A. CIVIL WORK
1. Digging and backfilling of hole 600mm x 900mm 65 Nos. 1500.00 97,500.00
to accommodate concrete pole base
2. Digging and backfilling of cable trench 2000 Mtrs. 300.00 600,000.00
3. Casting of standard concrete pole base 65 Nos. 10,000 650,000.00
4. Allow for cutting and mending of overlay asphalt 50 Mtrs. 1,500.00 75,000.00
road crossing
5. Construction of transformer plinth 1 Nos. 35,000.00 35,000.00
6. Construction of lighting kiosk plinth 1 Nos. 15,000.00 15,000.00
7. 75mm diam galvanized pipes for road crossing 18 Length 4,500.00 81,000.00
Sub-total (A) - - - 1,553,500.00
B. CABLES & OTHER ACCESSORIES
1. 4 x 25mm PVC/SWA/PVC cable (Nigerchin) 150 Mtrs. 1,350.00 202,500.00
2. 4 x 10mm PVC/SWA/PVC cable (Nigerchin) 2500 Mtrs. 1,100.00 2,750,000.00
3. 2.5mm twin + earth PVC cable [NWC] 25 Coils 8,000.00 200,000.00
4. PVC insulation tape 15 Rolls 35.00 525.00
Sub-total[B] - - - 3,153,025.00
C. POLES/FITTINGS & ACCESSORIES
1. 9.0m single arm galvanized street light pole to 65 Nos. 45,000.00 2,925,000.00
Engineers specification
2. 1 x 250w high pressure[Philips] sodium lamp 65 Nos. 30,000.00 1,950,000.00
fittings complete with
i. 250w choke (Thorn)
ii. 250-400w ignitor
iii. 25uf capacitor
6. 60A PVC connector 20 Rolls 500.00 10,000.00
7. 5/10A MCB breakers (MG) 65 Nos. 750.00 48,750.00
8. Installation materials shall include bolts & nuts Lot Sum 25,000 25,000.00
Sub-total[C] - - - 4,958,750.00
S/NO. DESCRIPTION QTY. UNIT RATE TOTAL
COLLECTIONS
A. CIVIL WORKS - - - 1,553,500.00
F. TOTAL 13,293,175.00