Académique Documents
Professionnel Documents
Culture Documents
CONTENTS
1.0 Purpose
The purpose of this procedure is to:
2.0 Scope
2.1 Personnel and Activities Covered by this Procedure
This procedure applies to all maintenance and construction work performed by Chevron
Pipe Line Company (CPL) workforce including but not limited to:
a) New construction;
b) Any work that requires:
o Hot Work Permit;
o Excavation Permit;
o Isolation Lockout/Tagout (LOTO);
o Confined Space Permit;
o Electrical Safe Work Permit.
c) Pipeline repair;
d) Pipeline replacement;
e) Tank or vessel maintenance and/or repair;
f) Hot taps;
g) Overhauling of equipment (pumps, compressors);
h) Site remediation projects; and
i) Any other work that is hazardous or unusual such as:
o Working from heights where personal fall protection is required;
o Overhead activities involving rigging in a congested area or over piping or
equipment in service; Unbolting, disconnecting, opening, or removal of any line,
process piping, equipment, or system that has been in service;
o Un-flanging or removal of heads, isolating blinds, blind flanges, man ways, process
piping, or equipment that has been in service;
o Working on live electrical equipment over 50 Volts;
o Removal of process valves and relief valves; and
o Construction work (includes the installation of new equipment and the modification
of existing equipment).
Delivery services
Pest control
Laundry service
Janitorial service
Utility service
Day to day loading and off loading at those facilities where it is part of their operation
ie. Terminal operations
3.0 Prerequisites
3.1 Qualified Third Party Person-in-Charge
Individual contractor hired by CPL as third party may assume the responsibility as a CPL
PIC, provided that the following apply:
Use of a PIC will be determined on a job-by-job basis.
Approval for using a Qualified Third Party Contractor as a PIC will be
determined based on work location and scope of work. Approval can be
authorized by either the Team Leader or Project Manager from CPL Projects
Management Group.
Qualified Third Party (PIC) Must be a Contractor separate and distinct from
the contractor performing the work (a third party who does not work for the
contractor, but works directly on behalf of CPL) who has been trained in CPL
applicable procedures, and understands the hazards, risks, exposures, and
associated impact to operations from the activities in the facility.
a) Team Leaders responsible for the assets and/or Project Manager, must approve the
individual to act as a PIC on behalf of CPL, and assure the Third Party PIC or PIC
Contractor is trained and qualified in the operations process.
b) The Third Party PIC must be trained on the applicable CPL Safe Work practices
permitting systems, by the Health Environment & Safety (HES) Training Group.
(See section 3.3 Specific Safe Work Practice Training for training requirements).
c) Upon completion of the Safe Work Practice Permit training, the individuals
knowledge must be validated (90% on test). All training must be attested to by the
Team Leader and/or Project Manager or designated CPL employee representative and
records maintained at the appropriate office.
d) The PIC qualification documentation must be in writing by the Team Leader and kept
on file. Qualified means trained in applicable procedures and understands the hazards,
risks, exposures, and associated impact to operations from the activities in that facility
or work location.
e) Certification for PIC is only valid for three (3) years from the day of training. Records
of the training shall be retained in the appropriate office for three (3) years.
f) Third Party PIC can sign any of the Safe Work Practice Permits (safe work, hot work,
confined space, and excavation). In no scenario will a Third Party PIC be allowed to
initiate or approve a Lockout/Tagout (LOTO.)
g) Permit Origination and Extensions: the Third Party PIC must review the permit(s)
requirements and receive daily concurrence by phone from the Team Leader and/or
Project Manager or their designated CPL employee representative, prior to signing
the Safe Work Practice Permit(s), (safe work, hot work, confined space, and
excavation) acknowledging concurrence per telecom. The Third Party PIC must sign
the permit in the appropriate place and sign the Team Leader and/or Project Manager,
or designated CPL employee name, which provided concurrence per telecom next to
their signature.
h) If the Team Leader and/or Project Manager or their designated CPL representative
does not concur with the Third Party PIC, verification must not be given per telecom
and work must not commence.
