Document : 21041-780-01-001
Section : Hot Air System
ATTACHMENT#9
Plant: Jazan Unit: 11 Part:
Client: Siemens
System: Auxiliary Systems
The party responsible for commissioning confirms that all commissioning activities detailed below have been
successfully performed.
Associated Certificates:
No outstanding items
Remarks:
Copies to:
Completion
No. Description Remarks
verified by client:
NOTE: Additional pages shall be attached as required. Total number of pages shall be indicated on each page.
FOR ACTION
Action taken/Remarks: