Académique Documents
Professionnel Documents
Culture Documents
PDVSA N TITULO
APROB. Luis Hernndez FECHA ABR.97 APROB. Carlos Corrie FECHA ABR.97
E1994 ESPECIALISTAS
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 1
Men Principal Indice manual Indice norma
Indice
1 INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
2 APPLICATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
3 REFERENCES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
3.1 PDVSA Petrleos de Venezuela . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
3.2 API American Petroleum Institute . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.3 ISA Instrument Society of America . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.4 NFPA National Fire Prtection Association . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.5 ISO International Standards Organization . . . . . . . . . . . . . . . . . . . . . . . . . 4
3.6 IEC International Electrotechnical Commission . . . . . . . . . . . . . . . . . . . . 4
4 DEFINITIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4.1 Class IA Liquids . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
4.2 Liquefied Petroleum Gas (LPG) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.3 Liquefied Natural Gas (LNG) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.4 Natural Gas Liquids (NGL) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.5 Flammable Liquid . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.6 Flash Point . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.7 Probability of Failure on Demand (PFD) . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.8 Valve Type A . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.9 Valve Type B . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.10 Valve Type C . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
4.11 Valve Type D . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
5 BASIC CONCEPTION OF DESIGN . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
6 SAFETY INTERLOCK SYSTEMS (SIS) . . . . . . . . . . . . . . . . . . . . . . . . 6
6.1 Aspects of Safety Interlock Systems Design . . . . . . . . . . . . . . . . . . . . . . . . 6
6.2 Applications . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
7 EMERGENCY ISOLATION SYSTEM . . . . . . . . . . . . . . . . . . . . . . . . . . 22
7.1 Aspects of Emergency Isolation Valve Design . . . . . . . . . . . . . . . . . . . . . . . 23
7.2 Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
8 EMERGENCY DEPRESSURIZATION AND DEINVENTORY SYSTEMS
(EDS) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
8.1 Design Aspects of Emergency Depressurizing . . . . . . . . . . . . . . . . . . . . . . 30
8.2 Design Aspects of Emergency Deinventorying Systems . . . . . . . . . . . . . 32
8.3 Water Displacement Systems . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
9 EMERGENCY VENTING SYSTEMS . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
9.1 Design Aspects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 2
Men Principal Indice manual Indice norma
9.2 Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
10 OVERPRESSURE RELIEF DESIGN . . . . . . . . . . . . . . . . . . . . . . . . . . 39
10.1 Relief Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
10.2 Overpressure Relief Devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
10.3 Miscellaneous Relief Devices . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
11 FLARE SYSTEMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
11.1 Types of Flares . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
12 BLOWDOWN SYSTEMS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
12.1 Aspects of Blowdown Systems Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 50
13 RESPONSIBILITIES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
APPENDIX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
A Reliability Theory . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 52
B Methods for Determining Safety Integrity Level for Safety Interlock Systems . . . . . . . . 53
B.1 Safety Layer Risk Matrix . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
B.2 Consequence Only Method . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
B.3 HAZOP Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
B.4 Fault Tree Approach . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 3
Men Principal Indice manual Indice norma
1 INTRODUCTION
This Standard establishes the minimal design requirements that must be met by
the safety interlock systems, emergency isolation systems, emergency
depressurizing, emergency venting, relief, flare, blowdown systems in equipment
and plants. These requirements guarantee a reasonable protection to personnel
and facilities against the potential risks of fire and/or explosion and hazardous
releases that can result in emergency situations in installations of the Industria
Petrolera y Petroqumica Nacional (IPPN).
The requirements established in official laws, regulations, decrees and Industrial
Standards in effect, will prevail over anything addressed in this Standard, except
when this is more stringent. This Standard is based on the application of the latest
technologies and industry practices established by recognized national and
international organizations and by the IPPNs own experience for preventing and
protecting against fires, explosions, and other hazardous releases.
This Standard is mandatory for all new facilities of IPPN, for major modifications
in existing installations, or when existing installations have risk levels that are not
compatible with the policies and objectives established at IPPN corporate level
regarding flammable and toxic release prevention and mitigation systems.
2 APPLICATIONS
This Standard is applicable to all facilities of the IPPN, located onshore and
offshore.
3 REFERENCES
The last edition of fallowing documents shall be used.
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 4
Men Principal Indice manual Indice norma
4 DEFINITIONS
4.1 Class IA Liquids
Flammable liquids having flash points below 73 F (22,8 C) and having a boiling
point below 100 F (37,8 F).
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 5
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 6
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 7
Men Principal Indice manual Indice norma
SIL PROBABILITY OF SAFETY EXAMPLES OF SYSTEMS THAT TYPICALLY
FAILURE ON AVAILABILITY WILL MEET THE SIL PFDAVG DEFINITION
DEMAND AVERAGE RANGE
RANGE (PFDAVG)*
SIL 1
101 to 102
0.9 to 0.99
Nonredundant design: typically a single sensor,
single logic solver, and a single final control
element. May consist of a simple relay or a
programmable electronic system (PES).
SIL 2 102 to 103 0.99 to 0.999 Partially redundant interlock design (some but
not all interlock system components provided
with backups). Requires more diagnostics and
typically includes redundancy of the logic solver
and sensors, with redundancy of the final control
element as necessary.
SIL 3
103 to 104 0.999 to 0.9999 Total redundancy (each component of the
interlock system installed with at least one
backup). Typically two separate and diverse one
of one voting (1oo1) arrangements, each with
their own sensor, logic solver, and final control
element. The 1oo1 arrangements would be
connected in a one of two (1oo2) voting scheme.
Diverse separation, redundancy, and exhaustive
diagnostic capabilities characterize this system.
