Vous êtes sur la page 1sur 14

IADC/SPE 77231

Technical Developments in Modular Rig Design Lowering Operator Costs


Greg J. Carter, SPE, Nautilus Offshore Company, Inc.

Copyright 2002, IADC/SPE Asia Pacific Drilling Technology


frontier of oil exploration moves to deeper water,
Thi s paper was prepared for presentation at the IADC/SPE Asia Pacific Drilling Technology operators are requiring smaller, more economical
held in Jakarta, Indonesia, 911 September 2002.
platforms. The size of the platform and rig are critical
This paper was selected for presentation by an IADC/SPE Program Committee following
review of information contained in an abstract submitted by the author(s). Contents of the
issues as to the viability of a play when marginal field
paper, as presented, have not been reviewed by the International Association of Drilling development becomes more significant in the Operators
Contractors or the Society of Petroleum Engineers and are subject to correction by the
author(s). The material, as presented, does not necessarily reflect any position of the IADC or portfolio. As the platforms shrink to reduce costs,
SPE, their officers, or members. Papers presented at the IADC/SPE meetings are subject to
publication review by Editorial Committees of the IADC and SPE. Electronic reproduction,
particularly in water deeper than 100 meters, so must
distribution, or storage of any part of this paper for commercial purposes without the written the equipment that services the wells.
consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is
restricted to an abstract of not more than 300 words; illustrations may not be copied. The
abstract must contain conspicuous acknowledgment of where and by whom the paper was
presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., fax
There are roughly 7,200 platforms built worldwide since
01-972-952-9435. 1975 according to Offshore Data Services. Roughly
3,200 of these are in the Gulf of Mexico while the
Abstract remaining 4,000 are in other parts of the world (1). Many
Modular workover and drilling platform rigs have played of these are small single well units are accessible only
an important role in the development of existing oil and by jack-ups. Of the 7,200 post 1975 platforms, an
gas fields since the 1960s. The past decade has seen estimated 60% (4,320) of them can be serviced by
tremendous design improvements in modular platform rigs. With the advent of new
both workover and drilling technology and associated cost savings, modular
operations. Improvements range platform rigs typically utilized in deeper offshore
from effective utilization of top drives platforms have become competitive with jack-ups in
for sidetracking and extended reach relatively shallower waters.
programs to minimizing weight and
space distribution of the rig to Generalizations about platform sizes can be ascertained
accommodate minimal space from offshore experience and observations. Through the
platforms. Case history studies will 1970s and up to the mid 1980s, Operators tended to
illustrate how technological developments in modular rig build platforms with larger deck space for contracted
design have increased an Operators invested return on remedial and drilling equipment. Operator budgets
their offshore platforms and hired drilling/workover rigs. tended to allow for larger platform construction in all
water depths. Since the mid-1980s, platform
INTRODUCTION construction budgets tend to be much tighter. Available
This report describes changes that have taken place in deck space on newer
modular platform rig designs and applications in platforms has decreased
response to Operators increased demands for cost greatly, particularly since
efficiency. The primary elements that influence design more production equipment
and application are platform space and rig component is taking up more top deck
changes. These elements will be examined and space. Over the past
supporting case histories discussed. decade, new platform
concepts such as Minimal
PLATFORM SPACE Space Platforms have been
A Modular Platform Rig is a self-contained, developed. The plan view of a Minimal Space Platform
independently powered drilling or workover rig that rests built in 1998 can be seen in Fig. 1 of page 8 comparing it
within or on top of an existing offshore platform structure to a larger platform built in 1974 in nearly the same
and is typically confined to a limited amount of deck water depth. Although the platform size is often dictated
space. The platform bears all the loads of the associated by the size of the reserve discovery and number of wells
rig equipment without the use of a tender barge. As the planned, the trend is towards smaller platforms given
2 G. CARTER IADC/SPE 77231

similar well programs. Another examples of pending Figure 3, page 9 (200 ton rig) and Figure 4, page 10
ideas towards smaller platforms are concepts such as (500 ton rig). As shown in these sketches, the design of
the SPP (Slim Production Platform) drilling and the substructure changed as
production system (2) shown to the right in Fig 2 and
discussed further in the Future of Modular Platform
Rigs section. Many Operators are leaning towards
these new ideas.

