Académique Documents
Professionnel Documents
Culture Documents
A. Shop Fabrication
1. Layout Cutting M.H./kg. (man hour/kilogram)
a. Built ups 0.0253
b. Shapes (Light) 0.0253
c. Checkered Flooring 0.0253
d. Round Bars 0.0469
e. Purlins 0.0253
f. Shapes (Heavy) 0.0206
g. Misc. Plates 0.0903
h. Open Webs 0.0614
3. Welding
a. Built ups 0.0218
b. Shapes (Light) 0.053
c. Shapes (Heavy) 0.0218
d. Misc. Plates 0.0748
e. Stairs 0.0748
f. Ladder Cage 0.0592
g. Open Web 0.053
Light 20#s/ft.
Medium 21-40#s/ft.
Heavy 41#s/ft.
B. Erection M.H./kg. (man hour/kilogram)
1. Open Web 0.0938
2. Purlins 0.055
3. Sag Rods/Brackets 0.1197
4. Shapes (Heavy)
Columns/Girders/Beams
1st Flr 0.0647
2nd Flr 0.0776
3rd Flr 0.0906
4th Flr 0.1035
5th Flr 0.1164
6th Flr 0.1294
7th Flr 0.1423
8th Flr 0.1553
5. Checkered Flooring 0.055
6. Stairs 0.1617
7. Ladder Cage 0.1607
Standard Crew
a. Layout/Cutting b. Rolling
1 - Steel Worker 1 - Press Operator
2 - Cutters 2 - Helpers
3 - Helpers
c. Blacksmithing d. Welding
1 - Steel Worker 2 - Welders
2 - Welders 2 - Helpers
3 - Helpers
B. Field Erection M.H./kg. (man hour/kilogram)
1. Bottom Plate 0.0679
2. Shell Plate
a. 1st course 0.0776
b. 2nd course 0.097
c. 3rd course 0.1164
d. 4th course 0.1359
e. 5th course 0.152
f. 6th course 0.165
g. 7th course 0.1778
3. Rafter/Column 0.152
4. Stairs/Railings 0.1617
5. Fittings 0.1617
Standard Crew
1 - Rigger
2 - Steel Worker
3 - Welder
5 - Helper
Elevated Tank with Steel Tower
2. Power Plant (2-66 MW Steam Power Plant) MH/MT 2" (2-1/4)" (2-1/2)"
Steam Generator / Boiler 125
Drum
Front Water Wall
Rear Water Wall
Side Water Wall
Economizer
Pre-heater
Pumps
Fabrication Crew
a. Layout & Cutting d. Fit-up & Assy
1 - Steel Worker 1 - Steel Worker
2 - Welders 2 - Welders
3 - Helpers 2 - Helpers
Volume of Weight of
Area of Welding
Deposited Deposited Weight of Manhour
Throat "t" Weld Metal Metal per Electrode/ft (MHR/ft)
(in^2) (in^3/ft) ft. (kgs/ft)
Volume Weight of
Welding Area of of Deposite Welding
Throat "t" Throat Weld Deposite d Metal Manhour
"thk" (in^2) d Metal per ft. (MHR/ft)
(in^3/ft) (kgs/ft)
Data:
Trial
1st 2nd 3rd Ave.
Position F&H F&H F&H
Welding Class E 7018 E 7018 E 7018
Electrode size (in) (5/32) (1/8) (1/8)
Current (AMF) 215 115 115
Welding time (min) 2 3.33 3.5 2.943
WT. of metal Deposited (kg) 0.048 0.08 0.08 0.0695
Deposit rate (MHR/kg) 0.694 0.694 0.729 0.706
Operating Factor (%) 30 30 30 30
Standard Welding Rate (MHR/kg) 1.18 1.18 1.24 1.2
Operating Factor - Includes setting, flux removing, etc. & other non-productive time
FLAME (O.A.) & WELDING ROD CONSUMPTION
Hand Mach.