* The concept of PFD is discribed in the PDVSA IRS02.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 8
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 9
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 10
Men Principal Indice manual Indice norma
programs, that may result in undue delays to repair SIS failed components and
thus, operate in an unsafe condition without SIS). The justification for installation
of energizedtotrip systems must be documented along with the unique
maintenance requirements for the system.
a. Diagnostics to detect failures in the wiring between the input sensors and
logic solver and between the logic solver and the final control elements. For
example, provision for a pilot current continuously monitored to ensure
circuit continuity, but of low enough magnitude not to affect proper
input/output operation.
The following general requirements apply for all safety interlock systems, and
include excerpts from ISAS84.01:
1. SIS operations should always be automatic, that is, its activation should not
depend on an operator responding to an abnormal condition. Operator
intervention may be part of the overall mitigation plan for a hazardous event,
but should be independent from the SIS.
2. A SIS may have a single safety function or multiple safety functions that have
a common logic solver and/or input and output devices. When multiple
safety functions share common components, the common components
shall satisfy the highest SIL of the shared safety function. Components of the
system that are not common must meet the SIL requirements for the safety
function they address. When multiple SISs are combined in a system where
they share common logic or components, the potential for common cause
faults is increased. Programming, accessibility, maintenance,
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 11
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 12
Men Principal Indice manual Indice norma
8. Any undetected single fault that causes a SIS failure shall result in an
automatic, predetermined, safe failure action; and/or a safe process
condition if the appropriate response action is undertaken.
9. The design shall apply codes and standards for environmental and
hazardous area classification (NFPA 70, National Electrical Code, Article
500).
10. SIS Input/Output power circuits shall be separated from circuits used for any
other purpose except where the sensor or final control element is shared.
11. Manual trips (push bottons, etc.) must be equipped with covers to avoid
accidental trips.
12. Control systems for safety interlock should be designed to be able to be
tested frequently without shut down of the equipment they are protecting.
13. A control valve from the BPCS shall not be used as the only final element
for SIL 3. A safety review shall be required to use a single BPCS control valve
as the only final element for SIL 1 and 2.
14. Safety interlock systems may be activated by signals originating in gas or fire
detection systems, according to PDVSA Standard IRI02 Sistema de
Deteccin de Gases Inflamables/Txicos and PDVSA Standard IRI01
Sistema Automtico de Deteccin y Alarma de Incendio.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 13
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 14
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 15
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 16
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 17
Men Principal Indice manual Indice norma
6.2 Applications
Safety interlock systems are to be installed in the following equipment and
process lines:
6.2.1 Compressors, turbines, motors
a. Compressors of a capacity greater than 150 KW (200 HP) operated from a
control room.
b. Reciprocating and centrifugal compressors; electrical motors; and internal
combustion, steam and gas turbines must have safety devices, shutdown
and alarm systems as indicated in Table 2.
c. Trip of emergency shutdown for compressor stations must be located, as a
minimum, in two locations separated at least 75 meters from each other, to
allow activation of the system if one location is inaccessible. An emergency
shutdown trip device must be located adjacent to the main entrance and the
another one outside the compressor station.
d. The activation of an emergency shutdown must perform the following
actions: trip the machine, close gas inlet and outlet lines, open purge valves,
close fuel feed to motors and turbines or deactivate feed to electrical motors.
The motors on the following equipment are the exception: firewater pumps,
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 18
Men Principal Indice manual Indice norma
cooling water and instrument air compressors and/or compressed air for
respiratory protection equipment, pumps for bearings, and valves and
motors necessary during emergencies as identified by the users
experience.
e. Combustible gas shutoff valves must be designed to fail closed upon loss
of the energy that activates them.
f. Depressurization valves must be designed to fail open upon loss of the
energy that activates them.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 19
Men Principal Indice manual Indice norma
AND COMPRESSORS
EQUIPMENT
COMPRESSORS INTERNAL TURBINES
ELECTRICAL
COMBUSTION
RECIPROC. CENTRIF. GAS VAPOR MOTORS
MOTOR
HIGH OR LOW VOLTAGE IN LINE S
MOTOR OVERLOAD S
HIGH WINDINGS TEMPERATURE A
FLAME FAILURE S
LOSS OF PURGE AIR A
HIGH TEMPERATURE IN CASING A A A
HIGH COOLING WATER TEMP. A
HIGH EXHAUST TEMPERATURE A
HIGH HIGH EXHAUST
A
TEMPERATURE
HIGH BEARING TEMPERATURE
A A A
HIGH COMBUSTION
A
TEMPERATURE
AXIAL DISPLACEMENT
HIGH DISCHARGE TEMPERATURE
S A A
EXCESSIVE VIBRATION A A A A A
OVERSPEED S S S S S
HIGH EXHAUST HEADER
A
PRESSURE
HIGH DISCHARGE PRESSURE A A
LOW DISCHARGE PRESSURE A
LOW LOW DISCHARGE PRESSURE S S
LOW SUCTION PRESSURE A A
LOW LOW SUCTION PRESSURE S S
HIGH LIQUID LEVEL IN SUCTION
A A
SCRUBBER
HIGH HIGH LIQUID LEVEL IN
S S
SUCTION SCRUBBER
HIGH FUEL GAS PRESSURE A
LOW FUEL GAS PRESSURE S
LOW OIL LEVEL (LUBE) A A A A A
HIGH LUBE OIL TEMPERATURE A A A A A
LOW OIL PRESSURE IN SEAL A
LOW LOW OIL PRESSURE IN SEAL S
LOW OIL LEVEL IN SEAL
A
OVERHEAD TANK
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 20
Men Principal Indice manual Indice norma
EQUIPMENT
COMPRESSORS INTERNAL TURBINES
ELECTRICAL
COMBUSTION
MOTORS
RECIPROC. CENTRIF. MOTOR GAS VAPOR
LOW LOW OIL LEVEL IN SEAL
S
OVERHEAD TANK
OVERHEAD TANK
HIGH LEVEL IN SEAL OIL
FAILURE OF STARTING CLUTCH
A
TO ENGAGE OR DISENGAGE
HIGH OIL PRESSURE A
LOW OIL PRESSURE (LUBE) A A A A A
LOW LOW OIL PRESSURE (LUBE) S S S S S
LOW CONTROL OIL PRESSURE A
HIGH OIL FILTER DIFFERENTIAL
A A A A A
PRESSURE
A: Alarm
S: Shutdown
6.2.2 Furnaces and Combustion equipment
a. An emergency isolation valve must be installed in process feed to furnace.
If this valve is manual, it must be located no closer than 15 meters from
furnace. If the valve is required to be installed closer than 15 meters from the
furnace, it must be remotely operated and insulated from heat according to
requirements in PDVSA Standard IRC03 Revestimiento Contra
Incendios.
b. An automatic closure valve with manual resetting must be installed in fuel
feed to furnace. This valve must be activated upon low fuel pressure, low
product flow or high temperature in exit line. In equipment using gas fuel, an
alternative may be to use double blocking and a vent activated by burner
flame detectors.
c. In addition to requirements in b., a process control valve in the fuel feed line
to the furnace must be provided with the capability to close remotely from
the control room. This requirement is applicable when the emergency
isolation valve is an automatic valve, then the same signal that actuates the
automatic valve must activate the control valve, which must provide a tight
seal. (See PDVSA K337)
d. All fuel streams to furnaces, boilers and other combustion equipment
(including pilot gas) must have a manual isolation valve located at least 15
meters from equipment, in an accessible site. This requirement can be
waived if there is a valve in the fuel feed line at the plant battery limits that
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 21
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 22
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 23
Men Principal Indice manual Indice norma
The values (distance/inventory) that appears on this section are given only as
reference. The final installation must be based on the performance of a
quantitative risk analysis according to the PDVSA IRS02.
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 24
Men Principal Indice manual Indice norma
ISOLATION VALVES
VALVE
MANUAL
TYPE
AUTOMATIC
VALVE REQUIREMENTS
OPERATION OPERATION
A B C* D*
Located at vessel nozzle (outside skirt). X
Located at least 7,5 meters horizontally from X X
protected equipment and at least 4,5 meters from
operating floor level.
Without location restriction (see note 1) X
Long stemmed operation from platform or above
the operating floor level (without chain or pulley).
X X
Accessible located at least 7,5 meters X X
horizontally from protected equipment.
Normally limited to 200 mm (8) valves and X
smaller.
Normally used only for 250 mm (10) valves and
larger.
X
Without restrictions on valve size X X
* All isolation valves type C and D must meet the following requirements:
NOTE 1:
It is preferable that the feed cables and signal cabling be buried up to a point immediately below
the remotely operated isolation valve. However, all the system components for operation of
isolation valves type D, installed externally and at 7,5 meters from the protected equipment, must
be able to remain operable for 20 minutes of fire exposure.
The relays for thermal overload should not be installed in electrical motors of emergency shutdown
or safety shutdown valves.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 25
Men Principal Indice manual Indice norma
AUTOMATIC ISOLATION VALVE
REMOTE ACTUATION TYPE OF VALVE
C** D**
Field location
See Notes 1, 2, 3 See Notes 1, 2, 3
Adjacent to valve X
Located at least 7,5 meters horizontally from X
protected equipment and at least 4,5 meters
above operating floor level.
Located at operating floor level and at least X
equipment.
12 meters horizontally from protected
Operation from platform or operating floor
X
level.
Accessibly located at least 7,5 meters X X
horizontally from protected equipment
* * All isolation valves type C and D must meet the following requirements:
NOTE 2:
In addition to the requirements indicated in Table 3, the actuation devices for
emergency operation of the isolation valves type D must meet the following
location requirements:
a. Must be installed in the control room for the following cases: valves on
furnace exit lines, isolation of compressors, steam purge, deinventory of
liquids and closure of critical flows (e.g., pump suction).
b. To isolate other equipment, these devices must be installed in the field. It is
preferable to locate and group near the access ways.
NOTE 3:
In addition to the requirements for the actuation devices and the isolation valves
type D indicated in Note 2, when valves type D are required for the startup of
equipment and testing of valves, they should meet the following requirements:
a. When the main emergency actuation device is located in the control room,
an additional actuation device must be installed adjacent to the remotely
actuated valve.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 26
Men Principal Indice manual Indice norma
b. When the main emergency actuation device is located in the field, there
should not be additional devices unless they are required for operational
reasons.
All the isolation valves type C and D must comply with the following requirements:
a. The valves must be actuated by a pneumatic rotation motor, electrical motor
or a hydraulic or pneumatic piston. Diaphragm operated valves should never
be utilized.
b. If the valves are air actuated, it must be ensured that the air supply is reliable
and the air backup capacity is capable of moving all the valves during two
(2) complete cycles, under fire conditions.
c. If the valves are actuated by an electrical motor, the energy source must
come from the unit emergency circuit and/or the installation. The capacity
of the emergency generator must be verified. Power may also be supplied
from the preferential system, in case there is no emergency circuit available.
d. If the valves are actuated by a hydraulic piston, all necessary arrangements
must be made so that in cases of extreme urgency where there is loss of
electricity, the pressure of the hydraulic oil would be sufficient to actuate at
least the critical valves.
e. The power sources to eliminate the electronic or pneumatic signal
transmission system must be highly reliable. The level of reliability must be
consistent with the specified SIL or equal to the power supply utilized in the
control room.
f. The emergency isolation valves that could be exposed to radiation produced
by a fire must comply with the requirement of the PDVSA IRC03
Revestimiento Contra Incendios.
g. The operational controls must consist of actuation devices to move the
valves to closed or open position, respectively.
h. All the manual operation control must be provided with adequate
mechanical guards to prevent accidental operation.
i. The remotely operated emergency isolation valves that are normally open,
do not require block valves or bypass. The remotely operated emergency
isolation valves that are normally closed, require block valves, installed
upstream of emergency valves so that it can be tested. This requriement
may be changed if deemed unnecessary as the result of a risk analysis.
j. The position of the block valves must be able to be identified by visual
inspection.
k. The device for actuating the automatic isolation valves type D must have
valve position indicator lights.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 27
Men Principal Indice manual Indice norma
7.2 Application
Individual block valves must be used with equipment such as pumps,
compressors, vessels, furnaces, heat exchangers and at plants battery limits, as
a function of the criteria described below.
7.2.1 Pumps
a. Pumps inaccessible in a fire must have isolation valves downstream or
upstream of connected equipment or remotely operated suction valve.
b. Install isolation valve (type B, C or D) in pump suction line, when inventory
in vessel is either:
Liquefied flammable gas over 2.100 gallons
Liquid hydrocarbons at temperature equal or greater than
autoignition its flash point and above 2.100 gallons inventory
Liquid hydrocarbons at 4.000 gallons
c. When there are pump suction lines from more than one vessel, emergency
isolation valves for equipment must be provided. If selection criteria result
in different types for valves indicated in Table 3 and 4, then, it is not required
to duplicate the isolation facilities, but the most demanding isolation
requirement must be applied.
d. If there is a requirement for isolation valve type D in multistage pumps with
parallel discharge headers, these valves must be installed at the suction of
each pump.
7.2.2 Compressors
a. Must install isolation valves at the inlet and outlet of the compressor train
driven by a single motor, turbine or engine greater than 150 KW (200 HP)
which handle flammable gases. See PDVSA K339.
1. solation valves of type B or D must be installed in compressors with
capacities between 150 KW to 750 KW (200 1000 HP).
2. Isolation valves of type D must be installed in compressors with capacities
greater than 750 KW (1.000 HP). However, normal practice is to use type
D valves for all compressors specified in a.1. The isolation valves must be
located at least 7,5 meters from compressor, if piping layout allows it.
b. If compressors are as specified in 7.2.2.a and are multi stage, with normal
capacity greater than 4 m3 (1.000 gallons) of hydrocarbons per stage at
normal levels, the valves must be installed in suction and discharge lines
between stages
c. For compressors, the purge suction and discharge valves must be
interlocked with shutdown of machine, such that upon shutdown of machine,
the purge valve opens and suction and discharge valve close.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 28
Men Principal Indice manual Indice norma
7.2.3 Vessels
Must install isolation valves for vessels with liquid hydrocarbons at a vapor
pressure of 1,05 kg/cm2 (15 psi) at 37,8 C (100 F) with the following conditions:
a. If inventory is between 4 and 40 m3 (1.056 10.560 gallons), calculated at
upper operational limit, include trays and vertical reboilers for the case of
towers (without taking into account the inventory level). Must install isolation
valves type A in each line with a diameter of 50 mm (2) or under that are
connected below the working level.
b. If inventory greater than 40 m3 (10.560 gallons) calculated as specified in
7.2.3.a, must install valve type A in each line connected below the range of
operational level, independent of diameter. These requirement could apply
to small inventories with special factors such as high corrosion rate, high
pressure, cryogenic or toxic materials, if a quantitative risk analysis has
justified it.
High Risk Vessels
High risk vessels are those that have large volumes of liquid hydrocarbons and
unfavorable risk conditions. Large volumes include those greater than 40 m3
(10.560 gallons) of liquid hydrocarbons stored at a temperature above their flash
point, measured from the highest working level. Unfavorable risk conditions
include, but are not limited to, limited access for firefighting, inadequate
separation between equipment and congested piping and equipment
arrangement. In general, the installation of block valves for this type of equipment
must be determined based on a risk analysis that takes into account the indicated
factors. However, isolation valves Type D must be installed in each normally open
line connected below the normal liquid level to allow for rapid isolation of the
vessel inventory in case of fire.
7.2.4 Furnaces
a. Must install block valves type B or D, to close the process flow (flammable
liquids) in the furnace coils, when the exit pressure in the coils exceeds 14,28
kg/cm2 (203 psi). These valves may be operated manually or automatically,
however, the valves for manual operation will be installed in each furnace
stream, at a minimum of 15 meters away from the furnace.
For furnaces with exit coil exit pressures above 71 kg/cm2 (1.015 psi),
isolation valves type D must be installed at the furnace outlet.
b. The installation of emergency isolation valves in the furnaces must be
supported by a risk analysis that covers the following factors: high pressure,
volatile liquids inventory, lack of steam purge systems downstream of the
oven, lack of system for deinventory, and design problems associated with
the safety system to guarantee flow continuity. Additionally, the criteria and
parameters established in Section 5 of this Standard must be considered.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 29
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 30
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 31
Men Principal Indice manual Indice norma
d. Valves type D with actuation from control room and discharge to a safe
location (normally a closed system or flare) must be installed in
depressurizing systems.