MODULAR PLATFORM RIGS


Modular platform rigs previously defined can be grouped
into classes according to hoisting capacity and
horsepower. For the purpose of this report, platform rigs
are grouped into four classes as shown in Chart 1, page
12. This report will focus on rig sizes designated as
class B and C, those ranging in capacity of 100 to
550 tons and 600 to 2,000 horsepower. The largest rigs
reach into the 3,000 hp, 750 ton capacity and require
larger components with heavier weights and derrick
barges to erect them on the platform.

Applications of the platform rig, such as workover or


drilling, and water depth are primary determinates as to
what class size of rig to put on the platform. Improved
rig designs have allowed smaller sized rigs to move into
larger capacity work, thus minimizing the required space
and capacity on the platform. Out of the approximately
929 working and non-working offshore rigs in the world,
31 percent (286 rigs) are self-contained modular
platform rigs (see Chart 2, page 12). Out of these 286
rigs, over half are in the North Sea, Northwest Europe,
and the Gulf of Mexico, USA (See Chart 3, page 12) (3). Figure 2 Slim Production Platform
TECHNOLOGICAL DEVELOPMENTS IN MODULAR
RIG EQUIPMENT
Many changes have taken place within the technological innovative ways to direct the loads into the platform
developments of modular rig design since the mid- capping beams developed. The substructures have also
1980s. The primary changes involve rig component evolved to consume less space on platforms. Instead of
sizes, top drives, cranes, mud processing equipment, spreading out, the rigs have become taller to enclose
and quarters (4-16). Obviously, the effectiveness of the more equipment in a given amount of space.
modular platform rig is only as good as the design.
TOP DRIVES:
RIG COMPONENT SIZES
Top drives have played a large role in the agility of
The first modular platform rig components were large modular rigs. They are being installed for sidetracking in
and bulky and/or mechanically inefficient. Many of these not only 300 ton and larger drilling rigs, but also in
inefficient rigs are still in operation today. Most of the smaller 120 ton to 200 ton primary functional workover
components of these rigs require large derrick barges to rigs. The top drives primary functions are to increase
erect them instead of relying on the existing cranes on trip efficiency and drill speed, improve well control, allow
the platforms. As the modular rig industry becomes for back-reaming, and improve the safety of the work
more competitive, advantages have been sought to out- environment for the drillfloor workers. With the evolution
perform the competition. Individual rig components in of smaller and more muscular top drives, smaller
recent years have become smaller, although small modular rigs have been able to incorporate the working
components do not necessarily imply a good rig design. efficiency of these units. In the past, the physical size
Some of the most important changes to take place have required of masts to install top drives were too large to
been the size and weight of the rig substructure, drillfloor adapt to the slimmer, lighter masts of today. With the
and mast. Examples of some of the new generation advent of improved technology in the electrical top drive,
platform rigs built within the past five years are shown in modular rigs can perform to their highest capability
IADC/SPE 77231 TECHNICAL DEVELOPMENTS IN MODULAR RIG DESIGN LOWERING OPERATOR COSTS 3