Thick (in.) Consumption Cutting Cutting
(lbs/lin.ft.) (in/min) (in/min)
1/8" 15 29 32
1/4" 30 26 28
3/8" 40 23 26
1/2" 50 22 24
3/4" 70 19 21
1" 80 18 19
1-1/4" 100 14 16
2" 160 13 14
3" 200 6 8
Thick (in)
Lg. Cut (in/electrode)
1/16" 14"
1/8" 13"
1/4" 11"
3/8" 9"
1/2" 7-1/2"
3/4" 6"
1" 3"
CO2 CLADDING, DRILLING, RIVETING & SEALANT
A. Cladding
1.) 4 men can install 4 pcs. 4'x8' cladding/day @12 hrs/day
= 4 x 12 hrs/day
4 (32) ft^2/day
= 0.375 mhrs/ft^2
B.) Buffing Materials for Mash Tub Kettle #2 of S.M.C. (July 1984)
2 pcs - scotch brite metal finishing wheel 4c (coarse)
= Php1910/pc x 2 = 3820
for first operation (thickness of wheel = 2"), as of July 1984
1980
ENGR. JR 38.50/day 1000/mo
ENGR SR. 57.50/day 1500/mo
Skilled 3.50/hr 281/day
Semi 3.00/hr 241/day
Labor 2.50/hr 20/day
STRESS RELIEVING
Supplies:
Diesel Fuel = 3drums/firing x 200 L/drum x 7.0517/L x 2 firings Note: Taken from R. Java
= 8462.00
O.A. = 1 set =Php600/set
= Php600.00 CRATING
W.R = 5kg x 30/kg = Php150.00 Materials:
= Php 150.00 6 x 3 - Lumber 1" x 6" x 3
Others =Php 200.00 12 - Lumber 2" x 3" x 3
=Php 200.00
TOTAL SUPPLIES COST = Php 9412.00 Mat'l Cost = 45 bd ft x Php 8
Labor & Supplies (20% of M
Labor: TOTAL COST
Set-up = 3m x 12 hrs/day x 4 days = 144 mhrs
Firing = 2m x 8hrs/firing x 2 firing = 32 mhrs Total Crating Area = 3 x 3 x 6
Hauling = 2m x 2hrs = 4 mhrs Cost/sq ft = Php 8.00
TOTAL LABOR 180 mhrs
Equipment Classification
Category Weight
1. Lightweight & compact Up to 1500#
2. Lightweight & bulky Up to 1500#
3. Heavy weight & compact 1 to 10 tons Note: The manhour figures include
4. Heavy weight & bulky 1 to 10 tons the labor required for loading,
unloading, moving and setting a piece
5. Heavy weight & compact 10 to 50 tons of equipment. Includes man-hours for
6. Heavy weight & bulky 10 to 50 tons the equipment operating crew.
Rigging Operations
1. Unload from open trailer with power rigging equipment to:
a.) Ground adjacent to trailer.
b.) Supporting base located in lower level.
c.) Supporting base located in intermediate level.
5. Line up:
a. Rough
b. Precise
MANHOURS FOR INSTALLATION OF PUMPS WITH DRIVER AND COMMON BASE PLATES
Rated HP Man-hours
1-1/2 to 10 24
15 to 50 32
60 to 100 48
125 to 200 54
250 to 500 64
600 to 1000 72
1000 to 1500 80
STEAM TURBINE GENERATOR UNIT
KW rating 1 2 3 4 5 6 7 8 Total
2000 200 600 6200 5100 1550 1500 1500 500 17150
2500 200 600 6200 5100 1550 1500 1500 500 17150
3000 200 700 6630 6100 1800 1750 2000 550 19730
4000 225 750 6850 6500 2000 1800 2150 600 20875
5000 250 825 7350 7300 2175 1850 2125 650 22525
6000 300 825 7350 7300 2175 1850 2125 650 22575
7500 300 850 7650 7550 2250 1900 2200 650 23350
10000 300 850 7950 7900 2350 1900 2275 700 24225
12650 350 850 7950 7900 2350 1900 2275 700 24275
15625 375 950 8700 8600 2450 2000 2425 800 26300
16500 400 1000 9000 8800 2500 2000 2500 800 27000
1. Unload & Handling Unloading at erection site or building, jacking, cribbing, skidding & moving to erection location
3. Lift, set & align Setting & aligning & hook-up of all components
4. Piping Installation of oil steam & generator piping, fitting and related instrumentations.
5. Oil, flush & test Oil flush, generator test, bearing inspection, balance test & close up for start-up.
instrumentations.
se up for start-up.
ABOVE GROUND PIPING MHRS/TON
ss 1x1
Pipe (dia.in.) Weight/M Page RRS 2M CISC 2014 Herkimer AG&P std.
3/4" 40 80
1 2.52 3.2 732 736 1130 681 975
1-1/4" 3.42 4.46 576 - 948 601 785
1-1/2" 4.01 5.36 483 513 800 542 670
2 5.5 7.47 398 410 690 518 580
2-1/2" 8.62 11.45 282 329 540 391 500
3 11.3 15.36 236 262 460 340 430
3-1/2" 13.38 18.6 216 - 438 319 370
4 16 22.3 194 245 388 F145 306 325
5 21.7 30.94 158 - 324 281 280
6 28.6 42.54 139 172 275 256 250
8 42.54 112 146 240 237 225
10 60.24 105 127 220 213 205
12 79.73 108 123 190 F135 221 190
14 93.71 109 124 198 213 185
16 123.46 110 126 190 188 182
20 182.96 119 127 185 169 178
24 254.36 113 127 180 F125 163 177
Scope: Field Fabrication and Erection
MH - 2M as of Jan 2010 per piece BI Piping
Elbow Pipe Weld Joint Reducer
Fittings valve Tee x1.5
reducer +50 SCH 40 SCH 80 + 100% con 1.1
3/8-3/4"4 1.5 MH 2.25 3 ecc 1.2
1"4 1.75 2.63 3.5 stwb 1.5
1-1/2"4 2 3 4 valve 1.5
2"4 2.5 3.75 5
2-1/2 / 3"4 3 4.5 6
4"4 4 6 8
as of Jan 2011few | med
6 15 | 11 27 36
8 18 | 14 33 44
10 22 | 16 39 52
12 28 | 19 45 60
Tee x 1.25
ELECTRIC MOTORS & GEARS MANHOURS FOR INSTALLATIONS
Mhrs
1. Up to 10 HP 6
2. 15 or 20 HP 8
3. 25 or 30 HP 10
4. 40 HP 14
5. 50 HP 16
6. 60 HP 18
7. 75 HP 22
8. 100 HP 26
9. 125 HP 30
10. 150 HP 36
11. 200 HP 38
12. 250 HP 44
13. 300 HP 54
14. 350 HP 60
15. 400 HP 62
16. 450 HP 68
17. 500 HP 72
18. 600 HP 84
19. 700 HP 96
20. 800 HP 104
21. 1000 HP 116
22. 1250 HP 144
23. 1500 HP 164
24. 1750 HP 174
25. 2000 HP 192
26. 2500 HP 212
27. 3000 HP 252
I. Structural Excavation VI. Architectural Specialties
1. Common Excavation 1. Doors
a. Hand 6.0 MH/M^3 a. Wooden
b. Machine 0.5 MH/M^3 b. Steel
2. Rock Excavation 8.0 MH/M^3 c. Aluminum
3. Hauling of Spoils 1.0 MH/M^3 d. Cyclone wire
II. Structural Backfill 2. Windows
1. By Hand 5.0 MH/M^3 a. Glass
2. By Machine 2.0 MH/M^3 b. Louver
III. Trenching c. Steels
1. By Hand 6.0 MH/M^3 3. Partitions/ Single Wall
2. By Machine 0.5 MH/M^3 Double Wall
IV. Conc. Edns. & Elev. Conc. Wooden Louver
1. Grade Members Cyclone Wire
a. Formwork 2.54 MH/M^2 VII. Structural Steel
b. Concreting 8.54 MH/M^2 1. Fabrication
c. Rebar 0.07MH/Kg a. Light
d. Finishing 0.4 MH/M^2 b. Heavy