When two (2) or more depressurization vents are installed in a process unit,
the type D remotely actuated block valves must actuate separately.
e. For determining depressurizing rate, the following aspects must be
considered:
Flow rate and heat supply to process.
Simultaneous depressurizing through normal process devices or
mechanisms cannot be relied upon.
The need for backflow to prevent the installation of automatic closure
devices such as check valves or control valves of other equipment
connected to a single depressurizing system.
f. Connections for depressurizing should discharge to a pressure relief
manifold or a vapor/liquid separator and ultimately to a flare system. If other
pressure relief devices are connected to the relieving manifold, the back
pressure imposed by the EDS must be considered in sizing the relief header
(see g).
g. The discharge manifold size must be determined assuming a fire in a single
fire zone with all depressurizing and relief valve systems in that zone lifting
simultaneously. This single fire zone must meet all of the following criteria:
Have equipment not provided with depressurization systems
Have equipment connected to same depressurization system
Equipment must discharge to the depressurization system as a result
of fire exposure.
Each fire risk area must be analyzed following the criteria set forth above.
The size of the header will be determined such that during the most critical
situation, the backpressure of all relief devices discharging to the header will
not exceed design limitations on the relief valves. When discharge manifolds
and relief headers are sized, the relief contingency that produces the
greatest backpressure must be identified. Cooling water failure, power
failure, and valve malfunction are examples of typical relief contingencies
that may be considered as they may require the activation of several
pressure relief devices.
h. The vapors from depressurization can be discharged to atmosphere if they
satisfy the criteria applied to atmospheric relief valves, including
environmental regulations, as long as the discharged products will be
vapors under any foreseeable circumstance.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 32
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 33
Men Principal Indice manual Indice norma
The water displacement method has limited application but it may be considered
as an alternative to isolation or deinventory of volatile liquids in high risk areas,
where there are no other alternatives.
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 34
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 35
Men Principal Indice manual Indice norma
9.2 Application
9.2.1 Venting of Tanks and Vessels
a. Fixed Roof Tanks (atmospheric)
Fixed roof tanks must be provided with vents to prevent positive pressures
or vacuum conditions exceeding the design limitations. Pressure variations
can be expected during filling and emptying of the tanks, due to atmospheric
temperature changes, or during fire situations in the area.
All fixed roof tanks must be provided with vacuum breakerpressure relief
valves when they store flammable liquids with flash points within 4 C (72 F)
of the maximum temperature expected at the liquid surface.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 36
Men Principal Indice manual Indice norma
Fixed roof tanks must be provided with additional venting capacity to reduce
the rupture possibility on the seams due to pressure oscillations caused by
vapor or light ends in the tank. The size of the venting must be in accordance
with API RP 2000. In situations where stored materials can generate vapors
in the flammable range, inert gas blanketing must be considered. Designs
for maintaining low flammable concentrations are discussed in NFPA 69,
Explosion Prevention Systems.
b. Low Design Pressure Vessels
Spheres or vessels designed for a maximum pressure of 1 kg/cm2 (14,3 psi)
must be designed in accordance with API 620. The relief valves may
discharge directly to the atmosphere through a vertical vent extending a
minimum of 3 meters above the highest structure of the vessel or platform.
The relief valves may also discharge to a flare system.
c. High Design Pressure Vessels
Spheres and cylindrical vessels must be designed in accordance with the
latest edition of the ASME Boiler and Pressure Vessel Code Section VIII
or other national or internationally recognized codes. When the relief valves
discharge directly to the atmosphere, they must do so through a vertical vent
piping extending a minimum of 3 meters above the highest structure of the
vessel or platform. The relief valve may also discharge to a flare system.
d. LPG Tanks
The discharge coming from the venting of pressure relief valves or from a
common header containing LPG must be routed to atmosphere or to a flare
system. When the discharge is routed to atmosphere, the area must be free
from potential flames that could affect other tanks, piping, equipment, and
structures. Similarly, the entrance of vapors to the LPG tank confined space
must be prevented.
e. Knockout drums
The purpose of a knockout drum is to receive the discharges from the relief
valves of a closed system, drains, or purged and diverted liquid or vapor
streams to be burned and disposed of safely in adequate storage. They are
designed to prevent liquid hydrocarbons from going directly to the flare.
The knockout drum is designed to separate liquids and vapors, but
additional condensation may occur if the vapors vented from the knockout
drum exit at a temperature above the ambient temperature.
Condensable knockout drum
The condensable knockout drum allows reducing the capacity requirements for
the flare and prevention of the discharge of condensable hydrocarbons to the
atmosphere. The condensable hydrocarbons and the water effluents are
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 37
Men Principal Indice manual Indice norma
discharged through a seal system into a contained drain system or slop tank and
the noncondensable light hydrocarbon vapors vent to the flare or atmosphere.
The knockout drum discharges vapors to a vent or flare system, which must
conform to the following conditions:
S The vent pipe must be located at a minimum of 15 meters above ground level
and at a minimum of 3 meters above any equipment that is located at a
horizontal distance of 15 m. Nevertheless, the vent pipe must be located at a
safe place based on the results of a dispertion analysis.
S The radiation intensity shall not exceed the limits for operational personnel
exposure (1500 BTU/hrft2).
S The design must take into consideration the adjacent equipment and work
areas in determining the adequate dispersion of flammable and toxic products.
S The vent must have means for vapor or inert gas injection, or other effective
means to prevent flame flashback and/or to extinguish it.
S The design pressure of the drum must be 10,5 kg/cm2 (1500 psi).
f. Disengaging Drum:
The disengaging drums are utilized to separate liquid hydrocarbons and
gaseous contaminants from the effluent streams in the plants. The object is
to allow safely discharge of effluent streams to the drain system.