without sacrificing mobility or component weight. See MUD PROCESSING EQUIPMENT


Figure 5, page 11, for examples of top drives installed in
newer generation platform rigs. Designing compact and effective mud processing
equipment such as mud pumps and processing tanks
Patents for top drives have existed since the 1920s, but can be a difficult task. Design criteria for this equipment
actual commercial applications of top drives did not will vary depending on rig size. Larger, 500 ton platform
occur until the mid 1980s with the introduction of 500 rigs usually incorporate the pumps and processing
ton capacity hydraulic units. Top drives were major equipment into the structure of the rig. Smaller,
construction upgrades to rigs through the late 1980s sidetracking/drilling platform rigs cannot always support
and early 1990s, taking up to two weeks to install and the addition of these components in their structures and
costing on average $2,000,000 (US). The early top must be placed alongside the rig. Pump manufacturers
drives were bulky and heavy, adding about 40 tons to and fabricators have become very creative with the
the weight of a rig. The interfacing of the mechanical weights and sizes of their equipment in order to
and electrical components of the top drives were time accommodate the down-sizing of rig components.
consuming, invasive and often required adding Figure 5, page 11, shows examples of a compact 1,000
extensions to the mast or derrick. horsepower mud pump and 335 barrel mud processing
equipment used with a smaller 200 ton modular drilling
Even from the early 1990s, top drives have come a long rig. Figure 5 shows how these components are tied into
way to assist modular platform rigs with their important larger, new generation platform rigs. Other mud
aspect of portability. Today modular platform rigs take processing equipment used to reduce component size
advantage of the many improvements in top drive size, and add efficiencies to the rig system are linear flow
adaptability and functionality. Whereas in the early shakers and continuous well servicing mud pumps.
1990s only 500 ton units were available, now anywhere
from 150 to 750 ton top drives can be found. Important QUARTERS
features found in todays electric top drives which add to
the speed, compactability and safety of modular rigs are Although quarters are not technically part of the modular
described in table 5.1 on page 13. (17-18): rig, many platforms require additional housing to
accommodate more workers. The contractor has been
CRANES put in the competitive position to find innovative ways to
bring lightweight and space efficient accommodations for
Two observed trends have taken place with cranes in the rig crew and Operator personnel. Cantilevering off
the offshore oil and gas industry - platform cranes have the edge of the platform is always a simple solution, but
become smaller and rig cranes have become larger. not always the safest or the most efficient method.
Operators tend to keep the size of cranes on their Adapting quarters to existing space on the platform
platforms to a minimum to keep costs associated with requires analysis of each individual platform
platform construction down. This often puts the burden characteristic. Many times additional quarters can be
of installing rigs with adequately sized cranes on the stacked on existing helidecks and buildings, or hung
contractor. Obviously, smaller rig component sizes as from safe structures. New material is now available to
mentioned earlier have contributed most to adapting to build lighter quarters for weight consideration.
smaller platform cranes. But in addition, contractors
owning newer high-tech modular rigs have adapted to TIME AND MOTION STUDIES
smaller platform cranes by changing the design of Time and motion studies pertain to utilizing people and
cranes they own and operate the rig with. Many of the machines to their maximum possible efficiency. The
smaller 120 ton to 250-ton capacity high tech modular most significant cost savings gained by the Operator
rigs do not require more than the typical 15-ton cranes from a platform rig is the efficiency in which the rig
seen on many offshore platforms. The larger class high- moves and operates. How well the modular platform rig
tech modular rigs in the 250 ton to 550 ton capacity is designed determines how efficiently it can be moved.
require larger 25 to 60 ton capacity cranes. These larger Since there are larger scales of costs associated with
cranes associated with the newer high-tech modular offshore work than onshore, a great amount of money
platform rigs have been designed with lighter individual can be saved by even the smallest time saving process.
components to allow the small platform crane to erect The primary functions to consider when analyzing the
these larger cranes. The newer cranes have also been efficiency of a platform rig are: rig moves, day-to-day
designed with a minimum number of components for operations and use of expendables. For instance, in a
speed and ease of installation. rig move the objective is to move from one location to
another in as short a time as possible. During this move,
the rig and associated overhead are no longer directly
working to find or increase oil and gas production. The
4 G. CARTER IADC/SPE 77231