3.3 Use of a Contractor PIC for Work Requiring Only a Safe Work
Permit
The Team Leader (TL) can designate any Qualified Contractor to act as a PIC to initiate
and sign Safe Work permits only. After receiving verbal approval from the Team Leader
or designee the Qualified Contractor can sign the permit and begin work. The Contractor
PIC must be trained on the applicable CPL Safe Work practices permitting systems, by
the Health Environment & Safety(HES)TrainingGroup. (See section 3.2 Specific Safe
Work Practice Training for training requirements). Team Leaders or designated CPL
employee representatives must confirm (test) the Contractor PICs knowledge of the
specific work operation and CPL Safe Work Permit process.
Possible Examples of (but not limited to) safe work permits only activities that can be
initiated and signed by a Contractor PIC are:
o Right-of -Way Mowing,
o Line Locate,
o Weed Spraying,
o Surveying,
o Window Air Conditioner Maintenance,
o Telecommunication Maintenance,
o Sign Maintenance,
o And/or any other job at the Team Leaders discretion.
Yes
Is the
Use SWA and complete
Job Scope No
the scope of work
complete?
Yes YES
Is a
Use SWA and complete
CPL JSA
the JSA
required?
Yes
Has the
No JSA been No
completed?
Yes
Yes
Yes
PIC files permit in the
appropriate office
Complete other permits as
required
5.0 Instructions
5.1 Permit Origination - General Section
The PIC initiates the safe work permit process by completing the general section of the
permit (See Appendix B, Safe Work Permit Form), and must specify:
a) the facility, job boundaries, and equipment being worked on;
b) date and time limits (schedule time);
c) description of the work;
d) tools/equipment to be used; and
e) person(s) conducting the work (PCW).
The PIC specifies the required CPL permits that will also need to be completed prior to
the beginning of work. These permits include LOTO (HES-203), Confined Space
(HES-201), Hot Work (HES-205), Excavation (HES-202), and other permits that
may apply. Some routine tasks may not require a permit. These tasks will be
determined by the Team Leader.
The PIC specifies and assures that a JSA is conducted on-site and remains on location
until the job is complete. If a CPL JSA is completed then Hazard Analysis section can be
skipped.
5.3 PPE
The PIC specifies the required Personal Protective Equipment (PPE) that will need to be
used (see HES-501).
When performing work alone, the same person cannot act as both the PIC (CPL PIC or
Contractor PIC) and PCW at the same time. For times when a single person is performing
the work alone, at a minimum, the single person must review the permits with, and attain
verbal approval from the Team Leader or Designee. This can be done per telecom or in
person. Once concurrence is received, the single person must note the name of the Team
Leader or Designee providing concurrence as the PIC, and sign the permit(s) as the PCW.
Any permit that does not contain the current date and required signatures and initials
is not valid and work cannot be performed.
the PIC and the PCW confirm that conditions are safe and the permit restrictions
continue to be met then date and sign the permit.
A permit may be extended for four consecutive shifts, not to exceed 12 hours per
shift.
Role Responsibilities
Description
Document History
CPL 204 Safe Work Safe Work Permits must be kept 2 years at the appropriate
Permit is used to document office appropriate office.
this procedure.
Appendix A Glossary
Team Leader responsible for the assets, or their designated
Person-in-Charge CPL employee representative, or a qualified third party
contractor, that has overall responsibility for determining
acceptable conditions in the area are safe for the task to be
performed and for the safety of personnel and equipment until
the job is complete.
Requestor/Work Owner The person who selects, hires, or oversees the work of a
contractor.
The act of maintaining or keeping something in proper
Maintenance condition or upkeep. Any activity, such as tests,
measurements, replacements, adjustments, and repairs,
intended to restore or retain.