The exit vapors for the disengaging drum can discharge to the atmosphere
or to the flare, however, for atmospheric discharge it must be subject to the
following conditions:
The vent pipe shall be located at a safe location based on the results
of dispersion and radiation analysis.
The radiation intensity shall not exceed the limits for operational
personnel exposure (1500 BTU/hft2).
Ground level or work platform level concentrations must not exceed
the threshold limit value (TLV) of any toxic vapor that could be vented.
The vent piping must be vertical and oriented upwards. It must be
provided with steam or inert gas injection for fire protection by
suffocating the fire or by forcing the flame to receed. Steam should not
be used in systems venting cold vapors (< 0C).
g. Waste Drums (Slop Tanks)
The design of plants must include safe elimination of waste products such
as:
Liquid hydrocarbons accumulated in noncondensable knockout
drums, coming from safety valves, closed drains and drains from
separator drums.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 38
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 39
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 40
Men Principal Indice manual Indice norma
bubble occupies volume and displaces the liquid surface upward. Individual
bubbles are able to rise (slip) through the liquid (with a velocity that depends on
the buoyancy and surface tension) but are retarded by viscosity and the foamy
character of the fluid. If a sufficient volume of bubbles become trapped, the liquid
surface reaches the height of the relief device and twophase flow occurs through
the relief device.
Two systems for which twophase relief can occur are:
S Relief due to a runaway reaction (either through vaporization of the material or
generation of noncondensible gases such as CO2 or N2).
S The initial relief due to fire exposure from a vessel with high liquid level (>50%
of total height) will generally be twophase.
If twophase relief is possible, recognized technology for twophase emergency
relief system design shall be used to avoid undersizing a relief device and the
potentially catastrophic vessel overpressurization. The methodology developed
by the Design Institute for Emergency Relief Systems (DIERS) Emergency Relief
Systems Design Using DIERS Technology, a consortium of companies under the
auspices of the American Institute of Chemical Engineers (AIChE), is an important
means for addressing twophase relief situations, not covered adequately by
ASME and API Standards.
In addition to the overpressure concerns associated with undersizing a relief
valve, it should be understood that installing a grossly oversized relief valve may
not make for increased safety as the relief valve may chatter, that is repeatedly
and rapidly open and close, resulting in vibrationinduced leaks or valve
malfunctioning. Hence, it is critical that the system be understood and the relief
valve sized appropriately.
10.1.3 Installation
The installation procedure must fallow ASME Section VIII Division I.
10.1.4 Spare Relief Valves
It is recommended that spare relief valves be provided to allow inservice
maintenance of one of the relief valves by switching rather than shutdown. The
following guidelines shall be used in the design of systems with inservice spares:
a. They should be installed in parallel and isolated by fullport, threeway or
transflow valves at the inlet and outlet (when connected to a header).
b. A bleed valve should be provided between the relief valve and the inlet block
valve.
c. If standard block valves are to be used, key locks must be used to assure
a proper isolation sequence.
d. Upon a release through a relief valve, the performance of the valve that
relieved must be checked while a spare is in use.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 41
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 42
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 43
Men Principal Indice manual Indice norma
S Blowdown (difference between the set pressure and the closing pressure) can
be specified as low as 2% of set pressure.
S A pilot operated relief valve can be specified to have modulating action, that is,
to open only in proportion to the relief requirement. Thus, it reduces the upset
obtained in the process unit and the product lost to the flare whenever a minor
overpressure situation occurs. A modulating pilot operated valve has zero
percent blowdown. It is designed to reclose at its set pressure.
S May cost less than direct spring valves for those larger than 3inch size.
The following are some disadvantages of pilot operated relief valves:
S The valves have more restrictive temperature limits than do springloaded
valves.
S The technology is more complicated and so it takes more knowledge to specify
a pilot operated valve and install it correctly.
S The valve needs design features generally not associated with a springloaded
reliefvalve. There may be a filter in the sensing line if the service is dirty and
a backflow preventer if the valve discharges to a flare header system.
S These valves have more restrictive metallurgy selection.
S They may cost more than direct spring valves for those smaller than 3inch size
S Usually limited to clean services (e.g., not recommended for crude oil service).
10.2.4 Rupture Disks
A rupture disk is a device actuated by inlet static pressure and is designed to
function by the bursting of a pressure retaining disk. A rupture disk assembly
consists of a thin, circular membrane, made of metal, plastic, graphite, or a
combination of materials, that is firmly clamped in a disk holder. It can be installed
alone or in combination with other pressure relief devices. When rupture disk
support plates are required, the reduction in flow area caused by the plate must
be allowed for in the rupture disk size selection.
The following are some advantages of rupture disks:
S They can be installed upstream or downstream of relief valves in highly toxic
or corrosive services, to prevent corrosive or hot fluid or particulates from
contacting the relief valve or seat. Only rupture disks that have a
nonfragmenting design may be used beneath a pressure relief valve. When
used in this manner, a pressure indicator or switch must be provided to sense
pressure between the rupture disk and the relief valve.
S More effective than a relief valve in protecting equipment from sudden
explosions.
S Depending on material of construction, they are more resistant to corrosion or
plugging than other relief devices.
S They have applications in viscous and slurry services.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 44
Men Principal Indice manual Indice norma
S In limited services they are more cost effective than relief valves.
S They rupture only when designated pressure is reached and, therefore, do not
simmer like a relief valve.
The following are some disadvantages of rupture disks:
S When a disk ruptures, the entire contents of the system it is protecting may be
lost (they do not reseat).
S It is difficult to detect if a disk is leaking unless other instruments like pressure
indicators or burst disk indicators, detectors or alarms are installed in the disk
assembly.