2. Suspended Member/Formwork 3.28 MH/M^2 2. Erection
Concreting 16.70 MH/M^2 a. Light
Rebar 0.03 MH/M^2 b. Heavy
Finishing 0.80 MH/M^2 VIII. Painting
3. Embedded Metal 0.27 MH/Kg 1. Equipment
4. Waterproofing 1.82 MH/M^2 2.Pipes
5. Joint Filler 0.01 MH/LF 3. Misc.
V. Roofing and Sidings IX. Instrumentation
1. Roofing/Metallic 0.07 MH/F^2 1. Indicators
Non-metallic 0.14 MH/F^2 2. Gauges
2. Siding 3. Controllers
a. doors 0.12 MH/F^2 4. Receivers
b. Non-metallic 0.14 MH/F^2 5. Panel Mounted Instr
6. Testing & Calibration
X. Equipment Installation
1. Light Equipment 100 MH/MT
a. Wooden 0.22 MH/F^2 2. Heavy Equipment 90 MH/MT
0.74 MH/F^2 XI. Equipment Insulation 1-1/2" thk 1.115 MH/F^2
c. Aluminum 0.75 MH/F^2 2-1/2" thk 1.353 MH/F^2
d. Cyclone wire 0.71 MH/F^2 3-1/2" thk 2.611 MH/F^2
XII. Pipe Insulation
0.30 MH/F^2 (1-1/2" 0 3-1/2" thk)
0.33 MH/F^2 1. 1/2" 1.306 MH/LF
0.30 MH/F^2 2. 3/4" 1.334 MH/LF
ons/ Single Wall 0.23 MH/F^2 3. 1" 1.386 MH/LF
Double Wall 0.32 MH/F^2 4. 1-1/2" 1.513 MH/LF
Wooden Louver 0.32 MH/F^2 5. 2" 1.602 MH/LF
Cyclone Wire 0.50 MH/F^2 6. 2-1/2" 1.737 MH/LF
7. 3" 1.810 MH/LF
8. 3-1/2" 2.000 MH/LF
110-130 MH/MT 9. 4" 2.150 MH/LF
60-70 MH/MT 10. 5" 2.250 MH/LF
11. 6" 2.350 MH/LF
70-100 MH/MT 12 8" 2.450 MH/LF
40-60 MH/MT 13. 10" 2.600 MH/LF
14. 12" 3.000 MH/LF
0.24 MH/SF/ 3 coats 15. 14" 3.740 MH/LF
0.30 MH/SF/ 3 coats 16. 16" 4.154 MH/LF
0.24 MH/SF/ 3 coats 17. 18" 4.567 MH/LF
18. 20" 4.950 MH/LF
24 MH/SET 19. 22" 5.335 MH/LF
16 MH/SET 20. 24" 5.694 MH/LF
24 MH/SET Equipment Insulation
24 MH/SET 1-1/2" thick F^2 1.115 MH
Mounted Instr 16 MH/SET 2-1/2" thick F^2 1.863 MH
& Calibration 40 MH/SET 3-1/2" thick F^2 2.611 MH
Pipe Insulation
1/2" LF 1.31 MH
3/4" LF 1.33 MH
1" LF 1.39 MH
1-1/2" LF 1.51 MH
2" LF 1.60 MH
2-1/2" LF 1.74 MH
3" LF 1.81 MH
3-1/2" LF 2.00 MH
4" LF 2.15 MH
5" LF 2.26 MH
6" LF 2.36 MH
8" LF 2.46 MH
10" LF 2.60 MH
12" LF 3.60 MH
14" LF 3.74 MH
16" LF 4.15 MH
18" LF 4.57 MH
20" LF 4.96 MH
22" LF 5.34 MH
24" LF 5.69 MH
FUEL CONSUMPTION
A. Earthworks:
1. Excavation
a. Common Excavation (manual only)
1. Common earth
2. Hard clay or sand and gravel
b. Rock and Adobe (manual and machine)
2. Backfill
3. Disposal
4. Earthfill
5. Gravefill
6. Soil Poisoning (2 application)
