONS LEARNED
an escalator. In a balanced matrix, the power is The lessons learned document includes the
equally balanced between the project manager and experience of the project manager on what was
the functional manager. done right or what was done wrong on the project
and what should a project manager do dierently on
the project.

14
PROJECT MANAGEMENT PROCESSES identied stakeholders, and the strategy for
managing those stakeholders.

The project management processes involve: INPUTS TO INITIATING PROCESS GROUP


Start Initiating the project The inputs to Initiating Process Group may include:
Plan Planning the project Business case
Act Executing the project Product description
Check and Act Monitoring and Controlling Linkage of companys strategy with the project
the project Likely stakeholders
End Closing the project Contracts
Current Industry Standards
Change Control System
Dened processes and procedures
Project Management Processes Templates from past projects
Historical Work Breakdown Structures (WBS)
Historical Estimates
INITIATING PROCESS GROUP Understanding companys culture
Ocial authorization of the project is received in the Possible team members
Initiating Process Group. The project manager
receives necessary information to begin the project. Lets discuss these points in detail:
It formally starts a new project.
PROGRESSIVE ELABORATION
Initiating Process Group can involve starting the The process of continually rening estimates and
project selection process. A project charter is scope is termed as Progressive Elaboration.
created, stakeholders are identied and high-level
needs of these stakeholders are identied. Outputs
of this process group involve project charter,

15
PROJECT MANAGER ASSIGNED actually doing the work. Project planning presents a
The project manager is assigned during the Initiating good opportunity to save time, resources and
phase in the project. money. A detailed analysis of whether the project
team can achieve the project objectives is done in
BUSINESS CASE the Planning process. All of the knowledge areas of
Business Case denes the reason why the project the project are assessed and a roadmap is identied
was started. The project manager needs to know the to accomplish the project successfully.
reason why the project was started. If the reasons
are known, the project activities get impacted in the Planning Process Group involves:
right way and the project team is able to bring the Creating a Project Management Plan
right outcome for the project. Identifying Stakeholders and their needs
Collecting Requirements
HIGH-LEVEL PLANNING IS DONE DURING PROJECT Dening Scope
INITIATING Creating WBS
High-level planning involves: Dening Work packages and Activities
1 Creation of High-level WBS Sequencing Activities
2 Perform order of magnitude estimating Estimating Activity Resources
3 Perform high-level risk identication Estimating Activity Durations
Developing Schedule
The high-level planning eort is a part of creating Estimating Costs
project charter, which is further used to document Determining Budget
project objectives, milestone schedules, and initial Planning Quality
budget of the project. Developing Human Resource Planning
Planning Communication
PLANNING PROCESS GROUP Planning Risk Management
Planning process allows creation of a blue-print of Identifying Risks
the project i.e. getting the project organized before

16
Performing Qualitative and Quantitative Risk Group. The focus is on managing people, following
Analysis processes, and distributing information.
Planning Risk Responses
Planning Procurements The actions required for Executing Process Group
are:
The output of the planning eort includes project Direct and Manage Project Execution
management plan and project documents. Project Perform Quality Assurance
planning is iterative. The individual management Acquire Project Team
plans are combined together into the overall project Develop Project Team
management plan. The amount of time spent in Manage Project Team
project planning and the level of detail achieved in Distribute Information
the plan should be appropriate to the needs of the Manage Stakeholder Expectations
project. Some projects cannot be fully planned to a Conduct Procurements
detailed degree at the start of the project. These
projects are organized by phases. Everyone is The process of project management is iterative and
involved in the project planning process. Project thus, not always performed in the same sequence.
manager compiles the project plan with inputs from Thus, execution means executing the latest revision
stakeholders, historical records, company policies, of the project management plan.
etc.
MONITORING AND CONTROLLING PROCESS
As changes occur, project plan needs to accommo- GROUP
date those changes. Monitoring and Controlling Process Group requires
several activities. It involves measuring the
EXECUTING PROCESS GROUP performance of the project with the project
Completing the work as dened in the project management plan, approving change requests,
management plan and meeting the project including corrective and preventive actions and
objectives is the purpose of Executing Process defect repair.

17
The actions required in Monitoring and Controlling CLOSING PROCESS GROUP
Process Group are: Project is completed only when the project closure is
Monitor and Control Project Work completed. The actions required for Closing Process
Perform Integrated Change Control Group are:
Verify Scope Close Project or Phase
Control Scope Close Procurements
Control Schedule Once the administrative pieces of project closure are
Control Costs completed and formal sign-o that the product of
Perform Quality Control the project is acceptable is received from the
Report Performance customer, other stakeholders, and/or the sponsor,
Monitor and Control Risks the project is closed. The project manager can thus
Administer Procurements release any resources who had been helping to close
the project.

18
ROLES IN PROJECT MANAGEMENT ROLE OF A PROJECT MANAGER
The role of a project manager is to manage the entire
project to meet its objectives.
Project Management involves multiple individuals.
Each individual plays a crucial role. Lets look at the The role may include:
dierent roles involved in Project Management. Assigned to the project no later than project
initiating
Helps write the project charter
In charge of the project; not necessarily the
resources
Does not have to be a technical expert
Inuences the project team and the atmosp-
here in which the team works by promoting
good communication, isolating the team from
having to deal with politics, enhancing the
positive aspects of cultural dierences, and
resolving team issues
Ensures professional interaction between the
project team members and other stakeholders
Coordinates interactions between the project
and key stakeholders
Selects appropriate processes for the project
Identies and analyses constraints and as-
sumptions
Leads and directs project planning eorts
Roles in Project Management Identies dependencies between activities

19
Must understand how to handle unrealistic Must have the authority and accountability
schedule requirements to produce a realistic necessary to accomplish the project manage-
schedule ment work
Understands and enforces professional and Must say no when necessary
social responsibility The only one who can integrate the project
Identies and delivers required levels of quality components into a cohesive whole that meets
Assists the team and other stakeholders during the customers needs
project execution Spends more time being proactive than dealing
Denes the project change management plan with problems (being reactive)
Maintains control over the project by measu- Accountable for project success or failure
ring performance and determining if there are Performs project closing at the end of each
any variances from the plan phase and for the project as a whole
Determines the need for change requests, Performs or delegates most of the project
including recommended corrective and management activities
preventive actions and defect repair, and either Overall, applies project management knowled-
approves or rejects changes as authorized or ge and uses personal and leadership skills to
submits the change request to the change achieve project success
control board
Uses metrics to see variances and trends in ROLE OF A PROGRAM MANAGER
project work The program manager is responsible for managing a
Works with team members to resolve varian- group of related projects. Projects are combined into
ces from the project management plan programs to provide coordinated control, support
Keeps the team members focused on risk and guidance. The program works to meet project
management and possible responses to the and program goals.
risks
Develops time and cost reserves for the project The role of the program manager may include:

20
Managing related projects to achieve results He should play an important role in launching
not obtainable by managing each project a new product in the market as per the market
separately study
Ensuring selected projects support the He should also be a sounding board for his
strategic goals of the organization operational team to stop production of any of
Providing oversight to adjust projects for the its non-performing products
programs benet Responsible to manage products performance
Guiding and supporting individual project in the market
managers eorts
ROLE OF A SERVICE MANAGER
ROLE OF A PRODUCT MANAGER A Service Manager is primarily responsible for
This role is focused on strategic activities to deliver managing service delivery for a given product or a
market requirements. service.

The role includes: He/She is primarily involved in:


Product Manager should be able to study the Monitoring the overall performance of his
market needs and identify the current Service area
opportunities and threats based on these Identifying metrics for performance and
nding and observations tracking them
He should be able to explore the opportunities Continue relationships with dierent teams
and minimize the threats to make his including the Information Technology (IT) team,
organization successful Business Partners and others
For products which are already in the market, Responsible to manage teams performance in
he should monitor their performance and also the service area
keep a close check on competitors products

21
ROLE OF A PRODUCT QUALITY MANAGER Identication of stakeholders: Stakeholders are
Product Quality Manager is primarily responsible for any individual who is impacted by the process.
managing the product quality. They can be sponsor, management team,
process owner, project manager, subordinates,
His role includes: analysts, users, among others. Project
Product Quality Manager has to identify the manager also plays a key role in identifying the
critical parameters/metrics that could fail the stakeholders and the requirements analyst
product when in use works with him for the identication.
He is responsible to identify and implement Dening Business Needs: The business needs
audit mechanisms for these products. The can include business requirements, functional
audit mechanism can include total products to requirements, non-functional requirements,
be sampled, the quality audit process, user requirements, information on size and
identication and selection of quality auditors, complexity of the project, assumptions and
their training process, calibrating quality constraints.
auditors, among others. Analyze Requirements: Analyze requirements
Quality Audit Manager should also create a include identifying the stated and un-stated
mechanism to track and monitor quality needs of the customer. Conicting and
performance of the product unambiguous requirements are identied and
further claried.
ROLE OF A PROCESS REQUIREMENTS ANALYST Document Requirements: Documenting the
The primary role of a process requirements analyst is requirements is another important role of a
to gather, analyze, document and validate the needs requirements analyst. The documentation has
of the project through various stakeholders. The role to be clear, concise, unambiguous and
encompasses working with the project or the complete.
product manager. Validate and Prioritize Requirements: This is an
important role where the analyst reaches out
The role can be divided into: to project stakeholders to validate the

22
documented requirements. Validating require- Provides information that helps develop the
ments is further accompanied by prioritizing project charter
them. Gives the project manager authority as
outlined in the project charter
ROLE OF A SPONSOR Helps organize work into appropriate projects
The role of a sponsor prior to (or during) project Sets priorities between projects
initiation: Encourages the nalization of high-level
Has requirements that must be met requirements and scope by the stakeholders
Is a project stakeholder Guides the process to get the project approved
Advocates for or champions the project, and formalized, assisted by the project
especially while the project concept is being manager as necessary
put together
Serves as a voice for the project or spokes- The role of a sponsor during project planning:
person to those who do not know about the Provides the project team with time to plan
project, including upper management May review the WBS
Gathers the appropriate support for the Supplies list of risks
project Determines the reports needed by manage-
Ensures buy-in throughout the organization ment to oversee the project
Provides funding Provides expert judgment
Provides the project statement of work Helps evaluate trade-os during crashing, fast
Provides information regarding initial scope of tracking, and reestimating
the project Approve the nal project management plan
May dictate milestones, key events, or the
project end date The role of a sponsor during project execution,
Determines the priorities between the monitoring and controlling:
constraints Protects the project from outside inuences
and changes

23
Enforces quality policies Decompose work packages for which they are
Provides expert judgment responsible into schedule activities
Helps evaluate trade-os during dicult times, Help identify dependencies between activities
tracking, and reestimating Provide time and cost estimates
Resolves conicts that extend beyond the Participate in risk management process
project managers control Comply with quality and communications plan
Approves or rejects changes or authorizes Help enforce ground rules
someone representing him or her to do so Execute the project management plan to
May direct that a quality assurance review is accomplish work dened in the project scope
performed statement
Claries scope questions Attend project team meetings
Works with the project manager to monitor Conduct process improvements
progress Recommend changes to the project, including
corrective actions
The role of a sponsor during project closing:
Provides formal acceptance of the deliverables Some team members may have project management
Supports the collection of historical records responsibilities in addition to their responsibilities of
from past projects implementing work. If so, they are considered part of
project management team.
ROLE OF THE TEAM
The team is a group of people who will complete ROLE OF STAKEHOLDERS AS A GROUP
work on the project. The team may help to: The stakeholder is anyone who can positively or
Identify and involve stakeholders negatively inuence the project, including the
Identify requirements customers or users, the project manager and team,
Identify constraints and assumptions the projects sponsor, program and portfolio
Create the WBS managers, the PMO functional managers within the

24
organization, and external sellers that provide In a matrix organization, the functional manager
services or materials for the project. shares responsibility for directing the work of
individuals with the project manager. In a project-
The stakeholders may be involved in: centric organization, the project manager does all of
The creation of the project charter and the the directing. In functional organization, the
project scope statement functional manager does all of the directing. It is the
Project management plan development responsibility of the project manager to avoid any
Approving project changes and being on the conicts with the functional manager and coordinate
change control board the respective needs regarding the use of resources
Identifying constraints to complete the project work.
Identifying requirements
Risk management The activities of a function manager may include:
The stakeholders may also become risk response Assign specic individuals to the team, and
owners. negotiate with the project manager regarding
resources
ROLE OF A FUNCTIONAL MANAGER Let the project manager know of other projects
A functional manager manages and owns the that may impact the project
resources in a specic department, such as IT, Participate in the initial planning until work
engineering, public relations, or marketing, and packages or activities are assigned
generally directs the technical work of individuals Provide subject matter expertise
from that functional area who are working on the Approve the nal schedule during schedule
project. development
Approve the nal project management plan
The degree to which a functional manager is involved during project management plan development
in the project depends on the form of organizational
structure:

25
Recommend changes to the project, including
corrective actions
Manage activities within their functional areas
Assist with problems related to team member
performance
Improve sta utilization

ROLE OF A PORTFOLIO MANAGER


The portfolio manager is responsible for governance
at an executive level of the projects or programs that
make up a portfolio. A project is included in a
portfolio based on the value of the project, the
potential return on investment, whether it meets the
corporate strategy, whether the level of risk
associated with the project is acceptable, and other
factors critical to organizational success.

The role of a portfolio manager may include:


Managing various projects or programs that
may be largely unrelated to each other
Ensuring selected projects provide value to the
organization
Working with senior executives to gather
support for individual projects
Getting the best return from resources
invested

26
SCOPE MANAGEMENT Scope denition helps us make sure that we are
doing all the work but only the work included in the
scope management plan. Gold plating a project
When a construction site is being built, the (adding extras) is not allowed.
constructor raises a fence on the site dening the
boundaries of the construction. This process of Changes in scope must be taken into consideration
building a fence is called scoping. Scope manage- all the knowledge areas of project management such
ment is the process of dening what work is required as time, cost, risk, quality, resources and customer
and then making sure all of that work and only that satisfaction. Integrated change management process
work is done. is required to approve changes to scope of a project.
Integrated Change Management includes updating
Scope management plan should include the detailed of Change Request Form by Change Originator and
process of scope determination, its management also tracking the change on Change Control Register.
and its control. This needs to be planned in advance.

Project manager must seek formal approval on a


well-dened and clearly articulated scope. To identify
scope, requirements must be gathered from all
stakeholders. Gathering requirements from only a Change Control Register
few stakeholders or only the sponsor might lead to
incorrect denition of scope.
Continuous monitoring of scope is required to
Large projects require more time, eort and determine what is and is not included in the project
resources to gather requirements and thus dening
the scope is important.

27
PRODUCT SCOPE
Product Scope is nothing but What customer
wants? An organization can execute another project
to identify a product scope or it could be the part of
requirements gathering of your project.

An example of product scope would be:

On a project to build a new software application, the


product scope is a new workow application that
fulls the requirements of our internal and external
customers. To determine if the project successfully
achieved the product scope, the resulting application
(the new product) is compared to the application
requirements, which are recorded in the require-
ments documentation and the project scope
statement for the project.

PROJECT SCOPE
The project scope is the work the project will do to
deliver the product of the project (i.e. the product
scope). In the software application development
example, the project scope is the work that is to be
done to develop the software application. This work
includes the planning, coordination, and
management activities (such as meetings and
Change Request Form
reports) that ensure the product scope is achieved.

28
These eorts are a part of project management plan topics that can be standardized for the organization,
and are further a part of the scope management however, every scope management plan is unique.
plan. At the end of the project or the phase, the The project manager uses the scope management
completed work is compared against the scope plan as a baseline to guide and measure the project
baseline in the project management plan to until closing. As discussed earlier, scope manage-
determine if the scope has been successfully ment plan is a part of project management plan.
completed.
Like other knowledge areas, a scope management
SCOPE MANAGEMENT PLAN plan may not be developed at one time. However, it
Scope management plan contains scope planning, could be developed in stages, or iterated during
execution and control. Scope management is created project planning. The project manager rst
as a part of Project Management Planning process determines how to dene the scope. Once the
and it is not included as a separate scope project is completely planned, the project manager
management process. Scope management plan tries has enough information to decide how the scope will
to answer: be executed and controlled. These decisions then
How will the scope be achieved by the project? become part of the scope management plan. The
The tools required to accomplish the project project manager can use another aspect of iteration.
scope In this iteration, the later parts of project planning,
The enterprise environmental factors required such as the Human Resources planning process, can
for accomplishing project scope add a new scope to the process, thereby changing
The organizational process assets required the scope management plan.
How the scope is managed and controlled
throughout the project? A project manager is required to have a good
understanding of the project scope to create a scope
Organizations should have templates, forms, or management plan. It is a major mistake to work on a
standards for scope management. These are critical project before the product and project scope are
for any project. Scope management plan may have

29
identied. Creating a scope management plan is a COLLECT REQUIREMENTS
required part of project management. Stakeholders of a project play a very critical role in
providing project requirements. Requirements are
SCOPE MANAGEMENT PROCESS the need of any project or a product. Requirements
Scope management process can be described as: should be able to fulll the stated objectives.
1 Determine Requirements: The project charter Requirements should not be included just because
describes projects business case. The project someone wants it. Requirements may be related to
manager should ensure that all requirements Quality, the business process, regulatory require-
support the projects business case. ments, compliance, project management, among
2 Needs of the stakeholders should be taken into others. All of the requirements (including products
consideration while dening product and and process) are taken into consideration by the
project scope. Collect Requirements Process.
3 Work Breakdown Structure (WBS) to be used to
break the scope into smaller and more The initiating phase involves dening the high-level
manageable pieces. requirements of the project and product during the
4 Scope management process should be created project charter phase. The Collect Requirements
from the customers viewpoint. process goes into the details of seeking additional
5 Scope performance is to be measured and and more specic inputs on those requirements and
adjusted as needed during the course of the any related supposition from all stakeholders. Any
project. miss in gathering these requirements may result in
Saying NO could become inevitable to avoid the failure of the project or may result in many
allowing unnecessary activities on the project changes or may even result in conicts throughout
because unnecessary scope adds cost, time and the project journey. Hence, this process of collect
eorts on the project which is not required. requirements is critical.