S Old disks or those subject to high cycle fatigue may experience premature
failure due to metal fatigue. To minimize this, rupture disk burst pressure should
be set considerably above the full range of operating pressures. They may
require replacement every year depending on plant operating and
maintenance procedures.
S Rupture disks are subject to mishandling. Careful installation is of extreme
importance. The disks are made of thin, fragile metals and any deformation
during assembly may weaken them and result in premature rupture. In
addition, they are often mistakenly installed backwards that is the side that
is designed to burst when it is overpressured is not facing the protected vessel
thus creating a greater hazard by potentially increasing rupture pressure.
S Burst pressures are sensitive to temperature variations.
S Some types require greater operating margins.
Rupture Disks / Relief Valve Assemblies
Rupture disks may be installed upstream of the relief valve to prevent corrosion
of the pressure relief valve if the process fluid is corrosive. The following features
must be included:
a. The relief device capacity must be derated as required by ASME or vendor
data.
b. A pressure monitoring device must be installed between the rupture disk and
the relief valve to ensure that the rupture disk may still burst, even if a pinhole
exists in the disk creating undue backpressure.
A rupture disk may be installed downstream of a relief valve to protect the valve
from atmospheric or downstream fluids or to prevent valuable, noxious, or
flammable materials from leaking through the pressure relief valve to the
atmosphere. If the rupture disk is located after the relief valve, the bleed off device
must be installed between the valve and the rupture disk.
10.2.5 Liquid Seals
Liquid seals are Utube hydraulic loops whose diameter and seal depth are sized
to pass the design relieving rate at the required design pressure.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 45
Men Principal Indice manual Indice norma
11 FLARE SYSTEMS
A flare provides a means for disposing of flammable, toxic or corrosive gaseous
effluents by burning them under controlled conditions and converting them to less
objectionable compounds. A flare must handle materials vented during all
operating conditions, including normal startup, and emergency conditions. The
three most common types of flares are discussed below.
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 46
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 47
Men Principal Indice manual Indice norma
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 48
Men Principal Indice manual Indice norma
Provision must be made for purging of the flare header with fuel gas or an inert
gas to avoid air leaks into the system if the flare gas pressure falls too low and to
prevent flameout due to low gas flow.
A separate flare system for oxygencontaining streams should be used if
necessary to avoid potential for explosions in the main header if flammable
concentrations are possible.
Water seals and flame arresters are used in flare systems to prevent flashback,
and molecular seals are also used to prevent air ingress. Water seal problems
include the creation of an uninterrupted gas passage through the water at high gas
flows, which can render the seal ineffective; the tendency to surge, which can
affect flare operation; and the need to continuously replace the water lost.
Proprietary water seals are available that overcome these difficulties.
The use of flame arrester and molecular seals are discouraged as they have the
serious disadvantage that they tend to plug up, obstructing the flare system.
11.1.5 General Flare Header Design Guidelines
Following are general guidelines for flare header design:
a. Extensive measures should be taken to avoid pockets, (i.e., low points) in
the flare header and associated piping.
b. Piping (discharge piping, subheaders and headers) should be free draining
to the knockout drum.
c. Consider intermediate knockout drums in or near process units if the flare
stack is located in a remote area of the plant.
d. Avoid sectionalizing the flare header to prevent maintenance problems with
valves and possible misoperation or malfunction.
e. Flare headers may collapse if a large volume of liquid is inadvertently
discharged into the header, exceeding the capacity of the piping supports.
To prevent such events, it is advisable to use criteria such as specifying the
pipe as halffull of liquid or otherwise ensure that the header can support the
weight of the liquid, and absorb the impact of any liquid slugs.
f. Flares handling combustible vapors from multiple relief valves must not be
used for venting air or steam during startup or at any time loss of flame is
likely.
g. Flame arresters should not be used in flare systems because they are
subject to plugging and during the cooling that follows a warm discharge, air
may be drawn back into the flare system through the flame arrester. Other
means for flashback prevention are more reliable such as continuous gas
purge.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 49
Men Principal Indice manual Indice norma
Collection Headers
It is desirable to combine effluent disposal systems based on similar pressures,
temperatures, compositions and quantities. The materials of construction of the
flare collection headers, flare stack and tip are determined by the composition of
the flare fluid (especially if corrosive or toxic) and the operating pressure and
temperature of the flare system. Some common headers and typical materials of
construction are:
S Cold flare header austenitic stainless steel is used for ethane and lighter
effluents which flash at 45C (50F).
S Intermediate Flare header low temperature carbon steel is used for cold, dry
effluents at temperatures from 45 to 0C (50 32F).
S Hot Flare Header carbon steel is used for hot, wet effluents above 0C (32
F).
S Sour Gas Header due to the corrosive and toxic nature of sour gas, a stainless
steel separate header and stack dedicated for sour gas is sometimes more
economical than providing a larger stainless steel header to handle a
combination of sour and nonsour streams.
11.1.6 Flare Knockout Drums
Design should conform to recognized codes and standards such as API RP 521.
Other considerations in the design of the knockout drum are:
a. A steam coil, jacket, or other means of heating is sometimes provided in the
drum to prevent high viscosity liquids from becoming too viscous to drain or
be pumped.
b. The drum should be sloped towards the liquid outlet nozzle.
c. Considerations should be given to the reactivity of all chemicals which may
be encountered, especially when external heating is applied.
11.1.7 Flare Seal Drums
The purpose of the seal drum is to prevent air ingress into the flare system, thus
providing flashback protection.