cost is even greater to the Operator when the platform Average time on platform = 1,335 hours
must be shut-in during any part of the rig move. All (55.6 days)
efforts must be made to minimize the number of lifts that Average of 4 wells are worked per platform.
must be put on or taken off a boat, the time it takes to Assumptions:
assemble or disassemble the rig components, and 7 rig moves per year (365 / 55.6days
reduce, if not eliminate, platform shut-in time. per platform)
Rig B = 120 hours (5 days) to move rig
CASE HISTORIES between platforms.
The following case histories of recent modular platform Two boats used to move the rig for both rig A
rig programs are used to prove estimated cost savings to &B
the operator. These examples are of varying rig size, Production rate on platform = 2,000 bbls /day
program work, and geographical location. Assumptions Operator requires platform to be shut-in during
are used in a comparative estimate to the cost of rig move.
alternative, less technologically evolved rig equipment.
Operator cost per hour during rig move =
Average day rates within the time frame of each case
US$1,875/hour
will be used as base cost estimates. As much
($3,000/day x2 boats)+($7,000/day rig
information as possible has been gathered from the
rate)+($20,000/day overhead & admin.) +
operator in each case. Sensitive well related information
($15,000 for shut-in 12 hours @US$15/bbl
is often protected by the Exploration and Production
@2,000 bpd) = $45,000/day = US$1,875
companies and not accessible.
/hour
Weather does not adversely effect the move.
A. GULF OF MEXICO - Case History
Calculations:
Operator Shell Offshore Inc.
Rig A rig move cost = (37 hours) x ($1,875/hour) =
Time Frame: April, 1989 through February,
$69,375
1992
Rig B rig move cost = (120 hours) x ($1,875/hour) =
Rig Class - 120 ton hook, 650 hp, electric rig
$225,000
Location 11 platforms (see table 6-1 page 13)
Difference = $225,000 - $69,375 = $155,625
Wells 65 total wells
Operator cost savings = ($155,625) x (7 rig moves
Program - Workover program.
per year) = US$1,089,375 / year
Information for table 6-1 was gathered from daily IADC
Results:
reports. Weather and platform crane mechanical failures
Comparing rig move times of Rig A (1.5 days) and
were included in the total hours required to move the rig.
Rig B (5 days), both 120 ton capacity rigs, and
A comparison to older, similar class rigs can be made
assuming all other variables listed above are the
assuming a 5 day rig move time for unimproved rigs.
same, results in an average savings of $1,089,375
From experience, moving older, unimproved modular
per year to the Operator (roughly $3,000/day). Not
workover rigs in the 120 ton range can add at least 3.5
only does the Operator save in rig associated costs,
days to a rig move. The increases in rig move times are
but it also gains by increasing its production level
due to heavier component lifts which require an
quicker by working over more wells in a shorter
additional crane to be installed on the platform,
period of time. This makes an even larger difference
inefficient component connections which require more
in present value terms.
time to assemble the rig, extra components that require
more time to install the rig and poor mechanical
B. ADRIATIC SEA Case History
assembly connections resulting in lost time from
mechanical malfunctions. The new technologically
Operator AGIP
advanced platform rigs overcome these problems by
Rig Class - 200 ton hook, 1,000 hp, electric rig
utilizing many of the improvements described in the
Location nine various platforms ( table 6-2 , page
Technological Developments in Modular Rig
14)
Equipment section. The results for this case history
Wells 41 wells
analysis are derived as follows.
Program - Workover program
Statistics:
The 200 ton modular platform rig in this case study has
Rig A = 37 hours (1.5 days) to move rig
been working in the Adriatic Sea for AGIP for over five
between platform.
years. It has made nine rig moves to platforms with a
relatively small amount of available deck space. As
IADC/SPE 77231 TECHNICAL DEVELOPMENTS IN MODULAR RIG DESIGN LOWERING OPERATOR COSTS 5

compared to the earlier Gulf of Mexico case history of 500 ton platform rig requires two boats for 8.5 days at
the 120 ton rig, this 200 ton rig had more associated rig $8,000 per day per boat to move the rig from one
equipment to match the needs of the Operator and the platform to another. Assume a rig mobilization day rate
work performed on the wells. Extra mud tankage, of $25,000 per day. The mobilization cost to the
generator, piperack structure, diesel tank, taller mast operator for the 500 ton rig comes out to roughly
and no rig moving after dark, lengthen rig move time $350,000. This can save the operator over $390,000
relative to the similarly designed 120 ton rig. (US) ($740,000 - $350,000) over the use of an API rig
with a derrick barge for one move. Assuming there are
Prior to 1993 AGIP utilized the H525 Saipem Ideco four moves in a year the average yearly savings would
model rig to perform workovers in the Adriatic. Although be more than $1,500,000 (US). This does not take into
this platform rig had excellent qualities, it was essentially account the costs saved by the operator by having less,
a modular rig welded together to be moved by a crane if any, platform shut-in time due to lack of
barge because the modular aspects were deemed to be welding required.
inferior to the presumed ease of a one-lift rig move. The
resulting rig was a half done effort where part of the rig 7 - ENRICHING THE VALUE OF THE EXPLORATION
was a single-lift, while the rest still had to be moved in AND PRODUCTION COMPANY
little pieces. Also, this rig had several cumbersome An important aspect in the development of modular rig
systems to meet local regulatory requirements. The technology is that it has immense enriching value for the
introduction of the fast moving 200 ton rig brought AGIP Exploration and Production Company. By bringing on-
cost effective rig moves and eliminated the need for line more wells in a shorter period of time the greater the
expensive crane barges, while it was designed to meet net present value of oil and gas becomes. In other
the regulatory requirements of the times with systems words, if in a one year time frame an exploration
integrated in the design. company drills or works-over 20% more wells than they
would have otherwise drilled without improved
technology, the company gains 20% more production for
C. TRINIDAD Case History revenue generation in current dollars instead of future
dollars. Current revenue has a greater impact on the
Operator Amoco value of the company than future revenue primarily due
Rig Class - 500 ton hook, 2000 hp electric rig to Net Present Value (NPV) and compounding.
Location Trinidad
Wells 17 wells 8 - THE FUTURE OF MODULAR PLATFORM RIGS
Program Drilling and Workover As modular platform rigs have developed to adapt to a
higher level of offshore competition and changes in
This 500 ton modular platform rig shown in figure 4 is demands from Operators, the need to continue
built with the same quick modular assembly concept improving designs and methods will not abate. Some of
design as the previous 120 ton and 200 ton rigs. The the greatest potential for modular platform rigs is minimal
500 ton rig does not require a derrick barge, sets up on a spaced platforms in all water depths, deep-water
very small footprint, has 148 lifts, requires no welding, platforms and marginal fields. Minimal spaced platforms
and is easy to assemble. It performs the same work as are emerging as Operators continue to find ways to cut
a standard 2000 hp API platform rig, yet can move development costs. Many Operators are requesting the
from one platform to another in roughly a quarter of the experience of drilling contractor engineers to help design
time as the API rig. Most importantly, it saves money platforms that can maintain as small deck space as
by not requiring a derrick barge. As shown in the data of possible and still perform the necessary drilling,
table 6.3, page 14, this modern 500 ton modular rig can completion, and workover operations. Modular platform
move from one platform to another in about 8.5 days, rigs must stay attune to the need to increase efficiency,
where-as the average 2000 hp API rig can take about 4 reduce size and weight as the Operator demands. The
days to move but requires an expensive derrick barge current deep-water frontier for finding large holdings of
and welding. Approximate cost savings to the operator reserves is demanding significant engineering
can be found making the following assumptions innovation. Platforms, such as SPARs and TLPs moving
and conclusions. into water depths of 5,000 feet (1,525 meters) and
The standard API 2,000 hp rated platform rig requires a deeper having greater impacting environmental forces
derrick barge. Assume $160,000 (US) per day for the requiring frugality of available deck space and applied
derrick barge and rig, which equals $640,000 (US) for a weight constraints. The future modular platform rigs
four day period to mobilize the rig onto the platform. Add must continue to be more operationally efficient, lighter,
another four days of rig time at $25,000 per day to prep smaller, and in the deep offshore environment,
the rig for working the well. This amounts to roughly dynamically engineered to withstand the demanding
$740,000 for the derrick barge assisted rig. The modern oceanic forces.
6 G. CARTER IADC/SPE 77231

Creativity will play a large part in the future of modular absorbing pads similar to those used in buildings for
platform rigs. Below are some ideas that could be earthquake areas. The pads would need to be
brought to fruition allowing there is enough cooperation designed for longer and larger cycles than those
between operator and contractor. experienced in earthquakes.

Lighter platform designs Concepts such as the Laser drilling As laser technology becomes
Slim Production Platform (see figure 2 on page 2) available, it could be applied to modular platform
can significantly reduce the weight of the platform. rigs. Although laser requires a large energy source,
The design reduces operator cost by incorporating a the centralized power station (mentioned above)
combination of smaller production modules, could possibly supply this resource. Drilling with
condensed deck space for platform rig packages, laser is currently being studied in the United States.
and utilization of deviated well conductors which It could possibly eliminate the need to run casing
reduce required well angle while drilling. since the laser is said to harden the walls of the hole
as it cuts the formation. The rig could be designed
Centralized power As the operator plans to with fewer and smaller components since weight on
develop a new field and install platforms, thought the bit and significant rotation is not required.
could be given to a centralized power station either
on land or on a centrally located platform. This
power station could supply power to platforms 9 - CONCLUSIONS
around it with enough reserve for the occasional
addition of drilling or workover rigs. The rigs would Historical data on the efficiency of newer
then not need to bring power packages to the modernized modular platform rigs demonstrates that
platform, reducing required space, weight and the Operators have gained significant cost savings
number of lifts. associated with innovative designs and more
efficient equipment. As demonstrated in the case
Platform storage Some of the most difficult history of smaller workover rigs, 50% to 100% of the
components of a modular platform rig to store on a rig rates can be saved by utilizing the most up-to-
platform are fluid (diesel and water) and bulk tank date modernized modular platform rigs.
storage. These components typically take up large
amounts of space and apply high deck loads. Efficiently designed platform rigs can eliminate the
Should the operator integrate larger tank storage need for expensive derrick barges, reduce rig move
into their platforms there would be greater efficiency time, bring production to the Operator sooner, and
in rig moves and less required top deck space. reduce or eliminate platform shut-in time.
Storage could be added into crane bases, platform
legs, or other unused space. There are many futuristic ideas to apply to modular
platform rigs that, if coordinated by Operators and
Consumable Pods Another idea to remove the Contractors, would significantly enhance the cost
large consumable loads off the platform, such as effectiveness of modular platform rig utilization.
potable and drilling water, mud, diesel, and dry bulk
material is by taking the loads completely off the Modular platform rigs are becoming smaller in size
platform. Remove these loads from the platform and weight, but also more mechanically efficient, in
structure and the platform can be designed with less response to exploration and production companies
required platform rig loads. Instead of using the desires to cut costs.
obvious weather dependant standby barge or lift
boat, build small tubular pods that can be moored The overall efficiency of a modular platform rig is
near the platform with appropriate internal pumps, determined by how well the rig is designed. Simply
and required safety mechanisms for vessel because a rig is smaller and lighter does not mean it
regulations and sea conditions. These tubular pods was designed well.
would have ballasting capabilities, easy to transport
and install and easily maintained. They would vary Modular platform rig technology developed over the
in capacity by varying the length of the tubular. past 10 years is having and will continue to have a
large impact upon the economics of developing
Dynamic compensation Significant rig weight existing deep-water and marginal offshore fields.
reduction and increased efficiency could be
developed by substituting motion compensators in
rigs within deep offshore waters with shock
IADC/SPE 77231 TECHNICAL DEVELOPMENTS IN MODULAR RIG DESIGN LOWERING OPERATOR COSTS 7

ACKNOWLEDGEMENTS 18. J.F. (Jim) Jones: Top Drive A Drilling


Enhancement that Pays Dividends, CADE/CAODC
The author would like to thank the many employees at Spring Drilling Conference, April 8, 1997, Paper No.
Nabors Industries, MEPECO SRL, Hydro Drilling 97-119 pp 1-8
International, Canrig Drilling Technology, OD&E, and
American Bureau of Shipping for their support and input
to this report. Their knowledge and assistance helped to
sow the seeds necessary for this proceeding.