Identication of project stakeholders is the rst step


before collecting requirements. You can use a

30
stakeholder register to record this information. The learned from other projects may highlight common
next step is to collect requirements from stakehol- mistakes done by other project managers in dening
ders. Do you think, it will be that easy to collect the area of scope to ensure such requirements are
requirements? For certain projects, there could be not missed on current projects.
multiple hundreds of stakeholders. Likewise even the
methods required for collecting those requirements INTERVIEWING
may be dierent for dierent stakeholders. The This technique may also be called as expert
project manager needs to engage devoted eort to interviewing. Various methods of interviews could
collect all the requirements before work is initiated be conducted by the project manager with project
on the project. If this is not done appropriately, a stakeholders to identify their requirements for the
large number of changes are required on the project product or the process. The interviews can be
leading to high cost and high eorts. Reviewing conducted as one-on-one, emails, phone calls, group
historical information and lessons learned could be setting, letters or any other method.
involved in the eort of collecting requirements. The
project manager makes a conscious choice to choose FOCUS GROUP
the most appropriate technique for project and the In a focus group, the moderator or the facilitator
stakeholders. Identication of risks during the risk plays a key role to gather inputs and thoughts that
management process could also use the same helps get the opinions and requirements for the
techniques of collecting requirements process. product or an aspect of the project from a specic
set of stakeholders or subject matter experts.
REVIEWING HISTORICAL RECORDS
Historical records and lessons learned are very FACILITATED WORKSHOPS
critical for the project team that helps in gaining The process of bringing together the individuals /
understanding of what were the requirements on stakeholders of dierent perspectives to dene the
similar projects and thus, help identify relevant requirements of the product or service is called as
processes. It also helps a new person understand facilitated workshops.
expectations from the respective teams. Lessons

31
BRAINSTORMING other. A request for information is sent to the
The method of brainstorming strives for group experts and their participation details are kept
think. It really does not just mean a meeting with anonymous. Their responses are compiled, and the
people to discuss ideas or seeking individual results are sent to back to them for further review
thoughts. Brainstorming helps produce large until a nal consensus is reached.
number of ideas in a short period of time. A
participant of the brainstorming session can share MIND MAPS
an idea of determining the scope. That idea A mind map diagram is used to generate ideas and
generates an idea from another participant which classify them into logical groups. It is a tool used to
leads to yet another idea, and so on. visually organize the information. Many ideas are
connected directly to the central core idea, and other
The participants of a brainstorming session can vary. ideas branch out from these.
Individuals from dierent functions, backgrounds
and perspectives can benet the brainstorming AFFINITY DIAGRAMS
session in a great way. The participants need not be The ideas generated from any other requirements
just the individuals from the organization, they could gathering techniques are grouped by similarities in
be from outside the organization as well. this technique. A title is given to each group of
requirements.
NOMINAL GROUP TECHNIQUE
This technique is done in continuation to the QUESTIONNAIRES AND SURVEYS
brainstorming meeting where the ranking of the A questionnaire is designed to seek responses from
most powerful ideas is done by the meeting respondents. The benet of questionnaires and
participants. surveys is that it can be sent out to a large group.

DELPHI TECHNIQUE OBSERVATIONS


This is a consensus technique with a dierence. In Observation technique involves watching a potential
this technique, the participants do not meet each user of a product at work.

32
They need to be reviewed, analyzed, approved or
rejected and prioritized before recording them in
project documents. A unanimous agreement on a
requirement from the group makes the decision
making easy. A single person making a decision for
the entire group is known as dictatorship technique.
This has an advantage of quick decision making,
however, also has a disadvantage of other
stakeholders not agreeing in decision making done
by the individual.

In group decision-making there are many conicting


Anity Diagram Example opinions. In these situations, groups may take a
majority approach. In this technique, the group takes
a decision which is supported by more than half of
PROTOTYPES the members. In case there is no majority support,
A model of the proposed product is a prototype. the group may go with the decision of largest
Stakeholders are presented the prototype to seek number of supporters. This is known as plurality
feedback. Multiple versions of prototype may be technique. There is another technique known as the
created till all the requirements are captured, the consensus approach. In this technique, the decision
model is nalized and approved. is made which is acceptable for the group. In case if
there are certain members of the group who did not
GROUP DECISION-MAKING support the decision, they will willingly accept that
There are multiple ways to make decisions in a most members of the group support.
group. Requesting inputs from all stakeholders may
result is generating multiple ideas. These ideas may
lead to confusion and may also lead to conicts.

33
REQUIREMENTS DOCUMENTATION Balancing stakeholder requirements is not limited to
Ones the team collect all requirements, it is time to the Collect Requirements Process, it goes beyond
document them. The documentation should be clear this. At a later stage in the project, it is identied that
and unambiguous. This documentation is an output certain stakeholder requirements do not match
of Collect Requirements Process. those of the project or those of other stakeholders.
In this situation, a conict may arise between
If the representation of information is not done stakeholders. Thus, the project manager may need
appropriately, the collected requirements may be to balance the requirements against the interests of
misunderstood. Hence, it is advisable to NOT assume the project and resolve any conicts.
that the collected requirements will meet the
objectives. Thus, it is important to ask the Clear project objectives are a prerequisite for
stakeholders if the collected requirements would be balancing stakeholder requirements. Another
meeting the stated objectives. This helps ensure that prerequisite is to identify and prioritize ALL the
the right requirements are collected and end output requirements from ALL of the stakeholders during
will be acceptable. Collect Requirements Process. If these prerequisites
are not met, balancing stakeholder requirements is
BALANCING STAKEHOLDER REQUIREMENTS an impossible task.
Balancing stakeholder requirements involve
prioritizing requirements. It also involves resolving RESOLVING COMPETING REQUIREMENTS
any conicts between them. It is an important aspect Each department of the organization has their own
of Collect Requirements Process. The project interest in the project. For example, the risk team
manager has to ensure that the requirements are may slow down the pace of the project if they
met within the stated project objectives. If the identify any risk and the operations team would have
requirements cannot be met, then the project an interest of completing the project faster. Having
manager needs to identify options to adjust the an amicable solution for both departments is crucial.
competing demands of scope, time, cost, quality,
resources, risk, and customer satisfaction.

34
These issues are complex and an intervention from REQUIREMENTS MANAGEMENT PLAN
management is required to resolve them. While Requirements Management Plan is an output of
resolving competing requirements, the project Collect Requirements process. The plan answers the
manager should identify which of the competing questions such as:
requirements resonate with the project business Which are the methods used to identify
case. A thorough review of project charter, the scope requirements?
statement and constraints will also be important What analysis is required for identied
factors in this regard. requirements?
How will the requirements be prioritize?
Any project request that does not relate to the How would the requirements be managed?
objectives of the project should be rejected. If the How would the requirements be tracked?
requirement is related to the reasons the project was What is required out of requirements
initiated but it does not fall within the project traceability matrix?
charter, this request should also be rejected. Change
requests related to the project charter need to be REQUIREMENTS TRACEABILITY MATRIX
discussed with project sponsor for approval. When In large projects, if the requirements are not
considering constraints, if the most important documented well, there is likelihood that they may
constraint is cost, then any requirements that would be lost. Determining requirements can involve one
increase the cost would not likely to be accepted. requirement leading to more rened requirements
Those that contain the cost (without serious impact and clarications. This can make it dicult for the
on other project constraints) would more likely be project manager and the project team to remember
accepted. Requests that do not fall within these where the requirements came from. Objectives of
guidelines can become part of a future project the project may not be met if these reasons for
instead. requirements are missed. Requirements Traceability
Matrix is another output of Collect Requirements
Process. The matrix is used throughout the project in
analyzing proposed changes to product or project

35
scope. The matrix helps in linking requirements to Planning process when the requirements have been
the objectives and/or other requirements to ensure determined. This information is used to identify the
the strategic goals are accomplished. schedule and the budget. This schedule and budget
may meet the expectations of the management or
sponsor. If they dont, the project manager needs to
review all the constraints of the project and needs to
maintain equilibrium of the requirements (scope)
against the budget and schedule. The project
manager needs to create options for meeting the
scope, time, and cost objectives of the project and
help management make a decision. Compressing the
schedule, identifying alternative ways to perform
Requirements Traceability Matrix
work on the project, or adjusting budget or the scope
are some of the tasks to be completed by project
manager while creating these options. A realistic
DEFINE SCOPE
schedule and budget that can achieve projects scope
The product and project scope is determined using
is the result of this exercise.
inputs from the requirements document (created in
Collect Requirements Process), project charter,
PRODUCT ANALYSIS
additional information about project risks,
Analysis of the objectives and description of the
assumptions, constraints, among others. This
product as stated by the customer and the sponsor
process is concerned with what is included and is not
is the purpose of Product Analysis. The output of this
included in the project and its deliverables.
analysis is identication of tangible deliverables.

Project planning is not a one-time process. A project


PROJECT SCOPE STATEMENT
cannot be planned right at the start and kept as it is.
Project scope statement is primarily an output of
Planning is an iterative process. Project Manager
Dene Scope Process. Development of project scope
continues to follow the Project Management

36
statement is a time consuming activity and may shows the complete scope of the project broken
require multiple stakeholder participation including down into manageable deliverables. A project will
experts from outside the organization. The project take longer than the scheduled time if a WBS is not
manager avoid including the following two things available. Project managers may also miss out on
while dening the project scope statement: certain important activities without the WBS. Thus,
1 Scope that is not approved: Project manager without a WBS, the project can be negatively
should identify areas where people requested impacted.
scope but it was not approved to be included
in the project.
2 Scope that is not needed: Project manager
should clarify areas where the scope could
easily be misunderstood.

Scope baseline is a combination of project scope


statement and WBS and WBS dictionary. Scope
baseline is a part of project management plan.
Project Scope statement can include:
Product Scope
Project Scope List of Activities as Actionables Example
Deliverables
Acceptance criteria of the product
Out of scope activities Most project managers make a list of activities as
Constraints and assumptions actionables. This may result in overlooking some
deliverables. Additionally, a list can be cumbersome
CREATE WORK BREAKDOWN STRUCTURE (WBS) and does not allow the project manager to clearly
All projects (large and small) require a WBS. It is a break down a large project into small appropriate
required element in project management. A WBS pieces. People do not get an understanding of the

37
project by looking at the list. A list is created by one The creation of WBS is a top-down eort. It involves
individual. Looking at the list, people do not know decomposing the deliverables, and the work
who has created the list. These are some of the required to produce them, into smaller pieces called
major drawbacks of creating a list of activities. work packages.

A WBS on the other hand has enormous advantages. Following are the rules to be followed for creating a
Using a WBS, no actionable is missed. A project WBS:
manager can easily break down the work into work 1 A team is involved in creating a WBS
packages, and the WBS shows how the work 2 The rst level is completed before proceeding
packages are drilled down. A WBS is created with any further in creating the WBS
input from stakeholders and the team. This 3 Each level of WBS is a sub-level (a smaller
automatically helps in seeking their buy-in and thus piece) of the level above
leads an improvement in their performance. 4 The entire project can be understood by
Creation of WBS is a process that allows the team to looking at all the levels of a WBS
walk through the project in their minds and thus 5 WBS does not include deliverables other than
improve the project plan. Thus, the execution of the the project
project is much easier and less risky. The
involvement of people increase and all feel that the A deliverable is considerable to be a work package
project is more achievable. A WBS shows a complete when:
hierarchy of the project, making it easier to see how 1 It can be estimated (both realistically and
one deliverable relates to another. condently)
2 It can be completed quickly
Its important to note that the WBS is NOT a 3 It can be completed without interruption
corporate organizational structure though it looks (without the need for more information)
like one. It has a dierent function that allows you to 4 May be outsourced or contracted out
break down a seemingly overwhelming project into
pieces you can plan, organize, manage and control.

38
WBS levels are numbered at a later stage. Work through all aspects of the project. Additionally, it can
packages are distinguished in the WBS using the be reused for other projects too and it does NOT
identication numbers assigned after completion of show dependencies.
the WBS. For some projects, the costs are not
managed at a work package level. Instead, they are The project manager decomposes the project using a
managed at higher level in WBS, called the control WBS. The term deconstruction and decomposition
account. are the same. This diagram indicates the relationship
of the components of a WBS.
As the planning process progresses, the team breaks
down the work packages from the WBS into activities
that are required to produce the work packages.
Note that this further breakdown of WBS into an
activity list is done as a part of the time management
process of Dene Activities. The team uses the
project scope statement, WBS, and the WBS
dictionary to help dene which activities are required
to produce the deliverables.

The foundation of any project is WBS. After creation


of WBS, everything that occurs in planning is related
to WBS. The project has a hierarchy and WBS is a
graphical picture of that hierarchy. WBS identies all
the deliverables to be completed. The activity is not a
part of the project if it is not in the WBS. The project
is built on the foundation of a WBS. WBS is extremely
important on a project. It should exist for every Relationship between WBS Components
project. It ensures that the project team is thinking

39
WBS DICTIONARY SCOPE BASELINE
For each work package, a WBS dictionary provides a The nal, approved version of certain pieces of a
description of work to be done. Benets of WBS project management plan is termed as a baseline. In
dictionary include, avoiding scope creep and scope management, baselines are the WBS, WBS
providing clear description of the deliverable. Output dictionary and the scope statement. All of these need
of Create WBS process is a WBS dictionary. A WBS to be approved by the management and stakehol-
dictionary can have multiple uses: ders before beginning the work. These baselines
It informs when work package is going to start, help in comparing the progress of the project to
thus acting as a work authorization system where the baseline says it should be.
Schedule milestone, acceptance criteria and
other information about the work package are For any deviations from the scope baseline, a change
included in a WBS dictionary request is needed. This change request goes through
It can be used as a control mechanism of what perform Integrated Change Control and if approved,
work is done gets added to the scope statement, WBS and WBS
The stakeholders have an increased under- dictionary. Any other components or documents
standing of the eorts involved in a work involved also need to be updated.
package with a WBS dictionary
Meeting the requirements and the scope baseline
are the measures of success of a project.

VERIFY SCOPE
The process of keeping the project on-track in terms
of the approved scope by frequent discussions
between customer or sponsor and seeking their
acceptance on completed deliverables.

WBS Dictionary

40
The inputs to Verify scope are: to ensure that the scope is being completed as per
Inputs from Perform Quality Control process plan. The project needs to be properly managed
validated deliverables using the Control Scope process.
Scope statement, WBS and WBS dictionary
Requirements Traceability Matrix Two components required for Control Scope Process
Requirements documentation are Scope Baseline from project management plan
and current completed work on the project.
The outputs of Verify scope are: Requirements documentation and Requirements
Accepted deliverables traceability matrix can also be helpful in Control
Change requests Scope process. A project manager identies if there
Updates to the project documents are any deviations against the baseline. A corrective
or preventive action is recommended in case
Verify scope process can be done at the end of each deviations exist. Change request originates in case
process phase. It can also be done as a part of any changes are required. The project manager
monitoring and controlling throughout the project. needs to identify and perform Integrated Change
Control process and subsequently update the
Verify scope process provides a formal acceptance by required documents.
the customer of interim deliverables whereas Close
project or phase is to get nal acceptance or sign-o Control Scope process believes in a proactive
from the customer for the project or phase as a approach. A project managers primary job is to
whole. control the project to meet the baselines as per the
project management plan. Changing scope without
CONTROL SCOPE following the Change Management process is not
Measuring the scope performance (for project and/ advisable.
or product) and managing scope baseline changes
are two major deliverables of Control Scope process.
A project manager needs to control scope frequently

41
TIME MANAGEMENT A schedule management plan should include the
methodology used to create the schedule. The
project manager should also describe the use of
A project managers key responsibility is to create a scheduling software. He should identify the
realistic project schedule. Before the project measurement guidelines i.e. should he measure the
execution begins, the project manager should process progress in hours, days, weeks, months or
identify if the planned end date is achievable. quarters. The schedule management plan should
also include the duration for each activity and the
SCHEDULE MANAGEMENT PLAN eorts required for those activities. All of this should
Schedule Management Plan requires thinking establish the project baseline. This baseline is to be
proactively before executing the project. It involves used to monitor and control the project during
thinking through several points, including: various phases. Project manager should also include
Individuals involved in the scheduling process a plan to mitigate any variances observed in the
Approach required to plan schedule of the schedule. Change Control Procedure should be in
process place to manage schedule changes. Reporting
Use of organizational processes and procedu- requirements should also be established.
res
Tools used for scheduling The measures of performance need to be planned in
Method to manage and control the project to advance and then captured and reported. Schedule
schedule baseline and manage any deviations management plan is a part of project management
plan and can be formal or informal. It expedites the
The schedule management plan is created as a part schedule estimation process by providing guidelines
of Develop Management Plan process in Integration on how estimates should be stated. During the
Management. A project manager must create a monitor and control phase, the deviation from the
schedule management plan and it is observed that in schedule baseline can be analyzed and acted upon.
real world scenarios most of the project managers Reporting of project is also determined by schedule
miss on this important aspect. management plan.

42
DEFINE ACTIVITIES When the project manager is dening the activities,
In scope management, we had created a WBS. WBS there may be too many components to adequately
resulted in Work packages. Work packages are used break-down the components and schedule it. In
as inputs in the Dene activities process. These work these situations, project managers use a technique
packages are broken down further into activities to called rolling wave planning. In this method, the
ensure that work packages are delivered. Each project manager need not plan all the details of the
activity is then estimated, scheduled, monitored and project right at the start. He can plan activities to the
managed. Thus, these activities should be small detail needed to manage the work only when he
enough. Sequencing of these activities is the next starts that phase of the project life cycle. There is a
process. likelihood that project managers can use this
planning method as an excuse for not planning the
Its important to note that in the real world, project project appropriately. This is not advisable.
managers may create activities when they are
creating work packages. Also, some project mana- Activity list and Activity Attributes are two outcomes
gers create network diagrams at work package levels of Dene Activities process. Activity attributes is the
and not at activity level. documentation of the details of the activities.
Milestones are also to be determined in the Dene
For dening activities, a project manager needs two Activities process.
critical things:
1 Scope baseline (scope statement, WBS and MILESTONES
WBS dictionary) Timeline for each of the dened activities is not
2 Availability of a project team considered as a milestone. Milestones are interim
deliverables of the project schedule. A summary of
Dening the activities involve making the estimates. milestones is included in the project charter. For
Involving the team early on in dening activities controlling the project, a project manager can
ensures that the estimates are more accurate. impose milestones (like a sponsor) during the
Sequence Activities or Develop Schedule processes.

43
Deviations from the planned activities are detected Arrow Diagramming Method (ADM)
when the milestone arrives and the project has not Graphical Evaluation and Review Technique
completed the activities required for the milestone. A (GERT)
list of appropriate milestones is created as a part of Project managers generally use PDM these days.
Dene Activities process. This milestone list becomes
a part of the project management plan and is added PRECEDENCE DIAGRAMMING METHOD (PDM) or
to the project scope statement and WBS dictionary ACTIVITY-ON-NODE (AON)
as part of iterations in planning. Finish-to-Start (FS): The successor can start
only after an activity nishes. This is the most
SEQUENCE ACTIVITIES commonly used relationship. Example: You
The output of Dene Activities is a list of activities must open the can of soft-drink before you
and milestones. In sequence activities process, these start to drink it.
activities and milestones are sequenced in the order Start-to-Start (SS): The successor can start only
of work performance. after an activity starts. Example: You must start
creating a presentation and wait for one-week
lag in order to have enough slides completed
to start the voice-over recording.
Finish-to-Finish (FF): The successor can nish
only after an activity nishes. Example: You
must nish the pilot before you nish
Sequence Activities gathering the complete feedback.
Start-to-Finish (SF): The successor can nish
only after an activity starts. This relationship is
METHODS TO DRAW NETWORK DIAGRAMS rarely used.
There are several network diagram methods
including:
Precedence Diagramming Method (PDM)

44
Mandatory Dependency (Hard Logic): A
mandatory dependency is the natural ow of
work being done (e.g. you must give the
command to print before you can print). It may
be required by the contract.

Discretionary Dependency (Preferred, Prefe-


rential, or Soft Logic): A project team cannot
easily change other types of dependencies,
however, they can change the discretionary
dependency. A discretionary dependency is
determined by the project manager and the
Precedence Diagramming Method (PDM) project team. Discretionary dependency is
quite useful when there is a need to compress
the project schedule or fast track the project.
G R A P H I C A L E VA L U AT I O N A N D R E V I E W
TECHNIQUE (GERT) External Dependency: Parties outside the
GERT is a computer simulation technique that allows project can also inuence the project. External
loops between activities. GERT is a modication to Dependency is based on the needs of a party
the network diagram drawing method. An example outside the project (e.g. labor union,
could be designing a program and testing it. After regulators, etc)
testing, it may or may not need to be redesigned.

TYPES OF DEPENDENCIES
Sequence of activities can be based on multiple
dependencies. Some of them are listed below:
Types of Dependencies

45
LEADS AND LAGS Project manager should manage the project
A lead may be used to indicate that an activity can schedule without any deviations to the
start before its predecessor activity is completed. For schedule baseline
example, editing of a book may start before the Project manager should manage project
write-up is nished. budget without any deviations to the cost
baseline
A lag is inserted waiting time between activities, such Integrated Change Control is used to approve
as needing to wait for completion of the application or reject all change requests
testing before nal roll-out of the application. Any issues related to schedule, cost, scope,
quality, or resources can lead to change
Sequence Activities process can also result in requests
identication of new risks. It may also lead to A project managers role is to analyze the
updates to activity list and activity attributes. project requirements, create new estimates
basis inputs from team members and his
ESTIMATION AN INTRODUCTION experience with relevant projects, and resolve
Critical points to be remembered for estimating any dierences to produce realistic objectives
activity resources or estimating activity durations are: Periodic recalculation of Estimate to Complete
Accuracy of estimation improves if it is done (ETC) is required to ensure adequate time,
basis WBS funds, resources, etc are available for the
Accuracy is also improved if estimation is done project
by the same person who does the work Project management plan should be revised as
Historical information provides critical insights changes are approved and necessary work is
for the process of estimation completed
Estimation will be more accurate if there are A non-acceptable project management practice
minimal or no changes in schedule, cost and is Padding
scope baselines Any agreed-upon estimates must be met by
the project manager

46
Estimates must be reviewed periodically to see However, the estimators are more often project team
if they are achievable and to check for padding members who are more familiar with the work that
and risks needs to be done. The estimators need to have
Reduction or elimination of risks can result in access to:
decreased estimates Activity resource requirements
Providing accurate and feasible estimates is Resource calendars
the responsibility of a project manager Historical data of the organization
Lessons learned about activity durations
ESTIMATE ACTIVITY RESOURCES Past project calendars
The type and quantity of needed resources are Dened scheduling methodology
determined after the activities are sequenced. A Company culture enterprise environmental
resource could be an equipment, materials or factors
people. Lack of resources is a common problem with Existing systems estimating softwares and
all projects and hence, a project manager must plan productivity metrics
and coordinate resources to avoid these problems.
This results in getting two outputs: Later in project planning, during the risk manage-
1 Dened activity resources requirements ment eorts, the time estimates and any other
2 Resource breakdown structure (RBS) information gathered during the estimating process
are considered when creating a risk register.
ESTIMATE ACTIVITY DURATIONS
The Estimate Activity Durations process is to Many project managers estimate activity durations
estimate how much time each activity will take. It is like this. Padding undermines a project managers
completed after dening and sequencing the ability of developing realistic schedules and budgets.
activities and the type and quantity of resources for
each activity are identied. Who should play a role of A pad is an extra time and cost added to an estimate
estimating these durations? Ideally, the estimators because the estimator does not have enough
should be those who will be doing the work. information. The potential need for time and cost

47
arises when the project has many unknowns and Risks and unknowns are identied
information is not available to clarify the unknowns.
This can be addressed with reserves through the risk HOW IS ESTIMATING DONE?
management process. Risk management is an The three methods used for estimating include
important process that converts uncertainties into analogous estimating, parametric estimating, three-
identiable opportunities and threats (risks). point estimating or reserve analysis. Estimation
Estimators need to identify these risks and discuss activity need to be completed by individuals who are
with the project manager. These risks should not doing the work.
remain hidden.
A project manager plays a key role during the
If many of the estimates are padded, the project will process of estimation. Some of his activities are
have an extravagant schedule. In this case, there is outlined:
no need of creating a schedule or a budget. In actual
real-world projects, the schedule and the budget are Enough information is provided to the team to
used as baselines against which project managers properly estimate each activity
measure projects performance. Thus, these Complete calibration should be made between
baselines should be as realistic and accurate as project manager and estimators to know how
possible and project managers need to adhere to rened their estimates may be
them. Padding is a poor sign of project management Validate the estimates
and it damages the reputation of a project manager. Prevent padding
Formulate a reserve
Padding will not be required if: Assumptions made during estimating are
A WBS is available with estimators recorded for later review
A WBS dictionary is also available with the
estimators
Time and cost reserves on the project are
identied through actual calculations

48
historical information, or it could just be a guess. The
technique is thus problematic.

The negative eects of one-point estimating on the


project are:
If an estimator estimates that it will take 15
days for an activity to be complete, and it takes
only 10 days, it can make the person who
provided the estimate look untruthful and
untrustworthy
It can hide critical information about risks and
uncertainties from the project manager
It can decrease the buy-in to the project
management process as it results in a schedule
that no one believes in
It forces people into padding their estimates
It often results in estimators working against
the project managers to protect their interest
Estimation Methods So, where could we use one-point estimates? For
projects that do not require a detailed, highly reliable
schedule, a one-point estimate can be used. A three-
ONE-POINT ESTIMATING point estimate is preferable.
Basis this technique, an estimate is made per activity.
For example, the person doing the estimating says ANALOGOUS ESTIMATING
that the activity will take one month. The estimator The last few projects similar to this one took nine
may estimate this time basis expert judgment, months, so this one should also. Similarly, last three
times this activity was completed, each took fteen

49
days, since we have no other information to use, we
will use fteen days as the estimate for this activity
and review the estimate when more details are
available. Expert judgment and historical information
is used to estimate using analogous estimating
technique.

PARAMETRIC ESTIMATING
Parametric estimating looks at the relationships
between the Xs (variables) on the Ys (activity) to
calculate estimates. The data primarily comes from
historical records such as previous projects,
industry requirements, standard metrics, other Parametric Estimations
sources.

There are two ways the estimator might create HEURISTICS


parametric estimates: A heuristic means rule of thumb. An example of a
Regression analysis (scatter diagram): A heuristic is the 80/20 rule or the Pareto principle.
regression analysis identies the impact of an This rule suggests that 80% of quality problems are
X on a Y i.e. impact of a variable on an activity caused by 20% of potential sources of problems.
by creating a mathematical formula to use in Results of parametric estimating can become
future parametric estimating. heuristics.
Learning curve: Example: The average handle
time of an employee in a call center reduces as THREE-POINT ESTIMATING (PERT ANALYSIS,
his tenure increases because of improved PROGRAM EVALUATION & REVIEW TECHNIQUE)
eciency. Since there is a very low probability of meeting the
project deadline on exactly one date, it is often best

50
to state estimates in a range using three-point management process. The Plan Risk Response
estimates. Analyzing what could go right and what process is executed to reduce the risk and a revised
could go wrong can help estimators determine an reserve is created. Project planning is thus an
expected range of activity, and if they state this range iterative process.
using three time (or cost) estimates, the project
manager can better understand the potential Contingency reserves and management reserves are
variation of the activity estimates and the overall two types of reserves for a project. Management
project estimate. With the three-point estimate, the reserves are additional funds kept as a contingency
estimators give an Optimistic (O), Pessimistic (P), and reserve to cover unforeseen risks. Contingency
most likely (M) estimate for each activity. This reserves are for the risks remaining after the Plan
ultimately provides a risk-based expected duration Risk Responses process.
estimate by taking either the average or weighted
average (using PERT analysis) of the three estimates. There is a major dierence between reserves and
padding. In padding, the team members determine
RESERVE ANALYSIS how much of a pad they want to attach to their
Identication of risks is done by Estimating. estimate. This is an arbitrary guestimate. In creating
Elimination of risks is done by completing the risk reserves, the information required to reliably
management process. This makes the estimates calculate the additional time or funds the project
more accurate and it also reduces the range of time may need, is available with the project manager.
and cost estimates. Time and money is saved by the
risk management process. DEVELOP SCHEDULE
After completing the network diagram and activity
One of the critical responsibilities of a project estimates, information is updated in a schedule. A
manager is to establish a reserve to accommodate schedule is calendar based.
for the risks that remain in the project after the risk
m a n a g e m e n t p l a n n i n g p ro c e s s h a v e b e e n To develop a nalized schedule, following steps need
completed. An initial reserve is estimated in the risk to be followed:

51
Keep a check on priorities of stakeholders SCHEDULE NETWORK ANALYSIS
Create multiple ways of completing work For creating a nal schedule, a schedule network
Identify risks and impact on other projects analysis is completed using an initial schedule.
Negotiate resource availability with managers Multiple techniques can be used to create the nal
Leads and lags to be applied to the schedule schedule such as:
Crashing, fast tracking, and reestimating to be Critical path method
used to compress schedule Schedule compression
Adjust components of a Project Management What-if scenario analysis
Plan Resource leveling
Use scheduling tool and perform calculations Critical chain method
to determine optimum schedule
Use models such as Monte Carlo analysis to CRITICAL PATH METHOD
simulate project & identify project completion A critical path is the longest path in a network
date diagram. The following steps are carried out in a
Level resources if necessary critical path method:
Seek approval on the nal schedule from the 1 Longest path is determined through the
team who created it network diagram
Seek stakeholder buy-in & formal management 2 Earliest and latest time when an activity can
approval start is determined
3 Earliest and latest date when an activity can be
Many of the actions of Develop Project Management completed is also determined
Plan process (in Integration Management Chapter)
are performed as a part of Develop Schedule NEAR-CRITICAL PATH
process. A near-critical path is close in duration to the critical
path. If the critical path and near-critical path are
closer to each other in length, it increases the risk of
the project. The project manager should focus on

52
monitoring and controlling activities on both critical For example, if you have a new resource who is still
and near-critical paths to avoid any delays to project learning and if you feel he will take longer to
completion. complete the task, you can allocate him to the
activity which has maximum oat. Thus, even if the
FLOAT (SLACK) activity is taking longer, it is less likely that the project
Floats are mainly of three dierent types: will be delayed.
Total Float (slack): The amount of time the
activity can be delayed without delaying the The amount of oat also indicates the time exibility
project end date. Total oat is considered as a the project members may have for each activity.
primary type of oat.
Free Float (slack): The amount of time the Formula for calculating oat:
activity can be delayed without delaying the Float = Late Start (LS) Early Start (ES)
early start date of the successor(s). Float = Late Finish (LF) Early Finish (EF)
Project Float (slack): The amount of time the
activity can be delayed without delaying the Either formula will give the same result.
externally imposed project completion date
required by the management or by the SCHEDULE COMPRESSION
customer. Unrealistic timeframe is one of the most common
problems of any project. If the customer or
Float and slack mean the same. Critical path stakeholders have requested for a date that cannot
activities have zero oat. Delayed projects or be met, or if the project has deviated considerably
projects that have imposed dates can have negative from the baseline, the project schedule requires
oat. Float is an advantage for the project. A oat can compression. It is the responsibility of the project
be used by the project manager to: managers to push back, present options, and make
1 Eectively manage the project sure the project is achievable by properly planning
2 Achieve better allocation of resources the project and using schedule network analysis
techniques like schedule compression. The schedule

53
compression technique helps in determining if the WHAT-IF SCENARIO ANALYSIS
desired project completion date can be met and if In creating a nalized, realistic schedule, it is helpful
not, what can be changed to meet the requested to ask What if a particular factor changed on the
date. This can be done right at the project planning project? Would that produce a shorter schedule?
stage. This technique is also used during integrated The assumptions for each activity can change and,
change control to look at the impacts changes to therefore, the activity durations can also change.
other parts of the project (i.e. cost, scope, risk, One of the ways to calculate the eect of these
resources, quality, etc) have on schedule. The changes is through a Monte Carlo Analysis.
objective is to compress the schedule without
changing the scope of the project. MONTE CARLO ANALYSIS
The outcome of the project is simulated by computer
FAST TRACKING software in Monte Carlo analysis. It is based on the
This technique involves doing critical path activities three-point estimate (optimistic, pessimistic, and
in parallel that were originally planned in a series. most likely) for each activity and network diagram.
Some of the disadvantages of fast tracking are:
Results in rework Following are the benets of the simulation:
Increases risk It suggests the probability of completing the
Requires more attention to communication project on any specic day
It suggests the probability of completing the
CRASHING project for any specic amount of cost
In crashing maintaining the project scope is It suggests the probability of any activity
important. This technique involves making cost and actually being on the critical path
schedule trade-os to determine how to compress It suggests the overall project risk
the schedule the most for the least cost. Crashing
always results in increased cost. It trades time with It is more accurate than other methods as it
money. simulates the actual details of the project and
calculates probability.

54
Monte Carlo analysis help deal with path PROJECT SCHEDULE
convergence, places in the network diagram where The schedule can be shown with or without
multiple paths converge into one or more activities, dependencies (logical relationships) and can be
thus adding risk to the project. Monte Carlo analysis shown in any of the following formats, depending on
is also used as a risk management tool to the needs of the projects:
quantitatively analyze risks. Network diagrams
Milestone chart
RESOURCE LEVELING Bar chart
A resource-limited schedule is produced using
resource leveling. If resources are limited, leveling MILESTONE CHART
lengthens the schedule and increases the cost and These are similar to bar charts but they only show
other constraints. events. Milestone charts are good tools for reporting
to management and to the customer.
CRITICAL CHAIN METHOD
Critical Chain method uses a network diagram and
develops a schedule by assigning each activity to
occur as late as possible to still meet the end date.
You add resource dependencies to the schedule, and
then calculate the critical chain. Starting at the end
date, you build duration buers into the chain at
critical milestones. These reserves, spread through-
out the project, will provide cushions for delays in
the scheduled activities. You manage these buers
so that you meet each individual milestone date and
thus the project milestone completion date as well.
Milestone Chart

55
BAR CHARTS (Gantt Chart) CONTROL SCHEDULE
Bar charts are weak planning tools, but they are Schedule control means looking for things that are
eective for progress reporting and control. They are causing changes and inuencing the sources of the
not project management plans. Bar charts do not change. If the project can no longer meet the agreed-
help organize the project as eectively as a WBS and upon completion date (the schedule baseline), the
a network diagram do. They are completed after the project manager might recommend the termination
WBS and the network diagram in the project of the project before any more company time is
management process. wasted.

Gantt Chart Example

56
COST MANAGEMENT

Managing project to the cost
Control cost
Manage cost variances
Time Management and Cost Management are
strongly connected. Many of the topics covered in Cost management plan forms a part of project
Cost Management are covered in Time Management management plan. Like other project management
as well. plans, even cost management plans requires
proactive thinking.
In Time Management chapter we studied the
creation of work packages. These work packages Some important steps involved in cost management
were further divided into activities. In multiple plan are:
projects, cost estimates are created basis these The way in which the cost estimates should be
activities. However, in large projects, cost estimates stated
are created at control account level. This level will be Cost estimates accuracy levels
equal to a work package level or higher than that. Instructions for identifying, tracking and
reporting cost performance
COST MANAGEMENT PLAN Reporting formats
Though the Cost Management Plan is a required part Bifurcation and denitions of direct and
of Project Management Plan, unlike time and scope indirect costs
management, it is not listed as a part of formally Maximum cap for cost expenditure
dened cost management process. The Develop Change control procedures required for cost
Project management Plan in Integration Manage- changes
ment involves creation of the cost management plan.
It is important to note that the step of creating the Maximum cap for cost expenditure allows project
cost management plan exists irrespective of where it manager and members to allow variation for cost. As
is created. Cost Management Plan focuses on: the cost increases beyond the ceiling provided,
Planning cost for the project actions should be taken to control it. These ceiling

57
numbers (maximum cap) are proactively thought performance levels is done in value analysis. Value
through by the project manager in the cost Analysis concurs with value engineering.
management planning stage.
COST RISK
LIFE CYCLE COSTING Any risk related to cost such as procurement risk,
Life cycle costing is taking into consideration of the cost management risk is termed as cost risk. This risk
whole life of the product, and not just the cost of the is not just covered in risk management and requires
project. For example, a product costs $50,000 which to be covered in all phases of the project.
has a very low maintenance cost ($5000) over its life
period. An alternate product is available for $38,000 ESTIMATE COSTS
however, has higher maintenance cost amounting to This process is related to estimating cost for each
$50,000 over the products life. As a project manager, identied activity of the project.
would you prefer reducing the cost of the project by The costs required to complete the project involve:
saving $12,000 (by buying the alternate product)? 1 Quality eorts
remember, this increases the maintenance cost for 2 Risk eorts
the company by $45,000. Or would you take into 3 Project management activities
consideration the entire life cycle costing of the 4 Resources
product and forgo $12,000 for a future saving of 5 Direct and Indirect costs
$45,000 for the company? 6 Overhead costs
7 Others
VALUE ANALYSIS
Value analysis focuses on decreasing cost of the TYPES OF COST
project without any degradation in scope and There are two types of cost:
performance levels. A systematic identication of Variable cost: As understood by the name,
various functions, assignment of values to those these costs vary with the amount of work
functions and identications of less costly resources being done. For example, cost of raw material,
and activities to be performed maintaining the labor wages, etc.

58
Fixed cost: These are non-variable costs. These Cost expenditure can be controlled if the
costs are xed and includes set up cost, project team is aware of the timing on when to
working capital, lease (rent), etc. buy the product. The other way that it can be
controlled is when project expenditures are
A cost can be direct or indirect cost: made in a time-phased manner. Thus, a
Direct Costs: The costs that can be directly schedule can aect cost. Likewise, cost can also
attributed to the work done in the project is aect schedule. If an activity is to be executed
considered as Direct Costs. Example include: on a project when the cost of purchasing the
travel and entertainment expenses, stationary raw material is very high, the activity may need
cost, labor salaries, etc. to be pre-poned or post-poned for the reasons
Indirect Costs: The overhead items or costs to accommodate the surge in price.
incurred that cannot be apportioned to a Human Resources Plan: The system to reward
specic project or activity and can be used for project members, rates of labor required and
multiple projects are termed as Indirect costs. number of resources (individuals) required for
the project and their cost are arrived at by the
INPUTS TO ESTIMATING COSTS human resource plan. This plan enables the
Following are the inputs that help in estimating costs project manager to keep the resources
better and quicker: motivated to work achieving savings and still
Scope Baseline: Scope baseline includes the ensuring the cost of the project is controlled.
project scope statement, WBS and WBS Risk Register: Risk is an eective contributor to
dictionary. It helps in allowing the project reduce time and money associated with the
manager to know what is in-scope and what is project. Cost is required to the work required
out-of-scope. to manage and control risks. These costs can
Project Schedule: A schedule is required before also lead to more risks such as cost risks. Thus,
a budget is created. The project schedule risk is both an input and output of Estimate
contains the list of activities, the allocated Cost process.
resources and the time when work will occur.

59
istorical Records and Lessons Learned: (PERT) estimating. Another method of estimation
Historical records from past projects are that we will now study is bottom-up estimating
extremely helpful to make the cost calculations technique.
and the estimates easier. The templates
provided by these records help in executing BOTTOM-UP ESTIMATING
these eorts faster and quicker. A project is nely distributed in the form of activities
Project Management Costs: Project manage- and work packages. The technique of bottom-up
ment eorts also require costs. The expense of estimating involves estimation of costs involved at
the project manager, status reports, change each activity or work package, rolling it up into
analysis, execution, etc are included in these control units and then nally to the overall project
costs. estimate. This is another reason why a WBS should
be well created by the project team. The process of
creating estimates involves the following items:

PROJECT MANAGEMENT SOFTWARE


Project management software can help in speeding
up the calculations required to estimate costs. These
calculations could include direct, indirect, overhead,
xed cost calculations for several hundred activities.
Risk Register
DETERMINING RESOURCE COST RATES
Resources can be internal human resources,
HOW IS ESTIMATING DONE? vendors, consultants, suppliers, external technicians,
Costs can be estimated using the methods that we among others. Project managers must have a know-
have already learned in the Time Management how of the rate involved for the resource cost.
Chapter i.e. One-point estimating, analogous
estimating, parametric estimating, and three-point

60
RESERVE ANALYSIS
Reserve analysis involves identication of activities
which have signicant risks and determination of the
total eorts (time and money) required to manage
these risks if they occur. There are two types of risks:
Known and Unknown risks. Contingency reserves
deal with known risks. Management reserves deal
with unknown risks. Padding should be avoided
when doing a reserve analysis.

COST OF QUALITY
Quality eorts are required for the project. The
amount of money added due to these eorts are
bifurcated as Cost of Quality.
Cost of Quality (CoQ)
ACCURACY OF ESTIMATES
Estimation of Costs is an iterative process. Costs
estimated during early stages of the project have There are dierent types of ranges for dierent
lesser accuracy and the ones estimated at later scenarios i.e. for preliminary cost estimation, the
stages have higher accuracy. Cost estimation should range will vary, for cost estimation during the
be made by the project manager in the form of conceptualization stage the range will vary and
ranges. Thus, the ranges will be higher at the start of similarly for feasibility and nal estimation, the
the project and will narrow down as project ranges will vary. The ranges will narrow down from
progresses. broad level to lower levels. Some of the techniques
are described:
ROUGH ORDER OF MAGNITUDE (ROM)
ESTIMATE: This estimate is generally made

61
during project initiation phase. A typical range A project manager MUST perform risk management
of estimates for ROM is +/- 50%, however, this activities and include reserves (contingency and
percentage will vary depending on how much management) when estimating the total cost of the
is known by the project team about the project project. The cost budget is cost baseline plus
when creating estimates. management reserves. The cost budget indicates the
BUDGET ESTIMATES: Done during the project total money the organization should have allocated
planning stage. The ranges varies from -10% to for the project.
+25%.
DEFINITIVE ESTIMATE: It is a more rened For creation of a budget, the process of cost
project cost estimate. A few project managers aggregation is used. In this concept, the activity costs
use a range of +/- 10% and others use -5% to are rolled up into work package costs, work package
+10% of range from actual. costs are then rolled up into control account costs
and control account costs are nally rolled up into
When the Estimate Cost process is completed, it project costs. Contingency cost is added to the cost
results into: baseline. Management reserves are added as a nal
Activity Cost Estimates with the explanation of step.
how these costs were derived
Changes or updates to other project manage- Comparison of cost baseline and cost budget is done
ment documents such as risk register, change by the project manager to parametric estimates,
control register, among others expert judgment or historical records for a sanity
check. If there are signicant variances between the
DETERMINE BUDGET reference data and project estimates, the project
In the process, the project manager determines the manager needs to investigate and ensure that the
amount of funds the organization needs to have estimates are correct.
available for the project by calculating the total cost
of the project. This calculation leads to creation of a Checking of the cash ow is the next thing to do.
Budget. There could be situations where the funding is not

62
available when it is required by the project. Hence, all A few activities that could be helpful for controlling
the activities need to be planned in a time-phased costs include:
manner and may be shown as an S-curve. Use of cost management plan; a cost manage-
ment plan helps the project manager plan for
The next step is to identify any constraints in the controlling cost of the project.
project charter. Project manager needs to reconcile Use of Organizational process assets; Organi-
the cost baseline and cost budget with these zation policies, procedures, tools or reporting
constraints. The reconciliation is done as a part of formats related to controlling costs can be
Integration Management process. If the project used.
estimate exceeds the constraints, the project Prevention of unnecessary changes; this is an
manager must meet the stakeholders and explain important activity. Prevention process involves
the reasons of exceeding the constraints and also identication the root-causes where high costs
share options to reduce project costs. Else, an are involved and mitigating them.
unrealistic budget is made available and it is Measure costs; another important factor that
considered to be a project managers fault. the project manager must be completely
involved in throughout the lifecycle of the
The output of Determine Budget process is Cost project is measuring the project cost for
Baseline. The eorts involved in determining budget variation from the baseline. This triggers either
process may lead to changes in other project into corrective or preventive actions.
management documents.
PROGRESS REPORTING
CONTROL COSTS The project manager should avoid usage of
Control costs process is focused on controlling cost guestimates for reporting progress. One of the
of the project as described in any other knowledge following techniques can be deployed by the project
area in the control section. manager:

63
50/50 Rule: An activity is considered 50%
complete when it begins and gets credit for the
rest 50% only when it is completed.
20/80 Rule: An activity is considered 20%
complete when it begins and gets credit for the
rest 80% only when it is completed.
0/100 Rule: An activity is considered 0%
complete when it begins and gets credit for the
100% only when it is completed.

EARNED VALUE MEASUREMENT


The benets of Earned Value include:
Provides the ability to the project manager to
track the project cost very well
Allows the project manager to look at other
more productive aspects of the project
Does not allow any space for guestimation of
project progress numbers
The performance measurement baseline is a
combination of scope, schedule and cost baselines.
Earned value measures project performance against
scope, schedule and cost baselines (performance
measurement baseline). Earned value measurement
is better, because it integrates cost, time and the
work done (or scope) and can be used to forecast
future performance and project completion dates
and costs.

64
QUALITY MANAGEMENT DEFINITION OF QUALITY MANAGEMENT
The process of creating and following policies and
procedures to ensure that a project meets the
Rework and defects are a direct outcome of lack of dened needs it was intended to meet from the
attention to quality. The higher the rework, more customers perspective is termed as Quality
time and money being wasted and busting the cost Management. Quality Management process ensures
and schedule baseline. no deviations occur from project requirements. Plan
Quality, Perform Quality Assurance and Perform
Lack of attention to quality needlessly add consider- Quality Control are a part of Quality Management
able risk to the project which results in tremendous process.
amount of rework and added expense.
QUALITY THEORISTS
It is important to know at the onset of the project A few important quality theorists include:
what acceptable quality is and how it will be Philip Crosby: Phil Crosby propagated that
measured on the project. This process of performing quality is conformance to requirements. The
Quality Management process helps avoid many concepts of cost of poor quality, prevention
issues at a later stage of the project. over inspection and zero defects were also
popularized by him.
DEFINITION OF QUALITY Joseph Juran: Joseph Juran dened quality as
The degree to which the project fullls the tness for use and advocated involvement of
requirements is dened as Quality. top management to address quality issues. The
80/20 principle developed by Vilfredo Pareto
A project cannot achieve quality if all of the stated was propagated by Joseph Juran.
and unstated requirements are dened in the project W. Edwards Deming: The 14 points to quality
scope statement. management and Plan-Do-Check-Act cycle
were propagated by Dr. W. Edwards Deming.

65
ACTIONS REQUIRED TO ENSURE QUALITY ON THE Collect problems, errors, and complaints, and
PROJECT review what can be done to prevent them from
Review of project charter and project scope reoccurring on the project
statement Have teams roaming the project looking for
Gather customers voice about the denition of quality improvements
quality
Identify the specic (desired) levels of GOLD PLATING
performance in the products and components Gold plating is all about giving the customer extra
of the products value of the product (such as more functionality,
Identify the levels at which the project can be higher-quality parts, more scope than required,
controlled (i.e. at work package level, at activity higher performance). Some organizations do have
level or more detailed levels) the policy that promotes adding value to customers
Identify if there are any activity levels and/or and going over an beyond fullling their requests, it
processes are applicable to the project is not recommended by advanced quality thinkers.
Determine the quality standards and processes The teams impression of what is valued by the
to use, when, and on what parts of the project customer and what the customer does not want is
Set standards to reach the level of quality often termed as Gold Plating. Most projects have
performance diculty in achieving the objectives of the project,
Set metrics to measure quality from customers gold plating can be done on certain projects and may
and stakeholders viewpoint not be done on certain others. This creates a gap in
Identify the procedures to eectively control customers expectations and hence gold plating is
the processes followed and standards are met not recommended.
Test the validity of assumptions before they
result in problems MARGINAL ANALYSIS
Make sure the team members understand the The point where the benets (revenue) that is to be
denition of quality for their work received from improving quality equals the

66
incremental cost to achieve that quality is termed as IMPACT OF POOR QUALITY
Marginal Analysis. Poor quality leads to:
Increased costs
CONTINUOUS IMPROVEMENT (OR KAIZEN) Low morale
Continuously looking for small improvements in the Low customer satisfaction
process is termed as Continuous Improvement. Increased risk
Kaizen is a Japanese word where Kai means Rework
Change and Zen means for the better. Schedule delays

JUST IN TIME (JIT) UNDERSTANDING THE DIFFERENCE BETWEEN


The concept of JIT involves having the suppliers PLAN QUALITY, PERFORM QUALITY ASSURANCE
deliver raw materials just when they are needed, AND PERFORM QUALITY CONTROL
thus reducing inventory to close to zero. JIT has Plan Quality focuses on:
supplemented reduction in high inventory costs Dening quality for the project
which is unnecessary. Identifying how quality will be achieved
Perform Quality Assurance focuses on:
TOTAL QUALITY MANAGEMENT (TQM) Work being done on the project
This philosophy encourages companies and their Ensures that the team follows the processes as
employees to focus on nding ways to continuously planned to produce projects deliverables
improve the quality of their products and their Perform Quality Control focuses on:
business practices at every level of the organization. Examination of actual deliverables of the
project
RESPONSIBILITY FOR QUALITY Ensure deliverables are correct and they meet
The ultimate responsibility of the product or project the planned level of quality
quality lies with the project manager. However, the
entire organization has responsibility relating to PLAN QUALITY
quality. The Plan Quality process requires inputs from:

67
Organizational process assets Occupational Safety and Health Administration
Enterprise environmental factors (OSHA): OSHA set standards for safety of
Stakeholder register workers in a plant.
Scope baseline (scope statement, WBS, WBS The United Nations Conventions on Contracts
dictionary) for International Sale of Goods (CISG): The
Schedule baseline CISG standard governs international sales
Cost baseline transactions.
Risk register
The project manager should also ensure that the
Objective of Plan Quality process is identication of project must comply with Organizational process
relevant organization/industry practices, standards, assets and Enterprise Environmental Factors. The
requirements for quality of the project, product of project manager must also plan the project so that it
the project, and project management eorts. meets customers quality standards. The project
manager must then dene any additional project
The output (result) of Plan Quality process is a specic standards and procedures that are needed. It
Quality Management plan. should be noted that when the project manager
denes additional standards and procedures, he
As a part of Plan Quality process, the project should take appropriate care that these new
manager needs to look for any standards that can practices do not violate other relevant standards.
help the project to avoid Reinventing the Wheel,
that can help in higher quality levels. Some available The project manager then needs to determine what
standards include: work is required to meet those standards created for
the project. Determination of specic measurements
ISO 9000: Created by International Organiza- that will be made each week, each month or for each
tion for Standardization (ISO) to help ensure deliverable should be made to ensure compliance
organizations have quality procedures and that with all standards.
they follow them.

68
It is important to note that the level of quality eorts chart shows whether the samples are within control
should be appropriate to the needs of the project. limits.
Quality must be balanced with other project
constraints. Lets now learn a few tools and
techniques used in Plan Quality process:

COST BENEFIT ANALYSIS


This technique helps the project manager weigh the
benets of the quality eorts versus the costs to
determine appropriate quality level and require-
ments for the project.

COST OF QUALITY (COQ)


COQ involves looking at costs of conformance and
non-conformance to quality and creating an
appropriate balance. The costs of conformance Control Chart
should be lower than costs of non-conformance.

CONTROL CHARTS A control chart can be used to monitor project


Control charts are SET UP in Plan Quality as a part of performance gures such as cost and schedule
the eort to dene quality on the project. They are variances. It primarily helps monitor production and
UTILIZED in Perform Quality Control to help other processes to see if the results are within
determine if the results of a process are within acceptable limits (i.e. in control). A special cause
acceptable limits. variation means the process is out of control.

During the Perform Quality Control process, samples


are taken and plotted on the charts. The control

69
UPPER AND LOWER CONTROL LIMITS OUT OF CONTROL
Control limits are acceptable range of variations of a The process is out of a state of statistical control
processs results. They are shown as two dashed when:
lines. The acceptable range of measurements A data point falls outside the control limits
between the upper and lower control limits is set by There are non-random data points; these may
the project manager and stakeholders based on the be within the upper and lower control limits,
organizations quality standard. This range is such as the rule of seven.
calculated based on +/- 3 sigma (standard Think of out of control as lack of consistency and
deviations). Data points outside this range indicate predictability in the process or its results.
the process is out of control.
RULE OF SEVEN
MEAN (AVERAGE) The rule of seven is a thumb rule (also known as
The mean is indicated by a line in the middle of the heuristics). It refers to a group or series of non-
control chart. It shows the middle of the range of random data points that total seven on one side of
acceptable variation. the mean. The rule of seven tells the project
manager that even if these points are within the
SPECIFICATION LIMITS control limits, they are not random and the process
Specication limits represent the customer s may be out of control.
expectations or contractual requirements for
performance and quality on the project. Specication ASSIGNABLE CAUSE / SPECIAL CAUSE VARIATION
limits are not calculated like control limits. They are If there is an assignable cause or special cause
stated by the customers. If the data points are variation, it means a data point or series of data
outside the control limits, the process is termed as points require investigation to determine the cause
Out of Control, however, if the data points are of variation.
outside the specication limits, the process starts
producing defects.

70
BENCHMARKING FLOWCHARTING
This technique involves looking at other projects to The Macro-level ow charting is termed as SIPOC.
get ideas for improvement on the current project SIPOC is an acronym for Supplier (S), Inputs (I),
and to provide a basis (or benchmark) to use in Process (P), Output (O) and Customer (C).
measuring quality performance.

DESIGN OF EXPERIMENTS (DOE)


DOE uses experimentation to statistically determine
what variables will improve quality. DOE is faster and
a more accurate statistical method that allows
project managers to systematically change all of the
important factors in a process and see which
combination has a lower impact on the project.

STATISTICAL SAMPLING
Doing quality audits for all the manufactured Macro-level Flow Charting (SIPOC)
products in a project might be a time-consuming
task. Here, it is best to take a sample of a population.
Sampling is used when: A owchart shows how a process or system ows
Auditing the population may take too long from beginning to end and how the elements
It costs too much interrelate. Flow charts can be used in many parts of
Auditing can also be destructive project management.
The sample size and frequency of measurements are
determined as a part of the Plan Quality process, and
the actual sampling is done in Perform Quality
Control.

71
picture of the item to be inspected, with space
to note any defects found.
Process Improvement Plan: The plan for
improving the processes is called the process
improvement plan and it becomes a part of
project management plan. Process improve-
ment plan helps save time by increasing
eciency and preventing problems. It also
saves money and increases the probability that
the customer will be satised.
Project Management Plan and Project Docu-
ment Updates: Updates to the project manage-
Process Flowchart ment plan and project documents are needed
throughout the project management process.