B. Rebarworks:
1. Reinforcing Steel
C. Formworks
1. Formwork Area (including the mh for formoil)
2. Falsework (1-use)
D. Concrete Works:
1. Concrete work volume (using 1 bagger mixer)
a. Slabs on fill
b. Footing and tie beams
c. Suspended slabs
d. Columns and beams
2. Concrete work volume (using 1 bagger or 2 bagger mixer)
a. Slabs on fill
b. Footing and tie beams
c. Suspended slabs (2nd and 3rd flr)
d. Columns and beams (using pails for 3 meter height only)
e. Columns and beams (1st, 2nd, 3rd flr using porta lift or hoisting machine
3. Using Ready Mix concrete with hoisting machine (for all structural members)
4. Using Ready Mix concrete with pump (for all members)
5. Grouting
6. Riprap
7. Concrete Pipe Laying (excluding excavation & backfilling)
a. 150 mm
b. 200
c. 250
d. 300
e. 380
f. 450
g. 500
h. 600
i. 750
j. 900
8. Vapor Barrier
9. Join Sealant
E. Masonry Works:
1. CHB Installation including rebars
a. 4" CHB
b. 6" CHB
c. 8" CHB
2. CHB Finishing
a. Tool Joint Finish
b. 1/2" thk plaster finish
c. 3/4" thk plaster finish
KS - MAN HOUR RATES PER ITEM OF WORK
0.12 (mh/kg)
(mh/sm)
2.5
2.75
3
0.5 to 1.0
1.75
2
F. Structural Steel Works:
1. Shop Fabrication
a. Layout-Cutting
Built-ups
Shapes
Checkered Flooring
Pound Bars
Purlins
Shapes (Heavy)
Misc. Plates
Open Web
b. Fit-up and Assembly
Built-ups
Shapes (Light)
Shapes (Heavy)
Misc. Plates
Stairs
Ladder Cage
Open Web
c. Alignment
Built-ups
d. Welding
Built-ups
Shapes (Light)
Shapes (Heavy)
Misc. Plates
Ladder Cage
Open Web
e. Painting
Brush
Spray
(For budget purposes for painting, use 0.02 mh/kg)
2. Erection
Purlins/Checkered Flooring
Sagrods/Bracket
Open Web
Stairs (light shape)
Ladder Cage
Truss on conc. Column with 5T Crane
2" B.I. Pipe frame for fence
Gs. 10 cyclone wire for fence (welded on 2" B.I. Pipe)
Column x 20 ft length with 25T Crane
Runway Girder (bolted connection)
Purlins (field fabrication)
0.0373
0.025
0.03
0.1189
0.1607
0.1125
0.1189
0.011
0.0281
0.012
0.0218
0.0748
0.0592
0.053
(mh/gal)
8
4
02 mh/kg)
(mh/kg)
0.06
0.12
0.1
0.09
0.16
0.05
2" B.I. Pipe) 0.07
1 (mh/sm)
0.09 (mh/sm)
0.08
0.1
(mh/sm)
1.5
1.75
0.7(mh/1m)
1.31(mh/1m)
2 (mh/sm)
1.5(mh/1m)
1(mh/1m)
2(mh/1m)
1(mh/pair)
8(mh/sht.)