REFERENCES

1. Worldwide Platforms Installed 1975 to present:


Offshore Data Services, Houston, Texas,
November, 2000.
2. Siro Brunato: The Slim Production Platform SPP ,
Manuscript prepared for the 1999 Offshore
Mediterranean Conference, December 1998. Hydro
Drilling International, Alessandria, Italy.
3. Offshore Rig Locator: Offshore Data Services,
Houston, Texas, December 1, 2000.
4. Joe Evangelista: Fifty Years of Crazy Ideas.
Surveyor (a quarterly publication of the American
Bureau of Shipping), March 1997, pp 22-27
5. Rick Von Flatern: New Wave Drilling Rigs Offer
Automation, Ergonomics and Economy. Petroleum
Engineer International, May 1996, pp 75-78
6. Keith Rappold: Modular Designs Highlight Several
New Rigs. Oil & Gas Journal, December 4, 1995,
pp 64-66
7. Dan McNabb: Compact Rigs Suited to Gulf Work.
Oil & Gas Journal, November 3, 1975, pp 64-66
8. Dira/Rapo: Fast Moving Workover Rig Adriatic 1.
D&P News AGIP, June 1995.
9. 50 Years of Offshore Innovation. The American
Bureau of Shipping, 1997.
10. Philip W. Wasterval and Sam C. Lynch: Modular
Platform Rig Design Reduces Operations, Capital
Costs. Drilling, January 1984, pp 56, 63-66.
11. Don Lyle: New Rigs Raise Efficiency. Harts Oil
and Gas World, October 1997, pp 22-25.
12. Duane Russell, James Armstrong, Jerry Shanklin:
Development of the Rigmaster Hydraulic Drilling
Rig, Drilling Technology Conference paper, March
7-9, 1978, pp 343-350.
13. Ian Shearer: Modular Rigs Reduce Topside
Weight, The Institute of Petroleum Petroleum
Review, October, 1990, pp 522-524.
14. John J. Filson: Offshore Industry: Introduction,
ABS, Part XI The Offshore Industry, pp 561-578.
15. James E Steele: Offshore Industry: Early Years
ABS, Part XI The Offshore Industry, pp 579-585.
16. Bruce G. Collipp: Offshore Industry 1950 1965:
Invention, ABS, Part XI The Offshore Industry, pp
586-593.
17. Allan S. Richardson: Electric Top Drive Systems,
IADC European Drilling Issues Conference, Berlin,
June, 1997.
8 G. CARTER IADC/SPE 77231

Built 1974

Typical 150 x 75 Gulf of Mexico platform in 71 meters of water.

Built 1998

Built 1998

1998 Gulf of Mexico Minimal Space Platform in 85 meters of water.

Figure 1 Comparing Platform Deck Sizes.


IADC/SPE 77231 TECHNICAL DEVELOPMENTS IN MODULAR RIG DESIGN LOWERING OPERATOR COSTS 9

Figure 3 200 Ton Modular Platform Rig


10 G. CARTER IADC/SPE 77231

Figure 4 500 Ton Modular Platform Rig


IADC/SPE 77231 TECHNICAL DEVELOPMENTS IN MODULAR RIG DESIGN LOWERING OPERATOR COSTS 11

Portable Hydraulic Top drive


Portable Electric Top Drive Portable Hydraulic Top Drive
System, 400 tons and 31,000
System, 250 tons and 30,000 System, 300 tons and
ft/lbs maximum torque.
ft/lbs maximum torque. 27,500 ft/lbs maximum
torque.

Expanded Mud Contioning Systems


Compact 335 bbl round bottom mud tank
equipped with 16-cone desander, two (2)
linear motion shale shakers, degasser, mud
agitatiors, mixing jets and hosing manifolds.

Figure 5
Auxiliary Mud PumpsCompact,
designed, 1,000 hp triplex mud pump
package. Note small deck space
required when installed.
12 G. CARTER IADC/SPE 77231

Class D
20 (7%)
2000 to 3000 HP
Class A = 6,700 to 9,800 M
550 to 750 Ton Capacity
1,000 to 2,000 HP
Class B = 4,900 to 6,700 M
Class C 250 to 550 Ton Capacity
58 (20%)
Class A 600 to 1,000 HP
Class C = 3,500 to 4,900 M
74 (26%) 100 to 250 Ton Capacity
165 to 600 HP
Class D = 1,500 to 3,500 M
60 to 100 Ton Capacity
Class B
134 (47%)
Sizes of 286 total worldwide Modular Platform Rigs

Chart 1

Asia
Submersibles Canada
7 (1%) Australia New Zealand 4 (1%) Arabian Sea / Persian Gulf
2 (1%)
Platform Tenders 6 (2%) 1 (0%)
31 (3%) Drillships Africa
Artic Other (Europe)
26 (3%) Caspian Sea 7 (2%) 1 (0%)
3 (0.3 %)
Barges 13 (5%)
43 (5%) Mediterranean / Black Sea North Sea & NW Europe
14 (5%) 84 (30%)
Semisubmersibles Mexico
151 (16%) 18 (6%)
Jack-Ups S. America (Venezuela,
382 (41%) Brazil & Other)
25 (9%)
USA Gulf of Mexico
USA Alaska & Pacific
80 (28%)
31 (11%)
Self Contained Platform
Rigs
286 (31%)