OUTPUTS OF PLAN QUALITY


Following are the results of the Plan Quality process:
Quality Management Plan: The quality mana-
gement plan is the process to determine what
quality is and to put a plan in place to manage
quality.
Quality Metrics: The project manager needs to
think through the areas on the project that are
important to measure and decide what
measurement systems are acceptable.
Quality Check List
Checklist: A quality checklist is the list of items
to inspect, a list of steps to be performed, or a

72
PERFORM QUALITY ASSURANCE OUTPUTS OF PERFORM QUALITY ASSURANCE
Perform Quality Assurance is an execution process Perform Quality Assurance leads to the following
that is performed while the project work is being outputs:
done. Following tools and techniques are used by Change requests
Perform Quality Assurance process: Updated standards and processes
Updated project management plan and project
PLAN QUALITY AND PERFORM QUALITY CONTROL documents
TOOLS AND TECHNIQUES
The tools and techniques of Plan Quality and PERFORM QUALITY CONTROL
Perform Quality Control processes are used as a part Perform Quality Control is a process of ensuring a
of Perform Quality Assurance process. certain level of quality in a deliverable, whether it be
a product or a service. Control means measure, and
QUALITY AUDITS that is a major function of Perform Quality Control
A team of auditors is responsible to see if the project process. It measures products or services to
is complying with company policies, standardized determine whether they meet the quality standards.
practices, and procedures and to determine whether
the policies, practices and procedures being used are In large companies, a quality control department
ecient and eective. may complete much of quality control work and
report the ndings to the project manager. The
PROCESS ANALYSIS project manager must be able to read and
The process analysis should be planned in at certain understand the quality measurement reports.
points in the project. Process analysis is a part of
continuous improvement eort on a project and Quality Control occurs throughout the life of the
focuses on identifying improvements that might be project. A few important terms related to quality
needed in processes. control are described:

73
MUTUAL EXCLUSIVITY Cause and eect diagram
Two events are said to be mutually exclusive if they Flowchart
cannot both occur in a single trial. Histogram
Pareto Chart
PROBABILITY Run Chart
Probability refers to the likelihood that something Scatter Diagram
will occur. It is expressed as a decimal or a fraction, Control Chart
on a scale of zero to one.
C A U S E A N D E F F E C T D I AG R A M ( F I S H B O N E
NORMAL DISTRIBUTION DIAGRAM OR ISHIKAWA DIAGRAM)
A normal distribution is a shape of a bell curve and is Cause and eect diagram is:
the most common probability density function. It is A creative way to look at the root causes
used to measure variations. Helps stimulate thinking, organizes thoughts
and generate discussion
STATISTICAL INDEPENDENCE Can be used to explore the factors that will
Statistical independence means the probability of result in a desired future discussion
one event occurring does not aect the probability of
another event occurring.

STANDARD DEVIATION (OR SIGMA)


A measure of range is its standard deviation. This
concept is also sometimes stated as a measure of
how far you are from the MEAN.

SEVEN BASIC TOOLS OF QUALITY


The following tools are known as seven basic tools of
quality:
Cause Eect Diagram

74
HISTOGRAM
A histogram displays data in the form of bars or
columns. This tool shows what problems are worth
dealing with. A typical histogram presents data in no
particular order.

Pareto Chart
Histogram Diagrams

RUN CHART
PARETO CHART (PARETO DIAGRAM) A run chart allows the project manager to look at
A Pareto chart is a type of histogram, but it arranges history to see if there is pattern of variation. It is a
the results from most frequent to least frequent to useful tool for controlling quality.
help identify which root causes are resulting in most
problems. It is based on 80/20 rule which states that
80% of the problems are due to 20% of the causes.
Pareto charts:
Help focus attention on the most critical issues
Prioritize potential causes of the problem
Separate the critical few from the trivial many

75
Run Chart

Scatter Diagram

SCATTER DIAGRAM
The scatter diagram tracks down variables to see if
they are related.

OUTPUTS OF PERFORM QUALITY CONTROL


The outputs of Perform Quality Control process are:
Measurements
Validated changes
Updates to project management plan and
project documents
Change requests
Lessons learned
Validated deliverables

76
HUMAN RESOURCES MANAGEMENT management team includes some of the team
members to help assist the project manager
with project management activities.
Human Resources Management involves: Team building activities are a required part of
An integral part of project management is an project management. A project manager
important function of human resource formally plans team building activities in
function i.e. creating recognition and reward advance.
system The project manager must track team member
Team members competencies need to be performance
improved and it is a critical responsibility of a
project manager The human resources responsibilities increase as the
Executing process group primarily includes size of the project team increases. The human
Human Resource Management resource management process involves:
Human Resource activities done by a project Identication of team members
manager requires documentation and is Dening roles and responsibilities
formal in nature Creation of reward systems
Formal roles and responsibilities are to be Improving team members performance
assigned to project team members to assist Track team and individual performances
the project manager in eective project
execution ROLES AND RESPONSIBILITIES
Project is coordinated by the project manager Clear identication of roles and responsibilities of
and planned by the teams management, team members, and other stakehol-
Resource availability must be continually ders on the project, using tools such as responsibility
conrmed by the project manager assignment matrix is a key activity of a project
The project team consists of a project manager.
manager, project management team and other
team members of a project. A project

77
ROLE OF A PROJECT SPONSOR / INITIATOR Send out letters of commendation to team
A sponsor is the one who provides nancial members and their bosses
resources for the project. A sponsor could also be a Make sure team members needs are taken
customer, senior management, others. Management care of
serves as a protector of the project. Create recognition and reward system
described in Human Resource Plan section
HUMAN RESOURCE RESPONSIBILITIES FOR
PROJECT MANAGERS DEVELOP HUMAN RESOURCE PLAN
The list of responsibilities of project managers is: One of the outcomes of develop human resource
Determine the resources required for the plan is dening the roles and responsibilities of team
project members. The Develop Human Resource Plan
Negotiate with resource managers for optimal process involves:
available resources
Create a project team directory O R G A N I Z AT I O N C H A R T S A N D P O S I T I O N
Create project job descriptions for team DESCRIPTIONS
members and other stakeholders There are multiple ways to record and communicate
Make sure all roles and responsibilities are roles and responsibilities including Responsibility
clearly assigned on the project assignment matrix, organization breakdown structu-
Understand the team members needs for res, resource breakdown structures, position descrip-
training related to their work on the project, tions. Additionally, any roles and responsibilities
and make sure they get the training expected of the team members need to be clearly
Create a formal plan covering such topics as assigned, in addition to the project activities the
how the team will be involved in the project team members are expected to complete.
and what roles they will perform a human
resource plan
Insert reports of team members performance
into their ocial company employment record

78
RESPONSIBILITY ASSIGNMENT MATRIX Another tool that can be used in place of RACI Matrix
This chart is used for cross-referencing team is known as ARMI Matrix where A stands for
members with activities or work packages they are to Approver, R Resource, M Member and I
accomplish. Interested Party.

RACI CHART (Responsible, Accountable, Consult, POSITION DESCRIPTIONS


and Inform) Position descriptions are like job descriptions but
This chart is a form of responsibility assignment only created for project work. They are usually
matrix that denes roles assignment more clearly documented in text format.
than the matrix discussed earlier.
HUMAN RESOURCE PLAN
A human resource plan is an output of Develop
Human Resource Plan. The human resources
planning requires a plan for when and how team
members are added, managed, controlled, and
released from the project.
RACI Matrix
The Human Resource Plan includes:
Roles and Responsibilities
Project Organization Charts
Stang Management Plan

ARMI Matrix

79
Position (Role) Descriptions

80
STAFFING MANAGEMENT PLAN Award prizes for performance
Stang Management Plan is a part of Human Recommend team members for raises or
Resource plan and includes: choice work assignments
Plan for sta acquisition Send notes to team members managers about
Resource calendars great performance
Sta release plan Plan milestone parties or other celebrations
Sta training needs Acquire training for team members
Rewards and recognition Adjust project to assign people to activities
Compliance they have been waiting to work on or remove
Safety them from disliked activities as a reward

REWARDS AND RECOGNITION SYSTEM Creating a reward and recognition system requires
Planning a system to reward resources can be a planning in advance of starting the project work.
signicant eort.
ACQUIRE PROJECT TEAM
A project manager must be able to motivate the Acquiring the project team involves the following:
team, especially when working on a project in a There could be some resources who are
matrix organization. Rewards and recognition is one preassigned to the project. Knowing those
of the most eective way to motivate and gain resources and conrming their availability is
cooperation from your team regardless of the required
reporting relationship. Best possible resources should be negotiated
by the project manager
The reward system might include several actions Hiring new employees
such as: Working with virtual teams
Say thank you more often Managing risks of scarce resources
Award prizes such as Team Member of the
Month recognition

81
PREASSIGNMENT HALO EFFECT
Some resources are assigned in advance to the The halo eect is something to be aware of when
project. A project manager has to work with these dealing with team members. There can be a
resources. tendency to rate the team members high or low on
all factors due to the impression of a high or a low
NEGOTIATION rating on some other specic factor.
Some resources may have to be acquired through
negotiation. To negotiate resources from within the DEVELOP PROJECT TEAM
organization, the project manager should: Develop Project team is a part of project execution.
Know the needs of the project and its priorities The process generally results in decreased turn-over,
within the organization improved individual knowledge and skills, and
Be able to describe the WIIFM (Whats In It For improved teamwork.
Me) to the resource manager by assisting the
project manager TEAM BUILDING ACTIVITIES
Do not ask for the best resources if the project Team building activities help the project team work
does not need them as a cohesive group working for the best interest of
Be able to prove why the project requires the the project and thus enhances the project
stated quality and quantity of resources. Use of performance. A few things to know include:
network diagram and project schedule is It is a project managers job to guide, manage,
helpful and improve the interactions of team members
Work with resource manager to deal with Trust and cohesiveness amongst team mem-
situations as they arise bers should be improved by the project
manager
VIRTUAL TEAMS All project activities should include team-
Virtual teams do not meet face to face. Thus, you can building activities
have the best of team members from dierent parts
of the world.

82
Throughout the life of the project, team Getting everyone involved in some planning
building activities require concerted eorts and exercises
continued focus
WBS creation is a team-building tool TRAINING
Team building should start early in the life of Training opportunities for team members help
the project improve their skills. They also decreases overall
project cost and schedule by increasing eciency.
Team building is also a science. There are formally Conducting training is a cost to the project and
identied stages of team formation and develop- should be paid by the project. It should be
ment. The stages are: documented in the human resource plan.
Forming; People are brought together as a
team GROUND RULES
Storming; There are disagreements as people Ground rules help establish standards and
learn to work together expectations for the team. The rules can address:
Norming; Team members begin to build good Honesty in all communications
working relationships Conict resolution methods
Performing; The team becomes ecient and Escalation procedures
works eectively together Whether it is allowable for people to interrupt
Adjourning; The project ends and the team is with another team member
disbanded Acceptable ways to interrupt when someone is
talking during the meeting
Team building activities can include: Consequences of late attendance
Taking classes together Rules for taking phone calls, email etiquettes,
Milestone parties reading text messages during the meeting
Holiday and birthday celebrations
Outside-of-work trips Setting rules can help eliminate conicts or problems
Creating the WBS with the team during the project because everyone

83
knows what is expected of them. For virtual teams, MANAGE PROJECT TEAM
ground rules are especially important. Manage project team involves day to day manage-
ment of people. Developing the team is dierent
CO-LOCATION (OR WAR ROOM) from managing the project team. It involves:
A project manager might try to arrange for the entire Encouraging good communication
team in each city to have oces together in one Working with other organizations
place or one room. This is called co-location and Using negotiation skills
helps improve communication, decrease the impact Using leadership skills
of conict (since all the parties are right there), and Observing what is happening
improves identify for the project team and for Using an issue log
management in a matrix organization. A war room is Keeping in touch
a central location for project coordination. A war Completing project performance appraisals
room is used for creating WBS, network diagram, Making good decisions
schedule, etc. Inuencing the stakeholders
Being a leader
REWARDS AND RECOGNITION Actively looking for and helping resolve
As dened in the human resource plan, the project conicts that the team members cannot
manager appraises performance and gives out team- resolve on their own
member-appropriate rewards and recognition in the
Develop Project Team process. OBSERVATION AND CONVERSATION
A little attention to things such as tone of emails,
TEAM PERFORMANCE ASSESSMENT phone conversations can tell us whats happening in
The project manager completes formal and informal the project (even for virtual teams). A project
team performance assessments as part of manager should continue to talk to people instead of
developing the project team. These assessments just looking at the reports to understand the nerve of
evaluate and enhance the eectiveness of the team the project.
as a whole.

84
PROJECT PERFORMANCE APPRAISALS Referent: Referent is the power of charisma
Evaluation of employees performance by their and fame. This power comes from another
supervisors is termed as Project Performance person liking the project manager, respecting
Appraisal. These days a 360-degree review has him, or wanting to be like him.
started taking place, where feedback from
supervisors, subordinates and even co-workers is MANAGEMENT AND LEADERSHIP STYLES
included. It helps in providing a clear picture of A project manager needs to use multiple leadership
actual performance. approaches throughout the life cycle of a project. The
term is called situational leadership. It refers to
ISSUE LOG using dierent leadership styles, based on the
Issue logs help project managers eectively control people and project work he or she is dealing with.
issues so they do not impact the project. It is used to
manage team members and stakeholders. The leadership and management styles include:
Directing; This style involves telling others what
POWERS OF THE PROJECT MANAGER to do
One of the major diculties for a project manager is Facilitating; When facilitating, project manager
getting people to cooperate and perform. This is a coordinates inputs of others
major issue in a matrix organization. The dierent Coaching; In coaching, the manager helps
types of power for the project managers include: others achieve their goals
Formal (legitimate): This power is based on the Supporting; A supporting leadership style
position of the project manager means the project manager provides assistan-
Reward: This power stems from giving rewards ce along the way
Penalty (Coercive): This power comes from the Autocratic; This is a top-down approach. Here,
ability to penalize team members the manager has the power to do whatever he
Expert: This power comes from being the or she wants
t e c h n i c a l ex p e r t o r ev e n t h e p ro j e c t Consultative; This is a bottom-up approach. It
management expert uses inuence to achieve results. The manager

85
obtains others opinions and acts as the necessary. This style can be appropriate with a
servant for the team highly skilled team
Consultative-Autocratic; In this style, the Analytical; This style depends on the managers
manager solicits input from team members, own technical knowledge and ability. Analytical
but retains the decision-making authority for managers often make the technical decisions
him or herself for the project, which they communicate to
Consensus; This style involves problem solving their teams
in a group, and making decisions based on Driver; A manager with a driver style is
group agreement constantly giving directions. His or her
Delegating; With a delegating style, the competitive attitude drives the team to win
manager establishes goals and then gives the Inuencing; The style emphasizes teamwork,
project team sucient authority to complete team building, and team decision making.
the work These managers work with their teams to
Bureaucratic; This style focuses on following inuence project implementation
procedures exactly
Charismatic; Charismatic managers energize CONFLICT MANAGEMENT
and encourage their team in performing Conict is INEVITABLE because of the following
project work reasons:
Democratic or participative; This style involves Requirements of many stakeholders
encouraging team participation in the decision- Limited power of the project manager
making process Necessity of obtaining resources from functi-
Laissez-faire; The French term laissez-faire onal managers
has been translated as meaning allow to act,
allow to do, or leave alone. A laissez-faire Conicts can be avoided by:
manager is not directly involved in the work of Informing the team of: Exactly where the
the team, but manages and consults as project is headed, Project constraints and

86
objectives, The content of the project charter, involves nding solutions that bring some
All key decisions and Changes degree of satisfaction to both parties.
Clearly assigning work without ambiguity or Withdrawal (Avoidance): In this technique, the
overlapping responsibilities parties retreat or postpone a decision on a
Making work assignments interesting and problem. Withdrawal is not usually the BEST
challenging choice for resolving conict.
Following good project management and Smoothing (Accommodating): This technique
project planning practices emphasizes agreement rather than dierences
of opinion
The seven sources of conict in the order of their Collaborating: In this technique, the parties try
frequency are: to incorporate multiple viewpoints in order to
1 Schedule lead to consensus
2 Project priorities Forcing: This technique involves pushing one
3 Resources viewpoint at the expense of another
4 Technical opinions
5 Administrative procedures PROBLEM SOLVING METHOD
6 Cost Problem solving method could include:
7 Personality 1 Dene the root problem
2 Analyze the problem
Conict is best resolved by those involved in the 3 Identify solutions
conict. The key conict resolution techniques are: 4 Pick solution
Confronting (Problem Solving): Confronting 5 Implement solution
means solving the real problem so that the 6 Review solution and validate improvement
problem goes away. Confronting leads to a
win-win situation.
Compromising: This is lose-lose situation, since
no party gets everything. This technique

87
OTHER GOOD TO KNOW TERMS, TOPICS AND MCGREGORS THEORY OF X AND Y
THEORIES McGregor believed that all workers t into one of two
EXPECTANCY THEORY groups, X and Y.
Employees who believe their eorts will lead to Theory X managers who accept this theory believe
eective performance and who expect to be that people need to be watched every minute. They
rewarded for their accomplishments will remain believe employees are incapable, avoid responsibi-
productive as rewards meet their expectations. lity, and avoid work whenever possible.
Theory Y managers who accept this theory believe
ARBITRATION that people are willing to work without supervision,
In arbitration, neutral party hears and resolves a and want to achieve. They believe employees can
dispute. direct their own eorts.

PERQUISITES (PERKS) MASLOWS HIERARCHY OF NEEDS


Some employees receive special rewards, such as Maslows pyramid (also called hierarchy of needs)
bonus, gain-share, good oces, etc. include physiological needs, safety needs, social
needs, esteem needs and self-actualization needs.
FRINGE BENEFITS
There are standard benets formally given to DAVID MCCLELLANDS THEORY OF NEEDS (OR
employees, such as educational benets, insurance, ACQUIRED NEEDS THEORY)
and prot sharing. This theory states that people are most motivated by
one of three needs listed in the table. A person
MOTIVATION THEORY falling into one category would be managed
Here are four motivation theories a project manager dierently than a person falling into another
needs to know: category.

88
Working conditions
Salary
Personal life
Relationships at work
Security
Status

What motivates people is the work itself, including


such things as:
Responsibility
Self-actualization
Professional growth
Recognition

This brings us to the end of the Human Resource


Management chapter. The work that is done as part
Maslow's Pyramid (Hierarchy of Needs) of creating the human resource plan on a project and
acquiring, developing, and managing the team
greatly impacts the next knowledge area, communi-
HERZBERGS THEORY cations management.
Herzbergs Theory deals with hygiene factors and
motivating agents.
Poor hygiene factors may destroy motivation, but
improving them, under most circumstances, will not
improve motivation. Hygiene factors are not
sucient to motivate people.
Examples of hygiene factors are:

89
COMMUNICATIONS MANAGEMENT Stakeholders are extremely important and an
indispensable part of any project. A project manager,
during the initiation phase, has the responsibility to
85% - 90% of a project managers time is spent in identify the stakeholders, and then throughout the
communicating. Communication related issues are lifecycle of the project, should continue to manage
the most frequent problems faced by the project their expectations, involvement and their inuence
manager. There is a need of structured communi- on the project.
cations management plan.
Steps involved from stakeholder identication to
Communicating on projects requirey an understan- managing their expectations and inuences
ding of: throughout the project:
Understanding the communication require- Identify ALL the stakeholders
ments from stakeholders Determine ALL of their requirements
Sharing with stakeholders on what communi- Determine their expectations
cation is required from them Determine their interests
Frequent updates to communication plan as Determine their level of inuence
per changing needs of the project Plan how the project manager will communi-
cate with them
STAKEHOLDERS Execute Communicate
The project managers need to be experts in project Manage their expectations and inuence
management and stakeholders are technical experts
in what needs to be done and how it needs to be IDENTIFY STAKEHOLDERS
done. Proper project management requires the The following are created or performed in the
project manager to identify the stakeholders, process of Identify Stakeholders.
determine their requirements, expectations and
inuence; then incorporate that information into the STAKEHOLDER ANALYSIS
product or project scope as needed. Stakeholder analysis involves:

90
Identication of stakeholders
Assessing their impact or inuence on the
project

To achieve the above, the project manager has


multiple ways:
He can use the initial list of stakeholders from
project charter
He can use records from past projects
He can also use data gathering techniques
such as brainstorming, interviewing Stakeholder Register
New stakeholders can suggest additional
names of stakeholders required for the project
STAKEHOLDER MANAGEMENT STRATEGY
Tools such as power/interest grids and salience A strategy of how stakeholders will be managed is an
models can be used to group stakeholders by output of Identify Stakeholders process. Either
qualications like authority levels, impact or stakeholders are managed individually or as groups.
inuence, or requirements. The results of these A project manager needs to identify which approach
classications help project managers determine how, would be easier and less time consuming. Some
what and when to communicate with each stakeholders require more time and some less for
stakeholder. getting managed. Stakeholders can be an asset to
the project or they may be a problem, depending on
STAKEHOLDER REGISTER how well is the project planned. Both negative and
Stakeholder register is an output of Identify positive aspects of stakeholders involvement in the
Stakeholders process. All the information about the project should be managed.
stakeholders is compiled in the Stakeholder Register.

91
PLAN COMMUNICATIONS plan, for project charter, memos, communica-
Planning communications involve considering the ting over long distances
performing organizations environment (i.e. Enter- Formal verbal: Used during presentation and
prise Environmental Factors), including its culture speeches
and expectations. The performing organizations Informal written: Used for Emails, handwritten
processes, procedures, historical records, lessons notes, text messages, instant messaging
learned and other information (i.e. organizational Informal verbal: Used in meetings, conversions
process assets) should also be taken into considera-
tion. The output is the Communications Manage- COMMUNICATION MODELS
ment Plan which is a component of Project Project management requires a more structured
Management Plan. approach to communications. Communication
models are comprised of three parts: the sender, the
During project initiating, the eorts begin to identify message and the receiver. Each message is encoded
stakeholders and their communication require- by the sender, gets transmitted to the receiver and is
ments. In planning, it is determined how to apply decoded by him. There are certain noise factors in
that information. The information and communica- communication models such as receivers education,
tion needs of the stakeholders are taken into language, cultural eect of the way the message is
consideration in the Plan Communications process. decoded by the receiver.

A clear and concise communication requires


handling communications in a structured way and
choosing the best type of communication for the
situation. Information can be expressed in the
following ways:
Formal written: It is used when there are
complex problems, for project management Project Communication Models

92
EFFECTIVE COMMUNICATION interactions, by telephone, fax, mail, or email;
For eective communication, the sender should through virtual or in-person meetings; and through
decode the message carefully, identify the intranet or internet-based forums for information.
communication method to be used to send the These dierent means of communications is termed
message and conrm if the message is understood. as Communication Technology.
The sender can be aware of the following communi-
cation factors: COMMUNICATION METHODS
Nonverbal; Most of what is communicated is Communication methods can be grouped into the
non-verbal. It is based on physical mannerism. following categories:
About 55% of all communication is non-verbal. INTERACTIVE COMMUNICATION; In this
Paralingual; Pitch and tone of voice also help to method two or more people interact with each
convey a message. other. An individual provides information
which is received by the other person who
EFFECTIVE LISTENING then responds to the information given by the
The receiver should decode the message carefully individual. Meetings, conference calls, video
and conrm the message is understood. This conferences are examples of Interactive
includes watching the speaker to pickup physical communication.
gestures and facial expressions, thinking about what PUSH COMMUNICATION; Unlike interactive
to say before responding, and using active listening, communication, this method involves sending
in which the receiver conrms that he/she is the information to the recipient with no
listening, expresses agreement or disagreement, or expectation of receiving the feedback. This is
asks for clarication. one-way streaming of information. Status
reports, mass-mailers, project updates sent to
COMMUNICATION TECHNOLOGY a large population are examples of push
Planning communications involve determining the communication.
specics of how to communicate each item. PULL COMMUNICATION: In this method, the
Communication can take place through face-to-face sender places the information at a central

93
location (like a sharepoint or a share drive) and Team should stick to the agenda during
the recipients responsible to use the meeting
information or need the information retrieve Team members and meeting attendees should
the details from that location. know their role in meetings before hand (for
example, one member could be the minute
CONTROL OF COMMUNICATIONS taker and the other could be a time-keeper)
The project manager cannot control all of the Meetings to include right audience
information Eective facilitation is required by project
The project manager needs to control the ow manager to chair and rules are to be kept in
of communication and the information shared view
in the communication For each action, the action owner and
About 85-90% of the project managers time is deliverable date to be assigned in the meeting
spent in communicating Minutes to be documented and published

MEETINGS
There are several rules for meetings. Some of them
are:
Meetings should have a time limit, and project
manager should keep to it
Recurring meetings should be scheduled in
advance
Action Plan Tracker
Meeting with the team should be regular
(however, need not be often)
Each meeting should have a specic purpose
and agenda
The agenda should be distributed to the
meeting attendees before the meeting

94
communication management plan must be in
writing. All stakeholder needs must be addressed.
Communication management plan becomes a part
of project management plan.

DISTRIBUTE INFORMATION
The project manager is responsible for distributing
project related information to many stakeholders of
the project. Dierent stakeholders need to receive
dierent information in various formats, and the
project manager should have identied in advance
on what each stakeholder needs to know, how, and
when. Implementing the Communications Manage-
ment Plan is the output of Distribute Information
Process. A project manager should be able to
Meeting Minutes distribute (send) information and also needs to make
sure that it is eective and ecient for the recipient.

COMMUNICATION CHANNELS MANAGE STAKEHOLDER EXPECTATIONS


Communication channels can be calculated using the Managing stakeholder expectations requires
formula: proactive actions from the project manager to make
N (N 1) / 2 where N = the number of people. the stakeholders feel that their needs and concerns
are atleast being considered, even if they are not
COMMUNICATION MANAGEMENT PLAN agreed to. The eorts of managing stakeholder
A communication management plan documents how expectations also allows the communication
the project manager manages and controls commu- channels to be open between the stakeholders and
nication. Communications are very complex. Hence, the project managers so that the stakeholders can

95
inform the project managers of potential risks, The reports should provide all the information
changes and other related information. needed by stakeholders to the level of detail required
by them. The needs of the projects should be
Attention to stakeholders needs is required for considered while designing the reports. The most
managing their expectations when the work is being appropriate method is to be used to send the
done. This helps in building trust, resolving conicts, reports. The method used to send reports plays a
preventing problems and increases belongingness of crucial role in getting the report read and acted
the stakeholder for the project. The project manager upon. A project manager must not spend all the time
can review multiple project documents such as only doing reporting activities. The project
stakeholder register, stakeholder management management plan can be used to identify perfor-
strategy, communications management plan, issue mance measurement baseline. This baseline can be
logs, and changes to determine the actions required used in the reports to measure the performance of
to manage stakeholder expectations. the project. All reports must give a clear, concise and
true picture of the information that is being depicted.
COMMUNICATION BLOCKERS Reports should not just include schedule, but also
The communication blockers include noisy include cost, scope and quality performance as well.
surroundings, improper encoding and decoding of The appropriate moment of recommending and
messages, making negative statements, culture, implementing corrective actions is known by looking
language, hostility, distance between those trying to at the reports. Report performance include looking
communicate, among others. at the future. The dierent types of performance
reports include:
REPORT PERFORMANCE Status Report; Reports the current performan-
Collecting information related to work performance, ce of the process against performance measu-
analyzing it, creating reports and sending them to rement baseline
respective stakeholders is involved in reporting Progress Report; Describes the total work
performance of the project. Report performance is a accomplished
part of communications management plan.

96
Trend Report; Whether performance has an
upward trend or a downward trend is reported
by the trend report
Forecasting Report; Future project status and
performance is reported basis current (or
historical) data
Variance Report; Compares actuals to baseli-
nes
Earned Value Report; This report integrates
scope, cost, and schedule measures to assess
project performance
Lessons Learned Documentation; Performance
reports are used as lessons learned for future
projects

This concludes the Communication Management


chapter. A project manager should spend time in the
early stages of the project to identify ALL stake-
holders and take a structured approach to communi-
cations by creating a communications management
plan.

97
RISK MANAGEMENT THREATS AND OPPORTUNITIES
Threats are events when occurred can negatively
impact the project, whereas opportunities are events
Risk Management is about anticipating risks and when occurred can positively impact the project.
having a plan in place that will resolve it when it
occurs. Risk management saves time, money and
eorts. It reduces unnecessary stress on project
team. Risk management helps prevent many
problems and helps make other problems less likely.

Risk Management activities are integral to a project


managers daily work. Through risk management, the
project changes from being in control of the project
manager to the project manager being in control of Threats and Opportunities
the project.

RISK MANAGEMENT Up to 90% of threats identied and investigated in


Risk management includes risk management risk management process can be eliminated.
planning, risk identication, the qualitative and
quantitative analysis of risks, risk response planning, UNCERTAINTY
and monitoring and controlling the risk responses. Lack of knowledge about an event that may occur
Risk management helps in increasing the possibility and reduce condence in the conclusions drawn
of positive events on the project and eectively from the data is termed as uncertainty.
reduces the possibility of negative events on the
project. RISK FACTORS
Risks can have various factors such as:

98
How likely is the probability that the risk event This results in getting additional time for the project
will occur? manager to perform other critical activities related to
The impact of the risk his project.
When will the risk occur during the course of
this project? We will be studying six management processes,
How many times will this risk occur? namely:
1 Plan Risk Management
RISK AVERSE 2 Identify Risks
An individual who avoids risk and thus, does not 3 Perform Qualitative Risk
want to take risks is known as Risk Averse. 4 Perform Quantitative Risk
5 Plan Risk Responses
RISK TOLERANCES AND THRESHOLDS 6 Monitor and Control Risks
The degree or level of risk that is acceptable is known
as Risk Tolerance. The specic point where risk PLAN RISK MANAGEMENT
becomes unacceptable is known as Risk Thresholds. The individuals involved in Planning Risk Manage-
ment include:
THE RISK MANAGEMENT PROCESS Project Manager
In processes where risk management is eectively Sponsor
carried out, we see: Team
Risk response planning is very robust. Hence, Customer
even if risks occur, they are eliminated. Other Stakeholders
An agenda is set to discuss risk items in every And Experts
meeting.
There is always a plan to deal with any risk Risk management process is structured and perfor-
events. med for the process. Risk management eorts are
not limited to creating a standardized checklist basis
the experience gained from past projects. Risk

99
management eorts should be based on the size, a subjective assessment of risk, even if
complexity and the skill levels of the project and dierent individuals rate the risk as 6, they may
project members. have dierent denitions. Thus, the denitions
of probability and impact help in standardizing
Plan Risk Management process involves planning the these interpretations and also help compare
total time to be spent on risk management based on risks between projects.
the needs of the project. It involves identifying the Stakeholder tolerances: For a successful
resources and the process of performing risk project, tolerance levels of stakeholders for
management. Organizational process assets are dierent risk categories such as cost, quality,
used eectively by the project manager to plan risk etc should be identied during project
management. initiation and claried regularly.
Reporting formats: Reporting formats of any
OUTPUTS OF RISK MANAGEMENT PLAN reports related to risk management are
The risk management plan may include: identied and nalized.
Methodology: The process of performing risk Tracking: Risk management requires regular
management is dened. traction by those involved in the project.
Roles and responsibilities: Individuals involved Hence, a tracking mechanism is to be dened
in performing risk managements are identied. for eective risk management.
Budgeting: Cost of risk management process is
determined. RISK CATEGORIES
Timing: The time when risk management Risk categories can be broad including the sources of
process should start is determined. risks that the organization has experienced. Some of
Risk categories the categories could be:
Denitions of probability and impact: The External: Government related, Regulatory,
probability and impact of any risk is generally environmental, market related.
rated on a scale of 1 to 10. 1 being the lowest Internal: Service related, Customer Satisfaction
and 10 being the highest. However, since this is related, Cost related, Quality related.

100
Technical: any change in technology related. DOCUMENTATION REVIEWS
Unforeseeable: Some risks about 9-10% can be The standard practice to identify risks is reviewing
unforeseeable risks. project related documents such as lessons learned,
articles, organizational process assets, etc.
TYPES OF RISK
In addition to risk categories, there are more INFORMATION GATHERING TECHNIQUES
classication of risk types: The given techniques are similar to the techniques
Business Risk: It could be a gain or loss used to collect requirements. Lets look at a few of
Pure (Insurable) Risk: It only results in a loss them.
(example: robbery, re, etc)
BRAINSTORMING
IDENTIFY RISKS Brainstorming is done with a group of people who
This process involves talking to all stakeholders and focus on identication of risk for the project.
non-stakeholders. It also involves reviewing
organizational process assets. Project managers
generally start risk identication from the onset of
the project. High-level risks are identied during the
project charter creation phase. Detailed risk
identication occurs during planning process. The
project scope statement, WBS and WBS dictionary
(scope baseline) are critical inputs for risk
identication. Some of the risk identication tools
and techniques include:

Brainstorming Results

101
DELPHI TECHNIQUE ASSUMPTION ANALYSIS
A team of experts is consulted anonymously. A list of Identication of dierent assumptions of the project
required information is sent to experts, responses and determining their validity, further helps in
are compiled, and results are sent back to them for identifying risks for the project.
further review until a consensus is reached.

INTERVIEWING
An interview is conducted with project participants,
stakeholders, experts, etc to identify risks.

ROOT CAUSE ANALYSIS


Root causes are determined for the identied risks.
These root causes are further used to identify SWOT Analysis
additional risks.

S W OT A N A LY S I S ( S T R E N G T H , W E A K N E S S , DIAGRAMMING TECHNIQUE
OPPORTUNITIES AND THREATS) Diagramming techniques such as Cause and Eect
Strengths and weaknesses are identied for the Diagram, Process Flow Charts, etc can be used for
project and thus, risks are determined. identication of risks.

CHECKLIST ANALYSIS OUTPUTS TO IDENTIFY RISKS


The checklist of risk categories is used to come up This process of Risk Identication results in creation
with additional risks for the project. of Risk Register.

RISK REGISTER
A Risk Register is a living document that is updated
regularly throughout the life cycle of the project. It

102
becomes a part of project documents and is included using a Low, Medium and High scale and the others
in the historical records that are used for future rate on a scale of 1 to 10. Likewise, the impact of
projects. each risk is also rated using an appropriate scale.
Some of the tools that can be used for qualitative
risk analysis include:

PROBABILITY AND IMPACT MATRIX


The matrix helps in identifying those risks which
require an immediate response. The matrix may be
customized according to the needs of the project.
Most companies do have a standardized template
Risk Register for this matrix and project managers could leverage
those templates as well. Use of standardized matrix
makes the matrix list more repeatable between
The risk register includes: projects.
List of Risks
List of Potential Responses
Root Causes of Risks
Updated Risk Categories

PERFORM QUALITATIVE RISK ANALYSIS


Qualitative risk analysis is a subjective analysis of the
identied risks. In this process of Perform Qualitative
Risk Analysis, a list of risks is identied by analyzing
the process for possibilities of risk that may occur Probability and Impact Matrix
during the project phases. The probability of each
risk is identied. Some project managers prefer

103
RISK DATA QUALITY ASSESSMENT RISK REGISTER UPDATES
Data is collated for the identied risks. The project Risk register is updated with:
manager tries to nd the precision of the data that Risk ranking for the project compared to other
must be analyzed for completing the qualitative projects
analysis of risks. List of prioritized risks and their probability
and impact ratings
For each risk, in Risk Data Quality Assessment, the Risks grouped by categories
project manager needs to determine: List of risks for additional analysis and
Extent of the understanding of the risk response
Data available List of risks requiring additional analysis in the
Quality and reliability of the data near term
Integrity of the data Watch-list (non-critical risks)
Trends
RISK CATEGORIZATION
Risk categorization means adding a category name PERFORM QUANTITATIVE RISK ANALYSIS
to each risk or creating groups of identied risks. It The next step of Qualitative risk analysis is to analyze
helps in clear identication of the category of work the probability and impact of risks in Perform
packages, processes, people or other potential Quantitative Risk. The purpose of Quantitative Risk
causes having most risks. Analysis is:
Identication of risk response that requires
RISK URGENCY ASSESSMENT urgent attention
A project managers should not only identify risks Identify the exposure of risk on the project
and determine responses to these risks, but also Identify the impact of risk on the objective of
identify which of these risks require urgent attention. the project
Some project managers may look at the urgency of Determine cost and schedule reserves that
the risk and the probability / impact rating of the could be required if risk occurs
project risks. Identify risks requiring more attention

104
A few actions are a part of Quantitative risk analysis. Determines the probability of completing the
They include: project on any specic day, or for any specic
cost
DETERMINING QUANTITATIVE PROBABILITY AND Determines the probability of any activity
IMPACT actually being on critical path
Some of the techniques of quantitatively determining Path convergence is taken into account
probability and impact of a risk include: Cost and schedule impacts can be assessed
Interviewing Results in a probability distribution
Cost and time estimating
Delphi technique DECISION TREE
Historical Records Decision tree helps analyze many alternatives at one
Expert judgment single point of time. They are models of real
Expected monetary value analysis situation. A decision tree takes into account future
Monte Carlo Analysis events in making the decision today. It helps
Decision tree calculate Expected Monetary Value in more complex
situations. It also involves Mutual Exclusivity.
M O N T E C A R L O A N A L Y S I S ( S I M U L AT I O N Prioritized list of quantied risks
TECHNIQUE) Amount of contingency time and cost reserves
The Monte Carlo analysis simulates the cost or needed
schedule results of the project. The primary inputs Possible realistic and achievable completion
for this analysis are the network diagram and dates and project costs, with condence levels,
estimates to perform the project. versus the time and cost objectives for the
project
A Monte Carlo analysis: The quantied probability of meeting the
Requires a computer based program project objectives
Evaluates the overall risk in the project Trends in quantitative risk analysis

105
PLAN RISK RESPONSES RISK RESPONSE STRATEGIES
The risk response planning involves determining The choices of response strategies for THREATS
ways to reduce or eliminate any threats to the include:
project, and also the opportunities to increase their AVOID; Focus on eliminating the cause and
impact. thus, eliminating the threat.
MITIGATE; there are certain risks that cannot
Project managers should work to eliminate the be eliminated. However, their impact can be
threats before they occur. Similarly, the project reduced. This is termed as mitigation of risks.
managers should work to ensure that opportunities TRANSFER; Transfer the risk to some other
occur. Likewise, the project manager is also party. Insurance purchases, warranties,
responsible to decrease the probability and impact guarantees, etc are examples of risk transfers.
of threats and increase the probability and impact of
opportunities. The choices of response strategies for OPPORTU-
NITIES include:
For the threats that cannot be mitigated, the project EXPLOIT; add work or change the project to
manager needs to have a robust contingency plan make sure the opportunity occurs
and also a response plan if contingencies do not ENHANCE; increase the probability and positive
work. impact of risk events
SHARE; allocate ownership of opportunity to a
It is not required to eliminate all the risks of the third-party
project due to resource and time constraints. A
project manager should review risk throughout the A response strategy for BOTH threats and opportu-
project. Planning for risks is iterative. Qualitative risk, nities:
quantitative risk and risk response planning do not ACCEPT; passive acceptance leaves action to be
end ones you begin work on the project. determined as needed, in case of a risk event.
Active acceptance may involve contingency
plans to be implemented if risk occurs and

106
allocation of time and cost reserves to the PROJECT DOCUMENTS UPDATES
project. A decision to accept risk must be Other documents that the project manager uses for
communicated to stakeholders. the projects also need to be changed/updated.