2(mh/pc)
H. Carpentry Works
1. Wooden Trusses/Purlins/Rafter
a. Purlins @ 0.60 m o.c. w/ 2"x2" wood cleats)
0.2 mh/bd ft
0.6 mh/sm
J. Miscellaneous Works:
1. Doors including finish hardware (installation only)
a. Hollow core flush type door
0.60 - 0.70 x 2.10
0.80 - 1.20 x 2.10
b. Solid Core Panel Door
Swing
Sliding
c. Louver Type Wooden Door
d. Steel Plate Door
Swing
Sliding
e. Aluminum or Steel Frame Glass Door
2. Windows (Installation only)
a. Steel Frame Glass Window
(fixed, awning or casement)
b. Aluminum frame glass window
(fixed or sliding)
c. Metal or GI Louver window
(jalousie)
d. Window Jamb or Door Jamb (Yacal)
1. Fabrication
2. Installation
K. Plumbing and Sanitary Works:
1. Pipes
a. PVC
1/2" - 1-1/2"
2" - 3"
4"
6"
b. G.I. Pipe
1/2" - 1-1/2"
2" - 3"
4"
6"
c. C.I. Pipe
2" - 3"
4"
6"
8"
2. Fittings
a. PVC
1/2" - 1-1/2"
2" - 3"
4"
6"
(mh/sm)
0.54
0.64
2.67
4.33
0.8
2.5
2
0.8
0.88
0.4
6.4
1.6
6 (mh/set)
4 (mh/sm)
4 (mh/sm)
6 (mh/sm)
5 (mh/sm)
8 (mh/sm)
10 (mh/sm)
5 (mh/sm)
5 (mh/sm)
4.5 (mh/sm)
3 (mh/sm)
(mh/1m)
0.5
0.67
0.83
1
0.58
0.67
0.83
1
1
1.33
1.67
2
(mh/pc)
0.5
0.8
1
1.5
b. G.I. Pipe
1/2" - 1-1/2"
2" - 3"
4"
6"
c. C.I. Pipe
2" - 3"
4"
6"
8"
Note: For C.O. use
3. Fixtures
a. Water Closets
b. Urinal
c. Lavatory
d. Kitchen Sink
e. Faucet
f. Shower Head
g. Floor Drain
4. Valves
3/4"
1"
1-1/4"
1-1/2"
2"
2-1/2"
3"
3-1/2"
4"
5"
6"
12"
L. Painting Works:
1. Masonry Surface
a. Install Scaffolds
b. Surface Preparation
c. Apply 1st coat Masonry Sealer
d. Apply 2nd coat flat latex
e. Apply 3rd coat flat latex
f. Demobilize
2. Wood Surfaces
a. Install Scaffolds
b. Surface Preparation
c. Apply 1st coat Wood Primer
d. Apply 2nd coat enamel
e. Apply 3rd coat enamel
f. Demobilize
3. Metal Surfaces
a. Brush Method
1. Install Scaffolds
2. Surface Preparation
3. Apply 1st Coat Primer
4. Apply 2nd Coat Quick Drying Enamel
5. Apply 3rd Coat Quick Drying Enamel
6. Demobilize
(mh/pc)
0.5
0.8
1
1.5
1
1.2
1.5
2
2
6 (mh/set)
4 (mh/set)
4 (mh/set)
4 (mh/set)
0.5 (mh/pc)
8 (mh/set)
2 (mh/pc)
(mh/pc)
5.28
5.61
5.75
5.94
6.27
7.92
9.24
11.22
13.53
15.18
17.16
30
(mh/sm)
0.25
0.08
0.14
0.16
0.18
0.08
0.25
0.1
0.14
0.15
0.16
0.08
0.25
0.29
0.12
0.15
t Quick Drying Enamel 0.16
t Quick Drying Enamel 0.08
b. Spray Method
1. Install Scaffolds
2. Surface Preparation
3. Apply 1st coat primer
4. Apply 2nd coat quick drying enamel
5. Apply 3rd coat quick drying enamel
6. Demobilize
Note: If the estimate requires for primer only,
item 1 and 2 shall be applied only
5. Varnish
a. Smoooth Finish Grain (closed grain)
1. Surface Preparation
2. Apply Paste Wood Filler
3. Apply Stain Varnish
4. Apply Lacquer Sanding Sealer
5. Apply Clear Gloss or Dead Flat Lacquer
b. Standard Finish Grain (Open Grain)
1. Surface Preparation
2. Apply Stain Varnish
3. Apply Lacquer Sanding Sealer
4. Apply clear glass or dead flat lacquer (2 application)
Note: If G.I. Sheets are used as sidings, provide man-hours for installation
and demobilization of scaffolds. Provide scaffold winch and accessories for
high rise buildings and for residential houses, use wooden platform or
scaffolding.