Location of working and non-working Offshore


All working and non-working Offshore Self-Contained Platform Rigs
Rigsorldwide Total = 286 Rigs
Total = 929 Rigs

Chart 2 Chart 3
IADC/SPE 77231 TECHNICAL DEVELOPMENTS IN MODULAR RIG DESIGN LOWERING OPERATOR COSTS 13

TABLE 5.1 Important features found in todays electric top drives

FEATURES CHARACTERISTICS ADVANTAGE to MODULAR PLATFORM RIGS


Allows power components to be shared with existing modular
Drive Electrical
rig power.
Greater range of capacity to match appropriate rig size. Only
Capacity 150 to 750 ton
500 ton available prior to early 1990s.
Length 5 to 8 meters Nearly half the length of the early 1990 models.
Weight 20 to 30 tons Weights have decreased from original 40 tons.
Installation 1 to 2 days Fast rig-up. Earlier models took over two weeks to install.
Costs have come down from over $2,000,000(US) in earlier
Cost Avg. $1,200,000(US)
models.
Folding monorail guide Easier portability. Earlier models were fixed and time
Interfacing (Mech)
track. consuming.
Interfacing Self contained modular Minimal interfacing. Earlier models were electrically fixed to
(Electrical) units. the rig and invasive.

TABLE 6.1
THREE YEAR WORKOVER PROGRAM
with MODERN 120 TON RIG
GULF OF MEXICO, USA
Platform Number Total Hours
DATE location of wells hours on to move
(Start) (Gulf of Mexico) Worked-over location rig
4/29/89 ST 26-F 3 1128 30
6/14/89 ST 26-C 2 792 36
7/17/89 ST 26-D 3 1848 42
10/2/89 ST 26-F (return) 2 744 27
11/2/89 ST 26-C (return) 7 1008 21.5
12/14/89 ST 26-D (return) 4 2328 36
3/21/90 ST 26-F (return) 3 1512 33
5/23/90 ST 26-C (return) 2 624 23
6/18/90 ST 26-D (return) 2 744 39
7/19/90 MP 194-A 8 2592 52.5
11/4/90 ST 26-D (return) 5 1128 44
2/12/91 SP 70-C 6 1416 30
4/11/91 SP 70-D 5 1128 52.5
9/10/91 MP 290-B 2 1104 31
10/25/91 SP 62-D 7 2544 52
2/8/92 SP 62-A 4 720 42
TOTAL = 65 21360 591.5
Average move time between platforms = 37 hours (1.5 days)
Average time on platforms = 1335 hours (55.6 days)
14 G. CARTER IADC/SPE 77231

TABLE 6.2
WORKOVER PROGRAM
with MODERN 200 TON RIG
ADRIATIC SEA, ITALY
Platform Number Total Days
DATE location of wells days on to move
(Start) (Adriatic Sea) worked-over location rig
8/24/93 Cervia B 2 74 9
11/7/93 Clara W 3 156 5
4/12/94 Garabaldi A 7 236 4
12/5/94 Antonella 3 176 5
6/1/95 Emma 8 295 3
3/23/96 Ago B 2 197 4
10/5/96 PC 80 2 144 8
2/27/97 Garabaldi B 7 210 5
10/4/97 Ago A 7 240 3
TOTAL = 41 1728 46
Average move time between platforms = 5 days
Average time on platforms = 192 days

TABLE 6.3
WORKOVER PROGRAM
With MODERN 500 TON RIG
TRINIDAD
Platform Number Total Days
DATE Location of wells drilled/ days on to move
(Start) (Trinidad) worked-over location Rig
11/19/97 IMMORTELLE 14 361 8.1
11/14/98 MOHOGANY 3 23 9.1
TOTAL = 17 384 17.2
Average move time between platforms = 8.6 days
Average time on platforms = 192 days

Vous aimerez peut-être aussi