Whenever the project manager is responding to Residual risks; there are risks that remain after
threats or opportunities: completion of risk response planning. Residual risks
Execution of strategies must be time-bound are those risks that are accepted and contingency
Eort selected must be appropriate to the plans are developed.
severity of the risk
A single response can be an action of multiple Contingency plans; they describe the specic actions
risk events that can be taken if specic opportunity or threats
A strategy can be selected not only by the occur. Risk response owners; Risks can be assigned
project manager, but also by the team, the to individuals who can develop risk responses and
stakeholders and experts also who will implement risk responses if those
opportunities or threats occur.
OUTPUTS OF PLAN RISK RESPONSES
Risk register, project management plans and project Secondary risks; these are those risks which may be
documents need to be updated as outputs of Plan created due to implementation of current risk
Risk Responses. responses.
Risk triggers; the events that trigger the contingency
PROJECT MANAGEMENT PLAN UPDATES response are risk triggers.
Project Management Plan can be updated by new Contracts; the contracts issued to deal with risks
work activities / packages that could be added, should be noted in risk register.
removed, or assigned to dierent resources, thus, Fall back plans; specic actions that are taken if
making planning an iterative process. contingency plans (or risk response plans) are not
eective.

107
Reserves (contingency); reserves are necessary for RISK REASSESSMENTS; The process of periodically
both time and cost risks. reviewing the risk management plan and risk register
and adjust the documentation as required is termed
MONITOR AND CONTROL RISKS as risk reassessment.
The list of actions involved in monitoring and RISK AUDITS; Risk audits helps the project manager
controlling risks are: prove that all the risks are identied, a plan of
Determine the occurrences of risk triggers mitigation for each major risk is available and risk
Identify and monitor residual risks response owners are prepared to take action.
Keep risk identication, analysis and monito- RESERVE ANALYSIS; while the work is being done,
ring an iterative process in the project reserve analysis is simply checking to see how much
Evaluate eectiveness of risk response plan reserve remains and how much might be needed.
Risk status should be collected and communi- STATUS MEETINGS; Risks should be a major point of
cated discussion in all team (project status) meetings.
Monitor risk management procedures CLOSING OF RISKS THAT ARE NO LONGER
Identify if additional risk responses need to be APPLICABLE; it allows the team to focus on
determined managing the risks that are still open.
Recommend corrective actions
Look for unexpected eects or consequences OUTPUTS OF MONITOR AND CONTROL RISKS
Update risk management and risk response The outputs are:
plans Risk register updates
Perform variance and trend analysis Change requests, recommended preventive
Use contingency reserves and adjust for and corrective actions
approved changes Project management plan updates
Project document updates
WORKAROUNDS; these are unplanned responses Organizational process assets updates
developed to deal with the occurrence of
unanticipated events or problems on a project.

108
PROCUREMENT MANAGEMENT action. A project manager is expected to understand
what procurement experts will need from them,
In Procurement Management, the basic knowledge provide the experts with that information, and then
and skills of a project manager should include being work with the procurement department throughout
able to help create, read and manage contracts. the life of the procurements.

AN OVERVIEW OF PROCUREMENT MANAGEMENT Post the decision of procuring goods or services, the
PROCESS procurement manager:
A formal process to obtain goods and services is Facilitate to create a Procurement Manage-
known as Procurement. Procurement Management ment Plan
Plan, Procurement Statement of Work (SOW), Create Procurement Statement of Work (SOW)
procurement documents, change requests, Determine type of contract
additional procurement documentation and lessons Determine procurement document: Request
learned are the outputs of a Procurement for Proposal (RFP), Invitation for Bid (IFB),
Management Process. Request for Quotation (RFQ)
Send the documents to the seller
Procurement department is the most common name Seller Reviews the documents, seeks additional
for the department that handles and controls information (if needed), sends required
procurements. In some companies, these depart- documents
ments are also called contracting, purchasing or legal Negotiations take place with the seller and
departments. A few skills required for managing contract is signed with right seller
procurements include possessing legal knowledge, Procurement administration is the next step
negotiation skills and understanding procurement Monitoring and Control of Procurement
process. administration is done
Procurement closure involves procurement
In case of a project requiring to buy goods or audit and lessons learned
services, the procurement department comes into Final Payment is made

109
BUYERS AND SELLERS Identify risks and create appropriate risk
Sellers are also called as contractor, sub-contractor, response plans for risk mitigation.
designer, vendor, etc. Project manager should tailor the contract to
the unique needs of the project.
IMPORTANT POINTS RELATED TO PROCUREMENT Project manager should be involved during
MANAGEMENT contract negotiations to maintain the relation-
Contracts cannot be informal. It requires ship with the seller.
formality. Project manager should protect the integrity of
All project management requirements should the contract.
be specically stated in the contract. Project manager should ensure all work such
A Change Management Procedure is the only as reporting, inspections and legal deliverables
way to include any activity in the contract, if are met. Release of liens and ownership of
that activity is not already in the contract. materials is another critical activity of the
Contracts are legally binding, the seller has no project manager.
choice but to perform as agreed in the Project Manager works with the procurement
contract. manager to manage changes to the contract.
Contracts help mitigate project risks.
Most governments back all contracts that fall CENTRALIZED / DECENTRALIZED CONTRACTS
within their jurisdiction by providing a court In a centralized contracting environment, there
system for dispute resolution. is one procurement department, and a
procurement manager handles multiple
THE PROJECT MANAGERS ROLE IN PROCUREMENT procurements for dierent projects.
A project manager should be able to read and In a decentralized contracting environment, a
understand the contracts. procurement manager is assigned to one
A project manager should ensure that scope of project full-time and reports directly to the
work and project management requirements project manager.
should be included in the contract.

110
PROCUREMENT MANAGEMENT PROCESS the project members understand the need of
The procurement process is designed to obtain a procurement.
seller at most reasonable prices. The process Risk Register; an understanding of risks
involves waiting time for the sellers to look at the uncovered to date is termed as risk register.
needs of the project and to respond. The process can Any procurement already in place for the
thus, take from one month to three months for this project; the project manager must manage
type of procurement. interface between multiple sellers and multiple
procurements on one project.
The project manager needs to be involved in the Identication of resources not available within
entire process of procurement management and he the performing organization; One of the critical
also needs to plan for the amount of time aspects is to determine if services need to be
procurements take. procured. This steps allows us to think about it.
The project schedule; the project schedule
The four sequential procurement management helps determine when the procurements are
processes are: needed.
1 Plan Procurements Initial cost estimates for work to be procured;
2 Conduct Procurements an initial cost estimate is required for each
3 Administer Procurements work that is getting procured to compare
4 Close Procurements between the sellers prices.
Cost baseline for the project; knowing the cost
INPUTS TO PROCUREMENT MANAGEMENT baseline helps to make sure the procurement
PROCESS ts within baseline costs.
Procurement Manager Assigned; If the amount
of procurement is high, a procurement PLAN PROCUREMENTS
manager needs to be assigned for the process. The buyer has needs and he has criteria using which
The Scope Baseline (WBS, WBS dictionary, he will select a seller. The plan procurements process
project scope statement); it helps in making involves creating procurement documents which

111
describes these details. Additionally, this process also PROCUREMENT MANAGEMENT PLAN
explains the procurement management plan. The This process involves the planning, execution and
Plan Procurements process includes: controlling of Procurement Management. It is done
Perform make-or-buy analysis after the organization has made a decision to
Create procurement management process procure the services or products from outside
Create a procurement statement of work for sources.
each procurement
Select a contract type for each procurement PROCUREMENT STATEMENT OF WORK
Create the procurement documents The work to be done on each procurement is called
Determine the source selection criteria procurement statement of work. The procurement
statement of work must be clear, complete and as
MAKE OR BUY ANALYSIS concise as possible. It should also describe all work
The organization has several constraints including and activities the seller is required to complete. The
one constraint, cost. The organization needs to activities also include meetings, reports and
decide about whether to do project work themselves communications.
or procure services for some or all the work.
TYPES OF PROCUREMENT STATEMENTS OF WORK
One of the main reasons to buy is to decrease the Procurement; this conveys what the nal
project constraints. However, organizations should product should be able to accomplish.
make if: Functional; this conveys the end purpose or
The organization has an idle plant or workforce the results than the specic procedures or
Work involves proprietary information or approach
procedures Design; this type conveys precisely what work
The organization wants to retain control is to be done.

Design procurements statement of work is most


commonly used in construction and equipment

112
purchasing. Performance and functional procure- additional costs if the costs are more than agreed
ments statement of work is used in areas that have upon costs. The buyer has the least cost risk in this
never been done before such as Information type of contract. The seller is duly concerned with
systems, information technology, research and the specications provided in the procurement
development, etc. Statement of Work (SOW).

CONTRACT TYPES A xed price contract is inappropriate when either of


The project manager selects the type of contract the parties (buyer or the seller) do not have expertise
basis the purchase of a product or a service, the or past experience to prepare the procurement
completeness of the statement of work, the level of statement of work or have detailed accounting
eort and expertise the buyer can devote to the records.
seller, whether incentives are involved for the seller,
the enterprise environmental factors, etc. There are situations where companies are not having
a complete know-how of the tasks to be done and
The three broad categories of contracts are: even when the scope is incomplete, they ask the
Fixed price (FP) sellers to provide a xed price. This leads to:
Time and Material (T&M) Forcing the seller to accept high level of risk.
Cost Reimbursable (CR) Seller needs to add huge amount of reserves
to cover their risks and the buyer then pays
FIXED PRICE (FP, or LUMP SUM, or FIRM FIXED more than otherwise required.
PRICE) Smart sellers can easily increase prots by
The acquiring of goods or services with well-dened cutting the scope of work and claim that work
specications or requirements and when there is the buyer wants requires change as it is
enough competition to determine a fair and outside the contract.
reasonable xed price, these are the situations
where a xed price contract is used. These are the In case if the seller realizes that he is not making any
most common types of contracts. The seller bears prots there is a risk that the seller might try to

113
remove some work that is described in the contract, costs of supplies and equipment that the seller might
take actions to save money, decrease quality, take be required to provide under contract might not be
the best people out of the project, among others. predictable.

FIXED PRICE INCENTIVE FEE (FPIF) PURCHASE ORDER


In an FPIF contract, prots are adjusted based on the The simplest type of xed price contract is a
seller meeting performance criteria in a progressive purchase order. This type of contract is signed by
manner such as completing the work in a cheaper one party instead of two parties i.e. it is unilateral
way, faster and better. FPIF contract involves instead of bilateral.
successive targets given to the sellers, in which the
target for the incentive is changed after the rst TIME AND MATERIAL (T&M) OR UNIT PRICE
target is reached. In this type of contracts, the buyer pays on a per-
hour basis or per-item basis. Time and material
FIXED PRICE AWARD FEE (FPAF) contracts are frequently used for service eorts in
In a FPAF contract, the buyer pays a xed price plus which the level of eort cannot be determined when
an award amount (a bonus) based on performance. the contract is awarded.
This is very similar to an FPIF contract, except the
total possible award amount is determined in COST REIMBURSABLE (CR)
advance and apportioned out based on perfor- A cost reimbursable contract is used when the exact
mance. scope of work is uncertain and, therefore, costs
cannot be estimated accurately enough to eectively
FIXED PRICE ECONOMIC PRICE ADJUSTMENT use a xed price contract. This type of contract
(FPEPA) provides for the buyer to pay the seller allowable
If there are uncertainties about future economic incurred costs to the extent prescribed in the
conditions (future prices) for contracts that exist for a contract. Following are common forms of cost
multi-year period, a buyer might choose a xed price reimbursable contracts:
contract with economic price adjustments. Future

114
COST CONTRACT COST PLUS AWARD FEE (CPAF)
A cost contract is the one in which the seller receives In a cost plus award fee contract, the buyer pays all
no fee (prot). costs and a base fee plus an award amount (a bonus)
based on performance. This is similar to CPIF
COST PLUS FEE (CPF) OR COST PLUS PERCENTAGE contract, except the incentive is a potential award,
OF COST (CPPC) rather than a potential award or a penalty. The
A CPF or CPPF contract requires the buyer to pay for award amount in CPAF contract is determined in
all costs plus a percentage of costs for a fee. advance and apportioned out depending on
performance. This is a type of incentive contract.
COST PLUS FIXED FEE (CPFF)
A cost plus xed fee contract provides for payment INCENTIVES
to the seller of actual costs plus a negotiated fee that Incentives are bonus for the sellers. Incentives are
is xed before the work begins. The fee does not designed to motivate the sellers eorts towards
vary with actual costs. things that might have not been emphasized
otherwise and to discourage seller ineciencies and
COST PLUS INCENTIVE FEE (CPIF) waste in the areas in which the incentives are
A cost plus incentive fee provides for the seller to be designated.
paid for actual costs plus a fee that will be adjusted
based on whether the specic performance WHEN ARE PAYMENTS MADE?
objectives stated in the contract are met. In this type Each contract will state when payments are to be
of contract, an original estimate of the total cost is made to the seller. Payments may be made as work
made (the target cost) and a fee for the work is is completed, as costs are incurred, according to a
determined (the target fee). The seller then gets a payment schedule, or only after the successful
percentage of the savings if the actual costs are less completion of the contract.
than the target costs or shares the cost overruns
with the buyer.

115
OTHER TERMS TO KNOW PROCUREMENT DOCUMENTS (BID DOCUMENTS)
Prots and costs have a distinct dierence. Prot is Once the contract type is selected and the
the amount of money the sellers has left after costs procurement statement of work has been created,
are paid. There are some terms that we would like to the buyer can put together the procurement
know: document, which describes the buyers needs to the
Price; the amount the seller charges the buyer. sellers. The dierent types of procurement docu-
Prot (fee); this is planned into the price the ments include:
seller provides the buyer. Request for proposal (RFP); RFPs request a
Cost; A buyers cost include a sellers cost plus detailed proposal on how the work will be
prot. For a seller, this is the amount charged accomplished, who will do it, etc.
to the seller to create, develop or purchase the Invitation for Bid (IFB); IFB usually just requests
product/service/raw materials. the total price to do all work.
Target price; this term is often used to Request for Quotation (RFQ); RFQs request a
compare the nal price with what was price quote per item, hour, meter, or other unit
expected. of measure.
Sharing ratio; incentives are usually expressed
as a ratio, e.g. 90/10. This sharing ratio The objective is to provide the seller a clear picture
describes how cost savings or cost overruns as much as possible. The procurement documents
will be shared between the buyer and the should include:
seller. Information for sellers: Background informa-
Ceiling price; the highest price the buyer will tion about the purpose of the buyer wanting to
pay is the ceiling price. get the work done, Procedure for trying to win
Point of Total Assumption (PTA); This only the work, Guidelines for preparing the
refers to xed price incentive fee contracts and response, The formats for responses, Source
refers to the amount above which the seller selection criteria the criteria the buyer will
bears all the loss of a cost overrun. use to evaluate responses from the sellers and
Pricing forms

116
Procurement statement of work condential and control, and who in the organization
Proposed terms and conditions of the contract will gain access to the condential information.
(legal and business)
Teaming Agreement (Joint Venture); often two sellers
SOURCE SELECTION CRITERIA believe that their chance of winning work from a
Source selection criteria are included in the buyer will be enhanced if they join forces for one
procurement documents to give the seller an procurement. In this case, they will sign a teaming
understanding of the buyers needs and to help the agreement with each other to address the legal and
seller decide whether to bid or make a proposal on business aspects of the arrangement.
the work. Source selection criteria become a basis
for the buyer to use in evaluating bids or proposals. Standard Contract; the contract terms and conditions
are most commonly created by the buyer, who may
The source selection criteria include: even put their terms and conditions into the
Number of years in business standard format that is used over and over for
Financial stability similar procurements. These types of standard
Understanding the need contracts need no further legal review if used as they
Price or life cycle cost are.
Technical ability
Quality of past performance Special Provisions (Special Conditions); The project
Ability to complete the work on-time manager must be able to read and understand
Project management ability standard terms and conditions and to determine
what needs to be added, changed, or removed from
The following are additional terms, the project the standard provisions. By doing so, the project
manager must be familiar with: manager can make sure the resulting contract
Nondisclosure Agreement; this is an agreement addresses the particular needs of the customer.
between the buyer and prospective sellers identify-
ing the information or documents they will hold

117
TERMS AND CONDITIONS Dispute resolution; the procedure that will be
The general categories of the terms and conditions used to settle any disputes, if they occur.
that can make up standard and special provisions Force majeure; this is a situation that can be
are: considered as act of God, such as re or freak
Acceptance; description to specically describe electrical storm. If a force majeure occurs it is
what is acceptable considered to be neither partys fault.
Agent; the name of authorized representative Incentives; the benets the seller receives for
from each party aligning with buyers objectives of time, cost,
Arbitration; this method uses private third quality, risks and performance.
parties to render a decision on the dispute. Indemnication (liability); identication of
Arbitration is paid for by the parties and is individuals liable for personal injury, damage
used because it is usually faster and cheaper or accidents.
than the courts. Independent contractor; this indicates the
Assignment; the circumstances under which seller is not an employee of the buyer.
one party can assign its rights or obligations Inspection; audit process done during
under the contract to another. execution of the project.
Authority; the names of individuals and their Intellectual property; patents, trademarks,
roles during project life cycle copyrights, books, etc.
Bonds; these are payments or performance Invoicing; which are the invoices, to whom they
bonds, if any, that must be purchased. are sent and what documents are required.
Breach Default; this occurs when obligation of Liquidated damages; estimated damages for
a contract is not met. specic defaults mentioned beforehand.
Changes; involves incorporation of change Management requirements; attendance,
management procedure. meetings, approval of sta assigned to the
Condentiality; information classication that project, etc.
decides which information is to be given to
which parties.

118
Material breach; this breach is so large that it Termination; stopping the work before its
may not be possible to complete the work completed.
under the contract. Time is of essence; this indicates deliverables
Notice; the place or individual to whom the are strictly binding.
correspondence is to be sent. Waivers; statements saying that rights under
Ownership; owner of tangible items (materials, contract may not be waived or modied other
buildings, equipment, etc) used in connection than by express agreement of the parties.
with or developed as a part of the contract. Warranties; promises of quality of the goods or
Payments; schedule of payments to be made, services delivered under the contract, usually
provision of late payment charges, reasons for restricted to a certain time period.
non-payments, etc. Work for hire; work provided under the
Procurement statement of work; if it is not a contract will be owned by the buyer.
separate document, it is included as a part of
the document. LETTER OF INTENT
Reporting; the reports, formats, frequency, A letter of intent is simply a letter without legal
stakeholders, are listed. binding, which indicates that the buyer intends to
Retainage; the amount of money, usually 5% to hire the seller. It gives the seller the condence that
10% withheld from each payment. This money the contract will be signed soon.
is paid when all the nal work is completed. It
helps ensure completion. PRIVITY
Risk of loss; this allocates the risk between Privity is a contractual relationship.
parties to a contract in the event goods or
services are lost or destroyed during the NONCOMPETITIVE FORMS OF PROCUREMENT
performance of a contract. Sometimes, work is awarded to a company without
Site access; requirements to access the site competition. The situations include:
where work is to be performed. Project manager is under extreme pressure
Seller has unique qualications

119
There is only one seller who can provide goods QUALIFIED SELLER LIST
and services If a buyer purchases the same type of services often,
Seller holds patent for the items you need the procurement team should nd, investigate, and
Other mechanisms exist to ensure sellers check the credentials of prospective sellers in
prices are reasonable advance.

Non-competitive procurements may include: BIDDER CONFERENCES


Single Source; a contact is established directly The bidder conference is an opportunity for the
with a preferred seller without going through buyer to discover anything missing in the
the procurement process. procurement documents. A bidder conference can
Sole Source; in this type of procurement, there be key to making sure the pricing in the sellers
is only one source. response matches the work that needs to be
completed and is, therefore, the lowest price.
CONDUCT PROCUREMENTS
Conduct procurements process involves getting the SELLER PROPOSAL
procurement documents to the sellers, answering A seller proposal is a response to the RFP (Request
sellers queries, having them prepare responses, For Proposal), RFQ (Request For Quotation) or an IFB
reviewing the responses to select the seller. To (Invitation For Bid).
initiate the process, it is important to attract the
sellers, it is done using various methods, such as: PROPOSAL REVIEW
After receiving the proposal, the buyer uses the
ADVERTISING source selection criteria identied in the Plan
An advertisement is placed in newspapers, Procurement process to assess the potential sellers
magazines, internet, etc to attract sellers. ability and willingness to provide requested products
or services.

120
The seller proposals are usually reviewed, compared, PRESENTATIONS
or selected by the evaluation committee using one or Some sellers may be asked to make presentations of
a combination of the formal, structured processes. their proposals to the buyer so the buyer can select
the most appropriate seller.
WEIGHTING SYSTEM
This allows the buyers evaluation committee to NEGOTIATIONS
select a seller by weighting the source selection The objective of negotiations is to obtain a fair and
criteria according to the evaluation criteria. reasonable price and develop a good relationship
with the seller.
INDEPENDENT ESTIMATES
The buyer may compare the sellers proposed cost Some of the negotiation tactics are:
with an estimated created in-house or with outside Attacks; If your organization cannot provide
assistance. the right details for the bid, perhaps it should
have not sent a response to our RFP!
SCREENING SYSTEMS Personal insults; If you cannot perform even
A screening system eliminates sellers who do not after 10 months of being in the organization,
meet the minimum requirements of the source you should leave!
selection criteria. Good guy/bad guy; one person is helpful to the
other side, while the other is dicult to deal
PAST PERFORMANCE HISTORY with.
The buyer may consider their past history with the Deadline; We need the closure of this task by
prospective sellers in determining which seller to 4:30 pm today.
award the procurement to. Lying; Lying may be hidden. It may also be
obvious.
Limited authority; limited authority statements
may or may not be true.

121
Missing man; act as if the decision maker is not
available and the current options are better. For a legal contract, we should have an oer,
Fair and reasonable; being impartial and acceptance of that oer, consideration, legal capacity
practical and legal purpose.
Delay; delay the point, discussion or decision
to a later date. ADMINISTER PROCUREMENTS
Extreme demands; these demands are not Managing the relationship between the buyer and
appropriate for the given contract. the seller and assuring both parties perform as
Withdrawal; lessening of interest shown by required by the contract is termed as Administer
emotional or physical withdrawal. procurements.
Fait accompli; this is a done deal.
The specic actions involved while Administering
Scope, schedule and price are the main items to Procurements are reviewing invoices, completing
negotiate in the contract. Other than these, other integrated change control, documenting every
items include responsibility, authority, applicable law, record, managing changes, authorizing payments to
project management process, payment schedule, the seller, interpreting what is and what is not in the
among others. contract, resolving disputes, procurement perfor-
mance reviews, performance reports, monitor cost,
CONTRACT schedule and technical performance against the
The contract denes the roles and responsibilities, contract, understanding the legal implications of the
make things legally binding and mitigate risks. A contract, controlling quality, among others.
contract is the entire agreement between both
parties. It also includes terms regarding payments, CONFLICT
reporting requirements, marketing literature, In the event of a conict, the procurement manager
proposal, and procurement statement of work, or a contract administrator is the one with authority
among others. Changes to the contract are made to change the contract. The project manager may
formally in writing.

122
initiate the change by requesting one, however, it CONTRACT INTERPRETATION
needs the approval for the procurement manager. Contract interpretation is important and may require
a lawyers assistance to understand it and interpret it
CONTRACT CHANGE CONTROL SYSTEM appropriately.
The system includes change procedures, forms,
dispute resolution processes, and tracking systems TERMINATION
as specied in the contract. Termination can be done for cause or convenience.
The contract should have provisions for termina-
PROCUREMENT PERFORMANCE REVIEWS tions.
During the Administer Procurements process, the
buyers project manager analyzes all available data to CLOSE PROCUREMENTS
verify that the seller is performing as they should. Procurements are closed when a contract is
completed OR when a contract is terminated before
CLAIMS ADMINISTRATION the work is completed. The Close Procurements is a
A claim is an assertion that the buyer did something part of Closing Process Group. All procurements
that has hurt the seller and the seller is asking for must be closed out, no matter the circumstances
compensation. The best way to settle them is under which they stop, are terminated, or are
through negotiation or through the use of the completed.
dispute resolution process.
Work that must be performed during Close
RECORDS MANAGEMENT SYSTEM Procurement phase:
Record-keep is of critical importance if actions taken Product verication; involves checking to see if
or situations that occurred during the procurement all the work is done correctly and satisfactorily.
are ever in question after the work is completed. A Negotiated settlement; nal settlement of all
record management system can be quite extensive claims, invoices and other issues.
and can include indexing systems, archiving systems, Financial closure; involves making nal
and information retrieval systems. payments and completing cost records.

123
Procurement audit; structured review of only
the procurements process.
Updates to records; making sure all of the
records of the project are complete and are
accessible in the records management system.
Final contract performance reporting; this is
creating a nal report.
Lessons learned; lessons learned from
everyone including the seller are documented
for the project.
Procurement le; the le includes contract,
changes, submittals from the seller, nancial
information, inspection results, lessons learnt.

FORMAL ACCEPTANCE AND CLOSURE


Once closure is completed and the seller has
received formal sign-o that the products of the
procurement are acceptable from the buyer, the
procurement is closed.

124
STAKEHOLDER MANAGEMENT identify the appropriate focus of each stakeholder as
an outcome of Identify Stakeholders process.

Stakeholders are individuals who get impacted by Stakeholders can include the customers, sponsors,
the project. Project Stakeholder Management employees, management, government and society as
involves identication of stakeholders, analysis of well. These stakeholders have a potential to exert
their expectations and inuences, development of positive or negative inuence on the project
appropriate strategies to work with the stakeholders deliverables.
and executing the process. Frequent communication
is required with the stakeholders. Needs and Stakeholder needs are to be identied at an early
expectations of the stakeholders require to be stage of the project to ensure all of their require-
understood. Most of the issues are due to lack of ments and voices are considered. The stakeholders
communication. Addressing those issues are also can be classied on the basis of their interest in the
important. Managing conicting interest and project, the level of inuence on the project outcome
involving stakeholders in key project decisions and and their involvement. For the success of the project,
activities is also crucial. All of this forms a part of the project manager needs to have a relationship
stakeholder management process. that is cordial and extremely success oriented.

Project manager is expected to possess the ability to Identify Stakeholders Process can receive inputs
identify the needs and inuences of the stakeholders from:
and to manage them eectively. Project Charter; Internal and external parties
related to the project are identied using the
IDENTIFY STAKEHOLDERS project charter.
The process of identifying individuals who are Procurement Documents; the parties involved
impacted by the project is known as Identify in a procurement contract are key project
Stakeholders Process. The project manager is able to stakeholders.

125
STAKEHOLDER ANALYSIS Classify the stakeholders basis logical catego-
Qualitative and quantitative analysis is required to ries of potential impact
systematically determine the interest of stakeholders Determine the likely reaction of these stakehol-
throughout the project. The benets of this analysis ders to respond in various situations
are identication of stakeholder interests, expecta- Plan the approach strategy to enhance their
tions, and inuences. Another benet includes positive support and reduce negative inuen-
identication of stakeholder relationships that can ces
be leveraged to build partnerships with stakeholders
to increase the probability of project success. Multiple classication models are used for
stakeholder analysis, including but not limited to:
Power/Interest grid; bifurcation of stakeholders
basis their level of authority and their level of
concern regarding project outcomes
Power/Inuence grid; bifurcation of stakehol-
ders basis their level of authority and their
level of involvement in the project
Power/Impact grid; bifurcation of stakeholders
basis their level of authority and their level of
impacting changes on project activities
Stakeholder Analysis Diagram
Salience model; describes categories of
stakeholders basis their power, urgency and
legitimacy
Steps involved in stakeholder analysis process are:
Identication of potential stakeholders inclu-
ding their roles, departments, interests,
knowledge, expectations, and inuence levels.
Identify and analyze potential impact each
stakeholder could generate

126
S t a ke h o l d e r i n f o r m a t i o n ; t h e i r n a m e ,
organizational position, location, role in the
project, business phone number, email
address, etc.
Stakeholder requirements; key expectations,
major requirements, involvement in the
project, etc is included here.
Stakeholder classication; a stakeholder could
be internal or external. A stakeholder can also
be supporter, resistor, neutral, etc.
Updating the stakeholder register is an iterative
process and should be updated regularly.

Stakeholder Interest Diagram PLAN STAKEHOLDER MANAGEMENT


Plan Stakeholder Management process involves
managing stakeholder expectations and inuences
BRAINSTORMING throughout the lifecycle of the project. This process
Brainstorming technique can be used to identify provides a plan to eectively interact with
stakeholders who belong to senior management, stakeholders and support projects interest. Project
other departments of the organization, lessons managers goal is to plan these actions so well that
learned, project managers who have worked on they impact the contribution of stakeholders on
similar projects, subject matter experts, consultants, projects, manage their expectations and also achieve
regulatory bodies, etc. project objectives.

OUTPUTS OF IDENTIFY STAKEHOLDERS INPUTS FOR PLAN STAKEHOLDER MANAGEMENT


Stakeholder register is updated with details such as: The inputs required to plan stakeholder manage-
ment include:

127
Project Management Plan; description of Engagement level of stakeholders can be classied
processes that will be applied to each stage of as:
the project, description of how work will be Unaware; stakeholders may be unaware of the
executed, planning and execution of human projects impact or its potential.
resources, change management procedure, Resistant; many stakeholders are generally
communications management plan are resistant to any changes to the project.
required for planning for stakeholder manage- Neutral; they will let things happen, they will
ment. not resist nor support.
Stakeholder Register; it provides the descrip- Supportive; these individuals are supportive to
tion of the interest, involvement and level of change, they are completely aware of the
authority of dierent stakeholders. potential of the project.
Enterprise Environmental Factors; organizati- Leading; these stakeholders will not just
onal culture, structure, political climate are support but wherever required will also lead
critical to manage stakeholders expectations. the project to success.
Organizational Process Assets; lessons learned
from previous projects and historical informa- A Stakeholder Engagement Assessment Matrix can
tion of the organization helps in understanding be used to identify the engagement levels of
the behavior of stakeholders and thus planning stakeholders. Here, C indicates current engagement
the actions eectively. and D indicates the desired level of engagement.

ANALYTICAL TECHNIQUES
The project manager needs to use his expert
judgment to decide the level of engagement at each
stage of the project from each stakeholder. Meetings
Stakeholder Engagement Assessment Matrix
and discussions can be held to discuss the
engagement level of stakeholders. There are
additional analytical techniques that could be used.

128
OUTPUTS OF PLAN STAKEHOLDER MANAGEMENT lifecycle of the project is termed as Management
One of the several outputs of Plan Stakeholder Stakeholder Engagement process.
Management is the Stakeholder Management Plan. It
is a component of the project management plan. The Activities involved in Manage Stakeholder Engage-
plan articulates management strategies to engage ment process are:
stakeholders for the project. Unlike procurement Ensure continued commitment of stakeholders
management, the stakeholder management plan can at all stages of the project.
be formal or informal, it can be detailed to the Ensure stakeholder expectations are met. The
minutest level or it can just be at a high level, it is tools used could be negotiations and commu-
based on the needs of the project. nication.
Anticipate future problems and address
When updating the stakeholder management plan, potential concerns throughout the lifecycle of
the validity of underlying assumptions be reviewed the project.
to ensure accuracy and relevancy.
Another output of Plan Stakeholder Management are A few critical points of Manage Stakeholder Engage-
the updates to project documents that include ment includes:
project schedule and stakeholder register. Stakeholder inuences are the highest at the
start of the project and as project progresses
MANAGE STAKEHOLDER ENGAGEMENT the inuences continue to reduce.
The key benet of Manage Stakeholder Engagement Project sponsors assistance to be taken by the
process involves seeking extended support from project manager whenever required.
stakeholders for projects success. This process of
communicating and working with stakeholders to I N P U T S F O R M A N A G E S TA K E H O L D E R
meet their needs / expectations, address issues as ENGAGEMENT
they occur, and build appropriate stakeholder Inputs for Manage Stakeholder Engagement include
engagement in project activities throughout the Stakeholder Management Plan, Communications
Management Plan, Change log and Organizational

129
Process Assets. The communications management O U T P U T S O F M A N A G E S TA K E H O L D E R
plan includes a documentation of stakeholders ENGAGEMENT
needs for communication requirements. Every Issue Logs, Change Requests, Project Management
stakeholder needs information for a specic purpose Plan Updates and Project Document Updates are
and thus, the formats, level of detail, content and common outputs. Organizational Process Assets get
language might need some alteration from updated with additional information:
stakeholder to stakeholder. All of this need to be Stakeholder notication; it is important to
taken into consideration as inputs when Managing notify stakeholders about project updates, any
Stakeholder Engagement. issue closures, etc.
Project reports; project reports such as status
Tools and techniques used to Manage Stakeholder dashboards, lessons learned, issue logs, etc are
Engagement include eective communication to be included.
methods such as use of email, meetings, process Project presentations; presentations made
updates through intranet, war rooms, among others. formally or informally also form as outputs of
Project manager uses eective interpersonal skills manage stakeholder engagement
including active listening, building trust, resolving Project records; correspondence, memos,
conict and overcoming resistance to change. meeting minutes, etc are included in records
Feedback from stakeholders;
Like interpersonal skills, the project manager also Lessons learned documentation.
requires Management Skills such as eective
facilitation of consensus towards achieving project CONTROL STAKEHOLDER ENGAGEMENT
objectives, inuencing people to support project, The process of monitoring project stakeholder
negotiate agreements to satisfy project needs and relationships is Control Stakeholder Engagement.
help modify organizational behavior to accept Adjusting strategies and plans for engaging
project outcomes. stakeholders is a part of controlling stakeholder
engagement. Stakeholder engagement should
continuously be monitored.

130
Thank you
I would like to thank you again for taking the time to
read Project Management Revealed. We hope that
you enjoyed reading this book as much as we had
enjoyed while we were writing it. It is our biggest
pleasure if we by any means manage to help you
build a strong Project Management foundation.

We know that it's a very complex, overwhelming


and overcrowded world with all Project Manage-
ment certications out there in the market.

And yet we managed to build our Project Manage-


ment certication programs more concrete,
attractive, helpful, useful and simpler than our
competition did. This is why we believe our valuable
students choose IO4PM over bureaucratic,
complex, expensive and half-baked solutions of our
competitors.

Our one-of-a-kind industry leading registration,


examination and certication process is very simple,
quick and completely online. Click on this link to nd
out all details: Project Management Certication

Jenny Evans, IO4PM