S10 Pgina : 1

Obra 0602010 CARRETERA TICACO - CANDARAVE


Subpresupuesto 001 CARRETERA TICACO - CANDARAVE
Fecha 16/11/2011
Lugar 230401 TACNA - TARATA - TARATA
Reporte subpartidas (Resumido)

Cdigo Partida Und Cantidad Precio S/. Parcial S/.

900303040109-0602010-01 PREPARACION DE SUELO ORGANICO m3 5,000.00000000 17.36 86,800.00


900400040013-0602010-01 MATERIALES PARA SEALIZACION TEMPORAL DE SEGURIDAD GLB 18.00000000 4,076.00 73,368.00
900401030093-0602010-01 CONCRETO F'C=140 KG/CM2. m3 240.77877200 292.45 70,415.75
900504011517-0602010-01 AGUA PARA LA OBRA m3 97,056.75112800 9.48 920,098.00
909001011339-0602010-01 EXTRACCION DE MATERIAL (CANTERA) m3 386,313.37093500 3.19 1,232,339.65
909001011340-0602010-01 ZARANDEO MECANICO m3 338,242.44421400 7.26 2,455,640.14
909001011341-0602010-01 LAVADO DE AGREGADOS m3 47,993.91036800 13.32 639,278.89
909001011342-0602010-01 ZARANDEO Y CHANCADO (PIEDRA) m3 47,307.89672100 22.96 1,086,189.31
909001011533-0602010-01 ACERO DE REFUERZO fy=4200 Kg/cm2 kg 156.40000000 3.62 566.17
909701020171-0602010-01 CORTE PARA MEJORAMIENTO m3 2,000.00000000 7.12 14,240.00
909701020207-0602010-01 PERFORACION Y DISPARO DE ROCA SUELTA m3 346,055.03000000 13.64 4,720,190.61
909701020208-0602010-01 EXCAVACION Y DESQUINCHE EN ROCA SUELTA m3 346,055.03000000 2.96 1,024,322.89
909701020209-0602010-01 PERFORACION Y DISPARO DE ROCA FIJA m3 389,121.01000000 14.53 5,653,928.28
909701020210-0602010-01 EXCAVACION Y DESQUINCHE EN ROCA FIJA m3 389,121.01000000 16.18 6,295,977.94
909701021304-0602010-01 CONFORMACION DE MEJORAMIENTO m3 2,000.00000000 7.80 15,600.00
909701021306-0602010-01 MATERIAL PARA RELLENOS m3 12,285.06500000 15.04 184,767.38
909701030307-0602010-01 CONFORMACION DE BASE GRANULAR m3 223,809.98400000 9.20 2,059,051.85
909701030308-0602010-01 MATERIAL SUB BASE GRANULAR m3 131,421.28800000 17.13 2,251,246.66
909701030407-0602010-01 MATERIAL DE BASE m3 121,194.14800000 30.42 3,686,725.98
909701031004-0602010-01 TRATAMIENTO SUPERFICIAL BICAPA1RA CAPA m2 495,356.61000000 1.83 906,502.60
909701031005-0602010-01 TRATAMIENTO SUPERFICIAL BICAPA 2DA CAPA m2 495,356.61000000 1.39 688,545.69
909701031352-0602010-01 CHANCADO DE AGREGADOS (BASE GRANULAR) m3 145,432.97760000 10.31 1,499,414.00
909701031353-0602010-01 PIEDRA CHANCADA PARA TSB m3 16,842.12474000 36.89 621,305.98
909701040110-0602010-01 EXCAVACION PARA ESTRUCTURAS m3 8.50000000 31.59 268.52
909701040204-0602010-01 ENCOFRADO Y DESENCOFRADO m2 34.68000000 45.25 1,569.27
909701040604-0602010-01 CONCRETO F'C=100 KG/CM2 m3 1,220.14000000 219.92 268,333.19
909701040802-0602010-01 CONCRETO F'C=140 KG/CM2 m3 4,789.52600000 281.99 1,350,598.44
909701040803-0602010-01 CONCRETO F'C=140 KG/CM2 + 30% PM m3 8.50000000 307.35 2,612.48
909701040912-0602010-01 CONCRETO F'C = 175 KG/CM2 m3 20,105.08640000 369.51 7,429,030.48
909701043157-0602010-01 TRANSPORTE DE PIEDRA m3 546.38700000 19.07 10,419.60
909701043163-0602010-01 ARENA ZARANDEADA m3 20,557.52794100 30.98 636,872.22
909701043164-0602010-01 PIEDRA CHANCADA m3 24,412.02435400 47.44 1,158,106.44
909701043165-0602010-01 TRANSPORTE INTERNO D=0.30 KM (PLANTA) m3 382,621.02122200 4.59 1,756,230.49
909701043166-0602010-01 PIEDRA MEDIANA DE 6" m3 3,951.49540000 35.48 140,199.06
909701043167-0602010-01 EXTRACCION Y RECOLECCION DE PIEDRA MEDIANA m3 23,519.29356000 20.75 488,025.34
909701043168-0602010-01 PIEDRA GRANDE m3 546.38700000 39.56 21,615.07
909701043169-0602010-01 EXTRACCION Y RECOLECCION DE PIEDRA GRANDE m3 682.98375000 16.39 11,194.10
909701043171-0602010-01 MATERIAL DE FILTRO m3 1,333.94240000 21.73 28,986.57
909701043172-0602010-01 EXTRACCION Y APILAMIENTO DE MATERIAL PARA AGREGADO FINO m3 1,333.94240000 3.96 5,282.41
909701043173-0602010-01 ZARANDEO MECANICO (AGREGADO FINO/FILTRO) m3 1,333.94240000 13.18 17,581.36
909701043174-0602010-01 RELLENO DE ZANJA DE DRENAJE: GRAVA D=1" - 3/8" m3 763.03000000 36.19 27,614.06
909701043175-0602010-01 ZARANDEADO GRAVA 1" - 3/8" PARA FILTRO m3 763.03000000 15.09 11,514.12
909701043176-0602010-01 PIEDRA MEDIANA DE 6" A 8" m3 12,848.00000000 35.48 455,847.04
909701044401-0602010-01 CURADO DE CONCRETO CON ADITIVO m2 171,685.20640000 0.95 163,100.95
909701044501-0602010-01 CONCRETO F'C=80 KG/CM2 m3 1,116.08700000 225.60 251,789.23
930101910101-0602010-01 EXCAVACION m3 280.00000000 23.54 6,591.20