(mh/sm)
0.25
0.2
0.04
0.05
0.06
0.08
0.05
0.08
0.14
0.15
0.5
0.25
0.21
0.24
0.26
0.5
0.21
0.24
0.52
CIVIL WORKS LABOR PRODUCTIVITY
1. Rebars
a. Foundation - 150 lbs/m^3
b. Wall - 200 lbs/m^3
c. Beams - 200 lbs/m^3
d. Floor Slab - 150 lbs/m^3
e. Columns - 200 lbs/m^3
3. Mortar
a. #4/sqm:
cement 0.375 bag/sqm
sand 0.0319 m^3/sqm
rebar 2 kgs/sqm
b. #6/sqm:
cement 0.5 bag/sqm
sand 0.0425 m^3/sqm
rebar 2 kgs/sqm
Earthful Estimate:
1 Solve for the volume (called Loose Volume) to be filled in.
2 Add 25% to this loose volume.
3 The sum called (Compact Volume) rounded to the next even number.
Note: Standard Truckload = 4 m^3
Volume in cubic meters x m^3 per truckload = Truckload (T)
Example:
Determine the number of bags of cement (1 cu.ft. = 1 bag) and
the quantities of the other aggregates required for 100 cu.m.
of concrete of 1;2;4 mix with the following given data:
Required Quantities:
Cement: 3529 = 687 bags
5.14
Nailing Strips: Factors in Board Feet per Sheet of Ceiling Board 4' x 8' Ceiling Board
Procedures of Estimate:
1. Utilize Net Area found in siding estimate
2. Multiply by required factor
3. Round to 10 bd ft if 100 or less;
round to 100 bd ft if over 100
Partitions: Estimating:
(A) Single Partitions
1. Solve for actual area covered (net area)
2. Solve for number of sheets based on stock sizes
3. Solve for partitions studs
(B) Double Partitions
1. Solve for actual area covered
(Note that if the same partition above was used, the net area would be doubled)
No. of Pieces per
Classification Stock Sizes
Sq. meter Sq. Foot Rounding
4" x 4" (0.1 x 0.1) 100 9.29 50
6" x 6" (0.15 x 0.15) 44 4.0876 50
Cement Tile
8" x 8" (0.2 x 0.2) 25 2.3225 50
20" x 20" (0.5 x 0.5) 4 0.3716 10
Vitrified Tiles 4" x 4" (0.1 x 0.1) 100 9.29 50
Glazed Tiles 4-1/4" x 4-/14" (0.108 x 0.108) 86 7.8965 50
2" x 2" (0.05 x 0.05) 480 44.592 50
Hexagonal Tiles 3" x 3" (0.074 x 0.074) 190 17.651 50
4-1/4" x 4-/14" (0.108 x 0.108) 95 8.8255 50
5 Point Hexagonal 2" 20 6.096 50
4 Point Hexagonal 2" 16 4.8848 50
Special Mould 4-1/2" 9 2.7433 10
Note: For wainscoting mould estimate by direct count.
Procedure of Estimate:
1. Compute total floor or wall areas. (Disregard minor plumbing outlet)
2. Multiply by respective factors.
3. Round up.
Notes:
1. Tile Cement mortar, unless otherwise indicated on the plan details or specifications, shall be 1cm thk.
2. Mortar volume shall be based on rounded value tiles.
3. Aggragates for mortar shall be rounded as follows:
Cement . . . 5 bags
Lime . . . 5 bags
Sand . . . 1 cu.m.
4. Use point hexagonal tiles along longer lengths
5. Use 4 point hexagonal tiles along shorter lengths
d be doubled)
l be 1cm thk.
CORRUGATED ROOFING SHEETS (efective roof coverage)
a. With 12" (30 cm) end lap and 2 corrugations side lap.
Commercial Size Efective Coverage
(width x length) Dimensions (efective) Area (sq.ft) Area (sq.m)
32" x 6'-0" 27" x 5'-2" 11.3 1.05
32" x 7'-0" 27" x 6'-2" 13.56 1.26
32" x 8'-0" 27" x 7'-2" 15.71 1.46
32" x 12'-0" 27" x 11'-2" 24.75 2.3
Notes:
1. In computing for a board feet, subtract first all floor openings
from gross floor area and multiply the factors above
2. Other structural wooden beams such as girders, girts ties and the
like should be estimated by direct count.