Seal drum design should conform to recognized codes and standards such as API
RP 521. Other considerations in the design of seal drums are:
a. They must be designed for at least 50 psig to withstand internal explosion.
b. The vapor space must be sized to avoid entraining the seal liquid in the flare
gas and to prevent surges of gas flow to the flare.
c. The seal drum capacity should have sufficient capacity to prevent backflow
under any circumstances.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 50
Men Principal Indice manual Indice norma
12 BLOWDOWN SYSTEMS
Blowdown systems are systems designed to safely dispose of condensable
vapors, contaminated aqueous effluents, and various other liquid streams
generated due to plant emergencies.
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 51
Men Principal Indice manual Indice norma
S For toxic, corrosive or pollutant fluids, drain through a closed drain system for
collection and recycle to the plant for recovery or treatment
S For uncontaminated cooling water and steam condensate, drain to a clean
water or oily water sewer.
12.1.2 Disengaging Facilities
Disengaging facilities remove organic vapors or liquids or other contaminants
from utilities such as cooling water or steam. Requirements for the safe design of
disengaging drums have been covered under Subsection 9.2.1
13 RESPONSIBILITIES
The responsibilities to ensure that the requirements set forth in this Standard are
met accordingly rest with the following individuals:
S Design of systems in compliance with these requirements is the responsibility
of the design engineer in charge of the project or sections.
S Review of the process safety of the design is the process safety coordinator.
S Assurance that the review team performs the required reviews is the
responsibility of the process safety coordinator.
S Determination of risk levels of project and conducting appropriate risk analysis
is the responsibility of the risk engineer.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 52
Men Principal Indice manual Indice norma
APPENDIX
A Reliability Theory
There are two concepts that form the basis for reliability analysis: repairability and
mission time.
Regarding interlock repairability, a device is repairable if maintenance can be
performed without hindering the capability of the interlock to work as designed
while the process is operating. A simple (but conservative) assumption is that
none of the components of the interlock system is repairable.
Mission time has to do with how long a device must function before it can be proof
tested and repaired. If the interlock system is not repairable, the only time it can
be safely tested and maintained is during shutdowns of the process system. This
time period between functional tests is the mission time during which the interlock
must be functional.
The reliability of an interlock system is defined as the probability that the interlock
system will function properly during its mission time, and is approximately:
P+
where
P = Probability that the component or system will not function as designed for the
entire mission time.
= Failure rate of a component (normally in failures per hour of service)
= Mission time the period of time that the component or system must operate
before being tested and repaired
If two failures must occur before the interlock system is incapable of operating, the
probability of failure is approximately:
P + 1 2
P + 1 2 2
P + 1 2 3
If the interlock system failure can occur in multiple ways, the probability that the
interlock system will fail during its mission time is
P total + Pi
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 53
Men Principal Indice manual Indice norma
From the previous equations, the following guidelines can be set forth to improve
interlock reliability:
S As the reliability of an interlock depends on two variables, namely
Failure rate of the components used, and
Inspection and proof test frequency,
S Reducing the failure rate of the components or increasing the inspection
frequency of the system will improve the safety performance of an interlock
system. Maintenance is as important as component selection.
S The addition of a redundant interlock component generally improves the safety
of the system. When adding redundant components, the component with the
highest failure rate must be added first.
S Common cause failures can completely negate the apparent improvement of
interlock performance when duplicate components of the same type are
installed to increase redundancy. Examples of common cause faults are listed
below:
Same lot of defective parts,
Same location for primary and backup systems in a fire situation for
example, they both would be damaged,
Common susceptibility to environmental factors such as water, dirt, oil,
temperature, etc.
Same electric power supply for control and interlock systems,
Same operator or maintenance technician involved in several critical steps
of an operation
S To combat the impact of common cause failures it is advisable to use diverse
(different) and redundant components. A disadvantage of redundancy is that
false alarms or trips occur more often. Voting systems are recommended, for
example, three measuring devices are fitted instead of two and two out of three
(2oo3) must indicate the signal of concern before automatic action is taken.
S On highly redundant systems, human errors or inadequate testing equipment
during testing/maintenance provides the opportunity for common cause failure
(tools, procedures, calibration, training, etc.). It is advisable that the test
schedule be staggered so different crews are used, at different times. Proper
testing procedures and equipment for testing is necessary.
S The reasons for installing redundancy should be clearly documented and
explained to avoid a common weakness of a redundant system: neglect in
repairing one redundant component, since there is a second one available.
B Methods for Determining Safety Integrity Level for Safety Interlock Systems
This appendix illustrates four methods for determining, as part of process safety
activities, the Safety Integrity Level for Safety Interlock Systems.
MANUAL DE INGENIERIA DE RIESGOS PDVSA IRP01
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 54
Men Principal Indice manual Indice norma
1 1 1
NA NA 1
NA NA NA
High
2 2 2
Moderate
Consequence Severity
High
3 3 3
2 2 3
Moderate
Effectiveness of
1 1 2 Protection Layers
Low
Low Moderate High Low
Liklihood of Ocurrence
of Initiating Events
PDVSA
REVISION FECHA
SAFETY INTERLOCK SYSTEMS, EMERGENCY
ISOLATION, EMERGENCY DEPRESSURIZATION 2 ABR.97
AND EMERGENCY VENTING SYSTEMS Pgina 55
Men Principal Indice manual Indice norma
that the design selection would be higher than predicted by other SIL selection (as
probability of occurrence is not taken into account and high consequence events
usually are infrequent). Erring on the side of designing a higher than necessary
SIL is a conservative approach. Sometimes it is preferred to save time spent in
risk evaluations and to incur the potential cost penalties imposed by selecting a
higher SIL than might otherwise result. Money spent on equal or better safety
performing SIS is felt to be a good investment on safety.